CN206717505U CN201720553708.9U CN201720553708U CN206717505U CN 206717505 U CN206717505 U CN 206717505U CN 201720553708 U CN201720553708 U CN 201720553708U CN 206717505 U CN206717505 U CN 206717505U
Authority
CN
China
Prior art keywords
steel pipe
fixed seat
air blowing
blanking
air pump
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720553708.9U
Other languages
Chinese (zh)
Inventor
许朝奎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jia Ying Feng Zhicheng Precision Hardware (shenzhen) Co Ltd
Original Assignee
Jia Ying Feng Zhicheng Precision Hardware (shenzhen) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jia Ying Feng Zhicheng Precision Hardware (shenzhen) Co Ltd filed Critical Jia Ying Feng Zhicheng Precision Hardware (shenzhen) Co Ltd
Priority to CN201720553708.9U priority Critical patent/CN206717505U/en
Application granted granted Critical
Publication of CN206717505U publication Critical patent/CN206717505U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Auxiliary Devices For Machine Tools (AREA)

Abstract

The utility model discloses a kind of blanking blowning installation, including air blowing steel pipe, bearing connection, fixed seat and air pump, fixed seat center offers small through hole, bearing connection center offers large through-hole, fixed seat one end communicates with air pump, in the large through-hole of fixed seat other end insertion bearing connection, one end of air blowing steel pipe is docked through bearing connection and with small through hole, and the other end of air blowing steel pipe through main shaft and is inserted at the dop of C-shaped spring clamp head;Screw on dop machines rear dop and unclamped, and the gas in air pump is exported by air blowing steel tube end part and blown off screw.By the way that air blowing steel pipe is inserted at the dop of C-shaped spring clamp head from tail end, when the screw on dop machines, the process of screw blanking directly just can be directly realized by air blowing process;Fixed seat is played a supporting role;Bearing connection mainly plays linking main shaft and rotates at a high speed with fixed seat and guide the function of air blowing steel pipe.

Description

Blanking blowning installation
Technical field
It the utility model is related to the technical field of screw production, more particularly to a kind of blanking blowning installation.
Background technology
Screw is the physics and mathematical principle of the inclined-plane circular rotating and frictional force using object, is fastened by easy stages The instrument of implements parts.Screw is the general saying of fastener, daily pet phrase.Screw is work indispensable in daily life Industry necessity:The minimum screw that such as camera, glasses, clock and watch, electronics use;TV, electric product, musical instrument, furniture etc. General screw;As for engineering, building, bridge then using large-scale screw, nut;Traffic tool, aircraft, electric car, automobile etc. are then It is used in combination for big primary screw.C-shaped spring clamp head is that a kind of one kind of device on milling machine that is used for is used for confining drill bit either milling cutter A kind of tubular fixture, be a kind of a kind of fixing device for being used for the fixed part reinforced and need to transform, Digit Control Machine Tool bullet Spring chuck.At present, in C-shaped spring clamp head, treated screw must be taken out by manipulator, place into new spiral shell to be processed Silk, can just remain in operation, and such operating efficiency is difficult to improve.
Utility model content
For weak point present in above-mentioned technology, a kind of blanking of the utility model offer is fast, the blanking of efficiency high is blown Device of air.
In order to achieve the above object, a kind of blanking blowning installation of the utility model, including air blowing steel pipe, bearing position, bearing Connector, fixed seat and air pump, the fixed seat center offer small through hole, and the bearing connection center offers big logical Hole, the bearing position are clamped between bearing connection and fixed seat, and described fixed seat one end communicates with air pump, the fixed seat In the large through-hole of other end insertion bearing connection, one end of the air blowing steel pipe through bearing connection and with small through hole pair Connect, the other end of the air blowing steel pipe through main shaft and is inserted at the dop of C-shaped spring clamp head;Screw on dop machines Dop unclamps afterwards, and the gas in air pump is exported by air blowing steel tube end part and blown off screw.
Wherein, the bearing connection includes concave part and bearing portion, and main shaft is set in the bearing portion outer surface, institute The groove that concave part protrudes from bearing portion and is more than large through-hole provided with radius is stated, the bearing position is contained in concave part.
Wherein, the fixed seat includes fixed part, connecting portion and elongated portion, and the fixed part is fixedly connected with air pump, The connecting portion is contained in the groove of concave part, is communicated in the elongated portion insertion large through-hole and with air blowing steel pipe.
Wherein, the blanking blowning installation also includes air pump connector and gasket seal, and described air pump connector one end leads to Cross gasket seal to communicate with air pump, and the air pump connector other end is connected with fixed seat, the both ends of the air pump connector Connector is mutually perpendicular to.
Wherein, the air blowing steel pipe includes the first steel pipe portion and the second steel pipe portion, the internal diameter in the first steel pipe portion with And external diameter is more than the internal diameter and external diameter in the second steel pipe portion, the one end in the first steel pipe portion is connected with the elongated portion of fixed seat, The other end in the first steel pipe portion is connected with the one end in the second steel pipe portion, the other end insertion c-type bullet in the second steel pipe portion At dop in spring chuck.
The beneficial effects of the utility model are:
Compared with prior art, blanking blowning installation of the present utility model, by the way that air blowing steel pipe is inserted into c-type bullet from tail end At the dop of spring chuck, when the screw on dop machines, directly just it can directly be realized by air blowing process under screw The process of material;Fixed seat is played a supporting role;Bearing connection mainly plays linking main shaft and rotates and draw at a high speed with fixed seat Lead the function of air blowing steel pipe.Blanking blowning installation of the present utility model, it is simple in construction, it is inserted directly into existing screwing machine In main shaft, and excessive area is not take up, while does not need manipulator to carry out the blanking of screw, that is, improve operating efficiency, Reduce the loss of energy again.
Brief description of the drawings
Fig. 1 is the structure chart of the utility model blanking blowning installation;
Fig. 2 is the phantom of the utility model blanking blowning installation.
Main element symbol description is as follows:
10th, air blowing steel pipe 11, bearing connection
12nd, fixed seat 13, air pump connector
14th, gasket seal 15, bearing position
101st, the first steel pipe portion 102, the second steel pipe portion
111st, concave part 112, bearing portion
121st, fixed part 122, connecting portion
123rd, elongated portion.
Embodiment
In order to more clearly state the utility model, the utility model is further described below in conjunction with the accompanying drawings.
Refering to Fig. 1, a kind of blanking blowning installation of the utility model, including air blowing steel pipe 10, bearing position 15, bearing connection 11st, fixed seat 12 and air pump, the center of fixed seat 12 offer small through hole, and the center of bearing connection 11 offers large through-hole, axle Hold position 15 to be clamped between bearing connection 11 and fixed seat 12, the one end of fixed seat 12 communicates with air pump, the other end of fixed seat 12 Insert in the large through-hole of bearing connection 11, one end of air blowing steel pipe 10 is docked through bearing connection 11 and with small through hole, is blown The other end of gas steel pipe 10 is through main shaft and inserts at the dop of C-shaped spring clamp head;Screw on dop machines rear dop Unclamp, the gas in air pump is exported by the end of air blowing steel pipe 10 and blown off screw.
Compared to prior art, blanking blowning installation of the present utility model, by the way that air blowing steel pipe 10 is inserted into c-type from tail end At the dop of collet, when the screw on dop machines, screw just can directly directly be realized by air blowing process The process of blanking;Fixed seat 12 is played a supporting role;Bearing connection 11 mainly plays linking main shaft and the high speed of fixed seat 12 Rotate and guide the function of air blowing steel pipe 10.Blanking blowning installation of the present utility model, it is simple in construction, it is inserted directly into existing screw In the main shaft of machining tool, and excessive area is not take up, while does not need manipulator to carry out the blanking of screw, that is, improved Operating efficiency, reduce the loss of energy again.
Fig. 2 is further regarded to, bearing connection 11 includes concave part 111 and bearing portion 112, and main shaft is set in bearing portion 112 outer surfaces, concave part 111 protrude from bearing portion 112 and are more than the groove of large through-hole provided with radius, and bearing position 15 is contained in recessed In groove portion 111.
In the present embodiment, fixed seat 12 includes fixed part 121, connecting portion 122 and elongated portion 123, fixed part 121 with Air pump is fixedly connected, and connecting portion 122 is contained in the groove of concave part 111, elongated portion 123 insert large through-hole in and with air blowing steel Pipe 10 communicates.
In the present embodiment, the blanking blowning installation also includes air pump connector 13 and gasket seal 14, air pump connection The one end of part 13 is communicated by gasket seal 14 with air pump, and the other end of air pump connector 13 is connected with fixed seat 12, air pump connection The both ends connector of part 13 is mutually perpendicular to.
In the present embodiment, air blowing steel pipe 10 includes the first steel pipe portion 101 and the second steel pipe portion 102, the first steel pipe portion 101 internal diameter and external diameter is more than the internal diameter and external diameter in the second steel pipe portion 102, the one end in the first steel pipe portion 101 and fixed seat 12 elongated portion 123 is connected, and the other end in the first steel pipe portion 101 is connected with the one end in the second steel pipe portion 102, the second steel pipe portion At dop in 102 other end insertion C-shaped spring clamp head.
Disclosed above is only several specific embodiments of the present utility model, but the utility model is not limited to this, The changes that any person skilled in the art can think of should all fall into the scope of protection of the utility model.

Claims (5)

1. a kind of blanking blowning installation, it is characterised in that including air blowing steel pipe, bearing position, bearing connection, fixed seat and gas Pump, the fixed seat center offer small through hole, and the bearing connection center offers large through-hole, described fixed seat one end with Air pump communicates, and in the large through-hole of the fixed seat other end insertion bearing connection, the bearing position is clamped in bearing connection Between fixed seat, one end of the air blowing steel pipe is docked through bearing connection and with small through hole, the air blowing steel pipe it is another One end is through main shaft and inserts at the dop of C-shaped spring clamp head;Screw on dop machines rear dop and unclamped, in air pump Gas is exported by air blowing steel tube end part and is blown off screw.
2. blanking blowning installation according to claim 1, it is characterised in that the bearing connection include concave part and Bearing portion, main shaft are set in the bearing portion outer surface, and the concave part protrudes from bearing portion and is more than large through-hole provided with radius Groove, the bearing position is contained in concave part.
3. blanking blowning installation according to claim 2, it is characterised in that the fixed seat includes fixed part, connecting portion And elongated portion, the fixed part are fixedly connected with air pump, the connecting portion is contained in the groove of concave part, the elongated portion Communicated in insertion large through-hole and with air blowing steel pipe.
4. blanking blowning installation according to claim 3, it is characterised in that the blanking blowning installation also includes air pump and connected Part and gasket seal, described air pump connector one end is communicated by gasket seal with air pump, and the air pump connector is another End is connected with fixed seat, and the both ends connector of the air pump connector is mutually perpendicular to.
5. blanking blowning installation according to claim 4, it is characterised in that the air blowing steel pipe include the first steel pipe portion with And the second steel pipe portion, the internal diameter and external diameter in the first steel pipe portion are more than the internal diameter and external diameter in the second steel pipe portion, described the The one end in one steel pipe portion is connected with the elongated portion of fixed seat, the other end in the first steel pipe portion and one end phase in the second steel pipe portion Even, at the dop in the other end insertion C-shaped spring clamp head in the second steel pipe portion.
CN201720553708.9U 2017-05-18 2017-05-18 Blanking blowning installation Active CN206717505U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720553708.9U CN206717505U (en) 2017-05-18 2017-05-18 Blanking blowning installation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720553708.9U CN206717505U (en) 2017-05-18 2017-05-18 Blanking blowning installation

Publications (1)

Publication Number Publication Date
CN206717505U true CN206717505U (en) 2017-12-08

Family

ID=60513480

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720553708.9U Active CN206717505U (en) 2017-05-18 2017-05-18 Blanking blowning installation

Country Status (1)

Country Link
CN (1) CN206717505U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110434606A (en) * 2019-09-04 2019-11-12 苏州台皇鑫精密机械有限公司 A kind of full-automatic wheat drawing screw kludge

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110434606A (en) * 2019-09-04 2019-11-12 苏州台皇鑫精密机械有限公司 A kind of full-automatic wheat drawing screw kludge

Similar Documents

Publication Publication Date Title
CN202655967U (en) Fixture for clamping external threaded shaft and sleeve workpieces
CN207642687U (en) A kind of 135 ° of connector turning clamping and positioning devices
CN105729300A (en) Clamp for cylindrical grinding of hollow shaft
CN201055919Y (en) Bore processing clamper
CN206717505U (en) Blanking blowning installation
CN207087407U (en) Hole processing clamp in a kind of thin-walled parts for numerically controlled lathe
CN104368861A (en) High-rigidity knife handle device
CN110977563A (en) Clamping tool for tubular workpiece
CN203509163U (en) Taper-shank end mill chuck of boring machine
CN204295035U (en) A kind of high rigidity handle device
CN210649696U (en) Floating clamping device for machining outer circle of connecting rod by lathe
CN201791996U (en) Connecting rod flat end surface clamp with included angle
CN209632597U (en) A kind of grip device of lathe process thin-wall circular dish type cavity mechanical part
CN202399049U (en) Device for automatically centering and clamping shaft parts
CN214490615U (en) Industrial robot writes frock of calligraphy
CN204867526U (en) Clamping device of lathe tailstock drilling instrument
CN220901927U (en) Bushing counting tool
CN216228015U (en) Clamp for machining ring parts by numerical control lathe
CN213888369U (en) Quick tool changing structure for boring machine
CN203887253U (en) Outwards-pressing-type inner expansion clamp cover
CN204565190U (en) The device of clamping processing tubing inner bore of part
CN210254325U (en) Internal expanding lathe fixture
CN204397382U (en) A kind of drill jig
CN203426756U (en) Axial positioning device for lathe machining
CN203140848U (en) ID type oversized large-headed drill special for printed circuit board (PCB)

Legal Events

Date Code Title Description
GR01 Patent grant