CN206188205U - Hoist device is used in prefabricated piping lane upset - Google Patents

Hoist device is used in prefabricated piping lane upset Download PDF

Info

Publication number
CN206188205U
CN206188205U CN201621075854.7U CN201621075854U CN206188205U CN 206188205 U CN206188205 U CN 206188205U CN 201621075854 U CN201621075854 U CN 201621075854U CN 206188205 U CN206188205 U CN 206188205U
Authority
CN
China
Prior art keywords
piping lane
upset
hole
prefabricated piping
hanging apparatus
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621075854.7U
Other languages
Chinese (zh)
Inventor
高洪刚
熊平
刘献伟
陈东升
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Construction Co Ltd of China Construction Third Engineering Division
China State Construction Technology Wuhan Co Ltd
Original Assignee
First Construction Co Ltd of China Construction Third Engineering Division
China State Construction Technology Wuhan Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Construction Co Ltd of China Construction Third Engineering Division, China State Construction Technology Wuhan Co Ltd filed Critical First Construction Co Ltd of China Construction Third Engineering Division
Priority to CN201621075854.7U priority Critical patent/CN206188205U/en
Application granted granted Critical
Publication of CN206188205U publication Critical patent/CN206188205U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model discloses a hoist device is used in prefabricated piping lane upset, it includes gallows, transverse hoisting roof beam, supporting legs and two couples, the gallows includes chassis and the crown bit that is upwards extended by the chassis, the both ends of crown bit are provided with a plurality of first through -holes, first through -hole is used for the connecting shackle, the bottom of chassis with the top of transverse hoisting roof beam is connected, the both sides of transverse hoisting roof beam are connected with two supporting legss respectively, two couples are connected respectively the bottom of two supporting legss all is provided with a plurality of second through -holes on every couple. The utility model discloses simple structure is the gallows that is exclusively used in the upset of prefabricated piping lane, can realize the upset of piping lane effectively.

Description

A kind of prefabricated piping lane upset hanging apparatus
Technical field
The utility model is related to building field, more particularly to a kind of prefabricated piping lane upset hanging apparatus.
Background technology
It is usually to be inserted in hoist cable using loop wheel machine to lift by crane for the lifting of large-scale component in building field, this side Method not only inefficiency, and hoist cable is likely to occur landing, there may be accident when serious, particularly, prefabricated piping lane need to also be Upset is realized during lifting, institute cannot meet use requirement in a conventional method.
Utility model content
Technical problem to be solved in the utility model is the deficiency existed for above-mentioned prior art, there is provided Yi Zhongjie The simple prefabricated piping lane upset suspension bracket of structure.
The technical scheme that the utility model is used for:
A kind of prefabricated piping lane upset hanging apparatus, it includes suspension bracket, horizontal hanging beam, support feet and two hooks;It is described Suspension bracket includes underframe and the crown bit upwardly extended by underframe, and the two ends of the crown bit are provided with multiple first through hole, described First through hole is used for connecting shackle, and the bottom of the underframe is connected with the top of the horizontal hanging beam, the both sides point of the horizontal hanging beam Two support feets are not connected with, described two hooks connect the bottom of described two support feets respectively, be respectively provided with each hook There are multiple second through holes.
In such scheme, the prefabricated piping lane upset hanging apparatus also include being lifted on respectively wherein one on each hook Two hoist cables of individual second through hole, the Heave Here of described two hoist cables is arranged at piping lane center position on the upper side, two Heave Heres Line parallel to piping lane length direction.
In such scheme, uniform intervals are distributed with multiple deep floors on the suspension bracket horizontal direction.
In such scheme, the both sides of the suspension hook are evenly distributed with reinforcement inner panel.
In such scheme, the number of the first through hole is four, each two first through hole along suspension bracket axial direction pair Claim distribution.
In such scheme, two the second through holes are provided with each hook, along the axial direction side of horizontal hanging beam on two hooks It is consistent with the length of piping lane to two symmetrical pitch-rows of the second through hole.
In such scheme, described two second through holes are intervally arranged along horizontal direction.
Having the beneficial effect that acquired by the utility model:The utility model simple structure, hoist cable is easy for installation, simple, energy The lifting of piping lane quickly is realized, while the upset of piping lane can be effectively realized.
Brief description of the drawings
Fig. 1 is prefabricated piping lane upset hanging apparatus structural representation of the present utility model.
Fig. 2 to Fig. 4 is the use state figure of hanging apparatus of the present utility model.
Specific embodiment
The utility model is described in further detail below in conjunction with the accompanying drawings.
As shown in Figures 1 to 4, a kind of prefabricated piping lane upset hanging apparatus that it is provided for the utility model embodiment, It includes suspension bracket 1, horizontal hanging beam 2, support feet 3 and two hooks 4.
The suspension bracket 1 includes underframe and the crown bit upwardly extended by underframe.The two ends of the crown bit are provided with multiple First through hole 5.The first through hole 5 is used for connecting shackle 7.The bottom of the underframe is connected with the top of the horizontal hanging beam 2.Institute The both sides for stating horizontal hanging beam 2 are connected to two support feets 3.Described two hooks 4 connect described two support feets 3 respectively.Institute State and be provided with multiple second through holes 6 on two hooks 4.Second through hole 6 is used to connect hoist cable 8.On the horizontal direction of suspension bracket 1 Uniform intervals are distributed with multiple deep floors.The both sides of suspension hook 7 are evenly distributed with reinforcement inner panel.In the present embodiment, first leads to The number in hole 5 is four, and each two first through hole 5 is symmetrical along the axial direction of suspension bracket 1.
In the present embodiment, the number of the second through hole 6 is 4.Two the second through holes 6, two are distributed with each hook 4 Second through hole 6 is intervally arranged along horizontal direction.Two hoist cables 8 are lifted on one of them second through hole on each hook 4 respectively 6.The Heave Here of two hoist cables 8 is arranged at the center of piping lane 9 position on the upper side, length of two lines of Heave Here parallel to piping lane 9 Degree direction.
In order to realize the upset of piping lane, using 2 eccentric liftings, the deadweight of piping lane can be so made full use of to be turned over Turn.As shown in Figures 2 to 4, specific practice is that Heave Here is located at the center of piping lane 9 position on the upper side, and two lines of Heave Here Parallel to the length direction of piping lane 9, when so lifting by crane, the nearly Heave Here side of piping lane 9 can first be lifted, and continue to lift by crane, then can be real The overturning and hoisting of existing piping lane 9.

Claims (7)

1. a kind of prefabricated piping lane upset hanging apparatus, it is characterised in that it includes suspension bracket, horizontal hanging beam, support feet and two Hook;The suspension bracket includes underframe and the crown bit upwardly extended by underframe, and the two ends of the crown bit are provided with multiple first Through hole, the first through hole is used for connecting shackle, and the bottom of the underframe is connected with the top of the horizontal hanging beam, the horizontal hanging beam Both sides be connected to two support feets, described two hooks connect the bottom of described two support feets respectively, each hook On be provided with multiple second through holes.
2. prefabricated piping lane upset hanging apparatus as claimed in claim 1, it is characterised in that the prefabricated piping lane is overturn with hanging Assembling device also includes being lifted on respectively two hoist cables of upper one of them the second through hole of each hook, the lifting of described two hoist cables Point is arranged at piping lane center position on the upper side, length direction of two lines of Heave Here parallel to piping lane.
3. prefabricated piping lane upset hanging apparatus as claimed in claim 1, it is characterised in that equal on the suspension bracket horizontal direction It is even to be intervally distributed with multiple deep floors.
4. prefabricated piping lane upset hanging apparatus as claimed in claim 1, it is characterised in that the both sides of the suspension hook are uniformly divided It is furnished with reinforcement inner panel.
5. prefabricated piping lane upset hanging apparatus as claimed in claim 1, it is characterised in that the number of the first through hole is Four, each two first through hole is symmetrical along the axial direction of suspension bracket.
6. prefabricated piping lane upset hanging apparatus as claimed in claim 1, it is characterised in that each is linked up with and is provided with two Individual second through hole, along two symmetrical pitch-rows of the second through hole of the axial direction of horizontal hanging beam and the length of piping lane on two hooks Degree is consistent.
7. prefabricated piping lane upset hanging apparatus as claimed in claim 6, it is characterised in that described two second through holes along Horizontal direction is intervally arranged.
CN201621075854.7U 2016-09-23 2016-09-23 Hoist device is used in prefabricated piping lane upset Expired - Fee Related CN206188205U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621075854.7U CN206188205U (en) 2016-09-23 2016-09-23 Hoist device is used in prefabricated piping lane upset

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621075854.7U CN206188205U (en) 2016-09-23 2016-09-23 Hoist device is used in prefabricated piping lane upset

Publications (1)

Publication Number Publication Date
CN206188205U true CN206188205U (en) 2017-05-24

Family

ID=58729579

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621075854.7U Expired - Fee Related CN206188205U (en) 2016-09-23 2016-09-23 Hoist device is used in prefabricated piping lane upset

Country Status (1)

Country Link
CN (1) CN206188205U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108726348A (en) * 2018-03-31 2018-11-02 浙江交工集团股份有限公司 A kind of prefabricated overturning and hoisting method of piping lane segment prostrate

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108726348A (en) * 2018-03-31 2018-11-02 浙江交工集团股份有限公司 A kind of prefabricated overturning and hoisting method of piping lane segment prostrate

Similar Documents

Publication Publication Date Title
CN204342250U (en) A kind of multi-state hoisting balance beam
CN101994318B (en) Lifting frame, hoisting system and hoisting method for vertically and rotatably hoisting steel reinforcement cage
CN106276577A (en) The suspension bracket of a kind of framework isolated footing and operational approach
CN107161857A (en) Hoisting system and method suitable for erecting flat thin-wall component
CN206188205U (en) Hoist device is used in prefabricated piping lane upset
CN204342257U (en) A kind of large-scale component turning device
CN103183283B (en) System and method for installing lifting rigging
CN206088728U (en) Novel large -scale gallows of taking a trial run
CN208182486U (en) Construction lifting mechanical device
CN203159036U (en) Line-shaped lifting appliance
CN204251194U (en) A kind of Novel hanging tool
CN202655839U (en) Movable pipe truss assembling clamping fixture
CN202687773U (en) Hoisting hook, and hoisting device of vehicle frame
CN203903768U (en) Adjustable loading and unloading lifting bracket for waste heat boiler module
CN104098018A (en) Reusable multistage balance beam combination system
CN203187370U (en) Inner mast hoisting device
CN206705563U (en) A kind of novel pile formula crane
CN207259107U (en) A kind of lifting gear for working at height
CN206705524U (en) Mobile transport formula portal frame
CN206188193U (en) Gallows has been used in prefabricated piping lane drawing of patterns
CN207108291U (en) A kind of straddle truck of fast demountable
CN206255759U (en) A kind of handling apparatus for refrigerator box body
CN207346987U (en) Frame-type self-balancing hanger
CN105752816A (en) Large gantry crane and height-increasing lifting beam capable of increasing the lifting height of large gantry crane
CN205772842U (en) Inverted arch prefabricated section suspender

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170524