CN206457913U - A kind of inspection shaft inner bag - Google Patents

A kind of inspection shaft inner bag Download PDF

Info

Publication number
CN206457913U
CN206457913U CN201621430263.7U CN201621430263U CN206457913U CN 206457913 U CN206457913 U CN 206457913U CN 201621430263 U CN201621430263 U CN 201621430263U CN 206457913 U CN206457913 U CN 206457913U
Authority
CN
China
Prior art keywords
inspection shaft
inner bag
courage
shaft inner
pipe joint
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621430263.7U
Other languages
Chinese (zh)
Inventor
杨小平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Wave Wave Environment Engineering Co Ltd
Original Assignee
Jiangsu Wave Wave Environment Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Wave Wave Environment Engineering Co Ltd filed Critical Jiangsu Wave Wave Environment Engineering Co Ltd
Priority to CN201621430263.7U priority Critical patent/CN206457913U/en
Application granted granted Critical
Publication of CN206457913U publication Critical patent/CN206457913U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sewage (AREA)

Abstract

The utility model belongs to water-treatment technology field, specifically related to a kind of inspection shaft inner bag, it is integrally formed, it is integrally placed in the inspection shaft basis dug and constitutes rain bilge well, including courage mouthful, courage body and courage bottom, the courage mouthful is planar structure, and the courage body is provided with pipe joint, and depth of precipitation is left in the bottom at the courage bottom and inspection shaft basis.The utility model has saved construction cost, the place short engineering time, makes the handing-over of rain bilge well and pipeline more reasonable, will not produce seepage, realize bottom plate and inspection shaft integration.

Description

A kind of inspection shaft inner bag
Technical field
The utility model belongs to water-treatment technology field, and specific utility model patent is related to a kind of inspection shaft inner bag.
Background technology
In the prior art, rain bilge well build by laying bricks or stones needs inspection shaft basis dig good and then elder generation's pouring reinforcement concrete bottom plate, Build the kinds of processes such as rendering by laying bricks or stones again and to reach that non-leakage particularly bilge well rings groundwater quality from face, and inspection shaft and pipeline Junction never has the construction method of good method (general to use box out and then pipe laying, sealing hole), so pacifies Easily there is rain effluent seepage after being completed due to geology sedimentation in dress, moreover, construction cost is high, the engineering time is long, sewage impurity Precipitation easily cause rain sewage conduct blocking.
Utility model content
The purpose of this utility model is to provide a kind of vehicle cab throttle system ergonomics test device, with solution State problem.
Embodiment of the present utility model provides a kind of inspection shaft inner bag, and it is integrally formed, and is integrally placed at the inspection shaft base dug Rain bilge well, including courage mouthful, courage body and courage bottom are constituted in plinth, courage mouthful is planar structure, and courage body is provided with pipe joint, courage bottom and basement Leave depth of precipitation in the bottom on well basis.
Further, dividing plate is provided with courage body, inspection shaft inner bag is divided into sedimentation basin and anaerobic pond by dividing plate, and sedimentation basin passes through pipeline Interface connects water inlet.
Further, inspection shaft inner bag is fiberglass-reinforced plastics detritus-tank inner bag.
Further, inspection shaft inner bag is concrete manhole inner bag.
Further, pipe joint is provided with groove and water proof ring, for being connected with seal for pipe joints.
Further, depth of precipitation is 500mm-600mm.
Embodiment of the present utility model additionally provides a kind of inspection shaft inner bag, and it is integrally formed, and is integrally placed in inspection shaft and constitutes Rain bilge well, including courage mouthful, courage body and courage bottom, courage mouthful are curved-surface structure, are recessed to courage body, for carrying pipeline, courage body is provided with Pipe joint, courage bottom away from inspection shaft shaft bottom leave in depth of precipitation, courage body be provided with dividing plate, dividing plate by inspection shaft inner bag be divided into sedimentation basin and Anaerobic pond, sedimentation basin connects water inlet by pipe joint.
Further, inspection shaft inner bag is fiberglass-reinforced plastics detritus-tank inner bag or concrete manhole inner bag.
Further, pipe joint is provided with groove and water proof ring, for being connected with seal for pipe joints.
Further, depth of precipitation is 500mm-600mm.
The beneficial effects of the utility model are compared with prior art:Construction cost is saved, the place short engineering time, has made The handing-over of rain bilge well and pipeline is more reasonable, will not produce seepage, realizes bottom plate and inspection shaft integration.
Brief description of the drawings
Fig. 1 is the structural representation of the utility model first embodiment;
Fig. 2 is the structural representation of the utility model second embodiment;
Fig. 3 is the structural representation of the utility model 3rd embodiment.
Embodiment
The utility model is described in detail shown each embodiment below in conjunction with the accompanying drawings, but it should explanation, These embodiments are not limitation of the utility model, and those of ordinary skill in the art are according to these embodiment institute works Energy, method or equivalent transformation or replacement in structure, are belonged within protection domain of the present utility model.
Join shown in Fig. 1, the present embodiment is green and environment-friendlyglass glass steel flat mouth inner bag, inner bag is integrally formed, is integrally placed at and digs Inspection shaft basis in constitute rain bilge well, including courage mouthfuls 11, courage body 12 and courage bottom, courage mouthful 11 is planar structure, using going out along knot Built by laying bricks or stones again above structure, flat mouth, courage body 12 is provided with pipe joint, depth of precipitation is left in the bottom at courage bottom and inspection shaft basis.Pipe Pipeline joint is provided with groove and water proof ring, for being connected with seal for pipe joints.Depth of precipitation is 500mm-600mm.
Join shown in Fig. 2, the present embodiment is green and environment-friendlyglass glass steel flat mouth inner bag, inner bag is integrally formed, is integrally placed at and digs Inspection shaft basis in constitute rain bilge well, inner bag matches somebody with somebody inner bag size according to the requirement of different inspection shafts, including courage mouthfuls 21, courage body 22 and Courage bottom, courage mouthfuls 21 is planar structure, using going out along structure, and courage body 22 configures multiple pipe joints, courage bottom and inspection shaft as needed Leave depth of precipitation in the bottom on basis.Dividing plate 23 is provided with courage body 22, inspection shaft inner bag is divided into sedimentation basin and anaerobic pond by dividing plate 23 Two parts, with the function such as precipitation and the processing of anaerobism Preliminary sewage, sedimentation basin connects water inlet by pipe joint.Pipe Pipeline joint is provided with groove and water proof ring, for being connected with seal for pipe joints, prevents leak.Depth of precipitation is 500mm-600mm.
Join shown in Fig. 3, the present embodiment is green and environment-friendlyglass glass steel inner bag, inner bag is integrally formed, and is integrally placed at structure in inspection shaft Into rain bilge well, including courage mouthful 31, courage body 32 and courage bottom, courage mouthful 31 is curved-surface structure, is recessed to courage body 32, for carrier pipe Road, courage body is provided with pipe joint, and courage bottom is left away from inspection shaft shaft bottom and dividing plate 33 is provided with depth of precipitation, courage body, and dividing plate 33 is by inspection shaft Inner bag is divided into sedimentation basin and anaerobic pond, and sedimentation basin connects water inlet by pipe joint.Pipe joint is provided with groove and water proof ring, For being connected with seal for pipe joints, leak is prevented.Depth of precipitation is 500mm-600mm.Compared with Fig. 2, the courage mouthful of the present embodiment is adopted With curved-surface structure, available for carrying pipeline, and good sealing effectiveness can be played.
Inner bag of the present utility model can also use armored concrete inner bag in addition to using fiberglass inner bag.
Technique effect of the present utility model includes:
1) rainwater (dirt) the well workload of earth excavation, saving engineering time and concrete floor when building by laying bricks or stones is reduced to pour Build.
2) there is the rain effluent seepage for preventing that rain (dirt) well from producing by sedimentation.
3) environmental protection can save artificial box out and sealing hole with the supporting installation of rain sewage pipe.
4) there is the impurity and anerobic sowage processing function in precipitation sewage, sewage is obtained preliminary purification.
5) ensure that each basement has the desilting area of certain volume, building by laying bricks or stones for inspection shaft is more standardized, standardize.
The a series of tool described in detail only for feasibility embodiment of the present utility model of those listed above Body illustrates that they are simultaneously not used to limit protection domain of the present utility model, all to be made without departing from the utility model skill spirit Equivalent implementations or change should be included within protection domain of the present utility model.
It is obvious to a person skilled in the art that the utility model is not limited to the details of above-mentioned one exemplary embodiment, and And in the case of without departing substantially from spirit or essential attributes of the present utility model, can realize that this practicality is new in other specific forms Type.Therefore, no matter from the point of view of which point, embodiment all should be regarded as exemplary, and is nonrestrictive, this practicality is new The scope of type limits by appended claims rather than described above, it is intended that the equivalency fallen in claim is contained All changes in justice and scope are included in the utility model.

Claims (10)

1. a kind of inspection shaft inner bag, it is characterised in that it is integrally formed, is integrally placed in the inspection shaft basis dug and constitutes rain sewage Well, including courage mouthful, courage body and courage bottom, the courage mouthful are planar structure, and the courage body is provided with pipe joint, the courage bottom and inspection shaft Leave depth of precipitation in the bottom on basis.
2. a kind of inspection shaft inner bag according to claim 1, it is characterised in that dividing plate, the dividing plate are provided with the courage body The inspection shaft inner bag is divided into sedimentation basin and anaerobic pond, the sedimentation basin connects water inlet by the pipe joint.
3. a kind of inspection shaft inner bag according to claim 1 or 2, it is characterised in that the inspection shaft inner bag is fiberglass-reinforced plastics detritus-tank Inner bag.
4. a kind of inspection shaft inner bag according to claim 1 or 2, it is characterised in that the inspection shaft inner bag is armored concrete Inspection shaft inner bag.
5. a kind of inspection shaft inner bag according to claim 3, it is characterised in that the pipe joint is provided with groove and waterproof Circle, for being connected with seal for pipe joints.
6. a kind of inspection shaft inner bag according to claim 3, it is characterised in that the depth of precipitation is 500mm-600mm.
7. a kind of inspection shaft inner bag, it is characterised in that it is integrally formed, is integrally placed in the inspection shaft basis dug and constitutes rain sewage Well, including courage mouthful, courage body and courage bottom, the courage mouthful are curved-surface structure, are recessed to the courage body, for carrying pipeline, the courage Body is provided with pipe joint, and the bottom on the courage bottom and inspection shaft basis is left and dividing plate is provided with depth of precipitation, the courage body, it is described every The inspection shaft inner bag is divided into sedimentation basin and anaerobic pond by plate, and the sedimentation basin connects water inlet by the pipe joint.
8. a kind of inspection shaft inner bag according to claim 7, it is characterised in that the inspection shaft inner bag is fiberglass-reinforced plastics detritus-tank inner bag Or concrete manhole inner bag.
9. a kind of inspection shaft inner bag according to claim 7, it is characterised in that the pipe joint is provided with groove and waterproof Circle, for being connected with seal for pipe joints.
10. a kind of inspection shaft inner bag according to claim 7, it is characterised in that the depth of precipitation is 500mm-600mm.
CN201621430263.7U 2016-12-25 2016-12-25 A kind of inspection shaft inner bag Expired - Fee Related CN206457913U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621430263.7U CN206457913U (en) 2016-12-25 2016-12-25 A kind of inspection shaft inner bag

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621430263.7U CN206457913U (en) 2016-12-25 2016-12-25 A kind of inspection shaft inner bag

Publications (1)

Publication Number Publication Date
CN206457913U true CN206457913U (en) 2017-09-01

Family

ID=59697367

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621430263.7U Expired - Fee Related CN206457913U (en) 2016-12-25 2016-12-25 A kind of inspection shaft inner bag

Country Status (1)

Country Link
CN (1) CN206457913U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106499038A (en) * 2016-12-25 2017-03-15 溧阳市后六东风玻璃钢制品有限公司 A kind of inspection shaft inner bag

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106499038A (en) * 2016-12-25 2017-03-15 溧阳市后六东风玻璃钢制品有限公司 A kind of inspection shaft inner bag

Similar Documents

Publication Publication Date Title
CN103693745B (en) A kind of enter the combined artificial wetland treatment process of river runoff pollution and device
CN202324159U (en) Combined prefabricated reinforced concrete sewage and rainwater inspection well
CN104563271A (en) Plastic inspection well and construction method thereof
CN206090779U (en) Municipal administration water supply and drainage pipeline connection structure
CN206457913U (en) A kind of inspection shaft inner bag
CN106368239A (en) Water stop structure arranged at position of expansion joint of urban underground comprehensive pipe rack and construction method of water stop structure
CN201502826U (en) Spigot-and-socket type fusing plastic pipeline
CN106499038A (en) A kind of inspection shaft inner bag
CN204352649U (en) Construction rainwater-collecting cyclic utilization system
CN102864833A (en) Application of finished plastic inspection well in outdoor drainage system
CN110093965A (en) A kind of water discharge method of construction site
CN202466544U (en) Irrigation and drainage ditch in coastal reclamation area
CN205677030U (en) A kind of drainage inspection well backfill structure
CN201400679Y (en) Prestressed steel cylinder concrete marsh gas generation tank
CN202466792U (en) Inspection well with connection short pipe
CN206319379U (en) A kind of greenery patches level distribution structure for improving water-holding capacity
CN205442832U (en) Urban rainwater sewage water purification system
CN103206009B (en) Construction method for preventing temperature deformation and leakage in glass fiber reinforced mortar sewage pipelines
CN203284877U (en) Leakage-proof inner container of underground pipe network inspection well
CN208268556U (en) Construct the composite pipe in sponge city
CN206512818U (en) A kind of plastic stone rockery construction waste water drainage system device
CN105060668A (en) Prefabricated reinforced concrete septic tank and assembly method thereof
CN201395856Y (en) Integrated composite manhole
CN206706975U (en) A kind of cistern
CN201180308Y (en) Plastic hydraulic drop inspection shaft

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170901

Termination date: 20211225

CF01 Termination of patent right due to non-payment of annual fee