CN206783114U - The hanging beam of steel box-girder - Google Patents

The hanging beam of steel box-girder Download PDF

Info

Publication number
CN206783114U
CN206783114U CN201621408526.4U CN201621408526U CN206783114U CN 206783114 U CN206783114 U CN 206783114U CN 201621408526 U CN201621408526 U CN 201621408526U CN 206783114 U CN206783114 U CN 206783114U
Authority
CN
China
Prior art keywords
girder
steel box
hanger
hanging beam
lifting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621408526.4U
Other languages
Chinese (zh)
Inventor
许金明
季富强
周维
鞠小刚
叶飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Zhenghua Heavy Industries Co Ltd
CCCC Highway Long Bridge Construction National Engineering Research Center Co Ltd
Original Assignee
Shanghai Zhenghua Heavy Industries Co Ltd
CCCC Highway Long Bridge Construction National Engineering Research Center Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Zhenghua Heavy Industries Co Ltd, CCCC Highway Long Bridge Construction National Engineering Research Center Co Ltd filed Critical Shanghai Zhenghua Heavy Industries Co Ltd
Priority to CN201621408526.4U priority Critical patent/CN206783114U/en
Application granted granted Critical
Publication of CN206783114U publication Critical patent/CN206783114U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model discloses a kind of hanging beam of steel box-girder, including:Girder and lifting equalizer bar.The top of girder has the first hanger, and the bottom of girder has the second hanger.Lifting equalizer bar is connected on the second hanger.First hanger is connected to driving, the second hanger connection steel box-girder.The hanging beam of the steel box-girder also includes auxiliary balance beam, and auxiliary balance beam is connected to the side of girder.The hanging beam of steel box-girder of the present utility model has well adapting to property, adapts to the Plate of Flat Steel Box Girder of various sizes and various working environments, reduces the potential safety hazard during construction operation.

Description

The hanging beam of steel box-girder
Technical field
Steel construction manufacture field is the utility model is related to, more specifically to the lifting tool of steel box-girder.
Background technology
In Plate of Flat Steel Box Girder shaped steel bridge manufactures industry, Plate of Flat Steel Box Girder that length and width dimensions differ can be produced as steel The part of bridge.When the Plate of Flat Steel Box Girder to differ to these length and width dimensions is lifted, transported, hanging beam need to be used.Conventional hangs In dress method, it can be worked in coordination using two drivings, be lifted by crane using steel wire rope and shackle.Due to Plate of Flat Steel Box Girder deadweight compared with Greatly, well beyond separate unit driving freight weight limit, it is therefore necessary to auxiliary lifting is carried out using hanging beam, if two drivings in hoisting process There is deviation in linkage, the weight of Plate of Flat Steel Box Girder can be caused all to cause this driving to transfinite by a driving carrying, this can be big Big increase potential safety hazard.Meanwhile the length of different steel box-girders differs, likely to be less than two driving limits of length direction hanger distance Position, will lead to not lift by crane.
Utility model content
The utility model proposes a kind of hanging beam of steel box-girder, including:Girder and lifting equalizer bar.The top of girder has the One hanger, the bottom of girder have the second hanger.Lifting equalizer bar is connected on the second hanger.First hanger is connected to driving, Second hanger connects steel box-girder.
In one embodiment, the top of girder sets two the first hangers, and the spacing of two the first hangers meets driving Spacing requirement.
In one embodiment, there is weight pound plate and supporting plate on the first hanger.
In one embodiment, the bottom of girder sets several second hangers, and two in several second hangers can form Combination with different spacing.
In one embodiment, the second hanger includes two shackle plates be arrangeding in parallel, has weight pound plate on shackle plate.
In one embodiment, equalizer bar tabular triangular in shape is lifted by crane, top has connecting hole, and bottom has lifting Hole.
In one embodiment, the connecting hole for lifting by crane equalizer bar is set by the way that pivot pin, axle sleeve are parallel with being bolted to two Between the shackle plate put so that lifting equalizer bar is connected on the second hanger.
In one embodiment, the hanging beam of steel box-girder also includes:Auxiliary balance beam, auxiliary balance beam are connected to the side of girder Face.
In one embodiment, girder is H profile steel component, and auxiliary balance beam is connected to the side of girder by connecting plate.
In one embodiment, girder is used in pairs, and auxiliary balance beam is arranged between two girders.
The hanging beam of steel box-girder of the present utility model has well adapting to property, adapt to various sizes Plate of Flat Steel Box Girder and Various working environments, reduce the potential safety hazard during construction operation.
Brief description of the drawings
The above and other feature of the utility model, property and advantage are by by with reference to the accompanying drawings and examples Describing and become apparent, identical reference represents identical feature all the time in the accompanying drawings, wherein:
Fig. 1 discloses the side block diagram of the hanging beam of the steel box-girder according to an embodiment of the present utility model.
Fig. 2 discloses the overlooking structure figure of the hanging beam of the steel box-girder according to an embodiment of the present utility model.
Fig. 3 discloses the structure chart that equalizer bar is lifted by crane in the hanging beam according to the steel box-girder of an embodiment of the present utility model.
Fig. 4 a and Fig. 4 b disclose the first use state of the hanging beam of the steel box-girder of an embodiment of the present utility model.
Fig. 5 a and Fig. 5 b disclose second of use state of the hanging beam of the steel box-girder of an embodiment of the present utility model.
Embodiment
With reference to shown in figure 1, Fig. 1 discloses the side view structure of the hanging beam of the steel box-girder according to an embodiment of the present utility model Figure.The hanging beam of the steel box-girder includes:Girder 103 and lifting equalizer bar 111.The top of girder 103 has the first hanger 102, main The bottom of beam 103 has the second hanger 104.First hanger 102 is connected to driving.In the illustrated embodiment, the top of girder 103 Portion sets two the first hangers 102, and the spacing of two the first hangers 102 meets spacing requirement of driving a vehicle.Each first hanger 102 It is upper that there is weight pound plate 101 and supporting plate 105.In one embodiment, it is smooth on the inside of the perforate of the first hanger 102 to ensure, treat After weight pound plate 101 and the first hanger 102 are welded in place, bore hole processing need to be carried out to perforate, and open up chamfering.The bottom of girder 103 Portion sets several second hangers 104, the second hanger 104 connection steel box-girder.In the illustrated embodiment, in the bottom of girder 103 There is provided four the second hangers 104.Four the second hangers 104 are matched by combination of two, can make up with different spacing Combination.These have the steel box-girder that the combination of different spacing can adapt to different length.With continued reference to shown in Fig. 1, each Two hangers 104 include two shackle plates be arrangeding in parallel, have weight pound plate on shackle plate.Lifting equalizer bar 111 is connected to second On hanger 104.Fig. 3 discloses the structure that equalizer bar is lifted by crane in the hanging beam according to the steel box-girder of an embodiment of the present utility model Figure.As shown in figure 3, the tabular that lifting equalizer bar 111 is triangular in shape, top have connecting hole, bottom has lifting eye.Illustrating Embodiment in, lifting equalizer bar 111 bottom is provided with two groups of lifting eyes, and the quantity of each group of lifting eye is two.So exist The bottom of each lifting equalizer bar 111 has four lifting eyes.Two groups of four lifting eyes enable lifting equalizer bar 111 more Various sizes of steel box-girder is adapted to well.In one embodiment, lift by crane and all pacify on connecting hole and lifting eye on equalizer bar 111 Equipped with weight pound plate, and carry out Boring.Fig. 1 is returned to, the connecting hole of lifting equalizer bar 111 passes through pivot pin 107, the and of axle sleeve 106 Bolt 108 is connected between two shackle plates be arrangeding in parallel so that lifting equalizer bar 111 is connected on the second hanger 104.Pin Axle 107, axle sleeve 108 are finished, and ensure the fit tolerance with the hole on the second hanger 104 and lifting equalizer bar 111.Together When, according to strength analysis calculation, bearing pin need to carry out surface hardening with proof strength.To ensure that each second hanger is being grouped Concentricity during installation, after bearing pin 107 being inserted to the second hanger 102, then to the welding of the second hanger 102.
With reference to shown in figure 2, Fig. 2 discloses the plan structure of the hanging beam of the steel box-girder according to an embodiment of the present utility model Figure.The hanging beam of the steel box-girder also includes auxiliary balance beam 109, and auxiliary balance beam 109 is connected to the side of girder 103.At one In embodiment, girder 103 is H profile steel component, and auxiliary balance beam 109 is square tube, and auxiliary balance beam 109 is connected by connecting plate 110 It is connected to the side of girder 103.With continued reference to shown in Fig. 2, girder 103 uses in pairs, and auxiliary balance beam 109 is arranged on two girders Between 103, play a part of balanced side force.
Fig. 4 a and Fig. 4 b disclose the first use state of the hanging beam of the steel box-girder of an embodiment of the present utility model.Its Middle Fig. 4 b are Fig. 4 a A-A to sectional view.Shown in Fig. 4 a and Fig. 4 b is the use state lifted in workshop.Lifted in workshop When, it will not be influenceed substantially by Cross Wind Force, therefore can be without using auxiliary balance beam.It is directly flat by girder 103 and lifting Weighing apparatus beam 111 lifts to steel box-girder 112.
Fig. 5 a and Fig. 5 b disclose second of use state of the hanging beam of the steel box-girder of an embodiment of the present utility model.Its Middle Fig. 5 b are Fig. 5 a A-A to sectional view.Shown in Fig. 5 a and Fig. 5 b is the use state of outfield lifting.When being lifted in outfield, It can be influenceed by Cross Wind Force, it is therefore desirable to use auxiliary balance beam.In the embodiment shown in Fig. 5 a and Fig. 5 b, at two Auxiliary balance beam 109 is added between girder 103.By girder 103, lifting equalizer bar 111 and auxiliary balance beam 109 jointly to steel Box beam 112 is lifted.
The hanging beam of steel box-girder of the present utility model has the advantages of following:
1) using after hanging beam of the present utility model, by being changed to vertical pulling force by oblique pulling force when steel box-girder lifts by crane, reduce Steel box-girder hanger reduces the generation of internal stress, steel box-girder overall structure is protected in side force caused by lifting.
2) steel box-girder is lifted by crane except internal field and also needs to consider outfield lifting, and using driving work compound, outfield is often adopted in internal field Lifting operation is carried out with gantry crane.Vehicling operation is generally double hook or four hook operations, and gantry crane is often made for single hook Industry.Hanging beam of the present utility model is suitable for different work requirement by adjusting intermediate equilibria beam.
3) different type steel box-girder length is inconsistent in same seat steel bridge.Hanger in girder lower end is two groups four altogether, It is suitable for the steel box-girder of different length.Different steel box-girder hanger groups can be adapted to by adjusting hanger position of opening on small equalizer bar Spacing.
4) the linkage operation of duplicate rows car is both needed to when being lifted by crane in steel box-girder workshop, safe spacing between driving be present, reference is existing Conventional travelling data, the hanger spacing of girder upper surface two are arranged to 11 meters, meet the existing spacing requirement mainly driven a vehicle.
5) it is bolt connection between girder and equalizer bar, convenient disassembly.It is four rod members after the completion of dismounting, can conveniently adopts Transported with fork truck.
Above-described embodiment, which is available to, is familiar with person in the art to realize or using of the present utility model, be familiar with ability The personnel in domain can in the case where not departing from utility model thought of the present utility model, above-described embodiment is made various modifications or Change, thus the scope of protection of the utility model is not limited by above-described embodiment, and should meet claims to mention Inventive features maximum magnitude.

Claims (10)

  1. A kind of 1. hanging beam of steel box-girder, it is characterised in that including:
    Girder, the top of girder have the first hanger, and the bottom of girder has the second hanger;
    Equalizer bar is lifted by crane, is connected on the second hanger;
    First hanger is connected to driving, the second hanger connection steel box-girder.
  2. 2. the hanging beam of steel box-girder as claimed in claim 1, it is characterised in that the top of the girder sets two first and hung Ear, the spacing of described two first hangers meet spacing requirement of driving a vehicle.
  3. 3. the hanging beam of steel box-girder as claimed in claim 2, it is characterised in that there is weight pound plate and support on first hanger Plate.
  4. 4. the hanging beam of steel box-girder as claimed in claim 1, it is characterised in that the bottom of the girder sets several second to hang Ear, two in several second hangers can form the combination with different spacing.
  5. 5. the hanging beam of steel box-girder as claimed in claim 4, it is characterised in that what second hanger be arranged in parallel including two Shackle plate, there is weight pound plate on shackle plate.
  6. 6. the hanging beam of steel box-girder as claimed in claim 5, it is characterised in that lifting equalizer bar tabular triangular in shape, Top has connecting hole, and bottom has lifting eye.
  7. 7. the hanging beam of steel box-girder as claimed in claim 6, it is characterised in that the connecting hole of the lifting equalizer bar passes through axle Pin, axle sleeve and it is bolted between two shackle plates be arrangeding in parallel so that lifting equalizer bar is connected on the second hanger.
  8. 8. the hanging beam of steel box-girder as claimed in claim 1, it is characterised in that the hanging beam of the steel box-girder also includes:Auxiliary is flat Heng Liang, auxiliary balance beam are connected to the side of girder.
  9. 9. the hanging beam of steel box-girder as claimed in claim 8, it is characterised in that the girder is H profile steel component, and the auxiliary is flat Heng Liang is connected to the side of girder by connecting plate.
  10. 10. the hanging beam of steel box-girder as claimed in claim 9, it is characterised in that the girder uses in pairs, auxiliary balance beam peace Between two girders.
CN201621408526.4U 2016-12-21 2016-12-21 The hanging beam of steel box-girder Active CN206783114U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621408526.4U CN206783114U (en) 2016-12-21 2016-12-21 The hanging beam of steel box-girder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621408526.4U CN206783114U (en) 2016-12-21 2016-12-21 The hanging beam of steel box-girder

Publications (1)

Publication Number Publication Date
CN206783114U true CN206783114U (en) 2017-12-22

Family

ID=60703301

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621408526.4U Active CN206783114U (en) 2016-12-21 2016-12-21 The hanging beam of steel box-girder

Country Status (1)

Country Link
CN (1) CN206783114U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109502473A (en) * 2018-12-22 2019-03-22 吉林大学 A kind of remote double cranes collaboration hanging apparatus

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109502473A (en) * 2018-12-22 2019-03-22 吉林大学 A kind of remote double cranes collaboration hanging apparatus

Similar Documents

Publication Publication Date Title
CN201882763U (en) Special carrying pole type beam of double-machine lifting crane
CN200951923Y (en) Transverse hanging bean for railway hoister
CN104326356A (en) Construction platform hanger with clear stress and adjustable hanging point
CN206783114U (en) The hanging beam of steel box-girder
CN106013003B (en) For lifting by crane the self-locking pull rod of gate
CN205034957U (en) I -steel is hoist for handling
CN206511803U (en) A kind of T-shaped hanging beam
CN204689351U (en) A kind of H profile steel structural elements suspender
CN106185597B (en) A kind of large size Analytic Tower merogenesis special hanger for hoisting and hanging method
CN204281029U (en) A kind of stressed clear and definite and adjustable operation platform suspender of suspension centre
CN202131004U (en) Balance hanging beam for combination operation of two cranes
CN104355232B (en) Truck turning device
CN204251194U (en) A kind of Novel hanging tool
CN203213018U (en) Lifting device for rigid hinges and large components
CN207226817U (en) A kind of suspender of shaped object handling
CN103231982A (en) Carrying pole bean of double-cast bridge crane for lifting super-large object
CN106081881A (en) A kind of precious stone special hoisting fixture
CN206126649U (en) Multi -functional detachable hoist and mount compensating beam
CN205527282U (en) Hoist and mount of rolling mill reduction gear are with two car special lifting device
CN206538090U (en) One kind lifting steel plate steel shoulder pole
CN210366609U (en) Crane hanging fork
CN213112167U (en) Special horizontal lifting appliance for fan-shaped track
CN104860188A (en) Steel plate lifting tool
CN207346987U (en) Frame-type self-balancing hanger
CN107934744A (en) Polar crane integral hoisting device for rapid

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant