CN206319457U - Air-flow guides and utilized system in a kind of double-layer curtain wall - Google Patents

Air-flow guides and utilized system in a kind of double-layer curtain wall Download PDF

Info

Publication number
CN206319457U
CN206319457U CN201621373765.0U CN201621373765U CN206319457U CN 206319457 U CN206319457 U CN 206319457U CN 201621373765 U CN201621373765 U CN 201621373765U CN 206319457 U CN206319457 U CN 206319457U
Authority
CN
China
Prior art keywords
curtain wall
layer curtain
cavity
air
transverse slat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201621373765.0U
Other languages
Chinese (zh)
Inventor
徐凯宏
李朕鸿
梁伟鹏
白视玮
罗青正
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Boda Construction Group Co Ltd
Original Assignee
Shenzhen Boda Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Boda Construction Group Co Ltd filed Critical Shenzhen Boda Construction Group Co Ltd
Priority to CN201621373765.0U priority Critical patent/CN206319457U/en
Application granted granted Critical
Publication of CN206319457U publication Critical patent/CN206319457U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Bearing And Curtain Walls (AREA)

Abstract

The utility model is related to air-flow in a kind of double-layer curtain wall and guides and utilize system, it includes internal layer curtain wall, outer layer curtain wall and central cantilever, the central cantilever includes internal connection end and external connection terminal, the inside connection end and the external connection terminal are located at the both ends of the central cantilever respectively, the internal layer curtain wall is connected with the inside connection end, the outer layer curtain wall is connected with the external connection terminal, the internal layer curtain wall and the outer layer curtain wall are hung on the steel construction of building simultaneously by the central cantilever, and form a cavity between the internal layer curtain wall and the outer layer curtain wall, the central cantilever is located in the cavity, the cavity is connected with air channel, the air channel is connected between the cavity and building elevator, air-flow produced by the cavity is directly directed into the building elevator by the air channel, wind-driven generator is provided with the air channel, airflow function in the air channel is on the wind-driven generator, the wind-driven generator is set to generate electricity.

Description

Air-flow guides and utilized system in a kind of double-layer curtain wall
Technical field
The utility model is related to a kind of air-flow guiding and utilizes system, particularly relates to a kind of gas applied in double-layer curtain wall Conductance draws and utilizes system.
Background technology
It is well known that double-layer curtain wall is also known as passage of heat curtain wall, type of respiration curtain wall, ventilation type curtain wall, energy-saving curtain wall etc..Its By inside and outside two layers of facade contexture, the air cushioning layer formed between an indoor and outdoor.Outer layer can be by bright frame, hidden frame or point branch Formula curtain wall is constituted.Internal layer can be made up of bright frame, frame concealed curtain wall or the door and window with opening door-leaf and access path.Can also be one The both sides of individual separate support structure set glass surface layer, form the less double-skin facade construction of space length.Its inside and outside curtain wall it Between formed a relative closure space.There is air inlet its underpart, and exhaust outlet is arranged at top, and controllable air flows shape therebetween State.Provided with controllable air inlet, exhaust outlet, sunshading board and blinds etc..The main function of double-layer curtain wall is to make construction outer layer Natural Changes in weather is effectively adapted to, the thermal and insulating performance of curtain wall is improved.The sound insulation property of curtain wall is improved, improves indoor bar Part.Its noise control effect that insulates against sound is notable in addition.
Double-layer curtain wall has inside and outside two layers of curtain wall layer, and will necessarily have a cavity between two layers of curtain wall layer, due to curtain Wall various pieces will necessarily be had air-flow by its different cavity of intensity of solar irradiation, if when specific implementation not Air-flow is exported from cavity to pole held and occur potential safety hazard, also occur the situation of curtain wall hot-spot in addition, and conventional art In be all to be exported air-flow by the way of air outlet is additionally opened up, but be accomplished by opening up number when curtain wall area is very big The numerous air outlet of amount can realize purpose derived from air-flow, meanwhile, simply simply air-flow is led in conventional art Go out, and it is not utilized completely, in turn result in the waste of wind energy, and this is the major defect for conventional art.
Utility model content
The utility model provides air-flow in a kind of double-layer curtain wall and guides and utilize system, and it can be to the gas in double-layer curtain wall Stream is guided and is used, and this is for main purpose of the present utility model.
The technical scheme that the utility model is used for:Air-flow guides and utilizes system in a kind of double-layer curtain wall, and it includes Internal layer curtain wall, outer layer curtain wall and central cantilever, the central cantilever include internal connection end and external connection terminal, connect inside this The both ends that end and the external connection terminal are located at the central cantilever respectively are connect, the internal layer curtain wall is connected with the inside connection end Connect, the outer layer curtain wall is connected with the external connection terminal, it is by the central cantilever that the internal layer curtain wall and the outer layer curtain wall is same When be hung on the steel construction of building, and form a cavity between the internal layer curtain wall and the outer layer curtain wall, the central cantilever In the cavity.
The cavity is connected with air channel, and the air channel is connected between the cavity and building elevator, is produced in the cavity Raw air-flow is directly directed into the building elevator by the air channel, is provided with wind-driven generator in the air channel, the wind Airflow function in road enables the wind-driven generator to generate electricity on the wind-driven generator.
By several, the air channel is connected the building elevator with the cavity simultaneously from top to bottom, is set in the air channel Narrow passage is equipped with, the wind-driven generator is arranged in the narrow passage.
The outer layer curtain wall includes shingle nail and partition panel, wherein, some pieces of shingle nails are stitched together to be formed each other The outer layer curtain wall, the partition panel is connected to the inner side of the shingle nail, meanwhile, the partition panel set in the cavity, by this every Disconnected plate isolates to form some airslides in the cavity, and by the airslide air-flow in the cavity can be smoothly directed to In the air channel, the internal layer curtain wall includes inner wall panel, and some pieces of inner wall panels are stitched together to form the internal layer curtain wall each other.
The partition panel is vertical with the shingle nail, also, the partition panel is arranged on the seaming position of the shingle nail.
The central cantilever includes outer pawl head, interior pawl head and connecting rod, wherein, the outer pawl head and the interior pawl head are set respectively Put at the two ends of the connecting rod, the outer pawl capitiform is into the external connection terminal, and the interior pawl capitiform is into the inside connection end.
The outer pawl head includes external splint and inner splint, and the external splint is folded on the lateral surface of the shingle nail, the inner clip Plate is folded on the medial surface of the shingle nail, and fixed screw is located in the external splint, the shingle nail and the inner splint successively, So that three be fixed together, between two pieces of the arbitrary neighborhood shingle nails, and fill out and be provided with the outer pawl head Sealed gluing block.
The interior pawl head includes connection framework and fixed frame, wherein, the fixed frame is screwed in the steel of building In structure, the connection framework includes two blocks of side plates, the first transverse slat and the second transverse slat, and two blocks of side plates be arranged in parallel, and this first Transverse slat and second transverse slat are set in parallel between two blocks of side plates, are surrounded and are formed with first transverse slat by two blocks of side plates One connecting cavity, by two blocks of side plates and first transverse slat, second transverse slat around forming a cavity, the cavity be located at this first Between transverse slat and second transverse slat, the fixed frame is located in the connecting cavity, and the fixed frame is fixedly connected at by screw On first transverse slat, boss is provided with second transverse slat, the connecting rod is fixedly connected in the boss, respectively should at two pieces The upper and lower ends portion of side plate is provided with neck, and sealing strip is inserted with the neck.
The connecting rod includes outside linking arm and inner side linking arm, and the outside linking arm is with the inner side linking arm by turning Axle is articulated, and is installed by such a structure design convenient construction, and the outer pawl head is arranged on the end of the outside linking arm, and The interior pawl head is arranged on the end of the inner side linking arm.
The partition panel is fastened in the outside linking arm, and the outside linking arm includes cursor and snap-arms, the rotation Arm is fixedly connected with the snap-arms, wherein, the snap-arms include two arm bodies, and two arm bodies be arranged in parallel, and should at two A holding chamber is formed between arm body, the partition panel is folded in the holding chamber, be screwed respectively on two arm bodies There is arm plate, being capable of being folded in partition panel stabilization in the holding chamber by the arm plate.
The inner side linking arm includes pivot end and inserted terminal, and the wherein pivot end is articulated with the cursor, should Inserted terminal is plugged in the boss of the interior pawl head, and cutting ferrule is also arranged with the inserted terminal, and the cutting ferrule is embedded in the inner wall panel In to fix relative position.
The beneficial effects of the utility model are:Because the curtain wall area outside buildings in general is all than larger, double-deck The cavity size formed in curtain wall also than larger, thus exist inside and outside double-layer curtain wall or between various pieces the temperature difference when Air motion will be occurred by waiting in the cavity, and then produce wind energy, when concrete application, if wind energy can not be directed simultaneously From the cavity outflow certainly will occur potential safety hazard and other it is many problem of, and be all using additionally opening in conventional art The mode for setting out air port exports air-flow, but is accomplished by opening up large number of air-out eloquence when curtain wall area is very big Purpose derived from air-flow can be realized, meanwhile, simply simply air-flow is exported in conventional art, and completely not to it Utilized, in turn resulted in the waste of wind energy, technology of the present utility model, passed through the wind-power electricity generation set in the air channel Wind energy produced by machine can make full use of the cavity of this in double-layer curtain wall is generated electricity, and is reached and is suited measures to local conditions to produce green electric power supply Purpose, it is emphasized that multiple elevator and elevator are equipped with current building, and the size of elevator All than larger, while using the air channel that the cavity its exhaust effect that is connected with multiple elevators is preferable.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model.
Fig. 2 is overlooking the structure diagram of the present utility model.
Fig. 3 is the structural representation that the utility model connects framework.
Fig. 4 is side structure schematic view of the present utility model.
Embodiment
As shown in Figures 1 to 4, air-flow guides and utilized system in a kind of double-layer curtain wall, and it includes internal layer curtain wall 10, outer layer curtain Wall 20 and central cantilever 30.
The central cantilever 30 includes internal connection end 31 and external connection terminal 32, the inside connection end 31 and this outside Connection end 32 is located at the both ends of the central cantilever 30 respectively.
The internal layer curtain wall 10 is connected with the inside connection end 31, and the outer layer curtain wall 20 is connected with the external connection terminal 32 Connect.
The internal layer curtain wall 10 and the outer layer curtain wall 20 are hung on to the steel knot of building simultaneously by the central cantilever 30 On structure 40, and a cavity 50 is formed between the internal layer curtain wall 10 and the outer layer curtain wall 20, the central cantilever 30 is positioned at the cavity In 50.
When specific implementation, because curtain wall area outside buildings in general is all than larger, in double-layer curtain wall The size of cavity 50 formed, thus should when there is the temperature difference inside and outside double-layer curtain wall or between various pieces also than larger Will occur air motion in cavity 50, and then produce wind energy, when concrete application, if wind energy can not be directed and from In the cavity 50 outflow certainly will occur potential safety hazard and other it is many problem of, and be all using additionally opening in conventional art The mode for setting out air port exports air-flow, but is accomplished by opening up large number of air-out eloquence when curtain wall area is very big Purpose derived from air-flow can be realized, meanwhile, simply simply air-flow is exported in conventional art, and completely not to it Utilized, in turn resulted in the waste of wind energy.
The cavity 50 is connected with air channel 60, and the air channel 60 is connected between the cavity 50 and building elevator 70.
Air-flow produced by the cavity 50 is directly directed into the building elevator 70 by the air channel 60.
Due to can all configure elevator in present high-rise, and elevator is all provided in elevator, this practicality New utilization air channel directly connects the cavity 50 with the building elevator 70, in not additionally increase air inlet, air outlet In the case of directly carry out air draft using elevator, can greatly simplify architectural construction, reduce curtain wall cost.
Be provided with wind-driven generator 61 in the air channel 60, the airflow function in the air channel 60 on the wind-driven generator 61, The wind-driven generator 61 is set to generate electricity, the power transmission produced by the wind-driven generator 61 is for people to use into building.
In technology of the present utility model, it can be made full use of by the wind-driven generator 61 set in the air channel 60 double Wind energy in layer curtain wall produced by the cavity 50 is generated electricity, and reaches the purpose for suiting measures to local conditions to produce green electric power supply, it is emphasized that , be equipped with multiple elevator and elevator in current building, and elevator size all than larger, simultaneously It is using the air channel 60 that the cavity 50 its exhaust effect that is connected with multiple elevators is preferable.
When specific implementation, the building elevator 70 passes through several air channels 60 and the sky simultaneously from top to bottom Chamber 50 is connected.
Narrow passage 62 is provided with the air channel 60, the wind-driven generator 61 is arranged in the narrow passage 62 to reach convergence The purpose that air-flow fully generates electricity.
When specific implementation, the outer layer curtain wall 20 includes shingle nail 21 and partition panel 22, wherein, some pieces of walls Panel 21 is stitched together to form the outer layer curtain wall 20 each other, and the partition panel 22 is connected to the inner side of the shingle nail 21, meanwhile, should Partition panel 22 is arranged in the cavity 50.
Isolate by the partition panel 22 in the cavity 50 and form some airslides 221, can be made by the airslide 221 Air-flow in the cavity 50 is smoothly directed in the air channel 60, to lift the speed and flow efficiency of air current flow.
When specific implementation, the partition panel 22 is vertical with the shingle nail 21, also, the partition panel 22 is arranged on the wall The seaming position of panel 21.
The internal layer curtain wall 10 includes inner wall panel 11, and some pieces of inner wall panels 11 are stitched together to form the internal layer each other Curtain wall 10.
When specific implementation, the shingle nail 21, the partition panel 22 and the inner wall panel 11 are all by can be by tempering Doubling glass is made, to lift the overall appearance effect of curtain wall.
When specific implementation, the central cantilever 30 includes outer pawl first 33, interior pawl first 34 and connecting rod 35, wherein, The outer pawl first 33 and the interior pawl first 34 are separately positioned on the two ends of the connecting rod 35, and the outer pawl first 33 forms the external connection terminal 32, the interior pawl first 34 forms the inside connection end 31.
The outer pawl first 33 includes external splint 331 and inner splint 332, and the external splint 331 is folded in the outer of the shingle nail 21 On side, the inner splint 332 is folded on the medial surface of the shingle nail 21.
Fixed screw is located in the external splint 331, the shingle nail 21 and the inner splint 332 successively, so that by three It is fixed together.
The outer pawl first 33 can by four pieces, the shingle nail 21 be fixed together simultaneously.
Filled out between two pieces of the arbitrary neighborhood shingle nails 21, and in the outer pawl first 33 provided with sealed gluing block 333.
The interior pawl first 34 includes connection framework 341 and fixed frame 342, wherein, the fixed frame 342 is screwed in On the steel construction 40 of building.
The connection framework 341 includes two blocks of side plates 343, the first transverse slat 344 and the second transverse slat 345.
Two blocks of side plates 343 be arranged in parallel, and first transverse slat 344 and second transverse slat 345 are set in parallel in two pieces and be somebody's turn to do Between side plate 343.
By two blocks of side plates 343 and first transverse slat 344 around one connecting cavity 346 of formation.
By two blocks of side plates 343 and first transverse slat 344, second transverse slat 345 around one cavity 347 of formation, the sky Chamber 347 is located between first transverse slat 344 and second transverse slat 345.
The fixed frame 342 is located in the connecting cavity 346, the fixed frame 342 by screw be fixedly connected at this On one transverse slat 344, boss 348 is provided with second transverse slat 345, the connecting rod 35 is fixedly connected in the boss 348.
The upper and lower ends portion of two blocks of side plates 343 is provided with neck 349 respectively, sealing strip is inserted with the neck 349, To reach the effect of waterproof.
The connecting rod 35 includes outside linking arm 36 and inner side linking arm 37, and the outside linking arm 36 is connected with the inner side Arm 37 is articulated by rotating shaft 38, is installed by such a structure design convenient construction, and the outer pawl first 33 is arranged on the outside The end of linking arm 36, and the interior pawl first 34 is arranged on the end of the inner side linking arm 37.
The partition panel 22 is fastened in the outside linking arm 36, and the outside linking arm 36 includes cursor 361 and clamping Arm 362.
The cursor 361 is fixedly connected with the snap-arms 362, wherein, the snap-arms 362 include two arm bodies 363, two The arm body 363 be arranged in parallel, and forms a holding chamber between two arm bodies 363, and the partition panel 22 is folded in the clamping In chamber.
Arm plate 364 has been screwed respectively on two arm bodies 363, can be by the partition panel by the arm plate 364 22 stable are folded in the holding chamber.
The inner side linking arm 37 includes pivot end and inserted terminal 371, and the wherein pivot end is articulated in the cursor 361 Together, the inserted terminal 371 is plugged in the boss 348 of the interior pawl first 34.
Cutting ferrule 372 is also arranged with the inserted terminal 371, the cutting ferrule 372 is embedded in the inner wall panel 11 with stationary phase pair Position.

Claims (6)

1. air-flow guides and utilized system in a kind of double-layer curtain wall, it includes internal layer curtain wall, outer layer curtain wall and central cantilever, should Central cantilever includes internal connection end and external connection terminal, and the inside connection end and the external connection terminal are located in this respectively The both ends of cantilever are entreated, the internal layer curtain wall is connected with the inside connection end, and the outer layer curtain wall is connected with the external connection terminal, The internal layer curtain wall and the outer layer curtain wall are hung on the steel construction of building simultaneously by the central cantilever, and in the internal layer A cavity is formed between curtain wall and the outer layer curtain wall, the central cantilever is located in the cavity, it is characterised in that:
The cavity is connected with air channel, and the air channel is connected between the cavity and building elevator, produced by the cavity Air-flow is directly directed into the building elevator by the air channel, wind-driven generator is provided with the air channel, in the air channel Airflow function on the wind-driven generator, the wind-driven generator is generated electricity.
2. air-flow guides and utilized system in a kind of double-layer curtain wall as claimed in claim 1, it is characterised in that:From top to bottom should By several, the air channel is connected building elevator with the cavity simultaneously, is provided with narrow passage in the air channel, the wind-force Generator is arranged in the narrow passage.
3. air-flow guides and utilized system in a kind of double-layer curtain wall as claimed in claim 1, it is characterised in that:The outer layer curtain wall Including shingle nail and partition panel, wherein, some pieces of shingle nails are stitched together to form the outer layer curtain wall, the partition panel each other The inner side of the shingle nail is connected to, meanwhile, the partition panel is set in the cavity, isolates shape in the cavity by the partition panel Into some airslides, by the airslide air-flow in the cavity can be smoothly directed in the air channel, the internal layer curtain wall Including inner wall panel, some pieces of inner wall panels are stitched together to form the internal layer curtain wall each other.
4. air-flow guides and utilized system in a kind of double-layer curtain wall as claimed in claim 3, it is characterised in that:The partition panel with The shingle nail is vertical, also, the partition panel is arranged on the seaming position of the shingle nail.
5. air-flow guides and utilized system in a kind of double-layer curtain wall as claimed in claim 3, it is characterised in that:The central cantilever Including outer pawl head, interior pawl head and connecting rod, wherein, the outer pawl head and the interior pawl head are separately positioned on the two of the connecting rod End, the outer pawl capitiform into the external connection terminal, the interior pawl capitiform into the inside connection end,
The outer pawl head includes external splint and inner splint, and the external splint is folded on the lateral surface of the shingle nail, inner splint folder It is located on the medial surface of the shingle nail, fixed screw is located in the external splint, the shingle nail and the inner splint successively, so that Three is fixed together, filled out between two pieces of the arbitrary neighborhood shingle nails, and in the outer pawl head provided with sealing Blob of viscose,
The interior pawl head includes connection framework and fixed frame, wherein, the fixed frame is screwed in the steel construction of building On, the connection framework includes two blocks of side plates, the first transverse slat and the second transverse slat, and two blocks of side plates be arranged in parallel, first transverse slat And second transverse slat is set in parallel between two blocks of side plates, is surrounded by two blocks of side plates and first transverse slat and form a company Chamber is connect, by two blocks of side plates and first transverse slat, second transverse slat around a cavity is formed, the cavity is located at first transverse slat Between second transverse slat, the fixed frame is located in the connecting cavity, the fixed frame by screw be fixedly connected at this On one transverse slat, boss is provided with second transverse slat, the connecting rod is fixedly connected in the boss, respectively in two blocks of side plates Upper and lower ends portion be provided with neck, be inserted with sealing strip in the neck.
6. air-flow guides and utilized system in a kind of double-layer curtain wall as claimed in claim 5, it is characterised in that:The connecting rod bag Outside linking arm and inner side linking arm are included, the outside linking arm is articulated by rotating shaft with the inner side linking arm, passed through Such a structure design convenient construction is installed, and the outer pawl head is arranged on the end of the outside linking arm, and the interior pawl head is arranged on this The end of inner side linking arm,
The partition panel is fastened in the outside linking arm, the outside linking arm include cursor and snap-arms, the cursor with The snap-arms are fixedly connected, wherein, the snap-arms include two arm bodies, and two arm bodies be arranged in parallel, and in two arm bodies Between form a holding chamber, the partition panel is folded in the holding chamber, and arm has been screwed respectively on two arm bodies Plate, can be folded in the holding chamber by the arm plate by what the partition panel was stablized,
The inner side linking arm includes pivot end and inserted terminal, and the wherein pivot end is articulated with the cursor, the grafting End be plugged in the boss of the interior pawl head, be also arranged with cutting ferrule on the inserted terminal, the cutting ferrule be embedded in the inner wall panel with Fixed relative position.
CN201621373765.0U 2016-12-15 2016-12-15 Air-flow guides and utilized system in a kind of double-layer curtain wall Withdrawn - After Issue CN206319457U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621373765.0U CN206319457U (en) 2016-12-15 2016-12-15 Air-flow guides and utilized system in a kind of double-layer curtain wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621373765.0U CN206319457U (en) 2016-12-15 2016-12-15 Air-flow guides and utilized system in a kind of double-layer curtain wall

Publications (1)

Publication Number Publication Date
CN206319457U true CN206319457U (en) 2017-07-11

Family

ID=59267975

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621373765.0U Withdrawn - After Issue CN206319457U (en) 2016-12-15 2016-12-15 Air-flow guides and utilized system in a kind of double-layer curtain wall

Country Status (1)

Country Link
CN (1) CN206319457U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106481004B (en) * 2016-12-15 2019-04-05 深圳市博大建设集团有限公司 Air-flow guiding and system is utilized in a kind of double-layer curtain wall

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106481004B (en) * 2016-12-15 2019-04-05 深圳市博大建设集团有限公司 Air-flow guiding and system is utilized in a kind of double-layer curtain wall

Similar Documents

Publication Publication Date Title
CN102174857A (en) Heat preservation ventilating rebuilding method of low-floor building external wall and roof
CN209891487U (en) Double-deck unit curtain wall construction in wind channel that leads to more
CN201065591Y (en) Respiration type solar energy curtain wall
WO2017005155A1 (en) Double-layer heat-insulated and ventilated skin structure for external building wall
CN201897282U (en) Power ventilator for doors, windows and curtain walls
CN206319457U (en) Air-flow guides and utilized system in a kind of double-layer curtain wall
CN206346364U (en) A kind of environmentally friendly hollow glass curtain wall of energy-saving double-layer
CN205776938U (en) Circulation dual layer elements curtain wall in energy-conserving intelligent
CN107893610A (en) A kind of shading integrated door and window structure
CN106801484A (en) A kind of full-automatic photovoltaic shutter breathing glass curtain wall
CN206722157U (en) A kind of full-automatic photovoltaic shutter breathing glass curtain wall
CN207405764U (en) A kind of energy saving and environment friendly green building device
CN206090973U (en) Double -deck energy -saving curtain wall
CN106481004B (en) Air-flow guiding and system is utilized in a kind of double-layer curtain wall
CN206903023U (en) A kind of environment-friendly type artificial components for building roof
CN202755866U (en) Door/window structure capable of forming air isolation chambers
CN102587807B (en) Hybrid ventilating window
CN205259859U (en) Solar energy light and heat window with sunshade heat preservation function
CN106246081A (en) A kind of ventilation type aluminum window
CN202913549U (en) Gallery type circulating curtain wall
CN202348065U (en) Energy-saving and environment-friendly door and window with generating functions
CN207660500U (en) A kind of air purification Energy Saving Windows
CN206521823U (en) A kind of environment protection ventilating lighting space structure
CN206319452U (en) A kind of large-span double-layer curtain wall connecting cantilever
CN214272538U (en) Double-layer curtain wall system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20170711

Effective date of abandoning: 20190405