CN206205270U - Perforation rib pull bar constraint rectangular steel-tube concrete column - Google Patents

Perforation rib pull bar constraint rectangular steel-tube concrete column Download PDF

Info

Publication number
CN206205270U
CN206205270U CN201620196537.4U CN201620196537U CN206205270U CN 206205270 U CN206205270 U CN 206205270U CN 201620196537 U CN201620196537 U CN 201620196537U CN 206205270 U CN206205270 U CN 206205270U
Authority
CN
China
Prior art keywords
pull bar
steel pipe
ribbed stiffener
steel
rectangular steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620196537.4U
Other languages
Chinese (zh)
Inventor
郑新志
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan University of Technology
Original Assignee
Henan University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan University of Technology filed Critical Henan University of Technology
Priority to CN201620196537.4U priority Critical patent/CN206205270U/en
Application granted granted Critical
Publication of CN206205270U publication Critical patent/CN206205270U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

The utility model discloses one kind perforation rib pull bar constraint rectangular steel-tube concrete column, including ribbed stiffener, pull bar, rectangular steel pipe, concrete.The ribbed stiffener is strip-form steel plate, and its thickness is identical with thickness of steel pipe.The ribbed stiffener upper connecting rod answers perforate through place, and hole size be able to pass through pull bar.The ribbed stiffener is evenly arranged on steel pipe pars intramuralis periphery, and vertical steel tube wall is installed using welding method.The pull bar uses common pull bar or reinforcing bar, passes perpendicularly through the tube wall of rectangular steel pipe, and along pillar height side long, short side is with appropriate spacing interlaced arrangement.The tie rod end is with steel pipe walls using welding or bolt connection.Ribbed stiffener is mutually coordinated with binding bar in the utility model, the bond-slip between steel pipe walls and concrete can be delayed, alleviate the local buckling of steel pipe walls, improve the lateral rigidity of steel pipe walls, the ability and the effect of contraction to core concrete of its resistance local buckling are lifted, so as to improve the bearing capacity and ductility of rectangular steel-tube concrete column.

Description

Perforation rib pull bar constraint rectangular steel-tube concrete column
Technical field
The utility model is related to building structure technology field, more particularly to a kind of rectangle steel using rib pull bar constraint of perforating Pipe concrete column.
Background technology
Rectangular steel-tube concrete column has the incomparable distinctive feature of circular steel tube concrete post, such as steel in engineer applied The pipe connection with beam easy to make is easily processed, easy construction, be easy to meet the relative development in architectural plane requirement, section and inertia Square is big, the advantages of be suitable as bending component, had attracted increasing attention in engineering practice.
For concrete-filled rectangular steel tube, because steel pipe is concentrated mainly on corner to core concrete effect of contraction, on four sides Middle part effect of contraction there's almost no, so steel pipe is much smaller than round steel pipe coagulation to the overall effect of restraint of core concrete Soil, its bearing capacity is much lower compared with circular steel tube concrete.Rectangular steel pipe section side long is weak to the effect of contraction of core concrete In short side, and steel pipe side shorter edge long is more easy to local buckling.
The lateral rigidity of rectangular steel-tube concrete column steel plate is effectively improved, delays the bonding between steel pipe walls and concrete Sliding, can lift the ability and the effect of contraction to core concrete of its resistance local buckling, reinforcing steel pipe and concrete Integraty, so as to improve bearing capacity and ductility.
Rectangular Cft Columns With Binding Bars post is using the horizontal water of setting on longitudinal cross section at spacing intervals The design form of flat binding bar.The advantage of this form is bar connection, and bilateral greatly strengthen to core coagulation to drawing The hoop constraint of soil, so that it is constraint weak spot to improve between the bearing capacity of steel core concrete column, but binding bar vertical, horizontal, Avoid the generation of these position local bucklings, operative constraint of the comprehensive formation to core concrete, it is necessary to which encryption constraint is drawn Bar arranges that drilling is excessive, and pull bar consumption is big.
Another way is that the form for setting ribbed stiffener in steel pipe periphery midpoint is strengthened concrete-filled rectangular steel tube.It is this The outer deformability of form ribbed stiffener containment surfaces is weak, and the loading later stage is easily caused disengaging with concrete binding failure, to delay or preventing Only the deformation of middle side edge is, it is necessary to larger stiffness ratio of stiffener to panel, consumes steel more.And, ribbed stiffener fails to be formed to core The hoop constraint of concrete, lateral confinement power is weaker than being connected to drawing for binding bar, although can to a certain extent delay local bending Bent generation, but it is limited to improve the bearing capacity of rectangular steel-tube concrete column.
The content of the invention
For the shortcoming and deficiency that overcome prior art to exist, the intensity of steel is made full use of, delay or avoid peripheral steel The longitudinally, laterally local buckling problem of plate, forms the one of the hoop constraint to core concrete, enhancing steel pipe and concrete Property, so that the axle pressure of rectangular steel-tube concrete column, bias bearing capacity, anti-seismic performance are improved, the utility model proposes one The mentality of designing and construction method for improving rectangular steel-tube concrete column lateral rigidity are planted, that is, rib pull bar constraint rectangular steel pipe of perforating is mixed Solidifying earth pillar.
Perforation rib pull bar constraint rectangular steel-tube concrete column integraty reinforcement technique is by the perforate on ribbed stiffener, constraint Pull bar is perforated and mistake, connection(Welding or bolt connection)In in steel pipe walls, effective effect of contraction is formed to perforate ribbed stiffener, entered And slow down the local buckling of steel pipe walls.This design constrains the point-like of binding bar in binding bar rectangular steel-tube concrete column Become the wire constraint of ribbed stiffener, be not required to encrypt binding bar, excessive perforate can be prevented effectively from steel pipe walls.With second side Formula is compared, and the setting of binding bar forms larger hoop constraint effect to steel pipe walls, it is not necessary to firm using larger floor Degree ratio, can effectively delay the bond-slip between steel pipe walls and concrete.
The utility model is adopted the following technical scheme that:
Perforation rib pull bar constraint rectangular steel-tube concrete column, including rectangular steel pipe, concrete, ribbed stiffener, pull bar.It is described to add Strength rib is strip-form steel plate, and its thickness is identical with thickness of steel pipe.The ribbed stiffener upper connecting rod answers perforate, the size in hole through position Pull bar be able to be passed through.The ribbed stiffener is evenly arranged on steel pipe pars intramuralis periphery, is connected using welding method perpendicular to steel pipe walls Connect.The pull bar uses common pull bar or reinforcing bar, passes perpendicularly through the side long of rectangular steel pipe, and short side is handed over along pillar height with appropriate spacing Mistake arrangement.The tie rod end is such as perforate plug welding mode, second from welding with the first connected mode of steel pipe walls Connected mode is to carry out mantle fiber treatment with thread cutter for steel bar in tie rod end, is connected by screw bolts through steel pipe walls tapping.
The beneficial effects of the utility model:
(1) perforate ribbed stiffener and binding bar are combined closely, and few steel using amount is increased do not increase difficulty of construction, shadow again In the case of ringing construction speed, the effect of contraction of continuous effective is formed in whole height in four middle side edges of steel pipe walls, improved Side constraint ability, delays or avoids the sliding between steel pipe and concrete, and the bullet between binding bar is slowed down to greatest extent Plastic buckling, makes rectangular steel pipe significantly be strengthened with the integraty of concrete.(2) premise of structural safety is being met Under, can to large extent with relatively thin steel plate thickness, less rib width of putting more energy into, the integraty of enhancing steel pipe and concrete is real Intensity now higher, rigidity and ductility.(3) restraining force for wearing pull bar will be uniformly transferred to steel plate by ribbed stiffener, make pull bar Point-like constraint be changed into wire constraint, it is to avoid stress concentration, steel pipe to the effect of contraction of core concrete relative to simple plus If the rectangular steel-tube concrete column of binding bar is more continuous and uniform, relative to the rectangular steel pipe coagulation for adding ribbed stiffener merely Earth pillar more can effectively reduce the integraty of steel quantity consumption, enhancing steel pipe and concrete., along along short transverse, ribbed stiffener is along section for pull bar Length direction is split steel plate, reduces the depth-width ratio and flakiness ratio of steel plate, so that its half buckle wavelength subtracts significantly It is small.For peripheral steel plate, pull bar constraint ribbed stiffener provides strong sidewise restraint, prevents the flexing that steel plate is too early, favorably In its intensity of performance, meanwhile, steel plate constrains core concrete again with pull bar as fulcrum with its bending rigidity, makes concrete multi-shaft It is pressurized and improves its intensity.(5) component is easy to be connected with other steel members of surrounding, can give full play to steel plate and concrete Two kinds of mechanical properties of material, not only improve and undertake vertical load, are conducive to undertaking horizontal loading again.
Brief description of the drawings
Fig. 1 is front elevation view of the present utility model;
Fig. 2 is side view of the present utility model;
Fig. 3 is the A-A profiles of Fig. 1, Fig. 2;
Fig. 4 is the front elevation view of special case of the present utility model, i.e. square steel tube concrete column;
Fig. 5 is the side view of special case of the present utility model, i.e. square steel tube concrete column;
Fig. 6 is the A-A profiles of Fig. 4, Fig. 5.
Shown in figure:The perforate ribbed stiffener 3- sections short side that 1- pull bars are set with steel pipe walls tie point 2- sections long side direction The ribbed stiffener position of opening 7- concrete of the perforate ribbed stiffener 4- pull bar 5- steel pipe 6- rectangular steel-tube concrete columns that direction is set
The perforate ribbed stiffener that different directions length of side direction is set is represented for square steel tube concrete column, 2,3.
With reference to embodiment and accompanying drawing, the present invention is described in further detail, but embodiments of the present invention are not It is limited to this.
Specific embodiment
Embodiment
One kind perforation rib pull bar constraint rectangular steel-tube concrete column, including section long side direction set perforate ribbed stiffener 2, Perforate ribbed stiffener 3, pull bar 4, rectangular steel pipe 5, concrete seven that section short side direction is set.The perforate ribbed stiffener is strip-form Steel plate, its thickness is identical with the wall thickness of steel pipe 5.The perforate ribbed stiffener upper connecting rod answers the size in perforate, hole be able to wear through position 6 Cross pull bar 4.The perforate ribbed stiffener is evenly arranged in the tube wall interior periphery of steel pipe 5, and welding method is used perpendicular to the tube wall of steel pipe 5 Connection.The pull bar 4 uses common pull bar or reinforcing bar, passes perpendicularly through the tube wall of rectangular steel pipe 5, along column section side long, short side with Appropriate spacing interlaced arrangement.The tie rod end is, from welding, such as to perforate with the first connected mode of steel pipe walls tie point 1 The modes such as plug welding, second connected mode is to carry out mantle fiber treatment with thread cutter for steel bar in tie rod end, through steel pipe walls perforate Place is connected by screw bolts.
Embodiment 1
It is a kind of perforate rib pull bar constraint rectangular steel-tube concrete column making step be:
(1)Intensity, size, the position of rectangular steel pipe, pull bar and perforate ribbed stiffener are determined according to design drawing requirement;
(2)Make rectangular steel pipe 5, perforate ribbed stiffener, the pull bar 4 of rectangular steel-tube concrete column;
(3)The position of measurement and positioning pull bar 4, bores in the pull bar 4 of the rectangular steel pipe of steel core concrete column through position 1 Hole;
(4)Perforate ribbed stiffener is welded on rectangle steel tube wall using welding manner method;
(5)Pull bar 4 is arranged in the hole that has been drilled of rectangular steel pipe through perforate ribbed stiffener, using perforation plug welding connection or Bolt connection;
(6)Concrete casting is entered in rectangular steel pipe, is conserved by construction requirement.
Above-described embodiment is the utility model preferably implementation method, but implementation method of the present utility model is not by described The limitation of embodiment, it is other it is any without departing from the change made under Spirit Essence of the present utility model and principle, modify, replace Generation, combination, simplification, should be equivalent substitute mode, be included within protection domain of the present utility model.

Claims (6)

1. a kind of perforation rib pull bar constrains rectangular steel-tube concrete column, it is characterised in that including rectangular steel pipe, concrete, perforate Ribbed stiffener, pull bar, the ribbed stiffener are evenly arranged on steel pipe pars intramuralis periphery, are pacified using welding method perpendicular to steel pipe walls Dress, the pull bar passes through ribbed stiffener osseotomy site, and along pillar height side long, short side is with appropriate spacing interlaced arrangement.
2. a kind of perforation rib pull bar according to claim 1 constrains rectangular steel-tube concrete column, it is characterised in that described to add Strength rib is strip-form steel plate, and its thickness is identical with thickness of steel pipe.
3. a kind of perforation rib pull bar according to claim 1 constrains rectangular steel-tube concrete column, it is characterised in that described to open Position perforate is passed through in pull bar on the ribbed stiffener of hole, the size in hole be able to pass through pull bar.
4. a kind of perforation rib pull bar constraint rectangular steel-tube concrete column according to claim 1, it is characterised in that it is described about Beam pull bar uses common pull bar or reinforcing bar, passes perpendicularly through the tube wall of perforate ribbed stiffener and steel pipe, and along pillar height side long, short side is with appropriate Spacing interlaced arrangement, tie rod end is connected with steel pipe walls.
5. a kind of perforation rib pull bar according to claim 4 constrains rectangular steel-tube concrete column, it is characterised in that the drawing Boom end selects welding with the first connected mode of steel pipe walls.
6. a kind of perforation rib pull bar according to claim 4 constrains rectangular steel-tube concrete column, it is characterised in that the drawing Boom end is connected by screw bolts with second connected mode of steel pipe walls.
CN201620196537.4U 2016-03-15 2016-03-15 Perforation rib pull bar constraint rectangular steel-tube concrete column Expired - Fee Related CN206205270U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620196537.4U CN206205270U (en) 2016-03-15 2016-03-15 Perforation rib pull bar constraint rectangular steel-tube concrete column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620196537.4U CN206205270U (en) 2016-03-15 2016-03-15 Perforation rib pull bar constraint rectangular steel-tube concrete column

Publications (1)

Publication Number Publication Date
CN206205270U true CN206205270U (en) 2017-05-31

Family

ID=58754954

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620196537.4U Expired - Fee Related CN206205270U (en) 2016-03-15 2016-03-15 Perforation rib pull bar constraint rectangular steel-tube concrete column

Country Status (1)

Country Link
CN (1) CN206205270U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106049755A (en) * 2016-03-15 2016-10-26 河南理工大学 Rectangular concrete-filled steel tube column restrained by rib-perforating pull bars
CN107237453A (en) * 2017-07-20 2017-10-10 殷诗宝 A kind of concrete filled steel tube coupled column
CN108979189A (en) * 2018-08-01 2018-12-11 苏州穹力机械科技有限公司 Beam column built from concrete combination ruggedized construction

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106049755A (en) * 2016-03-15 2016-10-26 河南理工大学 Rectangular concrete-filled steel tube column restrained by rib-perforating pull bars
CN107237453A (en) * 2017-07-20 2017-10-10 殷诗宝 A kind of concrete filled steel tube coupled column
CN108979189A (en) * 2018-08-01 2018-12-11 苏州穹力机械科技有限公司 Beam column built from concrete combination ruggedized construction

Similar Documents

Publication Publication Date Title
CN206090967U (en) Perforation rib pull rod restraint double -layer steel plate concrete shear force wall
CN107227808A (en) A kind of buckling-restrained steel plate shear force wall system of full assembled
CN103061453B (en) Double-perforated steel plate-concrete combined coupling beam
CN206233626U (en) Perforation rib pull bar constraint rectangular steel pipe outsourcing self-compacting concrete reinforced column
CN105064503A (en) Steel tube and core tube mixed structure
CN106049720A (en) Punched rib and pull rod constraint double-layer steel plate concrete shear wall
CN206205270U (en) Perforation rib pull bar constraint rectangular steel-tube concrete column
CN201367654Y (en) Combined shear wall of steel tube concrete, steel plate with holes and concrete
CN101435233B (en) Steel tube concrete - punching steel plate - concrete combined shear wall and manufacturing method thereof
CN106049755A (en) Rectangular concrete-filled steel tube column restrained by rib-perforating pull bars
CN103485443A (en) Window-shaped-steel-plate concrete shear wall and manufacturing method thereof
CN205712590U (en) A kind of fabricated shear wall and the attachment structure of Prefabricated concrete-filled steel tube post
CN106088639A (en) Perforation rib pull bar constraint rectangular steel pipe outsourcing self-compacting concrete reinforces RC post
CN102828559A (en) Node for combination beam and 45-degree arranged cross steel reinforced concrete column
CN206693403U (en) A kind of steel core concrete column and connected mode
CN207392209U (en) Lattice column batten plate with grid
CN207079628U (en) A kind of open pore steel plate steel reinforced concrete assembling rectangle piping lane section
CN203559502U (en) Window-shaped steel plate concrete shear wall
CN105350642B (en) The cap of one kind connection " rice " type Cast-in-place concrete beam
CN204645318U (en) A kind of overlaid plate type shear wall
CN203034879U (en) Casing refuge bin structure of existing masonry structure
CN206941865U (en) A kind of power consumption assembled combined steel plate shearing force wall with damper
CN205857531U (en) A kind of aspect is than the stirrup attachment structure of combined steel and concrete column
CN205822507U (en) A kind of steel plate combined shear wall
CN205776898U (en) Overall assembled reinforced concrete shear wall structure system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170531

Termination date: 20190315

CF01 Termination of patent right due to non-payment of annual fee