CN206220460U - For the operating platform of tower - Google Patents

For the operating platform of tower Download PDF

Info

Publication number
CN206220460U
CN206220460U CN201621109232.1U CN201621109232U CN206220460U CN 206220460 U CN206220460 U CN 206220460U CN 201621109232 U CN201621109232 U CN 201621109232U CN 206220460 U CN206220460 U CN 206220460U
Authority
CN
China
Prior art keywords
tower
operating platform
flat board
section steel
support arm
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201621109232.1U
Other languages
Chinese (zh)
Inventor
郑家宁
李亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huoerguosi Amperex Technology Ltd
Original Assignee
Huoerguosi Amperex Technology Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huoerguosi Amperex Technology Ltd filed Critical Huoerguosi Amperex Technology Ltd
Priority to CN201621109232.1U priority Critical patent/CN206220460U/en
Application granted granted Critical
Publication of CN206220460U publication Critical patent/CN206220460U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

The utility model discloses a kind of operating platform for tower.The operating platform for tower includes:Flat board and multiple support arms for people's activity, multiple support arms are located at flat board lower section, and support arm is scalable relative to flat board, and the inwall of tower is provided with multiple supports, and multiple support arms are respectively used to be overlapped on multiple supports.According to the operating platform for tower of the present utility model, operating platform simple structure, convenient regulation can effectively improve efficiency of construction.

Description

For the operating platform of tower
Technical field
The utility model is related to technical field of wind power generation, more particularly, to a kind of operating platform for tower.
Background technology
In correlation technique, in the tower building course of wind-driven generator, lifted successively typically by from lower to upper single Individual tower, is finally built into complete concrete tower.In existing assembling process, tower is in hoisting process, it is necessary in tower Inside the operation such as installed, be in the milk, being safeguarded to tower, it is flat that this is accomplished by an operation that can be installed inside tower Platform.
Utility model content
The utility model is intended at least solve to a certain extent one of technical problem in correlation technique.Therefore, this reality With a kind of operating platform for tower of convenient operation of new proposition.
The operating platform for tower according to the utility model embodiment includes:Flat board and multiple supports for people's activity Arm, the multiple support arm is located at flat board lower section, and the support arm is scalable relative to the flat board, the tower it is interior Wall is provided with multiple supports, and the multiple support arm is respectively used to be overlapped on the multiple support.
According to the operating platform for tower of the utility model embodiment, by setting flat board and multiple branch on platform Brace, and support arm opposing plates are scalable, the not only work high above the ground of convenient construction personnel, while different size tower can be met Overlap joint, so as to save production cost.
In some preferred embodiments, the first end of each support arm is located at the center position of the flat board, and Second end of each support arm extends in a radial direction, and multiple support arms radially distribute at the flat board bottom Portion.
In some preferred embodiments, each described support arm includes:Outer channel-section steel, the outer channel-section steel is provided with outside multiple fixed Position hole, interior channel-section steel, the interior channel-section steel is slidably disposed in the outer channel-section steel, and the interior channel-section steel is provided with location hole in multiple; Keeper, the keeper is used to pass through one of the outside fix hole and one of them described interior location hole so that in described Channel-section steel is positioned with the outer channel-section steel.
In some preferred embodiments, the support includes:Connecting plate, the connecting plate is fixed on the inwall of the tower On;Supporting plate, the supporting plate is connected and horizontally extending with the connecting plate, and the support arm is overlapped on the support On plate.
Further, the support also includes:Reinforcing plate, the vertical both sides of the reinforcing plate respectively with the connecting plate It is connected with the supporting plate, the reinforcing plate is two and is oppositely arranged.
In some preferred embodiments, the periphery of the flat board is provided with enclosing.
In some preferred embodiments, the flat board is provided with avoidance groove, the avoidance groove by the flat board side Edge is inwardly concaved.
Additional aspect of the present utility model and advantage will be set forth in part in the description, partly by from following description In become obvious, or by it is of the present utility model practice recognize.
Brief description of the drawings
Of the present utility model above-mentioned and/or additional aspect and advantage will from description of the accompanying drawings below to embodiment is combined Become substantially and be readily appreciated that, wherein:
Fig. 1 is the structural representation of the operating platform for tower according to the utility model embodiment;
Fig. 2 is the structural representation of support arm and support assorted in Fig. 1;
Fig. 3 is the structural representation of Fig. 1 medium-height trestles;
Fig. 4 is the structural representation of tower in Fig. 1;
Fig. 5 is the fixed schematic diagram of the support according to the utility model embodiment and tower;
Fig. 6 is the flow chart of the hanging method of the operating platform for tower according to the utility model embodiment.
Reference:
Operating platform 100, flat board 1, support arm 2, outer channel-section steel 21, outside fix hole 211, interior channel-section steel 22, interior location hole 221, Support 3, connecting plate 31, location and installation hole 311, supporting plate 32, reinforcing plate 33, enclosing 4 avoids groove 5, tower 6, prestress hole Road 61, sleeve built-in fitting 62, bolt 7.
Specific embodiment
Embodiment of the present utility model is described below in detail, the example of the embodiment is shown in the drawings, wherein ad initio Same or similar element or element with same or like function are represented to same or similar label eventually.Below by ginseng The embodiment for examining Description of Drawings is exemplary, is only used for explaining the utility model, and it is not intended that to of the present utility model Limitation.
In description of the present utility model, it is to be understood that term " " center ", " length ", " width ", " thickness ", " on ", D score, "front", "rear", "left", "right", " vertical ", " level ", " top ", " bottom ", " interior ", the orientation of instruction such as " outward " or Position relationship is, based on orientation shown in the drawings or position relationship, to be for only for ease of description the utility model and simplify description, Rather than indicate imply signified device or element must have specific orientation, with specific azimuth configuration and operation, because This is it is not intended that to limitation of the present utility model.
Additionally, term " first ", " second " are only used for describing purpose, and it is not intended that indicating or implying relative importance Or the implicit quantity for indicating indicated technical characteristic.Thus, define " first ", the feature of " second " can express or Implicitly include one or more this feature.In description of the present utility model, " multiple " is meant that two or two More than, unless otherwise expressly limited specifically.
, it is necessary to explanation, unless otherwise clearly defined and limited, term " is pacified in description of the present utility model Dress ", " connected ", " connection " should be interpreted broadly, for example, it may be fixedly connected, or be detachably connected, or integratedly Connection;Can mechanically connect, or electrically connect;Can be joined directly together, it is also possible to be indirectly connected to by intermediary, Can be two element internals connection or two interaction relationships of element.For one of ordinary skill in the art Speech, can as the case may be understand concrete meaning of the above-mentioned term in the utility model.
The operating platform 100 for tower according to the utility model embodiment is described with reference to Fig. 1-Fig. 4 first below.Such as Shown in Fig. 1-Fig. 3, according to the operating platform 100 for tower of the utility model embodiment, including:For the flat board 1 of people's activity With multiple support arms 2.
For the flat board 1 of people's activity, as shown in figure 1, flat board 1 is in substantial circular, in concrete tower construction period, constructor Member can stand and related operation is carried out on flat board 1, easy to operate, while the coordinating operation of multiple workmens can be met, so as to carry Efficiency of construction high.
Multiple support arms 2 are located at the lower section of flat board 1, and support arm 2 is scalable relative to flat board 1, it is preferable that the inwall of tower 6 Multiple supports 3 are provided with, multiple support arms 2 are respectively used to correspondence and are overlapped on multiple supports 3 to keep flat board 1 to consolidate, so as to protect Demonstrate,prove the safety of workmen.
According to the operating platform 100 for tower of the utility model embodiment, supplied by being set on operating platform 100 The flat board 1 and multiple support arms 2 of people's activity, can convenient construction personal security quickly complete related operation, while multiple supports Arm 2 can opposing plates 1 stretch, so as to installation of the operating platform 100 in different size tower 6 can be met, highly versatile is reduced Production cost.
In certain embodiments, the first end of each support arm 2 is located at the center position of flat board 1, and each support arm 2 First end gather in the center of flat board 1, the second end of each support arm 2 extends in a radial direction, and is put operating platform 100 is taken When in tower 6, the second end of each support arm 2 corresponds to be supported on multiple supports 3 of the inner side of tower 6 respectively, it is preferable that many Individual support arm 2 radially distributes in the bottom of flat board 1, and thus the support to flat board 1 is steady, and the stress of each support arm 2 is equal It is even.
Further, each support arm 2 includes:Outer channel-section steel 21 and interior channel-section steel 22.Specifically, as shown in Fig. 2 outer channel-section steel 21 With square-section, two end faces of outward opening channel-section steel 21 are opened wide, and outer channel-section steel 21 extends from the center of flat board 1 to edge, And outside fix hole 211 can be provided with outer channel-section steel 21, outside fix hole 211 can be multiple, and multiple outside fix holes 211 are along outer channel-section steel 21 roof is spaced apart, and substantially along the center line distribution of roof.
Similarly, interior channel-section steel 22 also has square-section, and two end faces of the inside channel-section steel 22 that is open are opened wide, and interior channel-section steel 22 Sectional area of the sectional area less than outer channel-section steel 21 so that interior channel-section steel 22 is slidably disposed in outer channel-section steel 21, and interior channel-section steel 22 Outer end stretch out the edge of flat board 1, be overlapped on the support 3 of the inner side of tower 6 with facilitating, it is preferable that can be set on interior channel-section steel 22 There is interior location hole 221, interior location hole 221 can be multiple, and multiple interior location holes 221 are spaced apart along the roof of interior channel-section steel 22, And substantially along the center line distribution of roof, advantageously, the outside fix hole 211 on outer channel-section steel 21 can be with the interior positioning on interior channel-section steel 22 The synchronous processing of hole 221, it is thus easy to operate, save man-hour.
Preferably, can be provided with keeper on support arm 2, keeper be used to passing through one of outside fix hole 211 and its In an interior location hole 221 so that interior channel-section steel 22 is positioned with outer channel-section steel 21, alternatively, keeper can be multiple, multiple Keeper can be each passed through the one of location hole on the one of location hole and interior channel-section steel 22 on outer channel-section steel 21, so that Outer channel-section steel 21 is connected firmly with interior channel-section steel 22, prevents load on platform excessive and causes the bending-buckling of support arm 2.
In some preferred embodiments, as shown in figure 3, support 3 includes:Connecting plate 31, supporting plate 32 and reinforcing plate 33, Wherein connecting plate 31 is fixed on the inwall of tower 6, specifically, as shown in figure 4, connecting plate 31 can be rectangular slab, and connection Location and installation hole 311 can be provided with plate 31, location and installation hole 311 can be multiple, and multiple location and installation holes 311 are spaced apart In the central region of connecting plate 31, and transversely linear distribution, location and installation hole 311 is adapted to pass through bolt 7 and is fixed on support 3 On the medial surface of tower 6, it is preferable that sleeve built-in fitting 62 can be previously provided with tower 6, sleeve built-in fitting 62 is substantially in pipe Shape, and opening towards tower 6 central open, thus bolt 7 may pass through the location and installation hole 311 on connecting plate 31 and continue depth In entering sleeve built-in fitting 62, so that stable connection of the support 3 in tower 6.
Supporting plate 32 is connected and horizontally extending with connecting plate 31, and support arm 2 is overlapped in supporting plate 32, such as Fig. 3 Shown, supporting plate 32 can also be rectangular slab, and supporting plate 32 extends from the bottom of connecting plate 31 along the inner side of tower 6, and vertically Connecting plate 31 is set, and when operating platform 100 is lifted in tower 6, the second end of support arm 2 is overlapped in supporting plate 32, with Realize the supporting role to flat board 1.
As shown in figure 3, reinforcing plate 33 can be triangular plate, and reinforcing plate 33 vertical both sides respectively with connecting plate 31 It is connected with supporting plate 32, the two ends of the hypotenuse of reinforcing plate 33 bear against the position on connecting plate 31 and supporting plate 32 close to outer end Put, it is preferable that reinforcing plate 33 is two and is oppositely arranged that is, two reinforcing plates 33 are set respectively positioned at the both sides of connecting plate 31 Reinforcing plate 33 can be effectively increased the intensity of support 3, so as to improve enabling capabilities of the support 3 to operating platform 100.
Preferably, the periphery of flat board 1 can be provided with enclosing 4, and enclosing 4 is upwardly extended along the periphery edge of flat board 1, enclosing 4 Can be that the integrative-structure for being formed is welded by metal tube, the cladding flat board 1 of enclosing 4 is set, and thus can play and workmen is protected Effect.
Advantageously, it is also provided with avoiding groove 5 on flat board 1, avoids groove 5 and inwardly concaved by the edge of flat board 1, avoids Groove 5 is used to support staircase, by staircase climbs up platform 100 with convenient construction personnel and carries out related operation, for example, remove and hang Ring, turn on lowering or hoisting gear etc. operation.
In some preferred embodiments, tower 6 can be made up of concrete, as shown in figure 4, tower 6 is annular, tower 6 wall is provided with the prestressed pore passage 61 of the height through wall, it is preferable that prestressed pore passage 61 could be arranged to it is multigroup, and often Group can include multiple, when tower 6 is lifted, can insert lifting in one of prestressed pore passage 61 first in each group Ring, the so convenient suspension hook by crane coordinate to be sling on hoisting ring with by tower 6, it is preferable that hoisting ring should be in tower 6 It is uniformly distributed, thereby guarantees that lifting of the crane to tower 6 is steady.
In some preferred embodiments, during docking between realize adjacent tower 6, workmen can first in operating platform Hoisting ring is taken out on 100, discharges crane, then location guide is worn in the prestressed pore passage 61 of lower end tower 6, so existed Next tower 6 is lifted on when in the tower 6, location guide can be penetrated in two prestressed pore passages of tower 6 61, realize phase Positioning between adjacent tower 6.
In certain embodiments, tower 6 can be assembled by multiple arcs tower piece, and alternatively, tower 6 can be by two Semicircular arc tower piece is docked to be formed, and certainly, tower 6 can also be spelled by the arc tower piece of several structures and size all same Connect and form, for example, can be three, four etc..
Further, the tower 6 being connected with basis can only include one layer of tower component, and tower component is by above-mentioned multiple arcs Shape tower piece is spliced, and in other embodiments of the present utility model, can also include that at least two stack from bottom to top Tower component, while multiple towers 6 can be divided into two groups, underlying multiple towers 6 are referred to as first group of tower component, Multiple towers 6 above first group of tower component are referred to as second group of tower component, wherein in first group of tower component Each tower 6 can be spliced to form by multiple arcs tower piece, and each tower 6 in second group of tower component can be integrated The loop configuration of formation, because concrete towers cartridge module needs larger radial ruler positioned at the tower 6 of bottom in the height direction It is very little, therefore each tower 6 in the first of bottom group of tower component can be carried out segmentation transport by transport for convenience, so that full Sufficient movement requirement.And because the radial dimension of concrete towers cartridge module superposed tower 6 in the height direction is greatly reduced, So that packaging efficiency and structural strength in order to improve tower 6, such that it is able to make each shape of tower 6 in second group of tower component The annular of shaping is integrally formed, is conducive to improving job schedule and efficiency.
Below with reference to Fig. 5-Fig. 6 descriptions according to the utility model embodiment to the above-mentioned operating platform 100 for tower Hanging method.As shown in Fig. 5-Fig. 6, hanging method may include steps of:
S10:Operating platform 100 is sling using crane.
When operating platform 100 is lifted, can be in by the flat board 1 of operating platform 100 first with many hoist cables on crane Vertical and horizontal interlock fixation, then suspension hook is hooked in into many centers of hoist cable, so that convenient lifting operating platform 100.
S20:Operating platform 100 is moved into the top of tower 6 and is discharged downwards.
During operating platform 100 is discharged, should be as steady as possible, and the length of support arm 2 should be less than the interior of tower 6 Footpath, thus can avoid during operating platform 100 is discharged, and support arm 2 causes to damage to the inwall of tower 6.
S30:Multiple support arms 2 of operating platform 100 are corresponded into multiple support 3 respectively and operating platform 100 is overlapped on On multiple supports 3.
S40:Other towers 6 are lifted to being provided with the tower 6 of operating platform 100 and carry out adjacent tower 6 Positioning.
S50:Lifted using the operating platform 100 lifted in tower 6 of the crane of tower 6 by lower section.
Preferably, operating platform 100 can include temporary operating platform and permanent operation platform, for specific tower Section, temporary operating platform can be used as permanent operation platform, stayed in tower 6, to facilitate follow-up operation.
S60:Institute above is overlapped on after the support arm 2 of the operating platform 100 is foreshortened into predetermined length State on the support 3 of tower 6.
Preferably, in the process of construction of pylon, tower 6 can include multiple and be sequentially stacked along the vertical direction, and on The diameter of portion's tower 6 less than adjacent lower tower 6 diameter, it is necessary to by support arm 2 during operating platform 100 is lifted Foreshorten to the length being adapted to fit in top tower 6.
S70:The tower 6 that operating platform 100 will be provided with is lifted to the top of tower 6 being installed in place and by adjacent tower Cylinder 6 is positioned.
Now, hoist cable can be tied up on the hoisting ring in tower 6, then hoist cable is hooked with suspension hook, advantageously, hoist cable is more long, Lifting is more laborsaving, but stationarity declines, and technical staff can be according to the length of actual selection hoist cable.
The hanging method that the utility model embodiment is provided, it is easy to operate.Build when, workmen can first with rise Heavy-duty machine slings operating platform 100;Operating platform 100 is moved into the top of tower 6 again and is discharged downwards;Then it is operation is flat Multiple support arms 2 of platform 100 correspond to multiple support 3 and operating platform 100 are overlapped on multiple supports 3 respectively;Again by other Tower 6 lift to being provided with the tower 6 of operating platform 100 and positioned adjacent tower 6;Using lifting tower 6 Crane the operating platform 100 in the tower 6 of lower section is lifted;Then the support arm 2 of the operating platform 100 is contracted It is overlapped on the support 3 of the tower 6 above after being as short as predetermined length;Operating platform is just finally installed 100 tower 6 is lifted to the top of tower 6 being installed in place and is positioned adjacent tower 6, thus constantly repeats above-mentioned Operation, realize the lifting of operating platform 100 and the overlap joint of adjacent tower 6.
To sum up, according to the operating platform 100 and hanging method for tower of the utility model embodiment, by platform Upper setting flat board 1 and multiple support arms 2, and the opposing plates 1 of support arm 2 are scalable, the not only work high above the ground of convenient construction personnel, The overlap joint of different size tower 6 can be met simultaneously, it is easy to operate, so as to efficiency of construction can be improved, reduce production cost.
Of course, it should be understood that in real work, will without strict order between above-mentioned steps S50 to S70 Ask, that is to say, that step S10 to S40 can be on the premise of ensureing operation completely and can reach final lifting purpose, can To carry out in any order, the tower 6 that position can will be for example not mounted to first is lifted to the top of tower 6 being installed in place And after positioning, then operating platform 100 is promoted to top tower 6, to carry out subsequent handling.
In the description of this specification, reference term " one embodiment ", " some embodiments ", " illustrative examples ", The description of " example ", " specific example " or " some examples " etc. means to combine specific features, the knot that the embodiment or example are described Structure, material or feature are contained at least one embodiment of the present utility model or example.In this manual, to above-mentioned art The schematic representation of language is not necessarily referring to identical embodiment or example.And, the specific features of description, structure, material or Person's feature can in an appropriate manner be combined in one or more any embodiments or example.
While there has been shown and described that embodiment of the present utility model, it will be understood by those skilled in the art that: In the case where principle of the present utility model and objective is not departed from various changes, modification, replacement can be carried out to these embodiments And modification, scope of the present utility model limits by claim and its equivalent.

Claims (7)

1. a kind of operating platform for tower, it is characterised in that including:
For the flat board of people's activity;
Multiple support arms, the multiple support arm is located at the flat board lower section, and the support arm is scalable relative to the flat board, The inwall of the tower is provided with multiple supports, and the multiple support arm is respectively used to be overlapped on the multiple support.
2. the operating platform for tower according to claim 1, it is characterised in that the first end of each support arm Positioned at the center position of the flat board, and the second end of each support arm extends in a radial direction, multiple supports Arm radially distributes in the flat plate bottom.
3. the operating platform for tower according to claim 1, it is characterised in that each described support arm includes:
Outer channel-section steel, the outer channel-section steel is provided with multiple outside fix holes;
Interior channel-section steel, the interior channel-section steel is slidably disposed in the outer channel-section steel, and the interior channel-section steel is provided with location hole in multiple;
Keeper, the keeper is used to pass through one of the outside fix hole and one of them described interior location hole so that institute Interior channel-section steel is stated to be positioned with the outer channel-section steel.
4. the operating platform for tower according to claim 1, it is characterised in that the support includes:
Connecting plate, the connecting plate is fixed on the inwall of the tower;
Supporting plate, the supporting plate is connected and horizontally extending with the connecting plate, and the support arm is overlapped on the branch On fagging.
5. the operating platform for tower according to claim 4, it is characterised in that the support also includes:Reinforcing plate, The vertical both sides of the reinforcing plate are connected with the connecting plate and the supporting plate respectively, and the reinforcing plate is for two and relative Set.
6. the operating platform for tower according to claim 1, it is characterised in that the periphery of the flat board is provided with encloses Gear.
7. the operating platform for tower according to claim 1, it is characterised in that it is recessed that the flat board is provided with avoidance Groove, the avoidance groove is inwardly concaved by the edge of the flat board.
CN201621109232.1U 2016-10-08 2016-10-08 For the operating platform of tower Withdrawn - After Issue CN206220460U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621109232.1U CN206220460U (en) 2016-10-08 2016-10-08 For the operating platform of tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621109232.1U CN206220460U (en) 2016-10-08 2016-10-08 For the operating platform of tower

Publications (1)

Publication Number Publication Date
CN206220460U true CN206220460U (en) 2017-06-06

Family

ID=58783275

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621109232.1U Withdrawn - After Issue CN206220460U (en) 2016-10-08 2016-10-08 For the operating platform of tower

Country Status (1)

Country Link
CN (1) CN206220460U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106481060A (en) * 2016-10-08 2017-03-08 霍尔果斯新国金新能源科技有限公司 Operating platform for tower and hanging method
CN111075208A (en) * 2020-01-03 2020-04-28 宜昌市洋坤建筑有限公司 A safe elevating gear for housing construction

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106481060A (en) * 2016-10-08 2017-03-08 霍尔果斯新国金新能源科技有限公司 Operating platform for tower and hanging method
CN106481060B (en) * 2016-10-08 2019-05-07 霍尔果斯新国金新能源科技有限公司 Operating platform and hanging method for tower
CN111075208A (en) * 2020-01-03 2020-04-28 宜昌市洋坤建筑有限公司 A safe elevating gear for housing construction
CN111075208B (en) * 2020-01-03 2020-09-01 宜昌市洋坤建筑有限公司 A safe elevating gear for housing construction

Similar Documents

Publication Publication Date Title
CN106481060A (en) Operating platform for tower and hanging method
CN102864936B (en) Combination lifting construction method for large-scale high hollow building roof of steel structure
CN102359302B (en) Extra-high voltage large-span iron tower assembling method
US20190136569A1 (en) Crane system incorporated into a tower
CN102213033A (en) Method of building a hybrid tower for a wind generator
CN206692235U (en) A kind of steel structure dome lifts by crane erecting device
CN105586833B (en) Stiff skeleton steel reinforcement cage global formation large-scale cast-in-place tall pier and thin wall construction method
CN101446075B (en) Synchronous vertical swing lift construction method for double inclination arc tower
CN102328881A (en) One-time hoisting device and method for ultra-large reinforcement cage
CN206220460U (en) For the operating platform of tower
CN104675171A (en) Construction method for single-piece hoisting of aluminum alloy vault of large vertical storage tank
CN105464456A (en) Method and lifting sling for assembling extra-high voltage transmission iron tower through helicopter
CN102720386A (en) Inversing method of inner side clustering hoop of vertical storage tank
CN101818563B (en) Jack-up integral lifting mobile platform and using method
EP2857615A1 (en) Mounting method and mounting device of a concrete tower formed with precast pieces
CN104499706A (en) Elevator well template platform and construction method thereof
CN110616706B (en) Construction method for layering binding in large-diameter pile foundation reinforcing steel bar hole
CN207511723U (en) A kind of flat arm tower crane supporting beam transporting device of new construction inner climbing type
CN110924723A (en) Construction method and hoisting device for earth-covered oil tank and using method
CN209924407U (en) Combined working platform for steel structure high-altitude installation
CN207144533U (en) The horizontal protective of building hoist basis conversion
CN106522207A (en) Reinforcement cage bracket and reinforcement cage mounting device
CN106429783A (en) Lifting device of concrete tower drum and lifting method applying lifting device
CN102427204B (en) Installation method for 1000kV alternating-current substation structure
CN105438940B (en) Hoisting construction method for large indoor water tank of nuclear power station

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20170606