CN206174148U - It subsides post -cast strip structure system to transfinite on ground - Google Patents

It subsides post -cast strip structure system to transfinite on ground Download PDF

Info

Publication number
CN206174148U
CN206174148U CN201621088258.2U CN201621088258U CN206174148U CN 206174148 U CN206174148 U CN 206174148U CN 201621088258 U CN201621088258 U CN 201621088258U CN 206174148 U CN206174148 U CN 206174148U
Authority
CN
China
Prior art keywords
pouring
podium
main building
settlement
buried dowel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621088258.2U
Other languages
Chinese (zh)
Inventor
杨宝春
张�杰
刘正权
杨发兵
李军
赵淑荣
徐烨
孙玉霞
唐春光
张谦
崔秀生
李猛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd
Original Assignee
Third Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd filed Critical Third Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd
Priority to CN201621088258.2U priority Critical patent/CN206174148U/en
Application granted granted Critical
Publication of CN206174148U publication Critical patent/CN206174148U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)

Abstract

The utility model provides an it subsides post -cast strip structure system to transfinite on ground, includes main building major structure, skirt house owner body structure and transfinites and subsides the post -cast strip structure, main building major structure side is connected with main building and expands the structure outward, skirt house owner body structure side is connected with the podium and expands the structure outward, transfiniting and subsiding post -cast strip structure both ends and connect respectively to expand outside main building and expand outside structure and the podium structurally, the width is 13m~21m. The utility model provides a traditional subside leading to because of the differential settlement is too big that post -cast strip construction side method exists the roof beam be unable closed, the poor stability of building, roof beam is cuted the overstocked seriously technical problem of waste of material that lead to of materials such as the not good operation of connection form complicacy between the good and template frame body of normally arch camber, structure the stress, template and steel pipe.

Description

A kind of pouring after settlement structural system that transfinites on the ground
Technical field
This utility model is related to a kind of pouring after settlement structural system that transfinites on the ground.
Background technology
Post-cast strip is commonly used to prevent and evade safety problem, can conscientiously lift construction quality, if post-cast strip arranges improper, Serious quality problems can be brought, and the stability of whole building can be reduced.In the design of building construction at present, major part building is high Degree is higher, and attached multilamellar podium, and vestibule form is generally between main building and podium.In traditional construction ground pouring after settlement with Arrange with basement post-pouring zone, post-cast strip width is 800mm, per layer is arranged until podium roofing.Because pouring after settlement is by main building Beam disconnects between podium, and the beam span reaches 15m~23m, if the indwelling 800mm width pouring after settlement in this beam, in large span There is following 4 shortcomings in position:One is because between main building and podium that big beam span, main building and podium differential settlement are big, cause beam without Method closure, building are uneven, and reduce the stability of whole building;Two is 800mm width pouring after settlement by beam between main building podium Two large divisions is truncated into, causes the beam cannot normally arch camber, it is possible to caused the later stage beam in " recessed " form, be unfavorable for that structure is received Power;Type of attachment is complicated between post-cast strip both sides beam-slab template support body and post-cast strip support body, bad operation, while this three parts frame Body material need to overstock always to main building bind, post-cast strip closing just dismountable, serious waste material;Four is that building is uneven Problem, and there is certain risk in construction.
Utility model content
The utility model proposes a kind of pouring after settlement structural system that transfinites on the ground, will solve traditional pouring after settlement Construction method exist the stability for causing beam to close because differential settlement is excessive, building is poor, beam be truncated cannot normally arch camber, Structure entirety stress is bad and template support body between the overstocking of materials such as the complicated bad operation of type of attachment, template and steel pipe cause The technical problem of material serious waste.
Technical solutions of the utility model are as follows.
One kind transfinites after pouring after settlement structural system, including main building agent structure, podium agent structure and sedimentation of transfiniting Band structure is poured, the main building agent structure side is connected with main building and extends out structure;The podium agent structure side is connected with skirt Room extends out structure;The pouring after settlement structure that transfinites is connected to that main building extends out structure and podium is extended out between structure, and width is 13m~21m.
Preferably, the width that the main building extends out structure is 1000 mm~1500mm;The podium extends out the width of structure For 1000 mm~1500mm.
Preferably, it is with podium agent structure while the vestibule section for pouring that the podium extends out structure;The main building is extended out Structure is with main building agent structure while the vestibule section for pouring;The pouring after settlement structure that transfinites is connected to skirt for two ends Room extends out the after-pouring vestibule section that structure is extended out in structure with main building.
Preferably, the main building extends out structure and transfinites between pouring after settlement structure by the connection of pre-buried dowel one; The podium extends out structure and transfinites between pouring after settlement structure by the connection of pre-buried dowel two.
Preferably, the pre-buried dowel one includes the pre-buried dowel one of beam and the pre-buried dowel one of plate;The beam is pre-buried One end of dowel one is located in main building agent structure, and curves hook solid, and the other end of the pre-buried dowel one of beam is beyond master Building is extended out outside structure end and the beam steel of the pouring after settlement structure that transfinites connects;One end position of the pre-buried dowel one of the plate In main building agent structure, and with the plate bar connecting of main building agent structure, the other end of the pre-buried dowel one of plate exceeds main building Extend out that structure end is outer and plate bar connecting of the pouring after settlement structure that transfinites.
Preferably, the pre-buried dowel one of the beam is not less than 1000mm beyond the length that main building extends out structure end;It is described The pre-buried dowel one of plate is not less than 500mm beyond the length that main building extends out structure end.
Preferably, the pre-buried dowel two includes the pre-buried dowel two of beam and the pre-buried dowel two of plate;The beam is pre-buried One end of dowel two is located in podium agent structure, and curves hook solid, and the other end of the pre-buried dowel two of beam exceeds skirt Room extends out structure end and the connection of the beam steel of the pouring after settlement structure that transfinites;One end of the pre-buried dowel two of the plate is located at In podium agent structure, and with the plate bar connecting of podium agent structure, the other end of the pre-buried dowel two of plate is outside podium Expand the plate bar connecting of structure end and the pouring after settlement structure that transfinites.
Preferably, the pre-buried dowel two of the beam is not less than 1000mm beyond the length that podium extends out structure end;It is described The pre-buried dowel two of plate is not less than 500mm beyond the length that podium extends out structure end.
Compared with prior art this utility model has the characteristics that and beneficial effect.
1st, vestibule beam, plate block position in the less position of stress;Because span is big, main building agent structure is constructed after binding When with the space for being available for adjusting, just not there is a problem of that differential settlement is excessive yet and cause vestibule beam slab to close;Connect simultaneously Can normally arch camber in the beam construction in later period of corridor region.
2nd, the method in this utility model extends out main building, podium agent structure side beyond 1000mm, after whole indwellings are Pour band, it is almost an entirety that this will make between main building podium beam, and vestibule beam is no longer separated, can smoothly arch camber, also beneficial to the later stage Beam slab closure;The pouring after settlement structure that transfinites simultaneously beam slab between integrally closed main building podium again after main building binds so that material Material no longer overstocks, and so as to avoid the waste of material, has saved cost.
3rd, the pouring after settlement structure that transfinites in this utility model will be overall as pouring after settlement between main building podium, it is to avoid Because main building podium differential settlement is larger beam slab is closed, the risk that building height is uneven, make the stability in the large of building It is protected.
4th, the pouring after settlement structure that transfinites in this utility model will be overall as pouring after settlement between main building podium, makes master Beam between building podium is not truncated, the long-span beams can smoothly arch camber as requested, be conducive to the more preferable stress of structure.
5th, pouring after settlement structure is transfinited while convenient construction, successfully prevent and evaded not in this utility model Necessary security risk, improves construction quality.
6th, in this utility model construction method step three, by the two ends of the support body of the pouring after settlement structure that transfinites respectively with master Building extends out the mould bases connection that the mould bases of structure, podium extend out structure, no matter any part in three part support bodys, between them Support body stability in the large is all improved mutually.
7th, main building agent structure, the beam of podium agent structure, plate intensity i.e. dismountable bottom after reaching in this utility model Support body, the support body of the pouring after settlement structure that transfinites needs just to start to set up after main building binds, it is to avoid overstocking for material, improves All transfer efficients of material, conventional construction method is vestibule bottom(In the range of 15~23m of span)Support body must retain always to Main building binds, and post empiricism is complete, at least overstocks 10 months, therefore this utility model, compares the saving of traditional method high degree Project cost.
Description of the drawings
Fig. 1 is the pouring after settlement structural system floor map that transfinites on the ground in this utility model.
Fig. 2 is to transfinite the support body of pouring after settlement structure in this utility model and main building extends out the mould bases attachment structure of structure Schematic diagram.
Fig. 3 is late poured band structure system floor map traditional in this utility model.
Structural representation when Fig. 4 is the post-cast strip closure construction in this utility model on basement roof.
Fig. 5 is the floor map of steel bar arrangement in this utility model.
Fig. 6 is main building agent structure central sill, plate steel bar arrangement schematic diagram in this utility model.
Fig. 7 is podium agent structure central sill, plate steel bar arrangement schematic diagram in this utility model.
Reference:1-podium agent structure, 2-main building agent structure, 3-transfinite pouring after settlement structure, 4-skirt Room extend out structure, 5-main building extend out the full hall frame of structure, 6-main building agent structure, 7-main building extend out the mould bases of structure, 8-it is super Limit pouring after settlement structure support body, 9-traditionally go up late poured band structure, 10-supporting table, 11-basement roof post-cast strip Protecting formwork, 12-flitch, 13-inclined plane, 14-basement roof, the pre-buried connection of 15-pre-buried dowel one, 151-beam The pre-buried connection of the pre-buried dowel two, 162-plate of the pre-buried dowel one, 16-pre-buried dowel two, 161-beam of muscle one, 152-plate Muscle two.
Specific embodiment
Basement post-pouring zone is followed to arrange as shown in figure 3, traditionally going up late poured band structure 9, the width of traditional late poured band structure 9 Spend for 800mm, per layer is arranged until podium roofing, the beam span reaches 15m~23m, 800mm width traditionally go up post-cast strip and is tied Beam between main building agent structure 2 and podium agent structure 1 is truncated into two large divisions by structure 9, cause beam cannot normally arch camber, have The later stage beam is likely to result in " recessed " form, be unfavorable for structure stress etc. defect.
This utility model transfinites pouring after settlement structural system from main building agent structure 2, the side of podium agent structure 1 on the ground Extend out 1000mm respectively, whole indwellings are the pouring after settlement that transfinites, 3~7 layers of whole indwellings are transfinited post-cast strip, that is, after sedimentation of transfiniting Pour bandwidth and reach 13m~21m, vestibule region is substantially all for post-cast strip, after main building agent structure 2 binds, using than setting Meter intensity carries higher leveled filling expansive concrete and pours pouring after settlement region of transfiniting.
As shown in Figure 1 and Figure 2, this pouring after settlement structural system that transfinites, including main building agent structure 2, podium body junction Structure 1 and the pouring after settlement structure 3 that transfinites, the side of main building agent structure 2 is connected with main building and extends out structure 5;The podium master The side of body structure 1 is connected with podium and extends out structure 4;The pouring after settlement structure 3 that transfinites is connected to main building and extends out structure 5 and skirt Room is extended out between structure 4, and width is 13m~21m.
In the present embodiment, it is 1000 mm~1500mm that the main building extends out the width of structure 5;The podium extends out structure 4 Width be 1000 mm~1500mm.
In the present embodiment, it is with podium agent structure 1 while the vestibule section for pouring that the podium extends out structure 4;The master It is with main building agent structure 2 while the vestibule section for pouring that building extends out structure 5;The one end of pouring after settlement structure 3 connection of transfiniting Extend out in structure 4 in podium, the other end is connected to the after-pouring vestibule section that main building is extended out in structure 5.
In the present embodiment, the main building extends out structure 5 and the pre-buried dowel one that pass through between pouring after settlement structure 3 that transfinites 15 connections;The podium extends out structure 4 and to be transfinited connected by pre-buried dowel 2 16 between pouring after settlement structure 3.
In the present embodiment, the pre-buried dowel 1 includes the pre-buried dowel 1 of beam and the pre-buried dowel one of plate 152;One end of the pre-buried dowel 1 of the beam is located in main building agent structure 2, and curves hook solid, meets beam main tendon Anchoring requires that the other end of the pre-buried dowel 1 of beam extends out the end of structure 5 and the pouring after settlement structure 3 that transfinites beyond main building Beam steel connects;One end of the pre-buried dowel 1 of the plate is located in main building agent structure 2, with main building agent structure slab Muscle colligation is overlapped, and the other end of the pre-buried dowel 1 of plate is extended out outside the end of structure 5 and the pouring after settlement that transfinites beyond main building The plate bar connecting of structure 3.
In the present embodiment, the pre-buried dowel 1 of the beam is not less than beyond the length that main building extends out the end of structure 5 1000mm;The pre-buried dowel 1 of the plate is not less than 500mm beyond the length that main building extends out the end of structure 5.
In the present embodiment, the pre-buried dowel 2 16 includes the pre-buried dowel 2 161 of beam and the pre-buried dowel two of plate 162;One end of the pre-buried dowel 2 161 of the beam is located in podium agent structure 1, and curves hook solid, meets beam main tendon Anchoring requires that the other end of the pre-buried dowel 2 161 of beam extends out the end of structure 4 and the pouring after settlement structure 3 that transfinites beyond podium Beam steel connects;One end of the pre-buried dowel 2 162 of the plate is located in podium agent structure 1, with podium agent structure slab Muscle colligation is overlapped, and the other end of the pre-buried dowel 2 162 of plate extends out the end of structure 4 and the pouring after settlement knot that transfinites beyond podium The plate bar connecting of structure 3.
In the present embodiment, the pre-buried dowel 2 161 of the beam is not less than beyond the length that podium extends out the end of structure 4 1000mm;The pre-buried dowel 2 162 of the plate is not less than 500mm beyond the length that podium extends out the end of structure 4.
Transfinite the construction method of pouring after settlement structural system for this ground, including step is as follows.
Step one:Post-cast strip on basement roof 14 carries out protection closing.
Step 2:Main building agent structure 2, podium agent structure 1, main building extend out structure 5 and podium extends out applying for structure 4 Work.
Step 3:The support body 8 and beam of the pouring after settlement structure that transfinites, template die plate are set up.
Step 4:The beam of the pouring after settlement structure 3 that transfinites, the construction of slab muscle.
Step 5:Pour the concrete of pouring after settlement structure 3 that transfinites.
Step 6:Maintenance.
In the present embodiment, because ground vestibule part-structure whole indwelling is the pouring after settlement structure that transfinites, it is impossible to effectively Masking rainwater, rubbish etc., so needing to close the post-cast strip on basement roof 14 before constructing on the ground, are protected.
The protection closing of the post-cast strip in step one on basement roof 14 is specially:In basement roof post-cast strip both sides Basement roof 14 on, along basement roof post-cast strip length direction a bar shaped supporting table 10 is respectively built by laying bricks or stones, in supporting table 10 Lateral surface cement mortar smears into inclined plane 13, equal jointing between inclined plane 13 and brick, between inclined plane 13 and top board;Then exist Ceiling board post poured band protecting formwork 11 under full floor file in two supporting tables 10, under basement roof post-cast strip protecting formwork 11 Surface is provided with flitch 12;After main building binds, pour before the pouring after settlement that transfinites construction and poured after basement and basement roof Band.
In the present embodiment, the supporting table 10 is formed for brick masonry, is close to brick outside and is used 1:2 cement mortar are smeared at 45 ° oblique Angle, the lid plank sheathing above brick, boat nail wood a tree, used in making timber for boats under plank sheathing.Rubbish, rainwater etc. enter post-cast strip and ground when preventing construction on the ground Lower room.
In the present embodiment, when main building agent structure 2, podium agent structure 1 are constructed, need to the pouring after settlement structure that transfinites 3 beam, slab muscle get rid of muscle process, and all plate muscle need to brush element slurry and be protected, and all beam steels need to package nut, and brush plain slurry Protection.
In the present embodiment, it is the vestibule constructed simultaneously with main building agent structure 2 that main building described in step 2 extends out structure 5 Section, the length of the vestibule section is 1000mm~1500mm;It is while applying with podium agent structure 1 that the podium extends out structure 4 The vestibule section of work, the length of the vestibule section is 1000mm~1500mm.
Construction main building agent structure 2, podium agent structure 1, main building extends out structure 5 and podium extends out the concrete of structure 4 Step is.
Step a:Main building agent structure 2, podium agent structure 1, main building extend out structure 5 and podium extends out the mould of structure 4 Plate, support are set up;
Wherein, main building extends out the mould bases 7 of structure and is independently arranged, and with the full interim drawknot of hall frame 6 of main building agent structure;
Podium extends out the mould bases of structure and is independently arranged, and expires hall frame interim drawknot with annex agent structure.
Step b:Main building agent structure 2, podium agent structure 1, main building extend out structure 5 and podium extends out the steel of structure 4 Muscle construct, and do the pouring after settlement structure 3 that transfinites get rid of muscle process.
Step c:Main building agent structure 2, podium agent structure 1, main building extend out structure 5 and podium extends out the mixed of structure 4 Solidifying soil is poured.
Step d:Maintenance.
In the present embodiment, it is to extend out knot in main building agent structure 2 and main building muscle to be got rid of described in step b and processes concrete grammar Pre- anchoring beam embedded ribs and plate embedded ribs in structure 5, and pre- anchoring beam is pre- in podium agent structure 1 and podium extend out structure 4 Bury muscle and plate embedded ribs;The plate embedded ribs extend out length that the end of structure 5 or podium extend out the end of structure 4 not beyond main building Less than 500mm;The beam embedded ribs extend out the end of structure 5 beyond main building or podium extends out the length of the end of structure 4 and is not less than 1000mm。
In the present embodiment, the beam embedded ribs are connected with the beam steel at the two ends of pouring after settlement structure 3 of transfiniting;The plate is pre- Bury the plate bar connecting of muscle and the two ends of pouring after settlement structure 3 of transfiniting.
In the present embodiment, after step 2 has been constructed, the full hall frame 6 of main building agent structure is removed with the full hall of annex agent structure During frame, main building extends out the mould bases that the mould bases 7 of structure extends out structure with annex and does not remove.
In the present embodiment, in step 3 when support body 8 and beam, the template die plate of the pouring after settlement structure that transfinites is set up, transfinite The two ends of the support body 8 of pouring after settlement structure extend out respectively the mould bases that the end of the mould bases 7 of structure, annex extend out structure with main building End connection;Meet beam arch camber and the requirement that the ratio of beam span is 3/1000.
In the present embodiment, in step 4, when beam, plate reinforcement construction, the length that staggers of two neighboring plate splice is not little In a jointing length, its jointing length is 1.3l(L is the longitudinal tensile reinforcing bar colligation lap of splice);It is two neighboring Not less than a jointing length, its jointing length is 35d to the length that staggers of beam steel joint(D is that beam steel is straight Footpath);In same jointing length, splice rate cannot be greater than 50%;Transfinite the slab at the two ends of pouring after settlement structure 3 Can overlap for colligation for colligation overlap joint between muscle and plate embedded ribs, or welded lap, wherein colligation overlap bonding pad Segment length is 1.3l(L is the longitudinal tensile reinforcing bar colligation lap of splice);The beam steel and beam at the pouring after settlement structure 3 that transfinites two ends It is the connection of Ι levels screw shell between embedded ribs, its jointing length is 35d(D is beam steel diameter), refer to 11G101-1.
Ι level screw shells have dividing for positive and negative silk, so adjacent two are got rid of muscle termination and must not be all positive silk or anti-silk, joist steel Muscle termination need to first cover upper cap nut, and element slurry protection is then brushed again.Muscle is got rid of in the both sides of same slab muscle or beam steel, answers a length one It is short, the anti-silk of a positive silk one.
In traditional construction, beam steel gets rid of muscle requirement and is:Beam upper reinforcement gets rid of muscle to beam span 1/3, and beam lower rebar is got rid of Muscle is to beam span 1/4, and in the present embodiment, beam span reaches 15~23m, then beam top get rid of muscle length be at least 5~ 7.6m, lower rebar is got rid of muscle length and is at least 3.75~5.75m, throws away so long reinforcing bar, and reinforcing bar can be under Gravitative Loads freely End is sagging, and in the time of 10 months, reinforcing bar has become extremely difficult to adjustment because creep effects, and job site is long It is abnormally dangerous that phase throws away such long reinforcing bar.
In the present embodiment, reinforcing bar both sides are all connected using Ι levels screw shell, and a positive and a negative, and this way is in theory Can be attached in any position, and beam steel is thrown away no less than 1000mm, and adjacent two cage bars stagger a company Section length is connect, it is because that the position is the less position of beam stress, the effective defect for solving traditional construction of this way.
In the present embodiment, in step 5 before the concrete of pouring after settlement structure 3 that transfinites is poured, cut main building and extend out knot Structure 5, podium extends out the laitance of structure 4 and the joint part of pouring after settlement structure 3 that transfinites, and is rinsed well with water;Pouring coagulation During soil, vibrating head is inserted pull out slowly soon, and vibrating head operating radius is 300mm, and each displacement is less than or equal to 1.5R(R is referred to The operating radius of vibrating head, i.e. 300mm), i.e., less than or equal to 450mm.
Content described in this specification embodiment is only enumerating for the way of realization to utility model design, and this practicality is new The protection domain of type is not construed as being only limitted to the concrete form that embodiment is stated, protection domain of the present utility model is covered Those skilled in the art according to this utility model design it is conceivable that equivalent technologies mean.

Claims (8)

1. a kind of pouring after settlement structural system, including main building agent structure of transfiniting on the ground(2), podium agent structure(1)With it is super Limit pouring after settlement structure(3), it is characterised in that:The main building agent structure(2)Side is connected with main building and extends out structure(5);
The podium agent structure(1)Side is connected with podium and extends out structure(4);
The pouring after settlement structure that transfinites(3)It is connected to main building and extends out structure(5)Structure is extended out with podium(4)Between, width For 13m~21m.
2. transfinite pouring after settlement structural system for ground according to claim 1, it is characterised in that:The main building extends out knot Structure(5)Width be 1000 mm~1500mm;The podium extends out structure(4)Width be 1000 mm~1500mm.
3. transfinite pouring after settlement structural system for ground according to claim 1, it is characterised in that:The podium extends out knot Structure(4)It is and podium agent structure(1)The vestibule section for pouring simultaneously;The main building extends out structure(5)It is and main building agent structure (2)The vestibule section for pouring simultaneously;The pouring after settlement structure that transfinites(3)Podium is connected to for two ends extend out structure(4) Structure is extended out with main building(5)On after-pouring vestibule section.
4. transfinite pouring after settlement structural system for ground according to claim 1, it is characterised in that:The main building extends out knot Structure(5)With the pouring after settlement structure that transfinites(3)Between pass through pre-buried dowel one(15)Connection;The podium extends out structure(4) With the pouring after settlement structure that transfinites(3)Between pass through pre-buried dowel two(16)Connection.
5. transfinite pouring after settlement structural system for ground according to claim 4, it is characterised in that:The pre-buried dowel One(15)Including the pre-buried dowel one of beam(151)With the pre-buried dowel one of plate(152);The pre-buried dowel one of the beam(151)'s One end is located at main building agent structure(2)In, and hook solid is curved, the pre-buried dowel one of beam(151)The other end exceed main building Extend out structure(5)Outside end and the pouring after settlement structure that transfinites(3)Beam steel connection;The pre-buried dowel one of the plate(152) One end be located at main building agent structure(2)In, and with main building agent structure(2)Plate bar connecting, the pre-buried dowel one of plate (152)The other end extend out structure beyond main building(5)Outside end and the pouring after settlement structure that transfinites(3)Plate bar connecting.
6. transfinite pouring after settlement structural system for ground according to claim 5, it is characterised in that:The pre-buried connection of the beam Muscle one(151)Structure is extended out beyond main building(5)The length of end is not less than 1000mm;The pre-buried dowel one of the plate(152)It is super Go out main building and extend out structure(5)The length of end is not less than 500mm.
7. transfinite pouring after settlement structural system for ground according to claim 4, it is characterised in that:The pre-buried dowel Two(16)Including the pre-buried dowel two of beam(161)With the pre-buried dowel two of plate(162);The pre-buried dowel two of the beam(161)'s One end is located at podium agent structure(1)In, and hook solid is curved, the pre-buried dowel two of beam(161)The other end exceed podium Extend out structure(4)End and the pouring after settlement structure that transfinites(3)Beam steel connection;The pre-buried dowel two of the plate(162)'s One end is located at podium agent structure(1)In, and with podium agent structure(1)Plate bar connecting, the pre-buried dowel two of plate(162) The other end extend out structure beyond podium(4)End and the pouring after settlement structure that transfinites(3)Plate bar connecting.
8. transfinite pouring after settlement structural system for ground according to claim 7, it is characterised in that:The pre-buried connection of the beam Muscle two(161)Structure is extended out beyond podium(4)The length of end is not less than 1000mm;The pre-buried dowel two of the plate(162)It is super Go out podium and extend out structure(4)The length of end is not less than 500mm.
CN201621088258.2U 2016-09-29 2016-09-29 It subsides post -cast strip structure system to transfinite on ground Expired - Fee Related CN206174148U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621088258.2U CN206174148U (en) 2016-09-29 2016-09-29 It subsides post -cast strip structure system to transfinite on ground

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621088258.2U CN206174148U (en) 2016-09-29 2016-09-29 It subsides post -cast strip structure system to transfinite on ground

Publications (1)

Publication Number Publication Date
CN206174148U true CN206174148U (en) 2017-05-17

Family

ID=58678140

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621088258.2U Expired - Fee Related CN206174148U (en) 2016-09-29 2016-09-29 It subsides post -cast strip structure system to transfinite on ground

Country Status (1)

Country Link
CN (1) CN206174148U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113137062A (en) * 2021-05-10 2021-07-20 山西四建集团有限公司 High-rise residential expansion type reinforcing belt construction method for replacing post-cast strip
CN115012537A (en) * 2022-06-30 2022-09-06 中国建筑一局(集团)有限公司 Construction method of settlement-spanning post-cast strip of stiffened steel transfer beam

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113137062A (en) * 2021-05-10 2021-07-20 山西四建集团有限公司 High-rise residential expansion type reinforcing belt construction method for replacing post-cast strip
CN115012537A (en) * 2022-06-30 2022-09-06 中国建筑一局(集团)有限公司 Construction method of settlement-spanning post-cast strip of stiffened steel transfer beam
CN115012537B (en) * 2022-06-30 2023-02-03 中国建筑一局(集团)有限公司 Construction method of settlement-spanning post-cast strip of stiffened steel transfer beam

Similar Documents

Publication Publication Date Title
CN107542196A (en) Prestressed concrete bidirectional laminated slab and preparation method
CN206667459U (en) A kind of pre-splicing Standard formula building of prefabrication type reinforced concrete shear wall
CN205421616U (en) Assemble integral shear force wall with steel pipe concrete edge member
CN207582764U (en) A kind of close spelling laminated floor slab connecting joint structure of end fluting
CN108035437A (en) A kind of prefabricated node of the high-strength high concrete assembled frame of ductility and connection method
CN210658744U (en) Concrete anti-bank waterproof structure
CN106436930B (en) Transfinite pouring after settlement structural system and construction method for a kind of ground
CN108798059A (en) A kind of old masonry seismic reinforcing structure and construction method
CN207919746U (en) A kind of prefabricated node of high-strength high concrete assembled frame of ductility
CN213952303U (en) Basement outer wall post-cast strip assembled protection wall construction structures
CN104790436B (en) Basement in high rise building top board pouring after settlement advance water stop construction method
CN114892552B (en) Box girder type bridge reconstruction construction method
CN107130715A (en) Teeth groove is poured after a kind of to be linked and packed the construction method of formula building roof system
CN105780992B (en) A kind of orthogonal spatial Rc Open-web Sandwich Plates floor construction engineering method
CN107130716A (en) After pour teeth groove and be linked and packed formula building roof system
CN110409900A (en) Hybrid connection precast prestressed concrete circle warehouse structure
CN112627030A (en) Gravity type anchorage structure of cable saddle buttress foundation and approach bridge foundation and construction method
CN113638304A (en) Concrete beam type bridge hidden cover beam structure system and construction method thereof
CN206174148U (en) It subsides post -cast strip structure system to transfinite on ground
CN206233560U (en) Wall formwork erecting structure
CN207110214U (en) A kind of prefabricated interior fill concrete wallboard
CN206829461U (en) After pour teeth groove and be linked and packed formula precast slab
CN206722216U (en) A kind of prefabricated girder of laminated floor slab
CN106284749B (en) A kind of connecting node of upper load-bearing precast concrete exterior wall and girder steel
CN209456992U (en) Low damage unilateral formwork supporting structure under campshed support system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170517