CN206289543U - Hanging Basket cantilever casting box girder sections concrete curing system - Google Patents

Hanging Basket cantilever casting box girder sections concrete curing system Download PDF

Info

Publication number
CN206289543U
CN206289543U CN201621183514.6U CN201621183514U CN206289543U CN 206289543 U CN206289543 U CN 206289543U CN 201621183514 U CN201621183514 U CN 201621183514U CN 206289543 U CN206289543 U CN 206289543U
Authority
CN
China
Prior art keywords
pipe
hanging basket
box
box girder
water receiving
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621183514.6U
Other languages
Chinese (zh)
Inventor
***
白晓宏
胡文柱
赵东升
赵甜甜
吴丹丹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Communications Planning Survey & Design Institute
Haiwei Engineering Construction Co Ltd of FHEC of CCCC
Original Assignee
Haiwei Engineering Construction Co Ltd of FHEC of CCCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Haiwei Engineering Construction Co Ltd of FHEC of CCCC filed Critical Haiwei Engineering Construction Co Ltd of FHEC of CCCC
Priority to CN201621183514.6U priority Critical patent/CN206289543U/en
Application granted granted Critical
Publication of CN206289543U publication Critical patent/CN206289543U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model provides a kind of Hanging Basket cantilever casting box girder sections concrete curing system, is related to the construction field of Hanging Basket cantilever casting box girder, including base plate curing means and automatic spraying device.Base plate curing means is pasted including mould, and mould patch is layed on bottom die of box-beam plate.Automatic spraying device includes control system, water system and multiple spray maintenance parts.Control system is electrically connected with water system, and water system is installed on the center of the box beam top board top surface for having poured.Spray maintenance part is connected with water system, and multiple spray maintenance part is fixedly installed in interior skid beam and outer skid beam respectively.The Hanging Basket cantilever casting box girder sections concrete curing system that the utility model is provided can comprehensively be conserved to sections concrete, so as to ensure box beam quality, save maintenance cost.

Description

Hanging Basket cantilever casting box girder sections concrete curing system
Technical field
The utility model is related to the construction field of Hanging Basket cantilever casting box girder, is poured in particular to a kind of Hanging Basket cantilever Build box girder segment concrete curing system.
Background technology
With the rise of prestressed concrete continuous rigid-framed bridge, high-block bridge continuous rigid frame cast-in-situ box girder by design extensively and Using.But the appearance of crack of box girder can produce high risks to bridge, the structural cracks for especially being caused by non-load factor, because Its complex genesis, the harm to bridge structure durability is serious, it is necessary to be controlled by.The heat conductivility of concrete material is very poor, In the presence of the temperature change that various factors causes, Prestressed Concrete Bridges inside configuration can produce it is sizable deformation and Stress.And as the across footpath of continuous rigid frame bridge gradually increases, requirement of its box-beam structure to concrete high-strength degree causes to be used The label more and more higher of concrete, volume, consumption are also increasing.With high performance concrete application, construction and maintenance work is more aggravated Will.Construction time, non-load factor crack was primarily due to that concrete curing is ineffective to be caused, generally, in order to ensure to conserve matter Amount, concrete surface should be under moisture state rather than alternation of wetting and drying state all the time.
At present, it is main manually to be spilt using to sections concrete top surface covering water-storage material in Hanging Basket cantilever pouring concrete curing Water curing, box beam inner chamber is manually sprinkled water, and web outer surface is sprinkled water or sprinkling healthy liquid.But box beam flange plate and base plate bottom surface are basic Maintenance cannot be implemented, and the position of nourishment there is also the shortcomings of randomness is big, and continuation is poor, so as to cause cantilever pouring case Girder segment concrete curing is not in place.
Utility model content
The purpose of this utility model is to provide a kind of Hanging Basket cantilever casting box girder sections concrete curing system, and it can be saved Human cost, is comprehensively conserved to Hanging Basket cantilever casting box girder sections concrete, improves box beam quality.
The utility model provides a kind of technical scheme:
A kind of Hanging Basket cantilever casting box girder sections concrete curing system, for being supported to Hanging Basket cantilever casting box girder sections concrete Shield.Hanging Basket cantilever casting box girder sections concrete includes box beam, Hanging Basket and box girder webs template.Box beam includes box beam top board, the box beam wing Listrium, box girder web and box beam base plate.Hanging Basket is installed on the top surface of the box beam top board for having poured.Box girder webs template includes Bottom die of box-beam plate, box beam outboard template and chamber inner template.Hanging Basket includes Hanging Basket main body, interior skid beam and outer skid beam.Interior skid beam is consolidated Dingan County is loaded on Hanging Basket main body, and positioned at the lower section of box beam top board, outer skid beam is fixedly installed in Hanging Basket main body, and positioned at box beam flange The lower section of plate.Hanging Basket cantilever casting box girder sections concrete curing system includes base plate curing means and automatic spraying device.Base plate is supported Protection unit is pasted including mould, and mould patch is layed on bottom die of box-beam plate.Automatic spraying device includes control system, water system and multiple Spray maintenance part.Control system is electrically connected with water system, and water system is installed on the box beam top board top surface that has poured Center, spray maintenance part is connected with water system, and multiple spray maintenance part is fixedly installed in interior skid beam and outer cunning respectively Liang Shang.
In the utility model preferred embodiment, above-mentioned water system includes water tank, high-pressure hydraulic pump and water receiving pipe, high pressure Water pump is connected with water tank, and water receiving pipe has the first water receiving mouth of pipe and the second water receiving mouth of pipe, and the first water receiving mouth of pipe connects with high-pressure hydraulic pump Connect, the second water receiving mouth of pipe is connected with spray maintenance part.
In the utility model preferred embodiment, above-mentioned spray maintenance part includes spray maintenance pipe and multiple shower nozzles, Spray maintenance pipe includes the first spray maintenance pipe and multiple second spray maintenance pipes, and the first spray maintenance pipe is provided with the connection mouth of pipe, The connection mouth of pipe is connected with the second water receiving mouth of pipe, and one end of multiple second spray maintenance pipes is connected with the first spray maintenance pipe, another End is connected with shower nozzle, and the connection mouth of pipe is connected with the second water receiving mouth of pipe, and the spray mouth of pipe is connected with shower nozzle.
In the utility model preferred embodiment, the spray direction of above-mentioned multiple shower nozzles is consistent.
In the utility model preferred embodiment, above-mentioned first spray maintenance pipe and the second spray maintenance pipe are PVC water Pipe.
In the utility model preferred embodiment, above-mentioned water receiving pipe includes the first water receiving pipe, and the first water receiving pipe is near height One end of water pump is connected with high-pressure hydraulic pump, and the other end is extended to along box beam top board near the side of outer skid beam and outer skid beam successively On institute's beam outboard template.
In the utility model preferred embodiment, above-mentioned water receiving pipe also includes the second water receiving pipe, and the second water receiving pipe is close to One end of high-pressure hydraulic pump is connected with high-pressure hydraulic pump, and the other end extends along box beam top board near the side of interior skid beam and outer skid beam successively To Inner Moulding Board in Building.
In the utility model preferred embodiment, above-mentioned first water receiving pipe and the second water receiving pipe are high-pressure hose.
In the utility model preferred embodiment, above-mentioned control system includes circulation back off timer and controller, follows Ring back off timer is connected with controller, and controller is connected with high-pressure hydraulic pump, and circulation back off timer is used at default interval Time is turned on and off high-pressure hydraulic pump.
In the utility model preferred embodiment, above-mentioned mould patch is multiple, and the lap-joint of two neighboring mould patch is by strong Power glue.
Compared to the Hanging Basket cantilever pouring that existing Hanging Basket cantilever casting box girder sections concrete curing system, the utility model are provided The beneficial effect of box girder segment concrete curing system is:
The bed die of sections concrete is conserved by base plate curing means, mould patch is pasted on the bottom surface of bottom die of box-beam plate Afterwards, then the construction of reinforcing bar and concrete is carried out, after form removal is removed, the mould is attached to concrete face and can play water conservation and air-entraining effect, so as to realize Maintenance to box beam base plate bottom surface;By automatic spraying device to the interior lateral surface of box girder web, the bottom surface of box beam top board and case Between-line spacing spray maintenance is entered in the bottom surface of beam flange plate, and the water supply time of water system is controlled by control system, is fixed on interior cunning Spray on beam and outer skid beam conserves part as interior skid beam and outer skid beam are migrated, so as to realize the interior outside to box girder web The maintenance of the bottom surface in face, the bottom surface of box beam top board and box beam flange plate.By Hanging Basket cantilever casting box girder sections concrete curing system Ensure that all concrete faces of cantilever box beam remain moisture state within curing period, so that Hanging Basket cantilever pouring concrete is obtained comprehensively Maintenance
Brief description of the drawings
In order to illustrate more clearly of the technical scheme of the utility model embodiment, below will be to be used needed for embodiment Accompanying drawing be briefly described, it will be appreciated that the following drawings illustrate only some embodiments of the present utility model, therefore should not be by Regard the restriction to scope as, for those of ordinary skill in the art, on the premise of not paying creative work, may be used also Other related accompanying drawings are obtained with according to these accompanying drawings.
Fig. 1 shows for the structure of the Hanging Basket cantilever casting box girder sections concrete curing system installment state of the utility model embodiment It is intended to;
Fig. 2 is the structural representation of Hanging Basket cantilever casting box girder sections concrete;
Fig. 3 is the structural representation of Hanging Basket cantilever casting box girder sections formwork for placing concrete;
Fig. 4 is the spray maintenance part of the Hanging Basket cantilever casting box girder sections concrete curing system of the utility model embodiment Structural representation.
Icon:10- water systems;12- high-pressure hydraulic pumps;13- water tanks;14- water receiving pipes;The water receiving pipes of 141- first;142- Two water receiving pipes;20- control systems;30- Hanging Baskets;32- Hanging Basket main bodys;Skid beam in 34-;The outer skid beams of 36-;40- spray maintenance parts; 42- shower nozzles;44- three-way connections;46- angle couplings;48- spray maintenance pipes;The spray maintenance pipes of 481- first;482- second is sprayed Maintenance pipe;50- box beams;51- box beam top boards;52- box beam flange plates;53- box girder webs;55- box beam base plates;56- box beams inner chamber; 60- box girder webs templates;61- chamber inner templates;62- box beam outboard templates;64- bottom die of box-beam plates.
Specific embodiment
It is new below in conjunction with this practicality to make the purpose, technical scheme and advantage of the utility model embodiment clearer Accompanying drawing in type embodiment, is clearly and completely described, it is clear that retouched to the technical scheme in the utility model embodiment The embodiment stated is a part of embodiment of the utility model, rather than whole embodiments.Generally described in accompanying drawing herein and The component of the utility model embodiment for showing can be arranged and designed with a variety of configurations.
Therefore, the detailed description of embodiment of the present utility model below to providing in the accompanying drawings is not intended to limit requirement The scope of the present utility model of protection, but it is merely representative of selected embodiment of the present utility model.Based in the utility model Embodiment, the every other embodiment that those of ordinary skill in the art are obtained under the premise of creative work is not made, all Belong to the scope of the utility model protection.
It should be noted that:Similar label and letter represents similar terms in following accompanying drawing, therefore, once a certain Xiang Yi It is defined in individual accompanying drawing, then it need not be further defined and explained in subsequent accompanying drawing.
In description of the present utility model, it is to be understood that term " " center ", " on ", D score, " interior ", " outward ", The orientation or position relationship of the instructions such as " bottom ", " top " are that, based on orientation shown in the drawings or position relationship, or the practicality is new Orientation or position relationship that type product is usually put when using, or the orientation or position that those skilled in the art usually understand Relation, is for only for ease of description the utility model and simplifies description, must rather than the equipment or element for indicating or imply meaning Must have specific orientation, with specific azimuth configuration and operation, therefore it is not intended that to limitation of the present utility model.
Additionally, term " first ", " second " etc. are only used for distinguishing description, and it is not intended that indicating or implying relatively important Property.
In description of the present utility model, in addition it is also necessary to explanation, unless otherwise clearly defined and limited, " setting ", The terms such as " installation ", " connection " should be interpreted broadly, for example, " connection " can be fixedly connected, or be detachably connected, Or be integrally connected;Can mechanically connect, or electrically connect;Can be directly connected to, it is also possible to by intermediary It is indirectly connected with, can is two connections of element internal.For the ordinary skill in the art, can be managed with concrete condition Solve concrete meaning of the above-mentioned term in the utility model.
Embodiment
Fig. 1 is referred to, a kind of Hanging Basket cantilever casting box girder sections concrete curing system is present embodiments provided, for Hanging Basket Cantilever casting box girder sections concrete is conserved.Hanging Basket cantilever casting box girder sections concrete includes box beam 50, Hanging Basket 30 and box girder webs Template 60 (referring to Fig. 3).
Fig. 2 is referred to, box beam 50 includes box beam top board 51, box beam flange plate 52, box girder web 53 and box beam base plate 55.Case Back plate 51, box beam flange plate 52, box girder web 53 and box beam base plate 55 surround box beam inner chamber 56.
Fig. 3 is referred to, box girder webs template 60 includes chamber inner template 61, box beam outboard template 62 and bottom die of box-beam plate 64.Hanging Basket 30 includes Hanging Basket main body 32, interior skid beam 34 and outer skid beam 36, and Hanging Basket main body 32 is installed on the box beam top board for having poured On 51 top surface, interior skid beam 34 is fixedly installed in Hanging Basket main body 32, and positioned at the lower section of box beam top board 51, outer skid beam 36 fixes peace Loaded on Hanging Basket main body 32, and positioned at the lower section of box beam flange plate 52.
Please continue to refer to Fig. 1, Hanging Basket cantilever casting box girder sections concrete curing system includes base plate curing means (in figure not Show) and automatic spraying device 100.
Base plate curing means is pasted including mould, after mould patch is layed on the bottom surface of bottom die of box-beam plate 64, then carries out reinforcing bar With the construction of concrete.The mould for being layed in bottom die of box-beam plate 64 is attached to after concrete placings, can play a part of water conservation and bleed in concrete face, And then realize carrying out effective maintenance to the bottom surface of the box beam base plate 55 of Hanging Basket cantilever casting box girder sections concrete.
In the present embodiment, above-mentioned mould patch pastes special glue by smearing concrete mould in the bottom surface of bottom die of box-beam plate 64, and mould is pasted Laid, and the lap-joint of two neighboring mould patch uses strength glue, so as to realize being seamlessly connected.
In the present embodiment, above-mentioned mould patch is permeable template cloth, certainly in other embodiment of the present utility model, also may be used Think other kinds of mould patch.
Please continue to refer to Fig. 1, automatic spraying device 100 includes water system 10, control system 20 and spray maintenance part 40.Water system 10 is electrically connected with control system 20.Spray maintenance part 40 is connected with water system 10, multiple spray maintenance portion Part 40 is respectively arranged in interior skid beam 34 and outer skid beam 36.
Water system 10 includes high-pressure hydraulic pump 12, water tank 13 and water receiving pipe 14.High-pressure hydraulic pump 12 is connected with water tank 13.Water tank 13 are installed at the end face center of the box beam top board 51 for having poured, and are electrically connected with control system 20.Water receiving pipe 14 includes the One water receiving pipe 141 and the second water receiving pipe 142, the first water receiving pipe 141 are connected near one end of high-pressure hydraulic pump 12 with high-pressure hydraulic pump 12, The other end extends to the box beam outboard template 62 of the side along box beam top board 51 near the side of outer skid beam 36 and outer skid beam 36 successively On, and be connected with the spray maintenance part 40 being installed in outer skid beam 36;Second water receiving pipe 142 is near one end of high-pressure hydraulic pump 12 It is connected with high-pressure hydraulic pump 12, the other end extends to box beam along box beam top board 51 near the side of interior skid beam 34 and outer skid beam 34 successively In inner template 61, and it is connected with the spray maintenance part 40 being installed in interior skid beam 34.
In the present embodiment, the first water receiving pipe 141 and the second water receiving pipe 142 are high-pressure hose, certainly new in this practicality In the other embodiment of type, or other water pipes.
In the present embodiment, control system 20 includes circulation back off timer and controller, circulation back off timer and control Device connection processed, controller is connected with high-pressure hydraulic pump 12, and circulation back off timer is used to be turned on and off in default interval time High-pressure hydraulic pump 12.
Fig. 4 is referred to, spray maintenance part 40 includes shower nozzle 42 and spray maintenance pipe 48, and in the present embodiment, spray is supported Shield part 40 also includes three-way connection 44 and angle coupling 46.Spray maintenance pipe 48 includes the first spray maintenance pipe 481 and multiple Second spray maintenance pipe 482.One end of first spray maintenance pipe 481 is provided with the connection mouth of pipe, the connection mouth of pipe and the second water receiving pipe 142 connections, the first spray maintenance pipe 481 sprays maintenance away from the other end that the mouth of pipe is connected with this by angle coupling 46 and second Pipe 482 is connected, and remaining second spray maintenance pipe 482 is connected by three-way connection 44 with the first spray maintenance pipe 481.
In the present embodiment, the first spray maintenance spray maintenance pipe 482 of pipe 481 and second is PVC water pipes, certainly at this In the other embodiment of utility model, or other water pipes.
In the present embodiment, spray maintenance part 40 includes installing the outside spray maintenance part 401 in outer skid beam 36 With the inner side spray maintenance part 402 in interior skid beam 34.
Refer to Fig. 1~Fig. 4, the step of use the maintenance process of Hanging Basket cantilever casting box girder sections concrete curing system for:
The installation of step one, Hanging Basket cantilever casting box girder sections concrete curing system:
Water system 10 is lifted at the end face center of box beam top board 51, high-pressure hydraulic pump 12 is connected with water tank 13.
Outside spray maintenance part 401 is installed in outer skid beam 36, inner side spray maintenance part 402 is installed to interior cunning On beam 34.
Water receiving pipe 14 is deployed to bottom basket, box beam outboard template 62 and the chamber internal model of Hanging Basket 30 along the both sides of box beam top board 51 On plate 61, the Single port of the first water receiving pipe 141 is connected with high-pressure hydraulic pump 12, another port and the installation of the first water receiving pipe 141 Outside spray maintenance part 401 in outer skid beam 36 is connected;The Single port of the second water receiving pipe 142 and high-pressure hydraulic pump 12 are connected Connect, the another port of the second water receiving pipe 142 is connected with the inner side spray maintenance part 402 in interior skid beam 34.
Control system 20 is connected with high-pressure hydraulic pump 12, the intermittent time of the work of high-pressure hydraulic pump 12 is set, and then controls spray The interval time of first 42 spray.
The uniform special glue for smearing mould patch on bottom die of box-beam plate 64, mould patch is routed on bottom die of box-beam plate 64, is used Mould patch is smoothed compression from centre to both sides by hand, and multiple Mo Tie lap-joints use strength glue, realizes being seamlessly connected.
Step 2, conserved using the top surface of top surface manually to box beam top board 51, box beam base plate 55:Box beam concrete placings After the completion of, concrete initial set is treated, geotextiles are covered on the top surface of the top surface of box beam top board 51 and box beam base plate 55, manually spilt Water curing.
Step 3, the bottom surface of box beam base plate 55 is conserved using box beam base plate curing means:In bottom die of box-beam plate 64 Bottom surface on paste mould patch after, then carry out the construction of reinforcing bar and concrete, after form removal is removed, mould is attached to that water conservation is played in concrete face and bleed is made With reaching the maintenance action of the bottom surface to box beam base plate 55.
Step 4, between-line spacing wet curing is entered to other positions of box girder segment concrete using automatic spraying device 100:Pass through The circulation back off timer control controller of time interval is set, and then has controlled high-pressure hydraulic pump 12.It is fixedly installed in interior cunning The spray maintenance part 40 of beam 34 and outer skid beam 36 is migrated with Hanging Basket 30, to lateral surface and medial surface, the case of box girder web 53 Between-line spacing spray maintenance is entered in the bottom surface of back plate 51 and the bottom surface of box beam flange plate 52.
Fig. 1~Fig. 4 is referred to, the work of the Hanging Basket cantilever casting box girder sections concrete curing system that the utility model is provided is former Reason is:The bed die of sections concrete is conserved by base plate curing means, after mould patch is pasted on the bottom surface of bottom die of box-beam plate 64, The construction of reinforcing bar and concrete is carried out again, and after form removal is removed, the mould is attached to concrete face and can play water conservation and air-entraining effect, so as to realize to case The maintenance of the bottom surface of beam base plate 55;By automatic spraying device 100 to the interior lateral surface of box girder web 53, the bottom surface of box beam top board 51 Enter between-line spacing spray maintenance with the bottom surface of box beam flange plate 52, the water supply time of water system 10 controlled by control system 20, The spray being fixed in interior skid beam 34 and outer skid beam 36 conserves part 40 as interior skid beam 34 and outer skid beam 36 are migrated, so as to realize Maintenance to the bottom surface of the interior lateral surface, the bottom surface of box beam top board and box beam flange plate of box girder web.By Hanging Basket cantilever pouring Box girder segment concrete curing system ensures that all concrete faces of cantilever box beam remain moisture state within curing period, so that Hanging Basket Cantilever pouring concrete is comprehensively conserved.
Preferred embodiment of the present utility model is the foregoing is only, the utility model is not limited to, for this For the technical staff in field, the utility model can have various modifications and variations.It is all it is of the present utility model spirit and principle Within, any modification, equivalent substitution and improvements made etc. should be included within protection domain of the present utility model.

Claims (10)

1. a kind of Hanging Basket cantilever casting box girder sections concrete curing system, for being supported to Hanging Basket cantilever casting box girder sections concrete Shield, the Hanging Basket cantilever casting box girder sections concrete includes box beam, Hanging Basket and box girder webs template, and the box beam includes box beam top Plate, box beam flange plate, box girder web and box beam base plate, the Hanging Basket are installed on the top surface of the box beam top board for having poured On, the box girder webs template includes bottom die of box-beam plate, box beam outboard template and chamber inner template, and the Hanging Basket includes Hanging Basket master Body, interior skid beam and outer skid beam, the interior skid beam are fixedly installed in the Hanging Basket main body, and positioned at the lower section of the box beam top board, The outer skid beam is fixedly installed in the Hanging Basket main body, and positioned at the lower section of the box beam flange plate, it is characterised in that the extension Basket cantilever casting box girder sections concrete curing system includes base plate curing means and automatic spraying device, the base plate curing means bag Include mould patch, mould patch is layed on the bottom die of box-beam plate, the automatic spraying device include control system, water system and Multiple spray maintenance part, the control system is electrically connected with the water system, and the water system is installed on and has poured The box beam top board top surface center, the spray maintenance part be connected with the water system, and multiple sprays are foster Shield part is fixedly installed in the interior skid beam and the outer skid beam respectively.
2. Hanging Basket cantilever casting box girder sections concrete curing system according to claim 1, it is characterised in that the water supply system System includes water tank, high-pressure hydraulic pump and water receiving pipe, and the high-pressure hydraulic pump is connected with the water tank, and the water receiving pipe has the first water receiving The mouth of pipe and the second water receiving mouth of pipe, the first water receiving mouth of pipe are connected with the high-pressure hydraulic pump, the second water receiving mouth of pipe with it is described Spray maintenance part connection.
3. Hanging Basket cantilever casting box girder sections concrete curing system according to claim 2, it is characterised in that the spray is supported Shield part includes spray maintenance pipe and multiple shower nozzles, and the spray maintenance pipe includes that the first spray maintenance pipe and multiple second is sprayed Maintenance pipe, the first spray maintenance pipe is provided with the connection mouth of pipe, and the connection mouth of pipe is connected with the second water receiving mouth of pipe, multiple One end of the second spray maintenance pipe is connected with the described first spray maintenance pipe, and the other end is connected with the shower nozzle, the company Adapter mouth is connected with the second water receiving mouth of pipe, and the spray mouth of pipe is connected with the shower nozzle.
4. Hanging Basket cantilever casting box girder sections concrete curing system according to claim 3, it is characterised in that multiple sprays The spray direction of head is consistent.
5. Hanging Basket cantilever casting box girder sections concrete curing system according to claim 3, it is characterised in that first spray It is PVC water pipes to drench maintenance pipe and the described second spray maintenance pipe.
6. the Hanging Basket cantilever casting box girder sections concrete curing system according to any one of claim 2-5, it is characterised in that The water receiving pipe includes the first water receiving pipe, and first water receiving pipe connects near one end of the high-pressure hydraulic pump with the high-pressure hydraulic pump Connect, the other end extends to the box beam outside along the box beam top board near the side of the outer skid beam and the outer skid beam successively In template.
7. Hanging Basket cantilever casting box girder sections concrete curing system according to claim 6, it is characterised in that the water receiving pipe Also include the second water receiving pipe, second water receiving pipe is connected near one end of the high-pressure hydraulic pump with the high-pressure hydraulic pump, another End is extended on the Inner Moulding Board in Building along the box beam top board near the side of the interior skid beam and the outer skid beam successively.
8. Hanging Basket cantilever casting box girder sections concrete curing system according to claim 7, it is characterised in that described first connects Water pipe and second water receiving pipe are high-pressure hose.
9. Hanging Basket cantilever casting box girder sections concrete curing system according to claim 1, it is characterised in that the control system System includes circulating back off timer and controller, and the circulation back off timer is connected with the controller, the controller and The high-pressure hydraulic pump connection, the circulation back off timer is used to be turned on and off the water under high pressure in default interval time Pump.
10. Hanging Basket cantilever casting box girder sections concrete curing system according to claim 1, it is characterised in that the mould patch It is multiple, the lap-joint of the two neighboring mould patch passes through strength glue.
CN201621183514.6U 2016-11-03 2016-11-03 Hanging Basket cantilever casting box girder sections concrete curing system Expired - Fee Related CN206289543U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621183514.6U CN206289543U (en) 2016-11-03 2016-11-03 Hanging Basket cantilever casting box girder sections concrete curing system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621183514.6U CN206289543U (en) 2016-11-03 2016-11-03 Hanging Basket cantilever casting box girder sections concrete curing system

Publications (1)

Publication Number Publication Date
CN206289543U true CN206289543U (en) 2017-06-30

Family

ID=59099828

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621183514.6U Expired - Fee Related CN206289543U (en) 2016-11-03 2016-11-03 Hanging Basket cantilever casting box girder sections concrete curing system

Country Status (1)

Country Link
CN (1) CN206289543U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106351130A (en) * 2016-11-03 2017-01-25 中交公局海威工程建设有限公司 Hanging basket cantilever casting box girder segment concrete curing system and hanging basket cantilever casting box girder segment concrete curing method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106351130A (en) * 2016-11-03 2017-01-25 中交公局海威工程建设有限公司 Hanging basket cantilever casting box girder segment concrete curing system and hanging basket cantilever casting box girder segment concrete curing method

Similar Documents

Publication Publication Date Title
CN106351130A (en) Hanging basket cantilever casting box girder segment concrete curing system and hanging basket cantilever casting box girder segment concrete curing method
CN104264995B (en) Automatic spraying conservation system for high-rise building shear wall structure
CN206646034U (en) The compound curing system of section concrete in being constructed applied to Hanging Basket cantilever pouring
CN104972554B (en) The automatic spray curing system of prefabricated T-shaped beam
CN106346601B (en) Concrete vertical member automatic spray curing system
CN206801065U (en) A kind of side wall concrete automatic maintenance device
CN204385675U (en) A kind of dedusting cooling system of adjustable control spraying altitude
CN204278202U (en) A kind of movable prefabricated beam automatic spray curing means
CN206289543U (en) Hanging Basket cantilever casting box girder sections concrete curing system
CN210969332U (en) Bridge construction is with spraying maintenance system
CN210589852U (en) Automatic spraying health preserving device of prefabricated box girder
CN206551186U (en) A kind of section box girder automatic sprinkler fire-extinguishing system
CN206467575U (en) A kind of bridge pier shaft concrete spray maintenance device
CN205818122U (en) A kind of high-speed railway large box girder concrete automatic spray curing system
CN207554073U (en) The light-duty convenient self-propelled two in tunnel serves as a contrast health rack
CN206428591U (en) A kind of concrete curing device based on Hanging Basket
CN213951977U (en) Health preserving equipment suitable for long-span prestressing force continuous rigid frame section concrete
CN206953259U (en) A kind of concrete door sprinkling curing system
CN208309395U (en) A kind of climbing formwork for construction pier stud concrete automatic maintenance device
CN207077600U (en) Preform production and maintenance canopy
CN206154492U (en) Bury shower nozzle intelligence maintenance system
CN208105057U (en) Pour pier stud automatic spray curing system
CN212688729U (en) Moisturizing device for bridge engineering maintenance
CN207240461U (en) A kind of concrete prefabricated dual-purpose curing means of beam fountain steam
CN107344388A (en) A kind of concrete prefabricated beam particular time curing means

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Zhang Zhixin

Inventor after: Zhong Mingquan

Inventor after: Bai Xiaohong

Inventor after: Hu Wenzhu

Inventor after: Zhao Dongsheng

Inventor after: Zhao Tiantian

Inventor after: Wu Dandan

Inventor before: Zhang Zhixin

Inventor before: Bai Xiaohong

Inventor before: Hu Wenzhu

Inventor before: Zhao Dongsheng

Inventor before: Zhao Tiantian

Inventor before: Wu Dandan

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20171227

Address after: 101100 Beijing City, Tongzhou District Road No. 568 Building No. 1 Xu

Co-patentee after: CHONGQING COMMUNICATIONS PLANNING SURVEY & DESIGN INSTITUTE

Patentee after: HAIWEI ENGINEERING CONSTRUCTION CO LTD OF FIRST HIGHWAY ENGINEERING Co.,Ltd. OF CCCC

Address before: 101100 Beijing City, Tongzhou District Road No. 568 Building No. 1 Xu

Patentee before: HAIWEI ENGINEERING CONSTRUCTION CO LTD OF FIRST HIGHWAY ENGINEERING Co.,Ltd. OF CCCC

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170630