CN206344497U - Diel preheating device - Google Patents

Diel preheating device Download PDF

Info

Publication number
CN206344497U
CN206344497U CN201621208324.5U CN201621208324U CN206344497U CN 206344497 U CN206344497 U CN 206344497U CN 201621208324 U CN201621208324 U CN 201621208324U CN 206344497 U CN206344497 U CN 206344497U
Authority
CN
China
Prior art keywords
intelligent controller
fuel
heater
diel
air blower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621208324.5U
Other languages
Chinese (zh)
Inventor
罗振
常青
张磊
衡思迎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Motor Dies Co Ltd
Original Assignee
Tianjin Motor Dies Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Motor Dies Co Ltd filed Critical Tianjin Motor Dies Co Ltd
Priority to CN201621208324.5U priority Critical patent/CN206344497U/en
Application granted granted Critical
Publication of CN206344497U publication Critical patent/CN206344497U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Spray-Type Burners (AREA)

Abstract

A kind of diel preheating device, including water heater casing, water tank, liquid-fuel tank, also include apparatus for gasifying fuel, injection burner, emission-control equipment, intelligent controller, injection burner is arranged on below water tank, apparatus for gasifying fuel is arranged on below injection burner, and injection burner includes:Fuel nozzle, injector, combustion chamber, fuel nozzle, injector and combustion chamber are sequentially communicated, apparatus for gasifying fuel includes gasifier and heater, gasifier is arranged on below heater, heater is arranged on below fuel nozzle, and gasifier and heater are electrically connected with intelligent controller respectively, and emission-control equipment is arranged on above water tank, intelligent controller is arranged in water heater casing, and emission-control equipment is electrically connected with intelligent controller.The utility model provides preheating for the processing of diel, and it is saved, efficient, environmental protection has very high promotional value.

Description

Diel preheating device
Technical field
The utility model belongs to a kind of diel auxiliary equipment field, more particularly, to a kind of pre- hot charging of diel Put.
Background technology
Diel is preferably first preheated using preceding to diel, otherwise diel and product to be processed it Between the temperature difference it is big, product ectonexine thermograde can be caused to increase, thermal stress is formed, product surface is cracked, or even cracking.
The content of the invention
In view of this, the utility model is directed to a kind of diel preheating device, to solve during diel processing Preheating.
To reach above-mentioned purpose, what the technical solution of the utility model was realized in:
In a kind of diel preheating device, including water heater casing, water heater casing with outlet pipe and water inlet pipe phase The water tank and liquid-fuel tank of connection, it is characterised in that:Also include apparatus for gasifying fuel, injection burner, exhaust-gas treatment dress Put, intelligent controller, heat-insulation layer, the first air blower and the second air blower, injection burner is arranged on below water tank, fuel gas Makeup, which is put, to be arranged on below injection burner, and apparatus for gasifying fuel is connected by cartridge with injection burner, injection type Burner includes:Fuel nozzle, injector, combustion chamber, fuel nozzle, injector and combustion chamber are sequentially communicated, the fuel gas Makeup is put including gasifier and heater, and gasifier is arranged on below heater, and heater is arranged on below fuel nozzle, gasification Device and heater are connected by cartridge, and gasifier and heater are electrically connected with intelligent controller respectively, and emission-control equipment is set Put above water tank, intelligent controller is arranged in water heater casing, and emission-control equipment is electrically connected with intelligent controller.
Further, first air blower, the second air blower are arranged on below injector, the first air blower, the second air blast Machine is electrically connected with intelligent controller.
Further, the emission-control equipment includes air exhauster, discharge duct, exhaust-air monitor, control valve and waste gas suction Device is received, air exhauster is arranged on above water tank, discharge duct is connected with air exhauster outlet, and exhaust-air monitor, control valve are set gradually On discharge duct, Waste gas absorbing device is arranged on below control valve, air exhauster, wasted nickel catalyst device, control valve and Waste gas absorbing device Electrically connected respectively with intelligent controller.
Further, the petrolift is arranged in alcohol radical liquid fuel tank, and petrolift is electrically connected with intelligent controller.
Further, the igniter is arranged in combustion chamber, and igniter is electrically connected with intelligent controller.
Further, the hydraulic pressure sensor is arranged on water inlet pipe, and hydraulic pressure sensor is electrically connected with intelligent controller.
Further, the temperature sensor is arranged in water tank, and temperature sensor is electrically connected with intelligent controller.
Relative to prior art, diel preheating device described in the utility model has the advantage that:
(1) the utility model is entered using the pipeline of mould inside to hot water is poured in pipeline to the diel before processing Row preheating, effectively prevents that to form thermal stress makes product surface cracking or even ftracture.
(2) diel preheating device described in the utility model using energy-conserving and environment-protective renewable resource alcohol-based fuel, Using gasifier, heater, injection burner, the alcohol-based fuel of liquid is set to gasify and be fired after being sufficiently mixed with air Burn, improve efficiency of combustion, save the energy.
Brief description of the drawings
Constitute a part of accompanying drawing of the present utility model to be used for providing further understanding to of the present utility model, this practicality is new The schematic description and description of type is used to explain the utility model, does not constitute to improper restriction of the present utility model. In accompanying drawing:
Fig. 1 is the structural representation of diel preheating device described in the utility model.
Description of reference numerals:
1- water heater housings;2- water tanks;3- apparatus for gasifying fuel;4- injection burners;5- emission-control equipments;6- intelligence Can controller;7- heat-insulation layers;8- water inlet pipes;9- outlet pipes;10- liquid-fuel tanks;11- petrolifts;12- gasifiers;13- is heated Device;The air blowers of 14- first;The air blowers of 15- second;16- fuel nozzles;17- injectors;18- combustion chambers;19- igniters;20- Hydraulic pressure sensor;21- temperature sensors;22- air exhausters;23- discharge ducts;24- exhaust-air monitors;25- control valves;26- gives up Aspiration device.
Embodiment
It should be noted that in the case where not conflicting, the feature in embodiment and embodiment in the utility model can To be mutually combined.
In description of the present utility model, it is to be understood that term " " center ", " longitudinal direction ", " transverse direction ", " on ", " under ", The orientation or position relationship of the instruction such as "front", "rear", "left", "right", " vertical ", " level ", " top ", " bottom ", " interior ", " outer " are Based on orientation shown in the drawings or position relationship, it is for only for ease of description the utility model and simplifies description, rather than indicate Or imply that the device or element of meaning must have specific orientation, with specific azimuth configuration and operation, therefore be not understood that For to limitation of the present utility model.In addition, term " first ", " second " etc. are only used for describing purpose, and it is not intended that indicating Or imply relative importance or the implicit quantity for indicating indicated technical characteristic.Thus, " first ", " second " etc. are defined Feature can express or implicitly include one or more this feature.In description of the present utility model, unless separately It is described, " multiple " are meant that two or more.
, it is necessary to which explanation, unless otherwise clearly defined and limited, term " are pacified in description of the present utility model Dress ", " connected ", " connection " should be interpreted broadly, for example, it may be fixedly connected or be detachably connected, or integratedly Connection;Can be mechanical connection or electrical connection;Can be joined directly together, can also be indirectly connected to by intermediary, It can be the connection of two element internals.For the ordinary skill in the art, on being understood by concrete condition State concrete meaning of the term in the utility model.
Describe the utility model in detail below with reference to the accompanying drawings and in conjunction with the embodiments.
As shown in figure 1, in diel preheating device, including water heater casing 1, water heater casing 1 with outlet pipe 8 and Water tank 2 and liquid-fuel tank 10 that water inlet pipe 9 is connected, it is characterised in that:Also include apparatus for gasifying fuel 3, injection type to burn Device 4, emission-control equipment 5, intelligent controller 6, heat-insulation layer 7, the first air blower 14 and the second air blower 15, injection burner 4 are arranged on the lower section of water tank 2, and apparatus for gasifying fuel 3 is arranged on the lower section of injection burner 4, and apparatus for gasifying fuel 3 passes through cartridge It is connected with injection burner 4, injection burner 4 includes:Fuel nozzle 16, injector 17, combustion chamber 18, fuel nozzle 16th, injector 17 and combustion chamber 18 are sequentially communicated, and apparatus for gasifying fuel 3 includes gasifier 12 and heater 13, and gasifier 12 is set Put below heater 13, heater 13 is arranged on the lower section of fuel nozzle 16, and gasifier 12 and heater 13 are connected by cartridge Connect, gasifier 12 and heater 13 are electrically connected with intelligent controller 6 respectively, emission-control equipment 5 is arranged on the top of water tank 2, intelligence Energy controller 6 is arranged in water heater casing 1, and emission-control equipment 5 is electrically connected with intelligent controller 6.
First air blower 14, the second air blower 15 are arranged on the lower section of injector 17, the first air blower 14, the second air blower 15 Electrically connected with intelligent controller 6.Intelligent controller 6 controls the first air blower 14, the second air blower 15 to be provided enough for combustion gas Air, when closing heating, intelligent controller 6 controls the first air blower 14, the second air blower 15 to be delayed closing in some seconds.
The petrolift 11 is arranged on the bottom of alcohol radical liquid fuel tank 10, and petrolift 11 is electrically connected with intelligent controller 6.
The igniter 19 is arranged in combustion chamber 18, and igniter 19 is electrically connected with intelligent controller 6.
The emission-control equipment 5 is provided with air exhauster 22, discharge duct 23, exhaust-air monitor 24, control valve 25 and given up Aspiration device 26, air exhauster 22 is arranged on the top of water tank 2, and discharge duct 23 is connected with the outlet of air exhauster 22, exhaust-air monitor 24, Control valve 25 is successively set on discharge duct 23, and Waste gas absorbing device 26 is arranged on the lower section of control valve 25, air exhauster 22, waste gas inspection Device 24, control valve 25 and Waste gas absorbing device 26 is surveyed to electrically connect with intelligent controller 6.Air exhauster 22 is analyzed by exhaust-air monitor 24 Exhaust gas constituents, find exceeded waste gas, are handled immediately by Waste gas absorbing device 26, improve Environmental Safety performance, close heating Afterwards, air exhauster 22 and exhaust-air monitor 24 are delayed closing in some seconds.
Hydraulic pressure sensor 20 is arranged on water inlet pipe 8, and hydraulic pressure sensor 20 is electrically connected with intelligent controller 6, hydraulic pressure sensing Water-flow signal is transferred to intelligent controller 6 for detecting whether there is water to flow through by device 18.
Temperature sensor 21 is arranged in water tank 2, and temperature sensor 21 is electrically connected with intelligent controller 6, when water temperature is higher than During the upper limit of design temperature, intelligent controller 6 closes combustion pump 11, stops fuel supply, and water heater stops heating;When water temperature is low When set-point temperature lower limit, the starting fluid pump 11 of intelligent controller 6, fuel supply starts, and water heater is begun to warm up.
Relative to prior art, diel preheating device of the present utility model uses reproducible alcohol radical liquid to fire Material as thermal source, it by petrolift 11, gasifier 12, heater 13 convey gaseous fuel enter in injection burner 3 with Air is lighted after being sufficiently mixed, and improves fuel economy, by the quick heat temperature raising of cold water in water tank 2, and it is useless that burning is produced Gas, by emission-control equipment, carries out exhaust-gas treatment by air exhauster 22.
Operation principle of the present utility model:Outlet pipe 9 is connected with the water inlet of the cooling water pipeline of mould inside, when making User opens cold water switch, and cold water is entered in water tank 2 by water inlet pipe 8, is now arranged on the hydraulic pressure sensor 20 on water inlet pipe 8 Sense that this water flowing signal is transferred to intelligent controller 6 by variation in water pressure, intelligent controller 6 opens petrolift by this signal 11st, gasifier 12, heater 13, the first air blower 14, the first air blower 15, igniter 19, the fuel by gasification, which enters, to be drawn Penetrate formula burner 3 and be sufficiently mixed after-combustion with air, by cool water heating, air exhauster 22 extracts the waste gas produced after burning out, leads to Emission-control equipment 5 is crossed to handle waste gas.Hot water after heating is flowed into be preheated in mould to mould, can pass through temperature Temperature signal is passed to intelligent controller 6 by degree sensor 21, the temperature for the water for controlling to enter in mould using intelligent controller 6 Degree.
Preferred embodiment of the present utility model is the foregoing is only, it is all at this not to limit the utility model Within the spirit and principle of utility model, any modification, equivalent substitution and improvements made etc. should be included in the utility model Protection domain within.

Claims (6)

1. in a kind of diel preheating device, including water heater casing (1), water heater casing (1) with water inlet pipe (8) with going out The connected water tank (2) of water pipe (9), liquid-fuel tank (10), it is characterised in that:Also include apparatus for gasifying fuel (3), injection type to fire Burner (4), emission-control equipment (5), intelligent controller (6), the first air blower (14) and the second air blower (15), injection type combustion Burner (4) is arranged on below water tank (2), and apparatus for gasifying fuel (3) is arranged on below injection burner (4), fuel gas makeup Put (3) to be connected with injection burner (4) by cartridge, injection burner (4) includes fuel nozzle (16), injector (17), combustion chamber (18), fuel nozzle (16), injector (17) and combustion chamber (18) are sequentially communicated, apparatus for gasifying fuel (3) bag Gasifier (12) and heater (13) are included, gasifier (12) is arranged on below heater (13), and heater (13) is arranged on fuel Below nozzle (16), gasifier (12) and heater (13) are connected by cartridge, and gasifier (12) and heater (13) are respectively Electrically connected with intelligent controller (6), emission-control equipment (5) is arranged on above water tank (2), intelligent controller (6) is arranged on heat In hydrophone casing (1), emission-control equipment (5) is electrically connected with intelligent controller (6).
2. diel preheating device according to claim 1, it is characterised in that:The emission-control equipment (5) includes Air exhauster (22), discharge duct (23), exhaust-air monitor (24), control valve (25) and Waste gas absorbing device (26), air exhauster (22) It is arranged on above water tank (2), discharge duct (23) is connected with air exhauster (22) outlet, exhaust-air monitor (24), control valve (25) It is successively set on discharge duct (23), Waste gas absorbing device (26) is arranged on below control valve (25), air exhauster (22), waste gas inspection Device (24), control valve (25) and Waste gas absorbing device (26) is surveyed to electrically connect with intelligent controller (6) respectively.
3. diel preheating device according to claim 1, it is characterised in that:First air blower (14), second Air blower (15) is arranged on below injection burner (4), the first air blower (14), the second air blower (15) by ajutage with Injection burner (4) is connected, and the first air blower (14), the second air blower (15) are electrically connected with intelligent controller (6) respectively.
4. diel preheating device according to claim 1, it is characterised in that:The petrolift (11) is arranged on liquid Fuel tank (10) is internal, and petrolift (11) is electrically connected with intelligent controller (6).
5. diel preheating device according to claim 1, it is characterised in that:Hydraulic pressure sensor (20) is arranged on into water Manage on (8), hydraulic pressure sensor (20) is electrically connected with intelligent controller (6).
6. diel preheating device according to claim 1, it is characterised in that:Temperature sensor (21) is arranged on water tank (2) in, temperature sensor (21) is electrically connected with intelligent controller (6).
CN201621208324.5U 2016-11-09 2016-11-09 Diel preheating device Expired - Fee Related CN206344497U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621208324.5U CN206344497U (en) 2016-11-09 2016-11-09 Diel preheating device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621208324.5U CN206344497U (en) 2016-11-09 2016-11-09 Diel preheating device

Publications (1)

Publication Number Publication Date
CN206344497U true CN206344497U (en) 2017-07-21

Family

ID=59317055

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621208324.5U Expired - Fee Related CN206344497U (en) 2016-11-09 2016-11-09 Diel preheating device

Country Status (1)

Country Link
CN (1) CN206344497U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108248090A (en) * 2018-03-19 2018-07-06 临沂大学 A kind of macromolecule chemical material production compression set

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108248090A (en) * 2018-03-19 2018-07-06 临沂大学 A kind of macromolecule chemical material production compression set

Similar Documents

Publication Publication Date Title
CN206234861U (en) A kind of biological alcohol oil mixing gas generator and its kitchen range
CN106195982A (en) Heating unit and include the steam generator of this heating unit
CN206344497U (en) Diel preheating device
CN104456947A (en) Heat accumulating type pure air heating system
CN106273648A (en) Diel preheating device
CN210334049U (en) Stamping die with preheating function
CN206207749U (en) The combustion control system and hotline heater of combustor
CN205655337U (en) Automatic dual -purpose energy -saving stove of water supply oil gas
CN104296367A (en) Infrared gas water heater
CN205619542U (en) Hot water, steam all -in -one
CN205717874U (en) A kind of useless cigarette preheating type boiler
CN201367971Y (en) Automobile fuel preheater
CN210345868U (en) Novel energy quick heating stove
CN105757971A (en) Waste smoke preheating boiler
CN105841337A (en) Hot water and steam all-in-one machine
CN206514290U (en) A kind of oil combustion stove
CN206831832U (en) A kind of light hydrocarbon carburetors
CN206215776U (en) A kind of stamping mold apparatus for supplying cool water
CN205717877U (en) A kind of useless cigarette reclaiming type boiler
CN205783764U (en) A kind of water heater in terms of boiler for domestic
CN203454133U (en) Dual-preheating type blast combustor
CN216897799U (en) High-pressure water heater boiler
CN210861137U (en) Waste gas waste liquid catalytic oxidation processing system
CN203893427U (en) Boiler waste heat recycling device
CN206942729U (en) A kind of environment-friendly and energy-efficient oil field petroleum machinery wax removal boiler car

Legal Events

Date Code Title Description
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170721

Termination date: 20211109