CN206616868U - A kind of build concrete pours device - Google Patents
A kind of build concrete pours device Download PDFInfo
- Publication number
- CN206616868U CN206616868U CN201720262860.1U CN201720262860U CN206616868U CN 206616868 U CN206616868 U CN 206616868U CN 201720262860 U CN201720262860 U CN 201720262860U CN 206616868 U CN206616868 U CN 206616868U
- Authority
- CN
- China
- Prior art keywords
- discharge pipe
- storage device
- concrete
- rotating machine
- electric rotating
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
Device, including storage device, and the lowering or hoisting gear being connected with storage device are poured the utility model discloses a kind of build concrete;Storage device is provided with agitating device, and agitating device is connected with electric rotating machine;Storage device side is connected with discharge pipe, and discharge pipe is connected with concrete pouring pump, and the end of discharge pipe is provided with discharging control valve plate;The lowering or hoisting gear, electric rotating machine and concrete pouring pump are connected with controller respectively.The utility model drives agitating device the concrete is constantly overturn by electric rotating machine, it is to avoid concrete produces lamination during standing;No longer need workman to support discharge pipe, whole work progress controls controller by a people, improves speed of perfusion, greatly reduce construction cost and labor intensity, improve concrete pouring construction efficiency.
Description
Technical field
The utility model is related to construction engineering technical field, more particularly to a kind of build concrete pours device.
Background technology
In building engineering, concrete structure construction, intensity, deformation, the durability of concrete are combined by it
Property reach jointly, then it is its premise that good concrete material, which is provided, but in construction, the dress of concreting
Put many people of needs to coordinate, workman is needed when especially pouring to support discharge pipe, low production efficiency.
The content of the invention
To solve the above problems, the utility model, which provides a kind of build concrete, pours device.
The technical solution of the utility model is:
A kind of build concrete, which pours device, includes storage device, and the lowering or hoisting gear being connected with storage device;Storage
Material device is provided with agitating device, and agitating device is connected with electric rotating machine;Storage device side is connected with discharge pipe, goes out
Pipe material is connected with concrete pouring pump, and the end of discharge pipe is provided with discharging control valve plate;The lowering or hoisting gear, electric rotating
Machine and concrete pouring pump are connected with controller respectively.
The storage device is provided with charging aperture.
The diameter of the charging aperture is sequentially reduced from top to bottom.
The storage device is provided with exhaust outlet.
The discharge pipe uses flexible pipeline.
The discharge pipe is provided with the liftable support with universal wheel.Screens groove is provided with liftable support, is used for
Fixed discharge pipe.
The lowering or hoisting gear uses electric hoist.
Relative to prior art, the utility model beneficial effect is:In concreting, concrete is entered by charging aperture
Enter storage device of the present utility model, in storage device, electric rotating machine drives agitating device concrete is constantly overturn, it is to avoid
Concrete produces lamination during standing;It is required during by operating lowering or hoisting gear that storage device risen into concrete construction
The height wanted, opens concreting pump, and discharge pipe is placed into the position for needing to pour, and adjusts the liftable of discharge pipe
Support starts to inject concrete to proper height.No longer need workman to support discharge pipe, whole work progress is controlled by a people
Controller processed, improves speed of perfusion, greatly reduces construction cost and labor intensity, improves concrete pouring construction effect
Rate.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model.
Wherein, 1 is storage device;2 be charging aperture;3 be lowering or hoisting gear;4 be agitating device;5 be electric rotating machine;6 be control
Device processed;7 be discharge pipe;8 be concrete pouring pump;9 be control valve plate.
Embodiment
As shown in Figure 1, a kind of build concrete, which pours device, includes storage device 1, and is connected with storage device 1
Lowering or hoisting gear 3;The bottom of storage device 1 is provided with agitating device 4, and agitating device 4 is connected with electric rotating machine 5;Storage device 1 one
Side is connected with discharge pipe 7, and discharge pipe 7 is connected with concrete pouring pump 8, and the end of discharge pipe 7 is provided with discharging
Control valve plate 9;Lowering or hoisting gear 3, electric rotating machine 5 and concrete pouring pump 8 are connected with controller 6 respectively.
Storage device 1 is provided with charging aperture 2.The diameter of charging aperture 2 is sequentially reduced from top to bottom.Storage device 1 is provided with row
Gas port.Discharge pipe 7 uses flexible pipeline.Discharge pipe 7 is provided with the liftable support with universal wheel.On liftable support
Screens groove is provided with, for fixing discharge pipe.Lowering or hoisting gear 3 uses electric hoist.
In concreting, concrete enters storage device 1 of the present utility model by charging aperture 2, in storage device 1
In, electric rotating machine 5 drives agitating device 4 concrete is constantly overturn, it is to avoid concrete produces lamination;Risen by operating
The height required when storage device 1 risen into concrete construction of falling unit 3, under gravity, accelerates concrete and exists
Flowing velocity in discharge pipe, while opening concreting pump 8, discharge pipe 7 is placed into the position for needing to pour, adjusted
The liftable support of whole discharge pipe 7 starts to inject concrete to proper height.Whole work progress controls controller by a people
6, speed of perfusion is improved, construction cost and labor intensity is greatly reduced, concrete pouring construction efficiency is improved.
Above-described is only preferred embodiment of the present utility model, it is noted that for those skilled in the art
For, under the premise of the utility model general idea is not departed from, some changes and improvements can also be made, these should also be considered as
Protection domain of the present utility model.
Claims (7)
1. a kind of build concrete pours device, it is characterised in that:It includes storage device, and is connected with storage device
Lowering or hoisting gear;Storage device is provided with agitating device, and agitating device is connected with electric rotating machine;Storage device side is connected with
Discharge pipe, discharge pipe is connected with concrete pouring pump, and the end of discharge pipe is provided with discharging control valve plate;The lifting
Device, electric rotating machine and concrete pouring pump are connected with controller respectively.
2. a kind of build concrete according to claim 1 pours device, it is characterised in that:The storage device is set
There is charging aperture.
3. a kind of build concrete according to claim 2 pours device, it is characterised in that:The diameter of the charging aperture
It is sequentially reduced from top to bottom.
4. a kind of build concrete according to claim 1 pours device, it is characterised in that:The storage device is provided with
Exhaust outlet.
5. a kind of build concrete according to claim 1 pours device, it is characterised in that:The discharge pipe is used
Flexible pipeline.
6. a kind of build concrete according to claim 1 pours device, it is characterised in that:The discharge pipe is set
There is the liftable support with universal wheel.
7. a kind of build concrete according to claim 1 pours device, it is characterised in that:The lowering or hoisting gear is used
Electric hoist.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720262860.1U CN206616868U (en) | 2017-03-17 | 2017-03-17 | A kind of build concrete pours device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720262860.1U CN206616868U (en) | 2017-03-17 | 2017-03-17 | A kind of build concrete pours device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206616868U true CN206616868U (en) | 2017-11-07 |
Family
ID=60233183
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720262860.1U Expired - Fee Related CN206616868U (en) | 2017-03-17 | 2017-03-17 | A kind of build concrete pours device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206616868U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110670594A (en) * | 2019-10-22 | 2020-01-10 | 国家电网有限公司 | Installation device of precast concrete tubular pile for overhead transmission line |
CN115584860A (en) * | 2022-10-11 | 2023-01-10 | 中国水利水电第六工程局有限公司 | Large-volume concrete pouring device and method |
-
2017
- 2017-03-17 CN CN201720262860.1U patent/CN206616868U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110670594A (en) * | 2019-10-22 | 2020-01-10 | 国家电网有限公司 | Installation device of precast concrete tubular pile for overhead transmission line |
CN115584860A (en) * | 2022-10-11 | 2023-01-10 | 中国水利水电第六工程局有限公司 | Large-volume concrete pouring device and method |
CN115584860B (en) * | 2022-10-11 | 2024-05-28 | 中国水利水电第六工程局有限公司 | Large-volume concrete pouring device and method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206616868U (en) | A kind of build concrete pours device | |
CN205653092U (en) | Tower crane of band plate material bracket | |
CN105507593A (en) | Multifunctional fast concrete pouring device | |
CN204342298U (en) | A kind of double track transfer crane | |
CN105387722A (en) | Vertical transportation method for refractory material in dual-chamber lime kiln chamber | |
CN103938900B (en) | Construction method of cooling tower and tower crane | |
CN203795865U (en) | Lifting tumbling barrel for super-high concrete casting | |
CN204456814U (en) | Plain type staircase hoistway operation platform | |
CN208054741U (en) | A kind of Large Precast Members hoisting and overturning device | |
CN207312995U (en) | One kind self-control bridge-collision-avoidance wall form hanging device | |
CN207224204U (en) | A kind of porous shale brick molding machine | |
CN217079730U (en) | Long arm type concrete bucket pouring device | |
CN206953259U (en) | A kind of concrete door sprinkling curing system | |
CN209261225U (en) | A kind of tool for pouring concrete into steel column | |
CN205036086U (en) | A hopper for concreting | |
CN207727580U (en) | A kind of position control and steel reinforcement cage positioning device | |
CN203320922U (en) | Supporting device for forming of elevator shaft template | |
CN207596350U (en) | A kind of forklift boom hoisting | |
CN205222519U (en) | Simple and easy rotatory bull ladle device | |
CN206882780U (en) | Casting auxiliary car | |
CN206128625U (en) | Smooth empty reverse mould device | |
CN207645633U (en) | A kind of reversal hanger for Rectangular Tunnel combined type section of jurisdiction | |
CN204914235U (en) | Novel mortar jar | |
CN207713332U (en) | A kind of concrete conveyance frame | |
CN206487146U (en) | A kind of construction site brick water drenching equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20171107 Termination date: 20180317 |
|
CF01 | Termination of patent right due to non-payment of annual fee |