CN206408544U - A kind of hardened system for lifting concrete structure bearing capacity - Google Patents

A kind of hardened system for lifting concrete structure bearing capacity Download PDF

Info

Publication number
CN206408544U
CN206408544U CN201720028546.7U CN201720028546U CN206408544U CN 206408544 U CN206408544 U CN 206408544U CN 201720028546 U CN201720028546 U CN 201720028546U CN 206408544 U CN206408544 U CN 206408544U
Authority
CN
China
Prior art keywords
girder
arch
hardened system
bearing capacity
arch ring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720028546.7U
Other languages
Chinese (zh)
Inventor
谢开仲
王红伟
郭晓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi University
Original Assignee
Guangxi University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi University filed Critical Guangxi University
Priority to CN201720028546.7U priority Critical patent/CN206408544U/en
Application granted granted Critical
Publication of CN206408544U publication Critical patent/CN206408544U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a kind of hardened system for lifting concrete structure bearing capacity, hardened system includes arch ring, arch springing and girder steel;The girder steel is connected to connection girder steel bottom surface at the top of the bottom surface of reinforced structure girder, the span centre of arch ring, and two ends of arch ring connect the concrete structures of reinforced structure girder both sides by arch springing respectively.The utility model hardened system can increase substantially the bearing capacity of reinforced structure, and hardened system can be adjusted flexibly, and structure stress is more scientific and reasonable, reinforce efficiency high, convenient later maintenance, quick, and fire resistance is good, and service life is long, and overall economic efficiency is high.

Description

A kind of hardened system for lifting concrete structure bearing capacity
Technical field
The utility model belongs to Reinforcement Technology of Concrete Structure field, more particularly to a kind of lifting concrete structure carrying energy The hardened system of power.
Background technology
At present, concrete structure reinforcement has bonding steel plate method, sticking carbon fiber, steel wire rope mesh sheet-composite mortar additional layer In place of method for strengthening, reinforcement method of enlarging section and a variety of methods of external prestressed strengthening method, but every kind of method all Shortcomings.
Bonding steel plate method, by realizing that joist support loading capability is improved being reinforced beam body bottom affixing steel plate.Affixing steel plate Method ruggedized construction form is single, and bearing capacity lifting is relatively low, and the connecting portion of steel plate and beams of concrete is key position, while It is weak part, it is impossible to give full play to the mechanics material property of steel, ruggedized construction reasonability needs into raising.
Sticking carbon fiber, composite method being reinforced beam bottom pasting carbon fiber composite material material by realizing load bearing beam The raising of ability.Carbon fibre composite method is relatively low to the lifting of beam body bearing capacity, and strength of materials utilization rate is not high, while carbon is fine There is durability and problem of aging in dimension material, under especially complicated adverse circumstances, carbon fibre composite not fire resisting, fire can be led Bearing capacity is caused to lose.
Steel wire rope mesh sheet-composite mortar additional layer method for strengthening:It is poly- by the outstanding permeability of adhesion strength and bending strength Close mortar attachment, the raising to be formed integrally to realize joist support loading capability of being combined closely with concrete.Weak point is:(1) to multiple The requirement for closing mortar performance and quality is higher, and product (polymer mortar) general performance of in the market supply is poor, if not special Door is prepared, and easily occurs safe mass problem;(2) unit price of high strength stainless steel silk and high performance composite mortar is higher, just passes through Ji angle considers to be short of, limited to the consolidation effect of structural-load-carrying capacity in addition;(3) before use, more careful skill need to be done The economic comprehensive assessment of art just can determine that its applicability.
Reinforcement method of enlarging section, take increase concrete structure or structures area of section, with improve its bearing capacity and Satisfaction is normally used.Relatively low to structural-load-carrying capacity lifting, the construction wet trade time is long, needs to limit lotus during concrete curing Carry, to traffic impact than larger, dead load increase, building are reduced using space after reinforcing.
External prestressed strengthening method, it is necessary to when wanting the force structure to reinforce to bridge main, can outside beam body (beam bottom with Beam both sides) reinforcing bar or steel tendon are set, and apply prestressing force, to improve the force-bearing situation of bridge, improve load carrying capacity of bridge.Deposit The problem of be that (1) external tendon is arranged in outside section, anti-corrosion, protect relatively difficult, easily by ectocine.(2) anchor and turn Stress concentration is also easy to produce to region, local stress is big, high is required to anchoring construction.(3) external tendon stretching force is smaller, it is impossible to fully The high advantage of external tendon intensity is played, the requirement to anchorage and intermediate plate is very high.(4) deformation of external prestressing steels and concrete Deformation is inconsistent, easily causes loss of prestress, and structural-load-carrying capacity is lifted relatively low.
The content of the invention
The technical problems to be solved in the utility model be to provide it is a kind of can increase substantially the bearing capacity of reinforced structure, Hardened system can be adjusted flexibly, and structure stress is more scientific and reasonable, reinforce efficiency high, convenient later maintenance, quick, fire resistance It is good, the hardened system and its construction method of the lifting concrete structure bearing capacity of service life length.
The utility model solves above-mentioned technical problem using following technical scheme:
A kind of hardened system for lifting concrete structure bearing capacity, including arch ring, arch springing and girder steel;The girder steel connection The connection girder steel bottom surface at the top of the bottom surface of reinforced structure girder, the span centre of arch ring, two ends of arch ring pass through arch springing respectively Connect the concrete structures of reinforced structure girder both sides.
Branch seat cushion is provided with the top of the span centre of the arch ring, bearing is placed on branch seat cushion, holder top connection girder steel bottom surface.
The inner side of the concrete structures is provided with built-in fitting, and the end of bar-mat reinforcement and arch ring is respectively welded in built-in fitting, and Pour into a mould concrete formation arch springing.
The girder steel top surface is pasted and is fastened by bolts with reinforced structure bottom plane of main girder.
The arch ring is multiple, is connected between two neighboring arch ring with transverse strut.
A kind of construction method for the hardened system for lifting concrete structure bearing capacity, comprises the following steps:
1. prefabricated arch ring;
2. the surface treatment of arch springing installation place
To the arch springing installation place surface cleaning on the inside of concrete structures and coarse processing;
3. template and support are set up;
4. assembling reinforcement net;
5. weld built-in fitting and arch ring is installed
Arch springing installation place is provided with built-in fitting, and bar-mat reinforcement and built-in fitting are welded, arch ring is then lifted, by the end of arch ring and Built-in fitting is welded;
6. casting concrete
Arch springing installation place casting concrete formation arch springing;
7. all arch rings 12 are completed and transverse strut is installed
Repeat step 1. to step 6., until completing the installation of all arch rings;Lateral ties are used between two neighboring arch ring Beam is connected, and the top surface of transverse strut is bolted or welded with reinforced structure bottom plane of main girder;
8. girder steel is installed in reinforced structure girder bottom
Girder steel top surface is pasted and firm by bolt with reinforced structure bottom plane of main girder;
9. branch seat cushion and bearing are placed at the top of arch ring span centre
Using jack by girder steel jacking, branch seat cushion and bearing are sequentially placed at the top of arch ring span centre, is then removed very heavy Top, construction is completed.
The utility model has the advantage of:
(1) in terms of bearing capacity lifting.The bearing capacity of reinforced structure, energy can be significantly increased in the utility model By the way that the ratio of rise to span of arch ring, section form, material rate, section form, the material rate of shaped steel, top lift size is adjusted flexibly Deng, bearing capacity increase rate is determined, and the adjustment and maintenance in later stage are very convenient, quick.
(2) in terms of structure type.Compared with existing reinforcement means, hardened system stress of the present utility model more science is closed Reason, can fully play material property, can utilize the advantage of reasonable in design well again.
(3) in terms of force-mechanism.Bonding steel plate method, sticking FRP method etc. is on the basis of reinforced structure once force-bearing It is upper to be reinforced, reinforce less efficient, the consolidation effect of the utility model hardened system can offset reinforced structure once Stress and secondary loading, reinforcing efficiency can be close to 100%.Compared with external prestress strengthening method, the utility model reinforces effect Fruit is notable, especially the loss of prestress problem in the absence of the later stage.
(4) in terms of later maintenance.Compared with existing reinforcement means, the utility model hardened system later stage can be carried out at any time The adjustment of consolidation effect, it is convenient and swift, and service life is much larger than other reinforcement means, and overall economic efficiency is high.
(5) in terms of fire resistance.The problem of sticking FRP method has one significantly is exactly that fire resistance is poor, meeting under fire effect Moment loses bearing capacity, and hardened system of the present utility model has advantage than sticking FRP method in terms of fire resistance.
Brief description of the drawings
Fig. 1 is the structural representation that the utility model hardened system is arranged on reinforced structure.
Fig. 2 is the floor map of the utility model hardened system.
In figure, 1:Bearing, 2:Branch seat cushion, 3:Jacking backing plate, 4:Jack, 5, built-in fitting, 6:Bar-mat reinforcement, 7:Arch springing, 8: Girder steel, 9:Reinforced structure girder, 10:Concrete structures, 11:Reinforced structure girder bearing, 12:Arch ring, 13:Laterally join Binder.
Embodiment
Embodiment of the present utility model is elaborated below in conjunction with the drawings and specific embodiments, but not constituted Limitation to the utility model claims.
A kind of hardened system for lifting concrete structure bearing capacity, including bearing 1, branch seat cushion 2, arch ring 12, the and of arch springing 7 Girder steel 8;The girder steel 8 is connected to the bottom surface of reinforced structure girder 9, and branch seat cushion 2, bearing 1 are placed at the top of the span centre of arch ring 12 It is placed on branch seat cushion 2, the top of bearing 1 connection girder steel 8 bottom surface;Two ends of arch ring 12 are reinforced by the connection of arch springing 7 respectively The concrete structures 10 of the both sides of structure girder 9.The two ends of reinforced structure girder 9 pass through reinforced structure girder bearing 11 respectively Connect the top of concrete structures 10.
The inner side of the concrete structures 10 is provided with built-in fitting 5, and bar-mat reinforcement 5 and arch ring 12 is respectively welded in built-in fitting 5 Simultaneously pour into a mould concrete formation arch springing 7 in end.
The top surface of girder steel 8 is pasted and firm by bolt with the bottom surface of reinforced structure girder 9.
The arch ring is multiple, is connected between two neighboring arch ring with transverse strut.
A kind of construction procedure of above-mentioned hardened system for lifting concrete structure bearing capacity:
1. prefabricated arch ring 12
The physical conditions such as the consolidation effect, the under-clearance that reach as needed and requirement, control the characteristic of arch ring 12 such as material Expect grade, section form and ratio of rise to span etc., make arch ring 12.
2. arch springing 7 pours the surface treatment at place
The place of pouring of arch springing 7 is located at the inner side of the concrete structures of reinforced structure both sides respectively.Coagulation is required during construction Native clean surface, pollution-free, impurity, oil stain, dust etc..First with dabbing machine to needing concrete surface to be processed to carry out dabbing Processing, laitance, debris surface are cut, and expose steel bar stress, are careful not to reinforcing bar in damage original structure, then with rotation steel Wire brush scavenging machine is cleaned, then removed with air blower or dust catcher drift along, particulate, rinsed one time with giant, it is to be dried after, i.e., It can be constructed.
3. template and support are set up
Template and support are set up at the place of pouring of arch springing 7.Template will have enough intensity, rigidity and stability, can safety Reliable to undertake the various loads being likely to occur in construction, the design shape of its secondary guarantee structure, size and each several part are mutual Between position accuracy, the seam of last template must be closely sealed, it is ensured that not spillage in concreting process.
4. assembling reinforcement net 6
Bar-mat reinforcement 6 will strictly by design drawing requirement colligation, note bar spacing, position it is accurate, colligation point firmly, is protected Card steel bar stress does not produce displacement, and the reinforcing bar crosspoint of bidirectional stress should all be fastened, and arch springing 7 is poured in place's reinforcing bar and original structure Bar connecting is together.
5. built-in fitting 5 is welded, arch ring 12 is installed
The place of pouring of arch springing 7 is provided with built-in fitting 5.Bar-mat reinforcement 6 is welded with built-in fitting 5, arch ring 12 is then lifted, by arch ring 12 Welded respectively with built-in fitting 5 end.
6. casting concrete
The casting concrete of arch springing 7.Concrete grade calculates selected according to Specific construction requirement and Design of Reinforcement.Pouring Cheng Zhong, vibrating head should avoid directly contacting with built-in fitting and reinforcing bar, need careful vibrate.After concrete formation, it need to strengthen supporting Shield, it is ensured that concrete pouring quality.
7. all arch rings 12 are completed and transverse strut 13 is installed
Above construction procedure is repeated, until completing the installation of all arch rings 12, transverse strut 13 is finally carried out and installs, it is horizontal Calculated and determined according to design to the size of connection beam 13, bolt is used between transverse strut 13 and each arch ring or is welded.
8. erection construction platform
Next step operation platform is set up between each arch ring 12, it is ensured that intensity, rigidity and stability meet safety in production and applied Work standard.
9. girder steel 8 is installed in the bottom of reinforced structure girder 9
A, the processing of the bottom surface of reinforced structure girder 9
Released in the bottom surface of reinforced structure girder 9 and reinforce position full-page proof, cut the rest area concrete surface 2 of girder steel 8~ Top layer mortar thick 5mm, makes solid exposed concrete, and formed at smooth mat surface, uneven surface using diamond bit soft peening Leveling.Surface laitance is removed with wire wheel again, top layer loose matter is rejected, surface dust is finally blown off with compressed air, and use first Benzene or industrial acetone wipe surface.To the layer inferior of larger area, repair smooth using polymer cement mortar after rejecting.Reinforce It is preceding to be scrubbed with acetone.
B, the bottom of reinforced structure girder 9 plant bury anchorage screw.
C, installation girder steel 8
Girder steel 8 can select shaped steel or steel plate, and blanking and processing, and the spiral shell buried according to scene plant are carried out according to actual setting-out Bar, to the supporting punching of girder steel 8, then carries out derusting with polishing abrasive machine or steel wire brush grinding machine and coarse by the upper surface of girder steel 8 Processing, polishing roughness is the bigger the better, and polishing lines should be vertical with bracing means Impact direction.Acetone is stained with absorbent cotton by girder steel 8 upper surface is wiped.Girder steel 8 is fixed on screw rod, and ensures the upper surface and the bottom surface of reinforced structure girder 9 of girder steel 8 Between gap in more than 3mm, to ensure that the thickness for irrigating glue-line, in more than 3mm, welding shaped steel or steel plate seam, completes peace Dress.
D, preparation structure glue.
E, edge sealing
By the edge sealing adhesive closed edge of girder steel 8.
F, reperfusion structure glue
Toward the gap reperfusion structure glue between the upper surface of girder steel 8 and the bottom surface of reinforced structure girder 9 until irrigating closely knit, Finally fill orifice is blocked with edge sealing adhesive.
G, the processing of the surface anticorrosion of girder steel 8
Girder steel 8, which solidifies closely knit effect, to remove all injection nozzles and blast pipe rearward, and remove the surface smut of girder steel 8 and Rust staining, preservative treatment is made to the exposed section of girder steel 8.
10. branch seat cushion 2 and bearing 1 are placed at the top of the span centre of arch ring 12
Using multiple jack 4 simultaneously by the jacking of girder steel 8, erection support pad 2 and bearing 1 at the top of the span centre of arch ring 12, branch Seat 1 is placed on branch seat cushion 2.For protection arch ring 12, the bottom of jack 4 can place jacking backing plate 3.Install branch seat cushion 2 and bearing 1 Dismounting jack and jacking backing plate 3, construct and complete afterwards.
Existing reinforcement means is reinforced on the basis of once force-bearing, such as affixing steel plate and carbon fiber, Reinforce efficiency comparison low, the utility model hardened system can offset the once force-bearing and secondary loading of structure after installing, reinforce Effect is controllable and the later stage is easy to adjust, quick, this be the utility model hardened system from other reinforcement means it is maximum it is different it Place, can be substantially improved structural-load-carrying capacity, with significant consolidation effect.
By taking monolithic beam as an example, with this hardened system, using simplified method, under gravity load effect, respectively from reason Structural reinforcement system is calculated by with two aspects of FEM calculation:
(1) theoretical side of hardened system is calculated
Reinforcing effectiveness formula is:
In formula:
η:Reinforce efficiency;MI:Maximal bending moment in reinforced structure girder before reinforcing;MII:Reinforced structure girder after reinforcing Middle maximal bending moment.
Wherein, MIWith MIIComputational methods:
1. before reinforcing, under gravity load effect, maximal bending moment is in reinforced structure girder:
Maximum sagging moment:
In formula:
MI- reinforce maximal bending moment in preceding reinforced structure girder;
q1- reinforced structure girder dead weight uniform;
L- reinforced structure girder computational lengths.
2. after reinforcing, under gravity load effect, maximal bending moment is in reinforced structure girder:
Maximum sagging moment:
In formula:
MII- reinforce maximal bending moment in preceding reinforced structure girder;q1- reinforced structure girder dead weight uniform;
q2(shaped steel) dead weight uniform of-reinforced structure girder bottom girder steel 8;
E1- modulus of elasticity of concrete;E2- shaped steel modulus of elasticity;
I1- reinforced structure girder section bending resistance the moment of inertia;
I2(shaped steel) the section bending resistance the moment of inertia of-reinforced structure girder bottom girder steel 8;
3. efficiency is reinforced
In actual reinforcing, q can be reduced using the material of high-strength light2, steel are not limited to, can be aluminium alloy etc., E is increased by reasonable Arrangement section form2I2So that efficiency is reinforced close to 100%.
(2) calculated in terms of the FEM calculation of hardened system
In order to verify the consolidation effect of this patent, calculated using ANSYS general finite meta softwares, calculate the transversal of beam Face size is 0.4m × 0.5m, beam span 10m, under gravity load effect, reinforce each node on front-axle beam (girder longitudinal direction every 1m set a node) amount of deflection be shown in Table 1.
Strengthening steel slab thickness is 0.015m, and the span for reinforcing arch ring is 10m, and the rise of arch ring is 4m, and steel select 40#A I-steel, size is 400mm × 142mm × 10.5mm.
Table 1 is calculated before and after beam is reinforced and contrasted
Measuring point is numbered Amount of deflection (mm) before reinforcing Amount of deflection (mm) after reinforcing Amount of deflection lifting values (mm)
1 0 0 0
2 1.6061 0.6933 0.9128
3 3.0382 1.2988 1.7394
4 4.1591 1.7556 2.4035
5 4.8709 2.0302 2.8407
6 5.1147 2.1167 2.9980
7 4.8709 2.0302 2.8407
8 4.1591 1.7556 2.4035
9 3.0382 1.2988 1.7394
10 1.6061 0.6933 0.9128
11 0 0 0
Find out as shown in Table 1, using hardened system of the present utility model, the amount of deflection (rigidity) of beam body has been obtained greatly after reinforcing The lifting of amplitude, in actually reinforcing, due to the overall humidification of crossbeam connection beam, the amount of deflection of beam body can also be carried further Rise, while the model of main arch ring I-steel, quantity, the parameter such as model, quantity of transverse strut can be adjusted, i.e. beam body Consolidation effect can be adjusted correspondingly according to different reinforcement criterias.

Claims (5)

1. a kind of hardened system for lifting concrete structure bearing capacity, it is characterised in that including arch ring, arch springing and girder steel;Institute State connection girder steel bottom surface at the top of the bottom surface that girder steel is connected to reinforced structure girder, the span centre of arch ring, two ends part of arch ring The concrete structures of reinforced structure girder both sides are not connected by arch springing.
2. a kind of hardened system for lifting concrete structure bearing capacity as claimed in claim 1, it is characterised in that the arch Branch seat cushion is provided with the top of the span centre of circle, bearing is placed on branch seat cushion, holder top connection girder steel bottom surface.
3. a kind of hardened system for lifting concrete structure bearing capacity as claimed in claim 1, it is characterised in that described mixed The inner side of soil structures is coagulated provided with built-in fitting, the end of bar-mat reinforcement and arch ring is respectively welded in built-in fitting, and pour into a mould concrete formed Arch springing.
4. a kind of hardened system for lifting concrete structure bearing capacity as claimed in claim 1, it is characterised in that the steel Top surface of the beam is pasted and is fastened by bolts with reinforced structure bottom plane of main girder.
5. a kind of hardened system for lifting concrete structure bearing capacity as claimed in claim 1, it is characterised in that the arch Enclose to be multiple, connected between two neighboring arch ring with transverse strut.
CN201720028546.7U 2017-01-10 2017-01-10 A kind of hardened system for lifting concrete structure bearing capacity Expired - Fee Related CN206408544U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720028546.7U CN206408544U (en) 2017-01-10 2017-01-10 A kind of hardened system for lifting concrete structure bearing capacity

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720028546.7U CN206408544U (en) 2017-01-10 2017-01-10 A kind of hardened system for lifting concrete structure bearing capacity

Publications (1)

Publication Number Publication Date
CN206408544U true CN206408544U (en) 2017-08-15

Family

ID=59554277

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720028546.7U Expired - Fee Related CN206408544U (en) 2017-01-10 2017-01-10 A kind of hardened system for lifting concrete structure bearing capacity

Country Status (1)

Country Link
CN (1) CN206408544U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106702914A (en) * 2017-01-10 2017-05-24 广西大学 Reinforcing system capable of improving load bearing capacity of concrete structures and construction method of reinforcing system
CN109137760A (en) * 2018-09-28 2019-01-04 广西大学 The active reinforcement means of multispan normal reinforced concrete beam bridge
CN109162212A (en) * 2018-09-28 2019-01-08 广西交通科学研究院有限公司 The active reinforcement means of single span normal reinforced concrete beam bridge
CN111140250A (en) * 2019-12-14 2020-05-12 同济大学 Method for determining reinforcing and strengthening time of shield tunnel structure bonded steel and application
CN111172901A (en) * 2020-03-09 2020-05-19 临沂大学 Novel bridge reinforcing apparatus based on high-performance steel fiber concrete
CN114000442A (en) * 2021-11-10 2022-02-01 陕西省交通规划设计研究院有限公司 Simply supported beam bridge reinforcing structure and reinforcing method thereof

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106702914A (en) * 2017-01-10 2017-05-24 广西大学 Reinforcing system capable of improving load bearing capacity of concrete structures and construction method of reinforcing system
CN106702914B (en) * 2017-01-10 2019-06-07 广西大学 A kind of hardened system and its construction method promoting concrete structure bearing capacity
CN109137760A (en) * 2018-09-28 2019-01-04 广西大学 The active reinforcement means of multispan normal reinforced concrete beam bridge
CN109162212A (en) * 2018-09-28 2019-01-08 广西交通科学研究院有限公司 The active reinforcement means of single span normal reinforced concrete beam bridge
CN111140250A (en) * 2019-12-14 2020-05-12 同济大学 Method for determining reinforcing and strengthening time of shield tunnel structure bonded steel and application
CN111172901A (en) * 2020-03-09 2020-05-19 临沂大学 Novel bridge reinforcing apparatus based on high-performance steel fiber concrete
CN114000442A (en) * 2021-11-10 2022-02-01 陕西省交通规划设计研究院有限公司 Simply supported beam bridge reinforcing structure and reinforcing method thereof

Similar Documents

Publication Publication Date Title
CN206408544U (en) A kind of hardened system for lifting concrete structure bearing capacity
CN106702914B (en) A kind of hardened system and its construction method promoting concrete structure bearing capacity
CN102747677B (en) Bridge and construction method thereof
CN108330835A (en) The construction method of setting bracket
CN107574762A (en) A kind of construction method for strengthening Cast-in-situ Beam 0# block construction qualities
CN101644032A (en) Beam-removing rib-increasing strengthening construction technology of highway bridge
CN113152306B (en) Small-radius large-gradient prefabricated T beam frame construction method
CN102817325A (en) Construction method of simply supported-continuous switching system of negative moment beam prestressed precast box beam
CN105297641A (en) Highway T beam diaphragm plate prestress reinforcing structure and working method for reinforcement using reinforcing structure
CN110863498A (en) Deep foundation pit combined supporting construction method next to subway station
CN204060020U (en) A kind of Reinforced Concrete Reinforcement structure
CN111074905A (en) Early-dismantling structure and construction method for bottom layer support beam of inner support system of deep foundation pit
CN107217597A (en) A kind of prestressed concrete bridge face is seamlessly connected the construction method of plate
CN205934713U (en) Prefabricated pin -connected panel anticollision wall
CN104233961A (en) Triangular supporting bracket of suspended cast bridge block 0
CN113322771A (en) Seamless bridge structure based on ultrahigh-toughness cement-based composite material and construction method
CN117488647A (en) Combined beam suitable for upper and lower two-layer steel truss web rods of overhead in urban area and construction method
CN114277672B (en) Large-span prestressed concrete bent cap structure and construction method thereof
CN112609584A (en) Prefabricated small box girder installation construction method for intelligent express way
CN209854528U (en) Toughness steel-concrete combined bridge floor
CN106087782A (en) A kind of remodeling method of the floating bowstring arch bridge of bridge floor
CN215947924U (en) Support bearing structure for pier stud bent cap
CN212294735U (en) Gantry crane track foundation beam
CN205474788U (en) Broad width box girder bridge girder roof reinforced structure
CN205259063U (en) A closed construction platform for going up stride construction of old bridge anticollision barrier of railway

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170815

Termination date: 20200110