CN206329145U - A kind of quick assembled type enclosure wall - Google Patents
A kind of quick assembled type enclosure wall Download PDFInfo
- Publication number
- CN206329145U CN206329145U CN201621404243.2U CN201621404243U CN206329145U CN 206329145 U CN206329145 U CN 206329145U CN 201621404243 U CN201621404243 U CN 201621404243U CN 206329145 U CN206329145 U CN 206329145U
- Authority
- CN
- China
- Prior art keywords
- prefabricated
- enclosure wall
- post
- assembled type
- panel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model is related to a kind of quick assembled type enclosure wall, and it includes more than two prefabricated posts, prefabricated panel, and described prefabricated post is reinforced concrete prefabricated column or shaped steel prefabricated post, and the left and right sides of prefabricated panel is fixed with a prefabricated post respectively.The utility model uses mechanization production in factory, and climate is not restricted, and component is accurate, and batch modularization is produced, and low, product quality, which is lost, in manufacturing process is more easy to be effectively controlled.The utility model lifts that speed is fast, it is low that construction site is required at the scene, it is short to social environment influence's cycle of surrounding, do not cause the superior overall performance of environmental pollution, enclosure wall cracking resistance.
Description
Technical field
The utility model belongs to green assembled architecture field, (contains base more specifically to prefabricated panel, prefabricated post
Plinth), prefabricated moulding moulding, can also top set patrolling a channel quick assembled type Assembled surrounding wall.
Background technology
At present, wall material mainly has two kinds:One is based on clay brick, porous brick, cement brick, clinker brick, aerated blocks
Masonry wall, two be with the enclosure wall of the compositions such as filled board, guardrail wires, metal fences net.
Masonry enclosure wall belongs to half wet trade in work progress, and labour demand is intensive, and the generation in work progress is raised
Dirt influences environment, long construction period and is influenceed by rainy weather;And metal enclosure wall needs daily antirust upkeep operation, antirust dimension
Protect in operation and produce escaping gases to environment and human hazard more.
Utility model content
The purpose of this utility model is to overcome the long construction period of traditional enclosure wall, have pollution and enclosure wall heavy to surrounding enviroment
Drop is irregular to be made there is provided a kind of factory the shortcomings of be also easy to produce slight crack, pollution-free, overall assembling speed is fast, surfacing, variable
The big green Assembled enclosing wall in shape space.
In order to achieve the above object, the technical scheme of the utility model offer is:
A kind of quick assembled type enclosure wall, it includes more than two prefabricated posts, prefabricated panel, and described prefabricated post is reinforcing bar
Concrete prefabricated column or shaped steel prefabricated post, the left and right sides of prefabricated panel are fixed with a prefabricated post respectively.
Preferably, prefabricated post side is hung over outside described prefabricated panel, or the two is welded or bolt connection.
Preferably, the described prefabricated post left and right sides is provided with dead slot, prefabricated panel two ends are arranged in dead slot, or two
Person is welded or bolt connection.
Preferably, lateral surface is provided with supporting embedded part or bolt hole in described reinforced concrete prefabricated column, top is set
It is equipped with lifting built-in fitting.Supporting embedded part of the present utility model is connected with temporary support, the other end of temporary support when mounted
Effectively it is fixed on ground.Supporting embedded part can be built-in bolt sleeve.Lifting built-in fitting interlocks in lifting with suspension hook, is easy to
Prefabricated post is lifted.It can hang nail to lift built-in fitting.
Preferably, described prefabricated post includes pedestal and column, pedestal is integral prefabricated with column.
Preferably, described prefabricated post includes pedestal and steel column, steel column bottom passes through built-in fitting with Chuck top
It is connected.
Preferably, described prefabricated post is using steel reinforced concrete rectangular column, different in nature post or H types, T-shaped steel column, base
Seat is made using armored concrete, the base that pedestal (or post connects pedestal) transport is embedded in digging up and filling in on-site hoisting and tamped
In hole.
Preferably, described prefabricated panel uses prefabricated reinforced concrete wall panel or autoclaved lightweight aerated concrete wallboard
Or composite wall board.Light-weighted autoclaved air entrained concrete prefabricated panel is 600mm per tile height, reaches that enclosure wall highly will by splicing
Ask, light-weighted autoclaved aerated concrete panel density is small compared with general cementitious material, effectively reduction enclosure wall fundamental importance;Precast concrete
Wall-plate level is integral prefabricated by enclosure wall requirement for height.Prefabricated panel can set lattice window, light-weighted autoclaved aerating according to requirements
Concrete prefabricated wallboard face can also be carved with lines.
Bear down on one and bear down on one with prefabricated panel preferably, described enclosure wall is additionally provided with prefabricated post, prefabricated post, which is beared down on one, to be arranged on
The top of prefabricated post, prefabricated panel bears down on one above prefabricated panel, and described prefabricated post is beared down on one welds between prefabricated post
Or bolt connection;Described prefabricated panel, which bears down on one, to be connected or welds or bolt connection using pin between prefabricated panel, or
It is connected with two ends prefabricated post.
Preferably, prefabricated post is beared down on one and prefabricated panel bears down on one using the thick light-weighted autoclaved air entrained concrete of 100mm~250mm
Plate, also can be needed to bear down on one using the prefabricated various shapes of armored concrete as attractive in appearance.
Preferably, being provided with patrolling a channel beam, the prefabricated patrol installed above of patrolling a channel beam at the top of described prefabricated post
Prefabricated patrolling a channel guardrail is installed above channel plate, prefabricated patrolling a channel plate.
Preferably, prefabricated patrolling a channel beam can use armored concrete precast beam or H type section steel beams.
Preferably, prefabricated patrolling a channel plate can use reinforced concrete prefabricated board or autoclaved aerated concrete slab.
Preferably, prefabricated patrolling a channel guardrail can use reinforced concrete prefabricated board or autoclaved aerated concrete slab or gold
Category, glass guardrail.
Preferably, described prefabricated panel thickness is 100mm~250mm, prefabricated panel width is in 3m~6m.Thickness and
Width also can be prefabricated on demand.
Lifting built-in fitting of the present utility model interlocks in lifting with suspension hook, is easy to prefabricated post to lift.Lifting built-in fitting can
To be to hang nail.
All kinds of prefabricated components of the present utility model are transported to scene after being made from factory, are formed after being assembled using lifting mode
Assembled enclosing wall.With to construction site requirement is low, construction is quick, do not cause environmental pollution, save labour and improves enclosure wall
The advantage of cracking resistance.
The technical scheme provided using the utility model, compared with prior art, is had the advantages that:
(1) the utility model uses mechanization production in factory, and climate is not restricted, and component is accurate, and batch modularization
Low, product quality is lost in production, manufacturing process to be more easy to be effectively controlled.
(2) the utility model lifts speed and requires social environment influence's week low, to surrounding soon, to construction site at the scene
Phase is short, do not cause the superior overall performance of environmental pollution, enclosure wall cracking resistance.
Brief description of the drawings
Fig. 1 is the structural representation of the quick assembled type enclosure wall of the utility model embodiment 1;
Fig. 2 is the side view of the prefabricated post of the utility model embodiment 1;
Fig. 3 is longitudinal sectional drawing of the prefabricated panel of the utility model embodiment 1;
Fig. 4 is the transverse cross of the quick assembled type enclosure wall of the utility model embodiment 1;
Fig. 5 is the sectional drawing of the prefabricated column foundation of the utility model embodiment 1;
Fig. 6 is the schematic diagram of the prefabricated base for posts of the utility model embodiment 2-3;
Fig. 7 is the sectional drawing that the prefabricated post of the utility model embodiment 1 is beared down on one;
Fig. 8 is the sectional drawing that the prefabricated panel of the utility model embodiment 1 bears down on one;
Fig. 9 is the structural representation of the quick assembled type enclosure wall of the utility model embodiment 2;
Figure 10 is the side view of the prefabricated post of the utility model embodiment 2;
Figure 11 is longitudinal sectional drawing of the prefabricated panel of the utility model embodiment 2;
Figure 12 is the transverse cross of the quick assembled type enclosure wall of the utility model embodiment 2;
Figure 13 is the structural representation of the quick assembled type enclosure wall of the utility model embodiment 3;
Figure 14 is longitudinal sectional drawing of the quick assembled type enclosure wall of the utility model embodiment 3;
Figure 15 is the transverse cross of the quick assembled type enclosure wall of the utility model embodiment 3;
Figure 16 is the prefabricated patrolling a channel plate plan of the quick assembled type enclosure wall of the utility model embodiment 3.
Mark explanation in schematic diagram:1st, foundation ditch;2nd, prefabricated post;3rd, prefabricated panel;4th, prefabricated panel bears down on one;5th, prefabricated post
Bear down on one;6th, supporting embedded part;7th, pre-buried heel slab;8th, steel column;9th, pin;10th, fixing bolt;11st, built-in fitting is lifted;12、
Pedestal;13rd, column;14th, prefabricated patrolling a channel beam;15th, prefabricated patrolling a channel plate;16th, prefabricated patrolling a channel guardrail.
Embodiment
To further appreciate that content of the present utility model, the utility model is described in detail in conjunction with the accompanying drawings and embodiments,
But embodiment not limited to this of the present utility model.
Embodiment 1
With reference to Fig. 1-5,7-8, a kind of quick assembled type enclosure wall that the present embodiment is related to, it includes prefabricated post 2, prefabricated panel
3rd, prefabricated panel bear down on one 4 and prefabricated post bear down on one 5.Prefabricated post 2 is the different in nature post of H types prefabricated reinforced concrete, backfill buried depth face with
It is down pedestal 12 (heel foundation), pedestal and column 13 are integral prefabricated.Lifting built-in fitting 11 is set at the top of prefabricated post, for prefabricated post
Lifting assembling is used.Lateral surface can be provided with supporting embedded part 6 in prefabricated post, and interim positioning is reinforced during for assembling.Enclose on prefabricated post edge
Wall direction both sides (or side) are provided with dead slot, after often across enclosure wall two ends prefabricated post assembling is in place, load pre- using lifting successively
Wallboard 3 processed, prefabricated panel 4, prefabricated post of bearing down on one bear down on one 5 so that the two ends of prefabricated panel 3 are arranged in dead slot, and prefabricated post is beared down on one 5 peaces
Mounted in the top of prefabricated post 2, prefabricated panel bears down on one 4 installed in the top of prefabricated panel 3.Lifting built-in fitting 11, which is used, hangs nail.Support
Built-in fitting 6 uses bolt collar.
The thickness of wallboard panels of the present utility model is 100mm~250mm, using light-weighted autoclaved air entrained concrete batten,
Can also be precast concrete curtain wall penel, every section of Assembled enclosing wall spacing 3m~6m, enclosure wall height can be spelled by actual operation requirements
Connect or customize.
The quick assembled type enclosure wall of the present embodiment is assembled using following steps:
(1) the good post reinforcing bar of colligation in die station, is setting temporary support pre-embedded bolt on Side shuttering inside and outside prefabricated post 2
Sleeve 6, assembles template, fixed to hang 11 after-pouring concrete of nail.
(2) concrete curing intensity reaches form removal after requirement, existing to storage space or construction by hanging the lifting of nail 11 transport
, in the foundation ditch 1 for being embedded in digging up and filling in and having tamped.
(3) prefabricated panel 3 of coagulation great soil group, prefabricated panel 4, prefabricated post of bearing down on one bear down on one 5 making ways with prefabricated post 2.
Embodiment 2
Reference picture 6,9-12, a kind of quick assembled type enclosure wall shaped steel column type and embodiment 1 of the present embodiment are substantially similar, its
Difference is:The prefabricated post 2 of the present embodiment includes pedestal 12 and H types steel column 8, the top of pedestal 12 and the bottom of steel column 8
It is connected using heel slab 7.Prefabricated panel is fixedly connected with prefabricated post using fixing bolt 10.Using pin 9 by prefabricated panel 3
Bear down on one with prefabricated panel and 4 be fixedly connected.
The quick assembled type enclosure wall of the present embodiment is assembled using following steps:The pedestal of the prefabricated post 2 of the present embodiment
12 are fabricated separately with steel column 8, assemble;Pedestal 12 is made using armored concrete;Prefabricated post 8 uses shaped steel column production;Pedestal
The 12 pre-buried steel column heel slabs 7 in top;The every section of Assembled enclosing wall intercolumniation 3m~6m of the present embodiment 2, may also set up smaller spacing.
Embodiment 3
Reference picture 6,13-16, a kind of quick assembled type enclosure wall shaped steel column type and embodiment 2 of the present embodiment are substantially similar,
Its difference is:The pendant of prefabricated panel 3 of the present embodiment is in the side of steel column 8, and the present embodiment is not required to set wallboard to bear down on one 4
Bear down on one 5 with prefabricated post, prefabricated patrolling a channel beam 14 is installed at the top of the opposite side of steel column 8, prefabricated patrolling a channel beam 14 is pre- by two
Post connection processed, prefabricated patrolling a channel plate 15 is stacked on prefabricated patrolling a channel beam 14 and by reserved peg hole or bolt connection,
The prefabricated top of patrolling a channel plate 15 is provided with prefabricated patrolling a channel guardrail 16, and prefabricated patrolling a channel guardrail 16 is logical by prefabricated patrol
The embedded part set on guidance tape 15 is connected.
The quick assembled type enclosure wall installation step be the same as Example 2 of the present embodiment, and assembling is set up on subsequent step successively
Prefabricated patrolling a channel beam 14, prefabricated patrolling a channel plate 15, prefabricated patrolling a channel guardrail 16.
Schematically the utility model and embodiments thereof are described above, the description does not have restricted, accompanying drawing
Shown in be also one of embodiment of the present utility model, actual structure is not limited thereto.So this area is general
Logical technical staff is enlightened by it, in the case where not departing from the utility model creation objective, being designed without creative with being somebody's turn to do
The similar frame mode of technical scheme and embodiment, all should belong to protection domain of the present utility model.
Claims (10)
1. a kind of quick assembled type enclosure wall, it is characterised in that:It includes more than two prefabricated posts, prefabricated panel, and described is pre-
Post processed is reinforced concrete prefabricated column or shaped steel prefabricated post, and the left and right sides of prefabricated panel is fixed with a prefabricated post respectively.
2. a kind of quick assembled type enclosure wall according to claim 1, it is characterised in that:Hung over outside described prefabricated panel pre-
Post side processed, or the two is welded or bolt connection.
3. a kind of quick assembled type enclosure wall according to claim 1, it is characterised in that:The described prefabricated post left and right sides is set
There is dead slot, prefabricated panel two ends are arranged in dead slot, or the two is welded or bolt connection.
4. a kind of quick assembled type enclosure wall according to claim 1, it is characterised in that:Described reinforced concrete prefabricated column
Interior lateral surface is provided with built-in fitting or bolt hole, and top is provided with lifting built-in fitting.
5. a kind of quick assembled type enclosure wall according to claim 1, it is characterised in that:Described reinforced concrete prefabricated column
Including pedestal and column, pedestal is integral prefabricated with column.
6. a kind of quick assembled type enclosure wall according to claim 1, it is characterised in that:Described shaped steel prefabricated post includes base
Seat and steel column, steel column bottom is connected with Chuck top by built-in fitting.
7. a kind of quick assembled type enclosure wall according to claim 1, it is characterised in that:Described prefabricated panel is using prefabricated
Reinforced concrete wall panel or autoclaved lightweight aerated concrete wallboard or composite wall board.
8. a kind of quick assembled type enclosure wall according to claim 1, it is characterised in that:Described quick assembled type enclosure wall is also
It is provided with prefabricated post and bears down on one and bear down on one with prefabricated panel, prefabricated post is beared down on one installed in the top of prefabricated post, prefabricated panel bears down on one installation
Above prefabricated panel, described prefabricated post is beared down on one welds or bolt connection between prefabricated post;Described prefabricated panel bears down on one
It is connected or welds or bolt connection using pin between prefabricated panel, or is connected with two ends prefabricated post.
9. a kind of quick assembled type enclosure wall according to claim 1, it is characterised in that:It is fixed with the top of described prefabricated post
Prefabricated patrol is installed above patrolling a channel beam, patrolling a channel beam prefabricated patrolling a channel plate installed above, prefabricated patrolling a channel plate
Passage guardrail.
10. a kind of quick assembled type enclosure wall according to claim 1, it is characterised in that:Described prefabricated panel thickness is
100mm~250mm, prefabricated panel width is in 3m~6m.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621404243.2U CN206329145U (en) | 2016-12-20 | 2016-12-20 | A kind of quick assembled type enclosure wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621404243.2U CN206329145U (en) | 2016-12-20 | 2016-12-20 | A kind of quick assembled type enclosure wall |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206329145U true CN206329145U (en) | 2017-07-14 |
Family
ID=59290389
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621404243.2U Active CN206329145U (en) | 2016-12-20 | 2016-12-20 | A kind of quick assembled type enclosure wall |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206329145U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109209011A (en) * | 2018-09-14 | 2019-01-15 | 上海建工二建集团有限公司 | Prefabricated enclosure wall bears down on one and its makes and construction method |
CN109667469A (en) * | 2018-12-29 | 2019-04-23 | 龙信集团江苏建筑产业有限公司 | A kind of prefabricated assembled recycling enclosure wall |
CN110847699A (en) * | 2019-11-28 | 2020-02-28 | 松塔知识产权运营武汉有限公司 | High-performance concrete prefabricated wall |
-
2016
- 2016-12-20 CN CN201621404243.2U patent/CN206329145U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109209011A (en) * | 2018-09-14 | 2019-01-15 | 上海建工二建集团有限公司 | Prefabricated enclosure wall bears down on one and its makes and construction method |
CN109667469A (en) * | 2018-12-29 | 2019-04-23 | 龙信集团江苏建筑产业有限公司 | A kind of prefabricated assembled recycling enclosure wall |
CN110847699A (en) * | 2019-11-28 | 2020-02-28 | 松塔知识产权运营武汉有限公司 | High-performance concrete prefabricated wall |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US5501057A (en) | Unit masonry fence and method for erecting | |
CN208502433U (en) | A kind of prefabricated assembled Assembled surrounding wall with vertical curtain wall penel component | |
CN206070562U (en) | Subassembly formula underground structure | |
WO2016062224A1 (en) | Integrated column-equipped heat insulation wallboard, manufacturing and building processes and corollary equipment thereof | |
CN103615110A (en) | Irregular oblique-crossing web-shaped grillage beam hyperbolic roof structure construction method | |
CN206329145U (en) | A kind of quick assembled type enclosure wall | |
CN112227759B (en) | Repair, reinforcement and migration method for historic building clean water wall | |
CN104947846B (en) | A kind of prefabricated integral frame light filling lining and preparation method thereof | |
CN201747122U (en) | Reusable precast assembled building fence wall | |
CN107989238A (en) | A kind of cast-in-place sandwiched heat-preservation shear wall structure, assembled architecture and engineering method | |
CN103590486A (en) | Anti-seismic energy saving three-dimensional mortise and tenon joint net fixing one-piece cast building structure and construction method | |
CN110005104A (en) | A kind of fabricated heat preservation decoration integrative laminated floor slab and its construction method | |
CN108118807A (en) | A kind of steel framework concrete partition and its construction method | |
CN213143104U (en) | Hoisting type finished product earth retaining enclosure device | |
CN110344535A (en) | A kind of prefabricated assembled combined wall board and construction method realized concealed beam and exempt from formwork | |
CN109267578B (en) | Inclined plane plain concrete structure and construction method thereof | |
CN209891805U (en) | Prefabricated assembled recycling enclosure | |
CN207110035U (en) | Assembled steel tendon concrete frame structure based on steel plate connection joint | |
CN213573164U (en) | Ancient building clear water wall body migration bottom reinforcing apparatus | |
CN111719578B (en) | Archaized building and construction process | |
CN205329714U (en) | Compound retaining wall structure of highway precast concrete piece | |
CN205444514U (en) | Bearing light insulation intergral template | |
CN110593440B (en) | Construction method of prefabricated wall structure | |
CN211229781U (en) | Novel prefabricated hollow enclosure | |
CN207597652U (en) | A kind of cast-in-place sandwiched heat-preservation shear wall structure and assembled architecture |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder |
Address after: 311419 Building No. 53, Yushan Village, Yushan Township, Fuyang City, Hangzhou City, Zhejiang Province Patentee after: Zhejiang Hangjiazetong Building Energy Saving New Materials Co., Ltd. Address before: 311419 Building No. 53, Yushan Village, Yushan Township, Fuyang City, Hangzhou City, Zhejiang Province Patentee before: Hangzhou Zetong Architecture Energy Saving New Materials Co., Ltd. |
|
CP01 | Change in the name or title of a patent holder |