CN206531493U - A kind of mining tunnel top plate displacement monitor - Google Patents
A kind of mining tunnel top plate displacement monitor Download PDFInfo
- Publication number
- CN206531493U CN206531493U CN201621467532.7U CN201621467532U CN206531493U CN 206531493 U CN206531493 U CN 206531493U CN 201621467532 U CN201621467532 U CN 201621467532U CN 206531493 U CN206531493 U CN 206531493U
- Authority
- CN
- China
- Prior art keywords
- bar body
- anchor bar
- spring
- top plate
- pressure sensor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Force Measurement Appropriate To Specific Purposes (AREA)
Abstract
The utility model specifically provides a kind of top plate displacement monitor for having and monitoring roadway roof displacement situation.Anchor bar body, anchor rod pallet board, nut, high sensitivity spring, pressure sensor are monitored including roadway roof displacement.Anchor bar body is fixed on back by using the mode of end anchorage, particular pallet is fixed on back by way of individually fixing through anchor bar body exposed junction, another pallet is installed in anchor bar body end head and fixation simultaneously, make to leave certain spacing between two pallets, high sensitivity spring is installed between, and pressure sensor is fixed between top tray and spring, the sinking of top tray is driven by top plate, the rock deformation pressure for generation of sinking is reached into pressure sensor by high sensitivity spring, thus the sinking displacement of back is calculated.This apparatus structure is simple, it is easy to accomplish.
Description
Technical field
The utility model is related to a kind of displacement monitoring technology of back, is supervised for the displacement of coal mine tunnel top board
A kind of method surveyed.
Background technology
In the colliery digging production process, back is suddenly pressed, caused strata behaviors, roadway in the roof from
Layer, so that inducing safety in production of the impact accident to colliery brings huge potential safety hazard, to reduce coal mine roof plate accident
Occur, with greater need for the monitoring strengthened to back.
The content of the invention
The purpose of this utility model is exactly to set up a kind of roadway roof displacement monitoring device, realizes that roadway roof displacement sinks
The real-time monitoring of amount.
To achieve the above object, the utility model takes following technical scheme.
A kind of roadway roof displacement amount monitoring technology, device mainly includes roadway roof displacement and monitors anchor bar body, anchor pole support
Disk, nut, high sensitivity spring, pressure sensor.Described spring displacement pressure sensor includes going deep into back
The anchor bar body in deep, described anchor bar body front end carries out end anchorage, and the rear end of described anchor bar body is provided with two end pallets,
Described one of end pallet, being fixed on by anchor bar body separately through nut on the top plate in tunnel makes anchor bar body and support
Disk is fixed on the end head of anchor bar body, two described pallets by nut without constant connection, another described end pallet
Between install and fix a high sensitivity spring, between the pallet that described spring is connected with top plate install pressure sensing member
Part.
The roadway roof displacement monitoring technology that the utility model is used further is configured, will using pressure sensor
Deformation force suffered by highly sensitive spring is exported.
The technical scheme provided from the utility model, mining tunnel top plate displacement monitor, by by anchor bar body
Front end is anchored in the rock stratum of top plate deep, in the exposed junction of anchor bar body, is reinforced top special trays in top through anchor bar body
On slate layer, lower tray is fixed on anchor bar body end by nut, makes to leave 5cm distance between two pallets, and holding in the palm
High sensitivity spring is installed, while installing pressure sensor between top tray and spring between disk.By this device, work as top
Slate layer is subjected to displacement, and high sensitivity spring stress is indicated the stressing conditions of spring by pressure sensor, so as to calculate top
The displacement of plate.The present apparatus is simple in construction and is easily achieved.
Brief description of the drawings
Fig. 1 is the top plate displacement monitor structural representation that the utility model is used:
Figure description of symbols:1st, anchor bar body;2nd, upper tray;3rd, pressure sensor;4th, high sensitivity spring;5th, bottom is held in the palm
Disk;6th, nut;7th, pressure display unit.
Embodiment
The embodiment of the present invention is described in further details below in conjunction with accompanying drawing.
The utility model include anchor bar body 1, upper tray 2, pressure sensor 3, high sensitivity spring 4, bottom tray 5,
Nut 6, pressure display unit 7, described its upper end of anchor bar body 1 go deep into back rock stratum deep and carry out end anchorage, described
Upper tray 2 through anchor bar body individually reinforce on roof strata, described bottom tray 5 is fixed on anchor by nut 6
The external end head of the body of rod 1, described high sensitivity spring is fixed between upper tray 2 and lower tray 5, described pressure sensing
Device 3 is fixed between top tray 2 and high sensitivity spring 4.By the external pressure display unit 7 of pressure sensor 3, so as to show Gao Ling
Rock deformation pressure suffered by sensitivity spring 4, and then the displacement that crushes is calculated according to elastic deformation Hooke's law.
The described upper end of anchor bar body 1 is goed deep into the rock stratum of back, carries out end anchorage.
Described upper tray 2, through anchor bar body 1 and can not be fixed on top plate with the contact of anchor bar body effectively.
Described high sensitivity spring 4 be connected with pressure sensor 3 and be fixed on upper tray 2 and lower tray 5 it
Between.
Described pressure sensor 3 is connected with pressure display unit 7, can show the high sensitivity bullet caused by crushing
The rock deformation pressure that spring deformation is produced.
Deep anchor pole head is anchored in the stable rock stratum in deep when the utility model is operated, when superficial part rock deformation is produced
During displacement can significantly compression spring, and then rock deformation pressure is transferred to pressure sensor and information is gathered, shown by pressure
The delivery spring rock deformation pressure of device 7.Pressure display unit 7 is attached into the two of tunnel to help to be easy to reading, record data at position.
The utility model is simple in construction, and the installment work of device just can be synchronously carried out when tunnel carries out driving supporting,
It is easily installed, it is easy to accomplish.By the pressure display unit of roadway's sides, it is easy to observe data.
More than embodiment be only the utility model preferably embodiment, but creation of the present utility model
This is not limited merely to, every any modification carried out within this creation principal, equivalent substitution are all contained in this creation
Within protection domain.
Claims (3)
1. a kind of mining tunnel top plate displacement monitor, its device mainly includes spring displacement pressure sensor, described
Spring displacement pressure sensor includes the anchor bar body for going deep into back deep, and described anchor bar body front end carries out termination anchor
Gu, the rear end of described anchor bar body is provided with two end pallets, and described one of end pallet is individually led to by anchor bar body
Crossing nut and being fixed on the top plate in tunnel makes anchor bar body with pallet without constant connection, and another described end pallet passes through
Nut, which is fixed between the end head of anchor bar body, two described pallets, installs and fixes a high sensitivity spring, described
The pallet that is connected with top plate of spring between pressure sensor is installed.
2. mining tunnel top plate displacement monitor as claimed in claim 1, it is characterised in that:Described high sensitivity spring
It is installed between upper tray and lower tray.
3. mining tunnel top plate displacement monitor as claimed in claim 2, it is characterised in that:Described pressure sensor
It is installed between upper tray and high sensitivity spring.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621467532.7U CN206531493U (en) | 2016-12-29 | 2016-12-29 | A kind of mining tunnel top plate displacement monitor |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621467532.7U CN206531493U (en) | 2016-12-29 | 2016-12-29 | A kind of mining tunnel top plate displacement monitor |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206531493U true CN206531493U (en) | 2017-09-29 |
Family
ID=59917542
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621467532.7U Expired - Fee Related CN206531493U (en) | 2016-12-29 | 2016-12-29 | A kind of mining tunnel top plate displacement monitor |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206531493U (en) |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108050987A (en) * | 2017-12-29 | 2018-05-18 | 天地科技股份有限公司 | Tunnel surface layer displacement monitor |
CN109238161A (en) * | 2018-09-21 | 2019-01-18 | 中国矿业大学 | A kind of observation device and observation method of tunnel surface absolute convergence amount |
CN109405785A (en) * | 2018-12-19 | 2019-03-01 | 石家庄铁道大学 | The determination method of side slope vibration displacement change monitoring device and slope displacement |
CN109631824A (en) * | 2018-12-20 | 2019-04-16 | 中国矿业大学 | A kind of tunnel is met head on empty top zone roof deformation amount monitoring device and method |
CN110470273A (en) * | 2019-09-19 | 2019-11-19 | 河南理工大学 | A kind of back sinking measurement ball monitoring method based on pressure difference |
CN111006574A (en) * | 2019-11-15 | 2020-04-14 | 山东科技大学 | Equipment and method for measuring displacement of roadway wall part |
CN111456787A (en) * | 2020-04-20 | 2020-07-28 | 辽宁工程技术大学 | Surrounding rock gradient deformation monitoring device based on scour prevention anchor cable and impact early warning method |
CN111852526A (en) * | 2020-06-04 | 2020-10-30 | 河北建筑工程学院 | Length-adjustable real-time monitoring anchor rod device |
CN112361923A (en) * | 2020-11-04 | 2021-02-12 | 华北科技学院 | Measuring device for monitoring coal mine tunnel roof deviation |
CN113804149A (en) * | 2021-08-23 | 2021-12-17 | 鞍钢集团矿业有限公司 | Monitoring and early warning device and method for stability of roadway roof |
WO2022056755A1 (en) * | 2020-09-17 | 2022-03-24 | 陈剑 | Geometric quantity measurement method and device |
CN114495455A (en) * | 2022-03-02 | 2022-05-13 | 中煤天津设计工程有限责任公司 | Mining tunnel roof surrounding rock displacement monitoring alarm device |
-
2016
- 2016-12-29 CN CN201621467532.7U patent/CN206531493U/en not_active Expired - Fee Related
Cited By (17)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108050987B (en) * | 2017-12-29 | 2019-12-10 | 天地科技股份有限公司 | Roadway surface displacement monitoring device |
CN108050987A (en) * | 2017-12-29 | 2018-05-18 | 天地科技股份有限公司 | Tunnel surface layer displacement monitor |
CN109238161A (en) * | 2018-09-21 | 2019-01-18 | 中国矿业大学 | A kind of observation device and observation method of tunnel surface absolute convergence amount |
CN109405785A (en) * | 2018-12-19 | 2019-03-01 | 石家庄铁道大学 | The determination method of side slope vibration displacement change monitoring device and slope displacement |
CN109631824A (en) * | 2018-12-20 | 2019-04-16 | 中国矿业大学 | A kind of tunnel is met head on empty top zone roof deformation amount monitoring device and method |
CN110470273B (en) * | 2019-09-19 | 2021-07-09 | 河南理工大学 | Roadway roof subsidence measuring ball monitoring method based on pressure difference |
CN110470273A (en) * | 2019-09-19 | 2019-11-19 | 河南理工大学 | A kind of back sinking measurement ball monitoring method based on pressure difference |
CN111006574A (en) * | 2019-11-15 | 2020-04-14 | 山东科技大学 | Equipment and method for measuring displacement of roadway wall part |
CN111456787A (en) * | 2020-04-20 | 2020-07-28 | 辽宁工程技术大学 | Surrounding rock gradient deformation monitoring device based on scour prevention anchor cable and impact early warning method |
CN111852526A (en) * | 2020-06-04 | 2020-10-30 | 河北建筑工程学院 | Length-adjustable real-time monitoring anchor rod device |
WO2022056755A1 (en) * | 2020-09-17 | 2022-03-24 | 陈剑 | Geometric quantity measurement method and device |
CN112361923A (en) * | 2020-11-04 | 2021-02-12 | 华北科技学院 | Measuring device for monitoring coal mine tunnel roof deviation |
CN112361923B (en) * | 2020-11-04 | 2022-02-01 | 华北科技学院 | Measuring device for monitoring coal mine tunnel roof deviation |
CN113804149A (en) * | 2021-08-23 | 2021-12-17 | 鞍钢集团矿业有限公司 | Monitoring and early warning device and method for stability of roadway roof |
CN113804149B (en) * | 2021-08-23 | 2023-07-21 | 鞍钢集团矿业有限公司 | Monitoring and early warning device and method for stability of roadway roof |
CN114495455A (en) * | 2022-03-02 | 2022-05-13 | 中煤天津设计工程有限责任公司 | Mining tunnel roof surrounding rock displacement monitoring alarm device |
CN114495455B (en) * | 2022-03-02 | 2023-08-22 | 中煤天津设计工程有限责任公司 | Mining tunnel roof surrounding rock displacement monitoring alarm device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206531493U (en) | A kind of mining tunnel top plate displacement monitor | |
CN102644482B (en) | Rock burst predicting and warning method | |
CN102587983B (en) | Comprehensive early-warning observation method for coal mine rock burst | |
CN205562534U (en) | Low coverage coal seam group bao shui exploitation simulation modeling experiment device | |
CN105759010B (en) | A kind of dynamic monitoring of mining influence tunnel and Stability Assessment method | |
Ding et al. | Strata behavior investigation for high-intensity mining in the water-rich coal seam | |
CN102455434A (en) | Monitoring method of working-face coal-body advanced stress | |
CN103321677A (en) | Method for actively controlling motion of coal mine critical layers by using strip filling walls | |
CN104089595B (en) | Stope base object model ruptures determination of distance method in advance | |
Zhang et al. | Mechanism of coal bump induced by joint slipping under static and dynamic stresses in graben structural area | |
CN202362466U (en) | Height detecting device for water flowing fracture zone on coal extraction working surface | |
CN106494460A (en) | The high ferro subgrade stability method for early warning in Strong tremor region | |
Turcotte | Practical applications of a rockburst database to ground support design at LaRonde Mine | |
CN205477749U (en) | Colliery anti -counterfeiting pushes up early warning device based on laser detection technology | |
CN202467929U (en) | On-line monitoring system for performance of filling body | |
CN109813465B (en) | Roadway surrounding rock stress in-situ dynamic monitoring device and working method | |
CN109506601A (en) | The quick detection device and its detection method of underground engineering top plate thickness | |
CN203430546U (en) | Roadway roof protective net of coal face | |
CN202485845U (en) | Device for monitoring lateral bearing pressure of stoping tunnel | |
CN102589763B (en) | Performance online monitoring system for filler | |
CN106290016B (en) | A kind of underground air impact disaster experimental rig | |
CN205537570U (en) | Liquid crystal display roof separation layer appearance | |
CN206360403U (en) | A kind of coal mine gob transformer station strut | |
CN209432084U (en) | The quick detection device of underground engineering top plate thickness | |
CN205477746U (en) | Monitoring instrument for heaving floor of coal mine tunnel |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170929 Termination date: 20171229 |
|
CF01 | Termination of patent right due to non-payment of annual fee |