CN206157676U - Two hoisting point pull rod gates - Google Patents

Two hoisting point pull rod gates Download PDF

Info

Publication number
CN206157676U
CN206157676U CN201621216479.3U CN201621216479U CN206157676U CN 206157676 U CN206157676 U CN 206157676U CN 201621216479 U CN201621216479 U CN 201621216479U CN 206157676 U CN206157676 U CN 206157676U
Authority
CN
China
Prior art keywords
gate
pull bar
locking
connecting plate
flap
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201621216479.3U
Other languages
Chinese (zh)
Inventor
李焰
李湖川
贾刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Chengdu Engineering Co Ltd
Original Assignee
PowerChina Chengdu Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Chengdu Engineering Co Ltd filed Critical PowerChina Chengdu Engineering Co Ltd
Priority to CN201621216479.3U priority Critical patent/CN206157676U/en
Application granted granted Critical
Publication of CN206157676U publication Critical patent/CN206157676U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Barrages (AREA)

Abstract

The utility model discloses a two hoisting point pull rod gates belongs to the hydraulic and hydroelectric engineering field for the solution can't shift out from the gate slot top because of being located two locking device between the pull rod when adopting two hoisting point pull rod gates, and then leads to the gate flap can't follow the problem of taking out in the gate slot. Two hoisting point pull rod gates, through set up slidable locking beam on locking platform, and the accessible is with corresponding locking beam and the direct fixed connection of gate flap, both can support the gate flap after having removed last a lesson connecting rod by corresponding locking beam with this when the bulkhead gate, can lift by crane out together with the locking beam no. 1 who is connected with the gate flap when hanging out the gate flap again, consequently solved owing to can't follow the problem that the gate slot took out because of being arranged in the unable gate flap that shifts out from the gate slot above and then lead to of two locking device between the pull rod when adopting two hoisting point pull rod gates, and then in can using actual engineering normally with two hoisting point pull rod gates.

Description

Double lifting point pull bar gate
Technical field
The utility model is related to Hydraulic and Hydro-Power Engineering field, more particularly to a kind of double lifting point pull bar gate and its maintenance side Method.
Background technology
In Hydraulic and Hydro-Power Engineering, generally have using pull bar hang winding gate carry out open and close operation gate structure;But this Class pull bar gate when using double lifting point Tiebar structure, because the locking device between two pull bars cannot be from gate slot top Remove, therefore cause gate flap to take out from gate slot, and then be not easy to carry out inspection operation to gate.Due to the problems referred to above Exist, often abandon, using the scheme of double lifting point pull bar gate, being changed to single design of lifting points to solve in current water conservancy and hydropower design Certainly this problem.But, for gate widths are than larger gate flap, when lifting by crane gate using single design of lifting points, its gate flap Stationarity is poor, and single suspension centre pull bar gate cannot meet the use demand of such gate.Therefore, being badly in need of one kind can solve to adopt Exist during double lifting point pull bar gate because the locking device between two pull bars cannot be removed from gate slot top, and then cause door The double lifting point pull bar gate scheme of the problem that leaf cannot take out from gate slot.
Utility model content
The utility model solve technical problem be:Because between two pull bars when using double lifting point pull bar gate Locking device cannot be removed from gate slot top, and then cause the problem that gate flap cannot take out from gate slot, can be with to provide one kind The double lifting point pull bar gate for solving the above problems and its repair method.
The utility model solves the technical scheme that its technical problem adopted:Double lifting point pull bar gate, including gate slot, also Including the locking platform for being arranged on gate slot top, the headstock gear mounting platform being arranged on above locking platform, install in headstock gear Headstock gear is installed on platform, gate flap moving up and down is provided with the gate slot;Also include pull bar, the pull bar has two Root, and two pull bars, along the width interval setting of gate flap, the lower end of pull bar is connected with gate flap, the upper end and top of pull bar Headstock gear on suspension centre connection;Also include locking beam, the locking girder span is located at the gate slot top, and locks Liang Keyan The width of gate slot is movably ridden on locking platform;It is corresponding with every pull bar to be provided with two locking beams, and two Locking beam is located at the both sides of the pull bar;First is respectively arranged with the downside of two locking beams between positioned at two pull bars Connecting plate, in gate flap upper end the second connecting plate is provided with;First connecting plate matches with corresponding second connecting plate, and can lead to Cross connecting bolt to connect the first connecting plate with corresponding second connecting plate.
It is further:Two piece first is respectively arranged with the downside of two locking beams between positioned at two pull bars Connecting plate, and two piece of first connecting plate is along the thickness direction interval setting of gate slot;On the upper end of gate flap and each locking beam Two piece of first connecting plate corresponding be provided with two piece of second connecting plate.
It is further:It is additionally provided with the positive stop for raising up in gate flap upper end, the positive stop there are two, and And two positive stops are along the width interval setting of gate flap;Two locking beams between two pull bars can be moved simultaneously To between two positive stops.
It is further:The both sides that gate slot thickness direction is located on locking platform are respectively arranged with slide rail, the slide rail Width along gate slot be arranged in parallel;Be respectively arranged with movable pulley at two ends of each locking beam, and the movable pulley with The slide rail of respective side coordinates.
It is further:The pull bar is formed by more piece connecting rod is detachably connected successively, is set in every section connecting rod It is equipped with locking limiting card.
In addition, the utility model also provides a kind of repair method of double lifting point pull bar gate, it adopts above-mentioned practicality new Double lifting point pull bar gate described in type, comprises the steps:
The first step, pull bar is sling together with gate flap by headstock gear, and make to be now placed in a section of pull bar the top Connecting rod passes completely through locking beam, then moves the locking beam positioned at pull bar both sides, makes locking beam right with next section connecting rod The locking limiting card answered coordinates to lock pull bar;
The connection of second step, the suspension centre for unclamping headstock gear and pull bar, then a section connecting rod of now pull bar the top is removed, Then again the suspension centre on headstock gear is saved into connecting rod with one of the top on remaining pull bar to be connected;
3rd step, the repetition first step and second step, until pull bar is only left to enter when final section connecting rod is connected with gate flap The step of row the 4th;
4th step, pull bar is sling together with gate flap by headstock gear, then four are locked outermost two in beams Individual locking beam is removed to both sides, while will move to middle part positioned at two middle locking beams, and makes on locking beam first to connect Fishplate bar the second connecting plate corresponding with gate flap aligns in a vertical direction;
5th step, pull bar is further sling together with gate flap by headstock gear, until lock the first connecting plate on beam with Stop when corresponding second connecting plate coordinates on gate flap, then connected the first connecting plate and corresponding second by connecting bolt Plate connects;
The connection of the 6th step, the suspension centre for unclamping headstock gear and pull bar, by two locking load bearing beam gate flaves being connected with gate flap, Then final section connecting rod is removed again, afterwards hangs gate flap from gate slot together with two locking beams being connected with gate flap Go out.
The beneficial effects of the utility model are:By arranging slidable locking beam on locking platform, and can pass through Corresponding locking beam is directly fixedly connected with gate flap, both can be by locking beam supporting removal accordingly most in bulkhead gate with this Gate flap after later section connecting rod, can hang out while gate flap is hung out together with the locking beam being connected with gate flap again, therefore Solve due to using during double lifting point pull bar gate because the locking device between two pull bars cannot be removed from gate slot top And then the problem that caused gate flap cannot take out from gate slot;And then double lifting point pull bar gate can be normally used actual work Cheng Zhong.In addition, by using repair method described in the utility model, can directly be connected with gate flap by will accordingly lock beam Connect, and gate flap is directly supported by locking beam, so can avoid needing extra setting during final section connecting rod is removed Loop wheel machine is hung gate flap using headstock gear to be attached the dismounting work of bar, can further be optimized the maintenance to gate and be grasped Make.
Description of the drawings
Schematic diagram when Fig. 1 is double lifting point pull bar gate actual installation described in the utility model;
Fig. 2 is the sectional view of Section A-A in Fig. 1;
Fig. 3 is the enlarged diagram of regional area D in Fig. 2;
Fig. 4 is structural representation when gate flap is connected with locking beam;
Fig. 5 is the sectional view of section B-B in Fig. 4;
Fig. 6 is the enlarged diagram of regional area C in Fig. 5;
Fig. 7 is the front view of pull bar;
Fig. 8 is the side view of pull bar;
It is labeled as in figure:Gate slot 1, locking platform 2, headstock gear mounting platform 3, headstock gear 4, gate flap 5, pull bar 6, suspension centre 7, Locking beam 8, the first connecting plate 9, the second connecting plate 10, connecting bolt 11, positive stop 12, slide rail 13, movable pulley 14, connecting rod 15th, limiting card 16 is locked.
Specific embodiment
The utility model is further illustrated with reference to the accompanying drawings and detailed description.
As shown in Fig. 1 to Fig. 8, double lifting point pull bar gate described in the utility model, including gate slot 1, also including setting In the locking platform 2 on the top of gate slot 1, the headstock gear mounting platform 3 of the top of locking platform 2 is arranged on, in headstock gear mounting platform 3 On headstock gear 4 is installed, be provided with gate flap moving up and down 5 in the gate slot 1;Also include pull bar 6, the pull bar 6 has Two, and two pull bars 6, along the width interval setting of gate flap 5, the lower end of pull bar 6 is connected with gate flap 5, pull bar 6 it is upper End is connected with the suspension centre 7 on the headstock gear 4 of top;Also include locking beam 8, the locking beam 8 is crossed on the top of the gate slot 1, And locking beam 8 can movably ride on locking platform 2 along the width of gate slot 1;It is corresponding with every pull bar 6 to be provided with two Individual locking beam 8, and two locking beams 8 are positioned at the both sides of the pull bar 6;Two locking beams 8 between positioned at two pull bars 6 The first connecting plate 9 is respectively arranged with downside, the upper end of gate flap 5 is provided with the second connecting plate 10;First connecting plate 9 with Corresponding second connecting plate 10 matches, and can be connected the first connecting plate 9 with corresponding second connecting plate 10 by connecting bolt 11 Connect.
Wherein, beam 8 is locked identical compared with the mode of the pull bar gate in technology to the lock mode of pull bar 6, i.e., typically Corresponding locking limiting card 16 is provided with pull bar 6;And by the way that locking beam 8 is moved near pull bar 6 on locking platform 2 After can make to lock accordingly limiting card 16 and be overlapped on locking beam 8, realize locking pull bar 6 by locking beam 8 with this, to hinder Only pull bar 6 is moved down.And when needing to unclamp the locking to pull bar 6, then two side shiftings of the beam 8 to pull bar 6 can will be locked, with Away from pull bar 6.Without loss of generality, pull bar 6 is generally formed by more piece connecting rod 15 is detachably connected, now can be in every section It is both provided with locking limiting card 16 accordingly in connecting rod 15.
In addition, for the structure such as headstock gear mounting platform 3 and headstock gear 4 and its mounting means with existing pull bar Gate is consistent;The effect of headstock gear 4 is to play the keying to gate to act on, i.e., can be by gate flap 5 together with pull bar 6 by headstock gear 4 Sling together or transfer.Can be accordingly that every pull bar 6 arranges one due to being provided with two pull bars 6 in the utility model Individual headstock gear 4, or also a headstock gear 4 can be connected with two pull bars 6 simultaneously.
Gate in the utility model is double lifting point pull bar gate, i.e., two pull bars 6, and two are connected with gate flap 5 Root pull bar 6 is generally spaced apart on the width of gate flap 5, with this support to gate flap 5 can be made more steady, can meet Situation when lock gate leaf is wider.And the utility model is further by the bottom of the locking beam 8 between positioned at two pull bars 6 Portion arranges the first connecting plate 9 and arranges corresponding second connecting plate 10 on the top of gate flap 5, is so needing bulkhead gate When, can be by the way that the first connecting plate 9 be connected with the corresponding corresponding matching of second connecting plate 10, you can will lock accordingly beam 8 with Gate flap 5 connects integral, afterwards again hangs out gate flap from gate slot 1 together with corresponding locking beam 8, to be overhauled.And And, directly it is connected with gate flap 5 due to will accordingly lock beam 8, so during final section connecting rod 15 is removed, may be used also Directly gate flap 5 is hung by locking beam 8, and without the need for being hung gate flap 5 by headstock gear or the extra loop wheel machine that arranges so as to gate Inspection operation enhanced convenience.Can be using company as the bindiny mechanism between the first connecting plate 9 and corresponding second connecting plate 10 Connecting bolt 11 is attached, and is attached using connecting bolt 11, dismounting of being also more convenient for;Accordingly should be first Bolt hole is provided with the connecting plate 10 of connecting plate 9 and second.
More specifically, the effectively connection of beam 8 and gate flap is locked in order to ensure each, can be between two pull bars 6 Two piece of first connecting plate 9 is respectively arranged with the downside of two locking beams 8, and two piece of first connecting plate further can be set 9 along gate slot 1 thickness direction interval setting;It is corresponding with two piece of first connecting plate 9 on each locking beam 8 in the upper end of gate flap 5 Be provided with two piece of second connecting plate 10.As shown in referring to the drawings 5, it is respectively provided with the both sides side of the thickness direction of gate flap 5 There is the second connecting plate 10, it is corresponding on each locking beam 8 accordingly to be provided with two piece of first connecting plate 9.
In addition, for the ease of to locking the positioning between beam 8 and gate flap 5, being further also provided with the upper end of gate flap 5 The positive stop 12 for raising up, the positive stop 12 has two, and two positive stops 12 are along the width of gate flap 5 Interval setting;Two locking beams 8 between two pull bars 6 can be moved between two positive stops 12 simultaneously.So, exist Before locking beam 8 and gate flap 5 are attached, first certain position-limiting action can be played by 12 pairs of locking beams 8 of positive stop, so may be used It is more convenient for being attached the first connecting plate 9 with corresponding second connecting plate 10.
More specifically, it is flat in locking referring to the drawings shown in 2 for the ease of locking movement of the beam 8 on locking platform 2 Both sides on platform 2 positioned at the thickness direction of gate slot 1 are respectively arranged with slide rail 13, and the slide rail 13 is parallel along the width of gate slot 1 Arrange;Movable pulley 14 is respectively arranged with the two ends of each locking beam 8, and the movable pulley 14 is matched somebody with somebody with the slide rail 13 of respective side Close.Certainly, in order that can remove from the surface of gate slot 1 positioned at the outermost two lockings beam 8 in the two ends of gate slot 1, should set The two ends from corresponding gate slot 1 for putting the two ends of slide rail 13 stretch out, i.e., the length of slide rail 13 should be more than the width of gate slot 1.
Above-mentioned double lifting point pull bar gate described in the utility model, its repair method comprises the steps:
The first step, pull bar 6 is sling together with gate flap 5 by headstock gear 4, and make to be now placed in the top of pull bar 6 One section connecting rod 15 passes completely through locking beam 8, then moves the locking beam 8 positioned at the both sides of pull bar 6, makes locking beam 8 with next section Corresponding locking limiting card 16 coordinates to lock pull bar 6 in connecting rod 15;
The connection of second step, the suspension centre 7 for unclamping headstock gear 4 and pull bar 6, now gate flap 5 will be by locking beam 8 together with pull bar 6 Carry, now a section connecting rod 15 of i.e. dismountable the top of pull bar 6, then again by the suspension centre 7 on headstock gear 4 and remaining drawing A section connecting rod 15 of the top connects on bar 6;
3rd step, the repetition first step and second step, when 6 remaining final section connecting rods 15 of pull bar are connected with gate flap Carry out the 4th step;
Both be performed a plurality of times to the circulation of the 3rd step by the above-mentioned first step, can by pull bar 6 except lowermost end one saves connecting rod All connecting rods 15 outside 15 are removed;Step 4 can be carried out afterwards;
4th step, pull bar 6 is sling together with gate flap 5 by headstock gear 4, then lock outermost in beams 8 by four Two locking beams 8 remove to both sides, while two middle locking beams 8 will be located at moving to middle part, and make on locking beam 8 First connecting plate 9, second connecting plate 10 corresponding with gate flap 5 aligns in a vertical direction;
5th step, pull bar 6 is further sling together with gate flap 5 by headstock gear 4, until locking the on beam 8 first connection Stop when corresponding with gate flap 5 second connecting plate 10 of plate 9 coordinates, then by connecting bolt 11 by the first connecting plate 9 with it is right The second connecting plate 10 answered connects;
6th step, the suspension centre 7 for unclamping headstock gear 4 and the connection of pull bar 6, are carried by two locking beams 8 being connected with gate flap 5 Gate flap 5, then removes again final section connecting rod 15, afterwards by gate flap 5 together with two locking beams 8 being connected with gate flap 5 Hang out from gate slot 1.
Above-mentioned steps four are then by locking being directly connected to for beam 8 and gate flap 5, directly being carried by locking beam 8 to step 6 Gate flap 5, while completing the dismounting to final section connecting rod 15.Afterwards, then by gate flap 5 together with locking beam 8 from gate slot 1 Hang out.Certainly, gate flap 5 can be hung out together with locking beam 8 from gate slot 1 using external loop wheel machine accordingly or is also adopted Gate flap connection locking beam 8 is hung out together from gate slot 1 with headstock gear 4.

Claims (5)

1. double lifting point pull bar gate, including gate slot (1), it is characterised in that:Also include being arranged on the locking platform on gate slot (1) top (2) the headstock gear mounting platform (3), being arranged on above locking platform (2), on headstock gear mounting platform (3) keying is provided with Machine (4), in the gate slot (1) gate flap moving up and down (5) is provided with;Also include pull bar (6), the pull bar (6) has two Root, and two pull bars (6), along the width interval setting of gate flap (5), the lower end of pull bar (6) is connected with gate flap (5), pull bar (6) upper end is connected with the suspension centre (7) on the headstock gear (4) of top;Also include locking beam (8), locking beam (8) is crossed on The gate slot (1) top, and lock beam (8) and can movably ride in locking platform (2) along the width of gate slot (1);With Every pull bar (6) is corresponding to be provided with two lockings beam (8), and two lockings beam (8) positioned at the both sides of the pull bar (6); The first connecting plate (9) is respectively arranged with the downside of two lockings beam (8) between two pull bars (6), in gate flap (5) Upper end is provided with the second connecting plate (10);First connecting plate (9) matches with corresponding second connecting plate (10), and can pass through Connecting bolt (11) connects the first connecting plate (9) with corresponding second connecting plate (10).
2. double lifting point pull bar gate as claimed in claim 1, it is characterised in that:Two between positioned at two pull bars (6) On the downside of locking beam (8) two piece of first connecting plate (9), and two piece of first connecting plate (9) are respectively arranged with along gate slot (1) Thickness direction interval setting;It is corresponding with two piece of first connecting plate (9) in each locking beam (8) in the upper end of gate flap (5) It is provided with two piece of second connecting plate (10).
3. double lifting point pull bar gate as claimed in claim 1, it is characterised in that:It is additionally provided with gate flap (5) upper end convex The positive stop (12) for rising, the positive stop (12) has two, and two positive stops (12) are along the width side of gate flap (5) To interval setting;Two between two pull bars (6) lockings beam (8) can be moved to simultaneously two positive stops (12) it Between.
4. double lifting point pull bar gate as claimed in claim 1, it is characterised in that:Gate slot (1) is located in locking platform (2) thick The both sides in degree direction are respectively arranged with slide rail (13), and the slide rail (13) be arranged in parallel along the width of gate slot (1);At each The two ends of locking beam (8) are respectively arranged with movable pulley (14), and the movable pulley (14) coordinates with the slide rail (13) of respective side.
5. the double lifting point pull bar gate as described in any one in Claims 1-4, it is characterised in that:The pull bar (6) is by more Section connecting rod (15) is detachably connected successively to be formed, and on every section connecting rod (15) locking limiting card (16) is provided with.
CN201621216479.3U 2016-11-11 2016-11-11 Two hoisting point pull rod gates Withdrawn - After Issue CN206157676U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621216479.3U CN206157676U (en) 2016-11-11 2016-11-11 Two hoisting point pull rod gates

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621216479.3U CN206157676U (en) 2016-11-11 2016-11-11 Two hoisting point pull rod gates

Publications (1)

Publication Number Publication Date
CN206157676U true CN206157676U (en) 2017-05-10

Family

ID=58658151

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621216479.3U Withdrawn - After Issue CN206157676U (en) 2016-11-11 2016-11-11 Two hoisting point pull rod gates

Country Status (1)

Country Link
CN (1) CN206157676U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638493A (en) * 2016-11-11 2017-05-10 中国电建集团成都勘测设计研究院有限公司 Double-hanging-point pulling-rod gate
CN110258465A (en) * 2019-06-26 2019-09-20 中国电建集团成都勘测设计研究院有限公司 Plane gate system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638493A (en) * 2016-11-11 2017-05-10 中国电建集团成都勘测设计研究院有限公司 Double-hanging-point pulling-rod gate
CN106638493B (en) * 2016-11-11 2018-09-18 中国电建集团成都勘测设计研究院有限公司 Double lifting point pull rod gate
CN110258465A (en) * 2019-06-26 2019-09-20 中国电建集团成都勘测设计研究院有限公司 Plane gate system

Similar Documents

Publication Publication Date Title
CN206157676U (en) Two hoisting point pull rod gates
CN112095493B (en) Pushing device of self-correcting guy rope hanging basket for bridge construction
CN204663081U (en) A kind of overhead system three-dimensional parking device
CN106638493B (en) Double lifting point pull rod gate
WO2019019855A1 (en) Single-drive, twin-chain transmission four-pillar elevator
CN210943719U (en) PC component board tipping arrangement
CN107089602A (en) The double gantries for setting loop wheel machine running of twin beams
CN209853572U (en) Boiler installation overhead hoist
CN108726358B (en) Batch hoisting device and method for main reinforcement of high-rise concrete structure
CN208843671U (en) A kind of novel wind power tower transloading equipment
CN207435918U (en) Box girder hoisting platform and girder lifting machine adopting same
CN110344334A (en) Steel reinforced concrete combined bridge construction method is done using two bridgings of dorsal funciculus formula Bridge Erector
CN215755931U (en) Large transformer hoisting equipment in factory building
CN205702718U (en) A kind of cage guide chamfer processing method and device
CN115140667A (en) Automatic device for hoisting in limited space tensioning operation
CN108421908A (en) A kind of automation equipment based on fine machine more mold exchange automatically
CN208072222U (en) Outward moving dismounting device for bridge high pier climbing mould crank arm beam
CN201817207U (en) Hoisting device for oil cylinder of automatic thickness control device of medium plate rolling mill
CN203878956U (en) Automatic lifting protection screen and construction platform combined system
CN205634553U (en) Rail mounted lift platform
CN111074319A (en) Aluminum profile oxidation treatment line
CN2751031Y (en) Horizontal quenching device for superlong axes parts
CN216178512U (en) Positioner is used in rocking arm production and processing
CN205934959U (en) Punching production line multilayer combo boxes puts up basis
CN109047850A (en) Girder steel clamping fixture for drilling

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20170510

Effective date of abandoning: 20180918

AV01 Patent right actively abandoned