CN206346308U - A kind of construction for facilitating structure base slab post-cast strip to clear up - Google Patents

A kind of construction for facilitating structure base slab post-cast strip to clear up Download PDF

Info

Publication number
CN206346308U
CN206346308U CN201621301038.3U CN201621301038U CN206346308U CN 206346308 U CN206346308 U CN 206346308U CN 201621301038 U CN201621301038 U CN 201621301038U CN 206346308 U CN206346308 U CN 206346308U
Authority
CN
China
Prior art keywords
catch pit
reserved
cast strip
waterproof
fish tail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621301038.3U
Other languages
Chinese (zh)
Inventor
姚坤
陈世伟
马恒力
郭继舟
李少祥
储勤波
张猛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
China First Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China First Metallurgical Group Co Ltd filed Critical China First Metallurgical Group Co Ltd
Priority to CN201621301038.3U priority Critical patent/CN206346308U/en
Application granted granted Critical
Publication of CN206346308U publication Critical patent/CN206346308U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

A kind of construction for facilitating structure base slab post-cast strip to clear up, including some fish tail and waterproof layers and reserved catch pit, fish tail and waterproof layer decline in certain slope, rule and rise arrangement, and reserved catch pit is arranged between two fish tail and waterproof layers to form bottom of slope.Reserved catch pit is provided with concrete cushion, brick fetal membrane, SBS waterproof rolls, GRC protection boards, concrete water-proof protective layer; concrete cushion is cast in reserved catch pit bottom; brick fetal membrane is built by laying bricks or stones in the reserved wall of catch pit four; the paving of SBS waterproof rolls is connected in reserved catch pit and with the fish tail and waterproof layer outside reserved catch pit; concrete water-proof protective layer is cast in the reserved catch pit bottom after paving SBS waterproof rolls, and GRC protection boards are bonded in the wall of reserved catch pit four after paving SBS waterproof rolls.The utility model utilizes slope, the combination of catch pit, and draining pump draws water in addition, reaches in post-cast strip without ponding;Easy construction, operating efficiency height, cleaning effect are notable.

Description

A kind of construction for facilitating structure base slab post-cast strip to clear up
Technical field
The utility model belongs to building engineering construction field, and in particular to a kind of structure for facilitating structure base slab post-cast strip to clear up Make.
Background technology
During Current Engineering Construction, in order to solve the relative settlement between main structure body or garage and podium, structure both shrinks The problems such as deformation and temperature stress are deformed, the mode of indwelling post-cast strip is used widely in architectural engineering.But midsole of constructing Plate pouring after settlement is only waiting agent structure to bind, and can just be poured after settlement stability, indwelling time is longer, easy ponding, Product rubbish, and clear up ponding, rubbish workload greatly and be not easily cleaned totally, such as clear up not thorough, after ensureing that post-cast strip is closed Waterproof quality it is unfavorable.Therefore, on the premise of the stability and agent structure energy smooth construction on basis is ensured, how to bottom plate Post-cast strip carries out Construction treatment, and before the closing of post-cast strip, internal ponding, garbage-cleaning can reach concreting condition, really Protect post-cast strip and occur without Seepage, it has also become engineers and technicians constantly inquire into the problem of research.
CN201520302805.1 patent discloses a kind of alter-pouring strips mould plate with tipping platform, and position is installed in alter-pouring strips mould plate A kind of template with tipping platform has been installed, side is fixed by door hinge, is opened when post-cast strip is cleared up, rubbish is poured out, when pouring Turnover panel is closed.The alter-pouring strips mould plate that the program is provided installs structure, solves in post-cast strip that construction garbage-cleaning difficulty is big, clear up The problem of effect is undesirable.But the post-cast strip of floor in balcony is only applicable to, it is not suitable for the cleaning of bottom plate rear pouring tape.
CN201220584882.7 patent discloses a kind of gutter for being applied to cleaning post-cast strip, is set in post-cast strip There is a gutter, and connected with sump on the outside of wallboard, by sump draining, reached in post-cast strip without ponding, side Convenient to operate.Construction garbage-cleaning difficulty is big in solution post-cast strip, substantially increase construction efficiency, it is ensured that construction quality.But In exterior wall and sump connectivity part, closure requires higher, and difficulty is big, and follow-up seepage probability is big, and be not suitable for Underground Extra-long, The application of super many post-cast strips.
CN201520929186.9 patent discloses a kind of late poured band structure, and one layer of protection steel is set on post-cast strip top Plate and water-proofing treatment, then carry out top earthing, do not influence earthing to construct again, solve in basement and main structure construction Be eager backfill when the rear pouring tape construction method that carries out.But exist after earthing, clear up the problem of post-cast strip rubbish is more difficult.
The content of the invention
The technical problems to be solved in the utility model is, in existing industry and civil buildings basement bottom plate rear pouring tape Ponding and rubbish are difficult to the deficiency cleared up there is provided a kind of construction for facilitating structure base slab post-cast strip to clear up, and are put by fish tail and waterproof layer The construction that slope is combined with reserved catch pit;Easy construction, labor intensity are low, operating efficiency is high, and cleaning effect is notable.
The utility model is to solve the technical scheme that is used of above-mentioned technical problem:
A kind of construction for facilitating structure base slab post-cast strip to clear up, including some fish tail and waterproof layers and reserved catch pit, waterproof Protective layer declines in certain slope, rule and rises arrangement, and reserved catch pit is arranged at two fish tail and waterproof layers to form bottom of slope Between (reserved catch pit connect with the bottom of slope of two fish tail and waterproof layers).
By such scheme, at bottom plate rear pouring tape, fish tail and waterproof layer carries out 3 ‰~5 ‰ towards reserved catch pit direction Fish tail and waterproof layer between slope, two neighboring reserved catch pit carries out 3 ‰~5 ‰ to reserved catch pit direction respectively with midpoint Slope.
By such scheme, the reserved catch pit is provided with concrete cushion, brick fetal membrane, SBS waterproof rolls, GRC protections Plate, concrete water-proof protective layer, concrete cushion are cast in reserved catch pit bottom, and brick fetal membrane is built by laying bricks or stones in reserved catch pit four Wall, SBS waterproof rolls paving is connected in reserved catch pit and with the fish tail and waterproof layer outside reserved catch pit, concrete Fish tail and waterproof layer is cast in the reserved catch pit bottom after paving SBS waterproof rolls, and GRC protection boards are bonded in paving SBS waterproofs The wall of reserved catch pit four after coiled material.
By such scheme, two neighboring reserved catch pit spacing Wei≤20m.
By such scheme, the reserved catch pit width and depth are 0.3~0.5m.
Compared with prior art, the beneficial effects of the utility model are:
1st, it is necessary to which use is a large amount of artificial in traditional basement post-pouring zone scale removal process, and cleaning effect is undesirable, to rear Pouring the quality with infiltration weak link can not ensure there is high hidden leakage defect, will be prevented using the utility model at post-cast strip Water conservation layer slope, and the reserved catch pit in post-cast strip, both construction being combined reach the purpose quickly cleared up, dropped Low basement bottom plate rear pouring tape cleaning work amount, so as to greatly reduce labor intensity, improve that operating efficiency is high, reduce Construction period, meanwhile, it also ensure that construction quality;
2nd, the utility model construction way utilizes slope, the combined use of catch pit, and post-cast strip is make use of to greatest extent Internal water accumulation self is collected, and is drawn water in addition using draining pump, is reached the condition without ponding in post-cast strip;
3rd, reserve catch pit and add SBS waterproof rolls plus GRC protection board ways, and SBS waterproof rolls and collection using brick fetal membrane It is connected as a single entity outside puddle, strengthens the waterproof effect of catch pit and whole engineering, with globality, treats that post-cast strip concrete is poured When building, the concrete of identical strength grade of concrete, primary concreting can be used with post-cast strip;
4th, compared with traditional basement bottom plate rear pouring tape cleaning effect, the utility model cleaning effect is notable, to post-cast strip The impervious waterproof quality gone out is significantly increased, and then reduces construction cost.
Brief description of the drawings
Fig. 1 is the structural representation for the construction that the utility model facilitates the cleaning of structure base slab post-cast strip;
Fig. 2 is the layout drawing of the adjacent reserved catch pit of the utility model;
Fig. 3 is the constructing structure figure in the reserved catch pit of the utility model;
In figure, 1- fish tail and waterproof layers, 2- reserves catch pit, 21- concrete cushions, 22- brick fetal membranes, 23-SBS waterproofs volume Material, 24-GRC protection boards, 25- concrete water-proof protective layers.
Embodiment
Technical solutions of the utility model are described in detail with example below in conjunction with the accompanying drawings.
As shown in figure 1, the construction described in the utility model for facilitating structure base slab post-cast strip to clear up, including some waterproofs are protected Sheath 1 and reserved catch pit 2, fish tail and waterproof layer decline and risen arrangement in certain slope, rule, and reserved catch pit 2 is arranged at Formed between two fish tail and waterproof layers 1 of bottom of slope (reserved catch pit 2 connects with the bottom of slope of two fish tail and waterproof layers 1).
At bottom plate rear pouring tape, fish tail and waterproof layer 1 carries out 3 ‰~5 ‰ slope towards the reserved direction of catch pit 2, adjacent Fish tail and waterproof layer 1 between two reserved catch pits 2 carries out 3 ‰~5 ‰ to the reserved direction of catch pit 2 respectively with midpoint and put Slope.
As shown in Fig. 2 the two neighboring spacing Wei of reserved catch pit 2≤20m, it is 0.3 to reserve the width of catch pit 2 and depth ~0.5m.
Protected as shown in figure 3, reserved catch pit 2 is provided with concrete cushion 21, brick fetal membrane 22, SBS waterproof rolls 23, GRC Backplate 24, concrete water-proof protective layer 25, concrete cushion 21 are cast in the reserved bottom of catch pit 2, and brick fetal membrane 22 is built by laying bricks or stones pre- Stay the wall of catch pit 2 four, the paving of SBS waterproof rolls 23 in reserved catch pit 2 and with the fish tail and waterproof layer outside reserved catch pit 2 1 is connected, and concrete water-proof protective layer 25 is cast in the bottom of reserved catch pit 2 after paving SBS waterproof rolls 23, and GRC is protected Backplate 24 is bonded in the wall of reserved catch pit 2 four after paving SBS waterproof rolls 23.
The utility model additionally provides a kind of method for facilitating structure base slab post-cast strip to clear up, and comprises the following steps:
1) construction for facilitating structure base slab post-cast strip to clear up as shown in Figure 1 is made:Including fish tail and waterproof layer 1 and reserved collection Puddle 2;
2) according to the design drawing size of basement bottom board, mixture proportioning in construction, reserved catchmenting in post-cast strip is set Cheat between 2 positions, adjacent reserved catch pit 2 away from≤20m, it is 0.3~0.5m to reserve the width of catch pit 2 and depth, in engineering cubic metre of earth In the excavation stage, at bottom plate rear pouring tape, according to the reserved catch pit position of positioning, earth excavation is carried out, setting for catch pit is reserved Put as shown in Figure 2;
3) fish tail and waterproof layer 1 is constructed:At bottom plate rear pouring tape, to the concrete surface of fish tail and waterproof layer 1 to reserved catch pit 2 Direction carries out 3 ‰~5 ‰ slope;The concrete surface of fish tail and waterproof layer 1 between two neighboring reserved catch pit 2, with midpoint Respectively to the slope of the reserved direction of catch pit 2 progress 3 ‰~5 ‰;
4) catch pit 2 is reserved to construct:Poured in the reserved bottom of catch pit 2 with spoil face condition of equivalent thickness, equality strength etc. The concrete cushion 21 of level, brick fetal membrane 22 and paving 3+4SBS waterproof rolls 23,3+4SBS are built by laying bricks or stones in the reserved wall of catch pit 2 four Waterproof roll 23 is connected with the fish tail and waterproof layer 1 outside reserved catch pit 2, after the construction of 3+4SBS waterproof rolls 23 is finished, The concrete water-proof coiled material protective layer 25 with engineering condition of equivalent thickness, equality strength grade, four walls are poured in the reserved bottom of catch pit 2 Bond GRC plates 24 to be protected, the constructing structure reserved in catch pit 2 is as shown in Figure 3;
5) when post-cast strip possesses sealing condition, first the reserved catch pit 2 of post-cast strip is cleaned out, to without ponding, nothing Rubbish, then using giant, by the fish tail and waterproof layer 1 of slope formula by construction rubbish that may be present, mud in post-cast strip Reserved catch pit 2 is rushed in other debris, it is ensured that post-cast strip no-sundries, reserved catch pit 2 is finally cleared up again.
It should be appreciated that for those of ordinary skills, can according to the above description be improved or converted, And all these modifications and variations should all belong to the protection domain of the utility model appended claims.

Claims (5)

1. a kind of construction for facilitating structure base slab post-cast strip to clear up, it is characterised in that including some fish tail and waterproof layers and reserved collection Puddle, fish tail and waterproof layer declines and risen arrangement in certain slope, rule, and reserved catch pit, which is arranged at, to be formed two of bottom of slope and prevent Between water conservation layer.
2. the construction according to claim 1 for facilitating structure base slab post-cast strip to clear up, it is characterised in that in bottom plate rear pouring tape Place, fish tail and waterproof layer carries out anti-between 3 ‰~5 ‰ slope, two neighboring reserved catch pit towards reserved catch pit direction Water conservation layer carries out 3 ‰~5 ‰ slope with midpoint to reserved catch pit direction respectively.
3. the construction according to claim 1 for facilitating structure base slab post-cast strip to clear up, it is characterised in that described reserve is catchmented Hole is provided with concrete cushion, brick fetal membrane, SBS waterproof rolls, GRC protection boards, concrete water-proof protective layer, and concrete cushion is poured Build in reserved catch pit bottom, brick fetal membrane is built by laying bricks or stones in the reserved wall of catch pit four, the paving of SBS waterproof rolls is being reserved in catch pit simultaneously It is connected with the fish tail and waterproof layer outside reserved catch pit, concrete water-proof protective layer is cast in after paving SBS waterproof rolls Reserved catch pit bottom, GRC protection boards are bonded in the wall of reserved catch pit four after paving SBS waterproof rolls.
4. the construction according to claim 1 for facilitating structure base slab post-cast strip to clear up, it is characterised in that two neighboring reserved Catch pit spacing Wei≤20m.
5. the construction according to claim 1 for facilitating structure base slab post-cast strip to clear up, it is characterised in that described reserve is catchmented It is 0.3~0.5m to cheat width and depth.
CN201621301038.3U 2016-11-30 2016-11-30 A kind of construction for facilitating structure base slab post-cast strip to clear up Expired - Fee Related CN206346308U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621301038.3U CN206346308U (en) 2016-11-30 2016-11-30 A kind of construction for facilitating structure base slab post-cast strip to clear up

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621301038.3U CN206346308U (en) 2016-11-30 2016-11-30 A kind of construction for facilitating structure base slab post-cast strip to clear up

Publications (1)

Publication Number Publication Date
CN206346308U true CN206346308U (en) 2017-07-21

Family

ID=59322203

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621301038.3U Expired - Fee Related CN206346308U (en) 2016-11-30 2016-11-30 A kind of construction for facilitating structure base slab post-cast strip to clear up

Country Status (1)

Country Link
CN (1) CN206346308U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109763518A (en) * 2019-01-30 2019-05-17 成都建工第四建筑工程有限公司 A kind of construction method of basement post-pouring zone
CN112065038A (en) * 2020-09-27 2020-12-11 中建八局科技建设有限公司 Base plate advanced water stop post-cast strip structure and construction method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109763518A (en) * 2019-01-30 2019-05-17 成都建工第四建筑工程有限公司 A kind of construction method of basement post-pouring zone
CN112065038A (en) * 2020-09-27 2020-12-11 中建八局科技建设有限公司 Base plate advanced water stop post-cast strip structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN101403218B (en) Processing method for basement water-proof concrete construction joint
CN105862873A (en) Construction method of underground water prevention and exterior wall structures of narrow space of deep foundation pit
CN203546762U (en) Triple waterproof advance water stop structure for post-cast strip
CN104631513A (en) Construction method for closing basement exterior wall post-cast strip
CN106759843A (en) A kind of outer wall of basement waterproof construction and its construction method
CN206346308U (en) A kind of construction for facilitating structure base slab post-cast strip to clear up
CN104790435A (en) Post-subsidence pouring belt advancing waterstop impermeable concrete structure and construction technology thereof
CN107489238A (en) A kind of waterproofing process of the movement joint of the roofing for successfully managing deformation condition and top plate
CN105133619A (en) Construction method for deep foundation pit of elevator shaft
CN107299678A (en) A kind of fabricated structure
CN206859272U (en) The interim block structure of outer wall of basement pouring after settlement
CN103031849B (en) Method for construction of arranging dewatering well in foundation pit and flexibly closing dewatering well
CN209538214U (en) A kind of late poured band structure of outer wall of basement
CN106638544A (en) Anti-seepage and anti-cracking construction method for ultra-large reinforced concrete bio-oxidation pond in cold area
JPH08269984A (en) Construction of basement in outside waterproofing construction method
CN212477835U (en) Civil engineering post-cast strip shutoff
CN212223970U (en) Prefabricated apron post-cast strip stagnant water temporary enclosed construction
CN110552546B (en) Method for building underground parking lot waterproof facility by using tower crane
CN209412844U (en) A kind of assembled resin concrete drainage ditch
CN207063190U (en) A kind of fabricated structure waterproof construction
CN207032254U (en) Operation support body of cancellation basement outer wall backfill
CN206233385U (en) A kind of basement high-low bay shears mine dam waterproof construction
CN107035006B (en) A kind of node waterproof method at laminated floor slab difference of height
CN218264006U (en) Waterproof drainage structure of basement
CN217949155U (en) Basement post-cast strip structure

Legal Events

Date Code Title Description
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170721

Termination date: 20211130

CF01 Termination of patent right due to non-payment of annual fee