CN206189389U - Underground continuous wall structure for reverse construction method - Google Patents

Underground continuous wall structure for reverse construction method Download PDF

Info

Publication number
CN206189389U
CN206189389U CN201621140959.6U CN201621140959U CN206189389U CN 206189389 U CN206189389 U CN 206189389U CN 201621140959 U CN201621140959 U CN 201621140959U CN 206189389 U CN206189389 U CN 206189389U
Authority
CN
China
Prior art keywords
purlin
pilaster
bar
joint bar
enclose
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621140959.6U
Other languages
Chinese (zh)
Inventor
崔衍斌
江咏
朱承峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Future Land Holdings Group Co Ltd
Original Assignee
Future Land Holdings Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Future Land Holdings Group Co Ltd filed Critical Future Land Holdings Group Co Ltd
Priority to CN201621140959.6U priority Critical patent/CN206189389U/en
Application granted granted Critical
Publication of CN206189389U publication Critical patent/CN206189389U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The utility model discloses an underground continuous wall structure for reverse construction method, include: the underground continuous wall main part, enclose purlin and pilaster, the underground continuous wall main part with it connects with the bar planting mode through enclosing the purlin joint bar to enclose the purlin, the underground continuous wall main part with the pilaster is passed through the pilaster joint bar and is connected with the bar planting mode. The pilaster is passed through pilaster joint bar shoving pours the shaping. It has and inserts the reinforcing bar of locating in the contignation of intermediate level to enclose in the purlin anchor. The underground continuous wall main part enclose the purlin and the pilaster connects into a whole through whole the watering of concrete. Pilaster joint bar and to enclose the purlin joint bar be HBR400 level reinforcing bar. The floor determination of position then encloses purlin joint bar determination of position, effectively reduces because of burying the inaccurate later stage problem of bringing of doing over again in a position. See from construction flow, the utility model discloses a structure neither needs the earlier stage embedded bar and ware of plugging into in underground continuous wall, does not also need the later stage chisel to bury the piece except that ground even wall concrete finds, and construction flow has obtained the simplification.

Description

A kind of contrary sequence method continuous underground wall structure
Technical field
The utility model is related to the realm of building construction, espespecially a kind of contrary sequence method continuous underground wall structure.
Background technology
In recent years, it is inverse to make with the extensive use of the increasing of super-sized foundation pit multi-storey basement and " contrary sequence method " Method has obtained extensive concern and research on building circle.Urban district site coverage is very suitable for greatly using " contrary sequence method " construction, it is neighbouring Building, subway, underground utilities and the surrounding environment situation sensitive to sedimentation and deformation.Engineering practice shows, main body underground structure It is combined with foundation pit supporting construction, using reverse construction, can be constructed simultaneously up and down, engineering image, progress is good, shorten and apply Work total lever factor;Structure level component substitutes that support stiffness is big, and fender body deformation is small, is conducive to surrounding environment and built construction thing Protection;Fender body, support and column use agent structure, it is to avoid the wasting of resources, the remarkable in economical benefits of engineering;Using envelope Close, adverse construction method, job site civilization, beneficial to urban construction and environmental protection;The design of main body underground structure more rationally, and has There is stronger economy.
Although the extensive use that reverse construction is obtained, the treatment of some key nodes is not often reached in practice of construction Promising result, for diaphram wall and pilaster, encloses the connected mode of purlin, and current Normal practice is horizontal structure when constructing, Reserved joint bar is set by the length of code requirement to make stage reinforcing bar and plug into use for suitable, subsequently plug into cylinder or wall position Plugging into the form for mechanically connecting, with adhesive waterproof tape to thread head bag in work progress between reinforcing bar and former reserved joint bar Wrap up in.There is problems with this construction method:
1st, diaphram wall and pilaster, enclose built-in fitting at purlin connecting node position and absolute altitude it is usually not accurate enough, nothing Method is smoothed out plugging into, and this is accomplished by the later stage and processes node embedded part again, is seriously delayed construction speed.
2nd, need to carry out ironware in advance and connector is pre-buried, work progress is relatively complicated.
3rd, for the engineering using the larger reinforcing bar of fragility, such as HRB400 grades of reinforcing bar is curved because the fragility of reinforcing bar is larger Easily it is broken afterwards.In casting concrete, concrete pump vibrates can influence reserved joint bar position so that built-in fitting fails.
The content of the invention
The purpose of this utility model is to provide a kind of contrary sequence method continuous underground wall structure, realize diaphram wall main body with Pilaster and enclose the connection of purlin.
The technical scheme that the utility model is provided is as follows:A kind of contrary sequence method continuous underground wall structure, including:Underground is continuous Wall main body, purlin and pilaster are enclosed, the diaphram wall main body is enclosed purlin and be connected in bar planting mode by enclosing purlin joint bar with described, institute Diaphram wall main body is stated to be connected in bar planting mode by pilaster joint bar with the pilaster.
Connector is connected by the way of bar planting and purlin and pilaster is enclosed, i.e., directly squeezed into agent structure reinforcing bar, this from The construction method of embedded bar and connector is fundamentally changed, its benefit has four:
First, avoiding situation about need to be constructed again because embedded part position is inaccurate, it is only necessary to dug to floor mark in the earthwork The height and position turns joint bar hole after eminence, and floor position determines then to enclose the determination of purlin joint bar position, effectively reduces because of embedded part position not The accurate later rework problem brought.
Second, from construction process, structure of the present utility model both do not needed early stage in diaphragm wall embedded bar and Connector, it is not required that the later stage, the substantial amounts of ground-connecting-wall concrete that cuts found embedded part, and construction process has obtained larger simplification, applied The reduction of work difficulty, accelerates construction speed.
Third, the utility model uses joint bar form, it is to avoid embedded bar bends fracture in concreting, or Being vibrated by concrete pump influences the situation of joint bar position.
Fourth, joint structure is simple, easy construction.
Preferably, the diaphram wall main body is enclosed purlin and is connected with intermediate layer contignation by described, described to enclose purlin Anchoring has the reinforcing bar being inserted in the contignation of intermediate layer.
Structure of the present utility model is particularly suited for the construction of contrary sequence method intermediate floor connecting node, is connected by enclosing purlin Connect diaphram wall main body and intermediate floor beam slab.
Preferably, the diaphram wall main body, described enclose purlin and the pilaster connects into one by whole the pouring of concrete Individual entirety.
One entirety is connected into by pilaster and ground-connecting-wall, preferably realizes that internal force is transmitted, it is ensured that the safety of building.Tool Body, the pilaster joint bar and purlin joint bar is enclosed for HBR400 grades of reinforcing bar.
The contrary sequence method continuous underground wall structure provided by the utility model, can bring following at least one beneficial effect Really:
1st, floor position determines then to enclose the determination of purlin joint bar position, effectively reduces because the embedded part position inaccurate later stage for bringing is returned Work problem.
2nd, from construction process, structure of the present utility model does not both need early stage pre-buried steel in diaphram wall main body Muscle and connector, it is not required that the later stage, the substantial amounts of ground-connecting-wall concrete that cuts found embedded part, and construction process has obtained larger letter Change, difficulty of construction reduction accelerates construction speed.
3rd, using joint bar form, it is to avoid embedded bar bends fracture in concreting, or is shaken by concrete pump Smash the situation of influence joint bar position.
4th, diaphram wall connecting node simple structure, easy construction.
5th, an entirety is connected into by pilaster and ground-connecting-wall, preferably realizes that internal force is transmitted, it is ensured that the safety of building.
Brief description of the drawings
Below by clearly understandable mode, preferred embodiment is described with reference to the drawings, a kind of contrary sequence method is connected with underground Above-mentioned characteristic, technical characteristic, advantage and its implementation for continuing wall construction are further described.
Fig. 1 is contrary sequence method diaphram wall structural representation.
Drawing reference numeral explanation:1st, diaphram wall main body, 2, enclose purlin, 3, enclose purlin joint bar, 4, intermediate layer contignation, 5, in Interbed beam reinforced steel bar, 6, pilaster, 7, pilaster joint bar.
Specific embodiment
In order to illustrate more clearly of the utility model embodiment or technical scheme of the prior art, accompanying drawing will be compareed below Illustrate specific embodiment of the present utility model.It should be evident that drawings in the following description are only of the present utility model one A little embodiments, for those of ordinary skill in the art, on the premise of not paying creative work, can also be according to these Accompanying drawing obtains other accompanying drawings, and obtains other implementation methods.
To make simplified form, the part related to the utility model is only schematically show in each figure, they are not Represent its practical structures as product.In addition, so that simplified form is readily appreciated, there is identical structure or work(in some figures The part of energy, only symbolically depicts one of those, or only marked one of those.Herein, " one " is not only Represent " only this ", it is also possible to represent the situation of " more than one ".
The utility model discloses a kind of embodiment of contrary sequence method continuous underground wall structure, contrary sequence method diaphram wall Structure includes:Diaphram wall main body 1, enclose purlin 2 and pilaster 6, diaphram wall main body 1 with enclose purlin 2 by enclose purlin joint bar 3 with Bar planting mode is connected, and diaphram wall main body 1 is connected by pilaster joint bar 7 with pilaster 6 in bar planting mode.
A preferred embodiment of the present utility model is that diaphram wall main body 1 is by enclosing purlin 2 and intermediate layer contignation 4 connections, anchoring has the intermediate layer beam reinforced steel bar 5 being inserted in intermediate layer contignation 4 in enclosing purlin 2.Diaphram wall main body 1, Enclose purlin 2 and pilaster 6 connects into an entirety by whole the pouring of concrete.Pilaster joint bar 7 and purlin joint bar 3 is enclosed for HBR400 grades of steel Muscle.
The invention also discloses a kind of contrary sequence method diaphram wall construction method, comprise the following steps:
S10, construction completes diaphram wall main body 1;
S20, after the earthwork is dug to respective storey absolute altitude, is drilled with for enclosing purlin joint bar 3 and wall in diaphram wall main body 1 The joint bar hole that post joint bar 7 is passed through;Plug in enclosing purlin joint bar 3 and pilaster joint bar 7 to joint bar hole;
S30, installs and encloses purlin 2 and pilaster 6 and intermediate layer contignation 4;
S40, casting concrete, and conserved.
It should be noted that above-described embodiment can independent assortment as needed.The above is only of the present utility model Preferred embodiment, it is noted that for those skilled in the art, is not departing from the utility model principle On the premise of, some improvements and modifications can also be made, these improvements and modifications also should be regarded as protection domain of the present utility model.

Claims (5)

1. a kind of contrary sequence method continuous underground wall structure, it is characterised in that including:Diaphram wall main body, purlin and pilaster are enclosed, The diaphram wall main body is enclosed purlin and is connected in bar planting mode by enclosing purlin joint bar with described, the diaphram wall main body and institute Pilaster is stated to be connected in bar planting mode by pilaster joint bar.
2. contrary sequence method continuous underground wall structure according to claim 1, it is characterised in that:The pilaster passes through the wall Post joint bar shove pours shaping.
3. contrary sequence method continuous underground wall structure according to claim 1, it is characterised in that:The diaphram wall main body It is connected with intermediate layer contignation by the purlin that encloses, it is described to enclose anchoring in purlin and have the steel being inserted in the contignation of intermediate layer Muscle.
4. according to any described contrary sequence method continuous underground wall structures of claim 1-3, it is characterised in that:The underground is continuous Wall main body, described enclose purlin and the pilaster connects into an entirety by whole the pouring of concrete.
5. according to any described contrary sequence method continuous underground wall structures of claim 1-3, it is characterised in that:The pilaster joint bar And purlin joint bar is enclosed for HBR400 grades of reinforcing bar.
CN201621140959.6U 2016-10-20 2016-10-20 Underground continuous wall structure for reverse construction method Active CN206189389U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621140959.6U CN206189389U (en) 2016-10-20 2016-10-20 Underground continuous wall structure for reverse construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621140959.6U CN206189389U (en) 2016-10-20 2016-10-20 Underground continuous wall structure for reverse construction method

Publications (1)

Publication Number Publication Date
CN206189389U true CN206189389U (en) 2017-05-24

Family

ID=58731734

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621140959.6U Active CN206189389U (en) 2016-10-20 2016-10-20 Underground continuous wall structure for reverse construction method

Country Status (1)

Country Link
CN (1) CN206189389U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108930275A (en) * 2018-07-25 2018-12-04 中国铁路设计集团有限公司 It is a kind of to face forever in conjunction with the ultra-deep shaft rapid constructing method along inverse combination
CN112681373A (en) * 2020-12-15 2021-04-20 中铁十一局集团建筑安装工程有限公司 Backfill reverse construction method for basement cantilever slab

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108930275A (en) * 2018-07-25 2018-12-04 中国铁路设计集团有限公司 It is a kind of to face forever in conjunction with the ultra-deep shaft rapid constructing method along inverse combination
CN112681373A (en) * 2020-12-15 2021-04-20 中铁十一局集团建筑安装工程有限公司 Backfill reverse construction method for basement cantilever slab

Similar Documents

Publication Publication Date Title
CN104895092B (en) The method that a kind of interim lattice column of inner support is used as permanent structure post
CN105178357A (en) Prefabricated subsurface structure under foundation trench open cutting condition and construction method for prefabricated subsurface structure under foundation trench open cutting condition
CN103334439A (en) Long-span reinforced concrete inner support structure of rectangular deep foundation pit and construction method of structure
CN109024651B (en) Steel pipe concrete mixed pile foundation and construction method
CN110080525B (en) Bidirectional synchronous construction method for high-rise building
CN106988303B (en) A kind of pile foundation and its construction method
CN102146672A (en) Method for constructing pile foundation in karst area
CN108035361A (en) A kind of advanced support supporting construction and its construction method
CN106894587A (en) Precast stair connection method
CN107013033A (en) A kind of concrete side wall formwork for placing and its construction method
CN106400982A (en) Stirrup-densified splicing joint for fabricated reinforced concrete columns
CN205778879U (en) Super-large-section tunnel drilling and blasting method enlarging constructing structure in situ
CN104295003A (en) Structural column construction method
CN105178358B (en) Vertical supporting system for reverse construction method and construction method of vertical supporting system
CN206189389U (en) Underground continuous wall structure for reverse construction method
CN106065668B (en) A kind of construction techniques
CN108316328A (en) A kind of pressurization sinking device and its construction method for open caisson construction
CN205935195U (en) Prefabricated building concrete beam column shaped steel built -up connection node construction
CN107443550A (en) Prefabricated cushion cap template and its installation method
CN106930278A (en) A kind of method that compromise joint pipe is used for support pile occlusion
CN105019645B (en) Fetch earth in contrary sequence method and the template system and construction method of xoncrete structure are built at mouth
CN101725147B (en) Construction process of first-inserting last-jetting type steel churning pile enclosing structure under low net space
CN108222283A (en) A kind of flexible connecting structure and its construction method for filling wall and main body frame
CN107975152A (en) The ductility connecting structure and construction method of first floor vertical member and basement roof
CN107288147A (en) Rock foundation pole and tower foundation construction method