CN206495142U - A kind of overhead pier column operation platform of assembled - Google Patents

A kind of overhead pier column operation platform of assembled Download PDF

Info

Publication number
CN206495142U
CN206495142U CN201720175143.5U CN201720175143U CN206495142U CN 206495142 U CN206495142 U CN 206495142U CN 201720175143 U CN201720175143 U CN 201720175143U CN 206495142 U CN206495142 U CN 206495142U
Authority
CN
China
Prior art keywords
platform
ring skeleton
platform unit
cat ladder
skeleton
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720175143.5U
Other languages
Chinese (zh)
Inventor
阙家奇
张建军
王其炎
杨勇
晏代泓
张超峰
陶然位
吴健
张明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Communications Construction Group Co Ltd
Original Assignee
Zhejiang Communications Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Communications Construction Group Co Ltd filed Critical Zhejiang Communications Construction Group Co Ltd
Priority to CN201720175143.5U priority Critical patent/CN206495142U/en
Application granted granted Critical
Publication of CN206495142U publication Critical patent/CN206495142U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model is related to a kind of overhead pier column operation platform of assembled, the multiple platform units for being superimposed and linking together including longitudinal direction, platform unit includes lateral frame and inner frame, lateral frame is made up of outermost side floor panels ring skeleton, lateral roof ring skeleton and multiple outer heel posts, and inner frame is made up of inner side bottom plate ring skeleton, inner side top plate ring skeleton and multiple interior heel posts;Provided with the people's row cat ladder for leading to platform unit top surface from platform unit bottom surface between lateral frame and inner frame, people's row cat ladder includes cat ladder skeleton and the multiple step on cat ladder skeleton, the upper side opening of platform unit, is stacked between multiple platform units after assembly and is connected by people's row cat ladder.The utility model is obtained by prefabricated multiple platform unit assembly, be instead of traditional scaffold building technique, has effectively been ensured construction safety, while saving artificial take splits into this, and can be repeatedly used in turn.

Description

A kind of overhead pier column operation platform of assembled
Technical field
This is related to engineering construction field, more particularly to a kind of overhead pier column operation platform of assembled using new.
Background technology
With the development of the society, economic fast development, resident trip takes a bus instead of walking, magnitude of traffic flow first mate increase, traffic Congestion has increasingly restricted the development in city.Because overpass can make full use of city space, there is alleviation urban highway traffic Obstruction, the function of improving urban traffic conditions so that it flourishes in each big city, and pier stud is one of overpass important Structure, its construction technology has vital effect to construction quality and safety.
At present, the most frequently used way of pier stud construction is using external scaffolding is set up as operation platform, because setting up scaffold Globality requires that high, steel pipe consumption is big, and needs one to take one per pier to tear open, and low construction efficiency seriously governs the construction speed of pier stud. And because workmen needs to carry constructing operation equipment on scaffold during operation, therefore there is larger potential safety hazard.
The content of the invention
In order to solve the above problems, it is an object of the invention to provide a kind of mechanization degree height, take and tear convenient and beneficial open In the overhead pier column operation platform of assembled for improving working security.
In order to realize above-mentioned purpose, present invention employs following technical scheme:
A kind of overhead pier column operation platform of assembled, including multiple platform units that longitudinal direction is superimposed and linked together, Platform unit include lateral frame and inner frame, lateral frame by outermost side floor panels ring skeleton, lateral roof ring skeleton and Multiple outer heel posts are constituted, and inner frame is by inner side bottom plate ring skeleton, inner side top plate ring skeleton and multiple interior heel post structures Into interior heel post is identical with outside stem height, and inner side bottom plate ring skeleton is located at platform unit with outermost side floor panels ring skeleton Bottom surface in, inner side top plate ring skeleton and lateral roof ring skeleton are located in the top surface of platform unit, from platform unit Both sides are seen up and down, and inner frame is distributed with lateral frame by " returning " font;It is provided between lateral frame and inner frame from platform Lead to people's row cat ladder of platform unit top surface for unit bottom surface, and people's row cat ladder includes cat ladder skeleton and on cat ladder skeleton Multiple step, the upper side opening of platform unit is stacked between multiple platform units after assembly and connected by people's row cat ladder.
As optimal technical scheme, the upper and lower ends of lateral frame and inner frame are respectively equipped with bolted connection, and The bolted connection of both sides is corresponded to two-by-two up and down, and two neighbouring platform units coordinate fixed connect by bolt and pad Connect.
As optimal technical scheme, add between outermost side floor panels ring skeleton and lateral roof ring skeleton provided with multiple Strengthening tendons.
As optimal technical scheme, the lateral surface of lateral frame installs protection network, and being provided with protection network is used for constructor The opening of member's turnover.
As optimal technical scheme, door is installed at the opening on protection network.
As optimal technical scheme, platform unit is using the processing of standardization section.
As optimal technical scheme, the height of platform unit is 2m.
The overhead pier column operation platform of assembled of the present utility model, is obtained by prefabricated multiple platform unit assembly, Height is highly connect using the overall assembly section by section of crane gear with pier stud, traditional scaffold building technique is instead of, it is effective to ensure Construction safety, while saving artificial take splits into this, and can repeatedly be used in turn, remarkable in economical benefits.It is high to meet different pier studs Spend construction requirement and convenient to assemble and disassemble, platform unit is using the processing of standardization section, according to the exercisable maximum height of workman's standing, The height of platform unit is 2m.According to specific pier stud construction height, spreading operation platform can complete pier stud each operation and apply section by section Work, mechanization degree is high, and peace is torn open rapid.
Brief description of the drawings
Fig. 1 is the structural representation of platform unit in the utility model.
Mounting structure schematic diagram when Fig. 2 is the utility model construction.
Embodiment
The preferred embodiment to this patent is described in further detail below in conjunction with the accompanying drawings.
As depicted in figs. 1 and 2, the overhead pier column operation platform of assembled includes multiple platform lists that longitudinal direction is superimposed Fixation is bolted between member, multiple platform units.Platform unit includes lateral frame 1 and inner frame 2, wherein outside Framework 1 is made up of at least four outer heel posts 11, an outermost side floor panels ring skeleton 12 and a lateral roof ring skeleton 13, Inner frame 2 is by least one interior heel post 21, an inner side bottom plate ring skeleton 22 and an inner side top plate ring skeleton 23 Constitute, interior heel post 21 is parallel and highly identical with outer heel post 11, inner side bottom plate ring skeleton 22 and outermost side floor panels ring bone Frame 12 is located in the bottom surface of platform unit 1, and inner side top plate ring skeleton 23 is located at platform unit 1 with lateral roof ring skeleton 13 Top surface in, inner frame 2 is located at the inner side of lateral frame 1 and both center superpositions, interior in terms of the both sides up and down of platform unit Body side frame is distributed with lateral frame by " returning " font.
The inner space that inner frame 2 is surrounded is used for the reserved construction space of pier stud 6, the inside and inner side of lateral frame 1 The transit passage of the outside composition workmen of framework 2, between inner side bottom plate ring skeleton 22 and outermost side floor panels ring skeleton 12 Platform floor 4 is installed, is provided between lateral frame 1 and inner frame 2 and leads to platform unit top surface from platform unit bottom surface People's row cat ladder, people's row cat ladder includes cat ladder skeleton 31 and the multiple step 32 on cat ladder skeleton 31, described to climb The lower end of terraced skeleton 31 is fixed on outermost side floor panels ring skeleton 12 and inner side bottom plate cyclic skeleton 22, the upper end of cat ladder skeleton 31 It is fixed on lateral roof ring skeleton 13 and inner side top plate cyclic skeleton 23.The upper side opening of platform unit 1 so that stacked to spell Connected between multiple platform units after dress by people's row cat ladder.Operation platform spatial operation is big.People's row cat ladder and platform unit Using integrated setting, cat ladder skeleton 31 is weldingly fixed in inner frame and lateral frame by angle steel, and pedal 32 is from anti- Sliding steel plate is made.
The upper and lower ends of lateral frame and inner frame are respectively equipped with bolted connection 5, and the bolt of both sides connects up and down Socket part 5 is corresponded to two-by-two so that two neighbouring platform units can be coordinated by bolt and pad to be fixedly connected, and is dismantled It is convenient.Because multiple platform units need longitudinally superimposed install when in use, it is therefore desirable to which platform unit has certain support Intensity, therefore, is provided with multiple reinforcements 14 at least between outermost side floor panels ring skeleton 12 and lateral roof ring skeleton 13. Because the overall volume of inner frame 2 is relatively small, itself opposite outer framework after external pressure is received is not susceptible to become Shape, therefore can decide whether to set between inner side bottom plate ring skeleton and inner side top plate ring skeleton according to the actual requirements Reinforcement.
In order to ensure the safety of workmen, protection network is installed in the lateral surface of lateral frame and protected, construction is prevented Personnel outwards fall in construction, while the opening passed in and out for workmen is left on protection network, preferably, in opening Locate installation door.And because inner frame is reserved pier stud construction space, constructs, do not set in the side of inner frame for convenience Put protection network.
The overhead pier column operation platform of assembled of the present utility model, is obtained by prefabricated multiple platform unit assembly, Height is highly connect using the overall assembly section by section of crane gear with pier stud, traditional scaffold building technique is instead of, it is effective to ensure Construction safety, while saving artificial take splits into this, and can repeatedly be used in turn, remarkable in economical benefits.It is high to meet different pier studs Spend construction requirement and convenient to assemble and disassemble, platform unit is using the processing of standardization section, according to the exercisable maximum height of workman's standing, The height of platform unit is 2m.According to specific pier stud construction height, spreading operation platform can complete pier stud each operation and apply section by section Work, mechanization degree is high, and peace is torn open rapid.

Claims (7)

1. a kind of overhead pier column operation platform of assembled, it is characterised in that what is be superimposed and link together including longitudinal direction is multiple Platform unit, platform unit includes lateral frame(1)And inner frame(2), lateral frame(1)By outermost side floor panels ring skeleton (12), lateral roof ring skeleton(13)And multiple outer heel posts(11)Constitute, inner frame(2)By inner side bottom plate ring skeleton (22), inner side top plate ring skeleton(23)And multiple interior heel posts(21)Constitute, interior heel post(21)With outer heel post(11)It is high Spend identical, inner side bottom plate ring skeleton(22)With outermost side floor panels ring skeleton(12)In the bottom surface of platform unit, medial roof Plate ring skeleton(23)With lateral roof ring skeleton(13)In the top surface of platform unit, from the both sides up and down of platform unit See, inner frame(2)With lateral frame(1)It is distributed by " returning " font;Lateral frame(1)With inner frame(2)Between be provided with from Lead to people's row cat ladder of platform unit top surface for platform unit bottom surface, and people's row cat ladder includes cat ladder skeleton(31)And installed in cat ladder Multiple step on skeleton(32), the upper side opening of platform unit, it is stacked assembled after multiple platform units between pass through people's row Cat ladder is connected.
2. a kind of overhead pier column operation platform of assembled according to claim 1, it is characterised in that lateral frame(1) And inner frame(2)Upper and lower ends be respectively equipped with bolted connection(5), and the bolted connection of both sides up and down is right two-by-two Should, two neighbouring platform units are coordinated by bolt and pad to be fixedly connected.
3. the overhead pier column operation platform of a kind of assembled according to claim 1, it is characterised in that in outermost side floor panels ring To skeleton(12)And lateral roof ring skeleton(13)Between be provided with multiple reinforcements(14).
4. a kind of overhead pier column operation platform of assembled according to claim 1, it is characterised in that lateral frame(1) Lateral surface install protection network, on protection network be provided be used for workmen pass in and out opening.
5. a kind of overhead pier column operation platform of assembled according to claim 1, it is characterised in that opening on protection network Door is installed at mouthful.
6. the overhead pier column operation platform of a kind of assembled according to claim 1, it is characterised in that platform unit is used Standardize section processing.
7. a kind of overhead pier column operation platform of assembled according to claim 6, it is characterised in that the height of platform unit Spend for 2m.
CN201720175143.5U 2017-02-24 2017-02-24 A kind of overhead pier column operation platform of assembled Active CN206495142U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720175143.5U CN206495142U (en) 2017-02-24 2017-02-24 A kind of overhead pier column operation platform of assembled

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720175143.5U CN206495142U (en) 2017-02-24 2017-02-24 A kind of overhead pier column operation platform of assembled

Publications (1)

Publication Number Publication Date
CN206495142U true CN206495142U (en) 2017-09-15

Family

ID=59806863

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720175143.5U Active CN206495142U (en) 2017-02-24 2017-02-24 A kind of overhead pier column operation platform of assembled

Country Status (1)

Country Link
CN (1) CN206495142U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108625292A (en) * 2018-06-01 2018-10-09 浙江交工集团股份有限公司 A kind of template assembly platform of prefabricated stand column
CN110331847A (en) * 2019-07-05 2019-10-15 中铁一局集团厦门建设工程有限公司 A kind of rectangular column construction operation platform
CN114837389A (en) * 2022-05-20 2022-08-02 中国建筑第八工程局有限公司 Construction operation platform and construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108625292A (en) * 2018-06-01 2018-10-09 浙江交工集团股份有限公司 A kind of template assembly platform of prefabricated stand column
CN108625292B (en) * 2018-06-01 2024-03-15 浙江交工集团股份有限公司 Template assembling platform of prefabricated stand column
CN110331847A (en) * 2019-07-05 2019-10-15 中铁一局集团厦门建设工程有限公司 A kind of rectangular column construction operation platform
CN114837389A (en) * 2022-05-20 2022-08-02 中国建筑第八工程局有限公司 Construction operation platform and construction method

Similar Documents

Publication Publication Date Title
CN206495142U (en) A kind of overhead pier column operation platform of assembled
CN104213508B (en) A kind of method utilizing stull and external tendon to control king-post displacement
CN104763109B (en) Quick construction method for pressed bottom tile of large-span steel structure factory building roof
CN106168057A (en) A kind of assembled steel lath band combined concrete shear wall and making construction method thereof
CN207296386U (en) A kind of combining structure of construction elevator and creeping formwork frame body
CN106087750B (en) Across the stake formula of pile integrative-structure does not land the construction method of construction steel platform
CN101876209B (en) Supertall building core tube construction safety fire protection system and device
CN202611714U (en) Tunnel assembly type construction trolley without welding
CN201762974U (en) System for simultaneous construction of upper horizontal structure and lower horizontal structure in core tube
CN207314147U (en) A kind of bridge construction employment row safety climbing ladder
CN207062771U (en) A kind of H types Pier Formwork platform integrated apparatus
CN206800712U (en) A kind of power consumption assembled combined steel plate shearing force wall of strip connecting plate
CN106758741B (en) Modular box type plate beam structure and pontic erection method based on box type plate beam structure
CN105275120B (en) The light steel concrete plate-column structure of prefabrication and assembly construction and its construction method
CN207846427U (en) A kind of upper and lower walkway of assembled foundation pit
CN208965581U (en) A kind of non-console mode tower crane platform
CN204023422U (en) A kind of assembling Coping Construction operating platform
CN105755959B (en) Suitable for the Sarasota construction auxiliary stand system and building method of different cross section
CN206722211U (en) A kind of construction steel structure assembled wallboard
CN107217685A (en) A kind of Portable piping lane side wall formwork jumbo
CN107605152A (en) The combination unit and its application method of a kind of construction elevator and creeping formwork support body
CN104018586A (en) Connecting device for steel structure column and steel structure column
CN211037760U (en) Novel instrument formula elevartor shaft construction operation platform
CN211473320U (en) Tool type external hanging rack for corridor
CN207244453U (en) A kind of suspension bridge light anchorage mast apparatus

Legal Events

Date Code Title Description
GR01 Patent grant