CN206803729U - A kind of continuous tunnel furnace - Google Patents

A kind of continuous tunnel furnace Download PDF

Info

Publication number
CN206803729U
CN206803729U CN201720450451.4U CN201720450451U CN206803729U CN 206803729 U CN206803729 U CN 206803729U CN 201720450451 U CN201720450451 U CN 201720450451U CN 206803729 U CN206803729 U CN 206803729U
Authority
CN
China
Prior art keywords
conveyer belt
blower fan
heating unit
furnace
continuous tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720450451.4U
Other languages
Chinese (zh)
Inventor
许志斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Industrial Park Huafu Science and Technology Co Ltd
Original Assignee
Suzhou Industrial Park Huafu Science and Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou Industrial Park Huafu Science and Technology Co Ltd filed Critical Suzhou Industrial Park Huafu Science and Technology Co Ltd
Priority to CN201720450451.4U priority Critical patent/CN206803729U/en
Application granted granted Critical
Publication of CN206803729U publication Critical patent/CN206803729U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Tunnel Furnaces (AREA)

Abstract

A kind of continuous tunnel furnace, including the first heating unit and the second heating unit are the utility model is related to, first heating unit includes furnace chamber, extends to the first conveyer belt of the port of export in the furnace chamber provided with electric furnace and the arrival end from the furnace chamber;Second heating unit includes blower fan and the second conveyer belt docked with first conveyer belt being arranged at below the blower fan, and second conveyer belt is highly consistent with first conveyer belt, and direction of transfer is identical.The utility model is by the use of traditional electric furnace as the first heating unit, if the heating effect of hot product to be added need to be adjusted, the waste of the energy can be avoided while heating effect is improved by controlling the blower fan in the second heating unit to realize.

Description

A kind of continuous tunnel furnace
Technical field
It the utility model is related to product firing equipment field, more particularly to a kind of continuous tunnel furnace.
Background technology
Continuous tunnel furnace is that the conventional heating that is used for preheats bow and arrow semifinished or finished goods automated production equipment, and it generally passes through heat Conduction, convection current, radiation complete heated baking process.Existing continuous tunnel furnace typically sets electrical heating in closed furnace chamber Stove, and conveyer belt is set in furnace chamber, hot product to be added is positioned on conveyer belt from entrance to outlet and moved, in moving process In, heated baking is carried out to product to be heated using the heating of electric furnace.If above-mentioned continuous tunnel furnace need to improve heating effect, it is necessary to Realized by increasing the power of electric furnace or extending the delivery time of hot product to be added on a moving belt, be unfavorable for heating The lifting of effect and the saving energy.
Utility model content
The utility model provides a kind of continuous tunnel furnace, to solve above-mentioned technical problem.
In order to solve the above technical problems, the utility model provides a kind of continuous tunnel furnace, including the first heating unit and second adds Hot cell, first heating unit include furnace chamber, are provided with electric furnace in the furnace chamber and the arrival end from the furnace chamber prolongs Extend the first conveyer belt of the port of export;Second heating unit include blower fan and be arranged at below the blower fan with described the Second conveyer belt of one conveyer belt docking, second conveyer belt highly consistent, direction of transfer phase with first conveyer belt Together.
It is preferred that the quantity of the blower fan is multiple, direction of transfer of multiple blower fans along second conveyer belt uniformly divides It is distributed in the top of second conveyer belt.
It is preferred that the quantity of the blower fan is multiple, direction of transfer of multiple blower fans edges perpendicular to second conveyer belt It is uniformly distributed in the top of second conveyer belt.
It is preferred that the quantity of the blower fan is multiple, the opening and closing of multiple blower fans are independent control.
It is preferred that the second conveyer belt upper surface is provided with materials and parts detection sensor, the materials and parts detection sensor with The control terminal of the blower fan and the control terminal of second conveyer belt connect respectively.
It is preferred that the end of second conveyer belt is provided with a Material collecting box for harvesting.
It is preferred that a bearing sensor is provided with below the Material collecting box for harvesting, the bearing sensor and the control of the blower fan The control terminal at end, the control terminal of electric furnace, the control terminal of the first conveyer belt and the second conveyer belt connects respectively.
Compared with prior art, continuous tunnel furnace provided by the utility model, including the first heating unit and the second heating unit, First heating unit includes furnace chamber, is provided with electric furnace in the furnace chamber and the arrival end from the furnace chamber extends to outlet First conveyer belt at end;Second heating unit include blower fan and be arranged at below the blower fan with first conveyer belt Second conveyer belt of docking, second conveyer belt is highly consistent with first conveyer belt, and direction of transfer is identical.This practicality It is new by the use of traditional electric furnace as the first heating unit, if the heating effect of hot product to be added need to be adjusted, control can be passed through The blower fan in the second heating unit is made to realize, the waste of the energy is avoided while heating effect is improved.
Brief description of the drawings
Fig. 1 is the structural representation of continuous tunnel furnace in the embodiment of the utility model one.
In figure:The heating units of 10- first, 11- furnace chambers, 12- electric furnaces, the conveyer belts of 13- first, 20- second heat list Member, 21- blower fans, the conveyer belts of 22- second, 23- materials and parts detection sensor, 30- Material collecting box for harvesting, 31- bearing sensors, 40- are to be heated Product.
Embodiment
To enable above-mentioned purpose of the present utility model, feature and advantage more obvious understandable, below in conjunction with the accompanying drawings to this The embodiment of utility model is described in detail.It should be noted that the utility model accompanying drawing is using simplified form And non-accurately ratio is used, only to purpose that is convenient, lucidly aiding in illustrating the utility model embodiment.
Continuous tunnel furnace provided by the utility model, as shown in figure 1, including the first heating unit 10 and the second heating unit 20, First heating unit 10 includes furnace chamber 11, and electric furnace 12 and the arrival end from the furnace chamber 11 are provided with the furnace chamber 11 The first conveyer belt 13 of the port of export is extended to, specifically, hot product 40 to be added is positioned over 13 enterprising line position of the first conveyer belt and puts shifting It is dynamic, while product 40 to be heated is heated using electric furnace 12;Second heating unit 20 includes blower fan 21 and set It is placed in the second conveyer belt 22 docked with first conveyer belt 13 of the lower section of blower fan 21, second conveyer belt 22 and institute The highly consistent of the first conveyer belt 13 is stated, direction of transfer (direction shown in arrow in figure) is identical, so, can be by the first conveyer belt Hot product to be added 40 on 13 is smoothly transferred to the second conveyer belt 22, realizes hot product 40 to be added from the first heating unit 10 to The transfer of two heating units 20.The utility model is by the use of traditional electric furnace 12 as the first heating unit 10, if needing to adjust The heating effect of hot product 40 to be added, can by change the second heating unit 20 whether unlatching, and the specific number of blower fan 21 Measure to realize, the waste of the energy is avoided while heating effect is improved.
It is preferred that please continue to refer to Fig. 1, the quantity of the blower fan 21 is multiple, and multiple blower fans 21 transmit along described second The top (embodiment as shown in Figure 1) of second conveyer belt 22 is uniformly distributed in 22 direction of transfer;Certainly, multiple blower fans 21 can also be uniformly distributed in the top of second conveyer belt 22 along the direction of transfer perpendicular to second conveyer belt 22, only It need to ensure that the hot product to be added 40 on the second conveyer belt 22 is heated evenly.
It is preferred that the quantity of the blower fan 21 is multiple, the opening and closing of multiple blower fans 21 are independent control, also To say, the opening and closing of multiple blower fans 21 can independent control, be easy to control the particular number and distribution mode of blower fan 21.
It is preferred that please continue to refer to Fig. 1, the upper surface of the second conveyer belt 22 is provided with materials and parts detection sensor 23, institute State materials and parts detection sensor 23 be used for detect the second conveyer belt 22 on whether there is hot product 40 to be added, the materials and parts, which detect, to be sensed Device 23 is connected respectively with the control terminal of the blower fan 21 and the control terminal of second conveyer belt 22, when materials and parts detection sensor 23 detect when hot product 40 to be added being not present on the second conveyer belt 22, the conveyer belt 22 of blower fan 21 and second are closed, with further Save the energy.
It is preferred that please continue to refer to Fig. 1, the end of second conveyer belt 22 is provided with a Material collecting box for harvesting 30, specifically, described The lower section of Material collecting box for harvesting 30 is provided with control terminal, the electric furnace of a bearing sensor 31, the bearing sensor 31 and the blower fan 21 The control terminal of 12 control terminal, the control terminal of the first conveyer belt 13 and the second conveyer belt 22 connects respectively, that is to say, that works as collection Hopper 30 take away blanking when, i.e., bearing sensor 31 detects Material collecting box for harvesting 30 not when gathering materials, close the He of the first heating unit 10 Second heating unit 20, avoid hot product 40 to be added from continuing to heat and move, further save the energy.
In summary, continuous tunnel furnace provided by the utility model, including the first heating unit 10 and the second heating unit 20, institute Stating the first heating unit 10 includes furnace chamber 11, is provided with electric furnace 12 in the furnace chamber 11 and the arrival end from the furnace chamber 11 prolongs Extend the first conveyer belt 13 of the port of export;Second heating unit 20 includes blower fan 21 and is arranged at the lower section of blower fan 21 The second conveyer belt 22 docked with first conveyer belt 13, the height of second conveyer belt 22 and first conveyer belt 13 Unanimously, direction of transfer is identical.The utility model is treated by the use of traditional electric furnace 12 as the first heating unit 10 if need to adjust The heating effect of product 40 is heated, heating effect can improved by controlling the blower fan 21 in the second heating unit 20 to realize While avoid the waste of the energy.
Obviously, it is new without departing from this practicality can to carry out various changes and modification to utility model by those skilled in the art The spirit and scope of type.So, if these modifications and variations of the present utility model belong to the utility model claims and its Within the scope of equivalent technologies, then the utility model is also intended to including these changes and modification.

Claims (7)

  1. A kind of 1. continuous tunnel furnace, it is characterised in that including the first heating unit and the second heating unit, the first heating unit bag Furnace chamber is included, extends to the first conveyer belt of the port of export in the furnace chamber provided with electric furnace and the arrival end from the furnace chamber;Institute Stating the second heating unit includes blower fan and the second conveyer belt docked with first conveyer belt being arranged at below the blower fan, Second conveyer belt is highly consistent with first conveyer belt, and direction of transfer is identical.
  2. 2. continuous tunnel furnace as claimed in claim 1, it is characterised in that the quantity of the blower fan is multiple, and multiple blower fans are described in The direction of transfer of second conveyer belt is uniformly distributed in the top of second conveyer belt.
  3. 3. continuous tunnel furnace as claimed in claim 1, it is characterised in that the quantity of the blower fan is multiple, and multiple blower fans are along vertically The top of second conveyer belt is uniformly distributed in the direction of transfer of second conveyer belt.
  4. 4. continuous tunnel furnace as claimed in claim 1, it is characterised in that the quantity of the blower fan is multiple, the unlatching of multiple blower fans It is independent control with closing.
  5. 5. continuous tunnel furnace as claimed in claim 1, it is characterised in that the second conveyer belt upper surface is provided with materials and parts detection and passed Sensor, the materials and parts detection sensor are connected respectively with the control terminal of the blower fan and the control terminal of second conveyer belt.
  6. 6. continuous tunnel furnace as claimed in claim 1, it is characterised in that the end of second conveyer belt is provided with a Material collecting box for harvesting.
  7. 7. continuous tunnel furnace as claimed in claim 6, it is characterised in that a bearing sensor is provided with below the Material collecting box for harvesting, it is described Bearing sensor and control terminal, the control terminal of electric furnace, the control terminal of the first conveyer belt and the second transmission of the blower fan The control terminal of band connects respectively.
CN201720450451.4U 2017-04-26 2017-04-26 A kind of continuous tunnel furnace Expired - Fee Related CN206803729U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720450451.4U CN206803729U (en) 2017-04-26 2017-04-26 A kind of continuous tunnel furnace

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720450451.4U CN206803729U (en) 2017-04-26 2017-04-26 A kind of continuous tunnel furnace

Publications (1)

Publication Number Publication Date
CN206803729U true CN206803729U (en) 2017-12-26

Family

ID=60738273

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720450451.4U Expired - Fee Related CN206803729U (en) 2017-04-26 2017-04-26 A kind of continuous tunnel furnace

Country Status (1)

Country Link
CN (1) CN206803729U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112549757A (en) * 2020-12-16 2021-03-26 东莞市华芯联科技有限公司 Batch production equipment and process for ceramic piezoresistive sensors

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112549757A (en) * 2020-12-16 2021-03-26 东莞市华芯联科技有限公司 Batch production equipment and process for ceramic piezoresistive sensors

Similar Documents

Publication Publication Date Title
CN203529952U (en) Aluminum chloride crystal roasting system
CN101836674B (en) Microwave-assisted heating combined belt type drier
CN207269742U (en) A kind of multistage apparatus for baking
CN206803729U (en) A kind of continuous tunnel furnace
CN204177150U (en) A kind of fully automatic vacuum tunnel oven
CN206744471U (en) A kind of Gluten drying plant
CN209065756U (en) It is a kind of for drying the oven of sheet glass
CN203848658U (en) Continuous heating furnace
CN206222839U (en) Radix Angelicae Sinensis apparatus for baking with water content detection
CN205300226U (en) But temperature monitoring's electric hot drying case
CN206380553U (en) A kind of continuous tunnel furnace for biscuit baking system for automatically controlling air-out
CN207407649U (en) A kind of jasmine tea spiral continuous low-temperature baking room
CN207299865U (en) A kind of energy-saving tea drier
CN207180278U (en) A kind of Chinese medicine dryer
CN206990480U (en) A kind of heat deformations test machine
CN205980673U (en) Continuous drying equipment of board
CN206300448U (en) One kind patch bottom section bilayer NIR baking oven streamlines
CN214582424U (en) Continuous reduction equipment for graphene oxide film
CN204830721U (en) Shunting peanut drying device
CN205419086U (en) Belt conveying device
CN203776063U (en) Tea leaf drying machine
CN207091480U (en) A kind of continuous cooling device
CN206978658U (en) A kind of foodstuff dryer
CN207850032U (en) A kind of heating furnace of Bilateral heating wind-guiding
CN105558003A (en) Grain drying machine with cold air replenishing device

Legal Events

Date Code Title Description
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171226

CF01 Termination of patent right due to non-payment of annual fee