CN206111181U - Freeze novel steel sheet wall of a well structure of well - Google Patents

Freeze novel steel sheet wall of a well structure of well Download PDF

Info

Publication number
CN206111181U
CN206111181U CN201620846100.0U CN201620846100U CN206111181U CN 206111181 U CN206111181 U CN 206111181U CN 201620846100 U CN201620846100 U CN 201620846100U CN 206111181 U CN206111181 U CN 206111181U
Authority
CN
China
Prior art keywords
steel plate
high strength
wall structure
shaft wall
structure according
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620846100.0U
Other languages
Chinese (zh)
Inventor
秦勇
程桦
闫红新
王勇
汪春芹
姚直书
石昌盛
***
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HEFEI DESIGN RESEARCH INSTITUTE FOR COAL INDUSTRY
Anhui University of Science and Technology
Original Assignee
HEFEI DESIGN RESEARCH INSTITUTE FOR COAL INDUSTRY
Anhui University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HEFEI DESIGN RESEARCH INSTITUTE FOR COAL INDUSTRY, Anhui University of Science and Technology filed Critical HEFEI DESIGN RESEARCH INSTITUTE FOR COAL INDUSTRY
Priority to CN201620846100.0U priority Critical patent/CN206111181U/en
Application granted granted Critical
Publication of CN206111181U publication Critical patent/CN206111181U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a freeze novel steel sheet wall of a well structure of well, include: wall of a well inboard is located to the plastic slab, the reinforcing bar net is located the plastic slab is inboard, a steel sheet section of thick bamboo and pit shaft axis parallel arrangement to it puts to be located pit shaft central point, the concrete, pour in between plastic slab, the steel sheet section of thick bamboo. The utility model discloses can the wide application in all kinds of mine construction, composite shaft lining can not only construct and bears great water and soil pressure, can reduce wall of a well thickness, shaft excavation section and the volume of freezing the engineering etc. Moreover to reduce the total cost of mine construction.

Description

Freezing wells with high strength RC new steel plate shaft wall structure
Technical field
This utility model is related to mine support construction applications, and more specifically, this utility model is related to one kind and presses with being used for Big freeze-wellboring pit shaft borehole wall supporting construction (freezing wells with high strength RC new steel plate shaft wall structure).
Background technology
Pit shaft is the throat of mine, is mine construction the features such as with service year limit for length because of the particularity of its position Construction Difficulties.According to statistics, the shaft lining breakage example of construction freezing method is of common occurrence, and pit shaft is successive in construction and production process Generation freeze section borehole wall Support structure damage, or even individually pit shaft causes to flood the major accidents such as well.It is embodied in freeze section well There is in various degree the phenomenons such as cracking, fracture, breakage in wall construction, keep in repair multiple repeatedly, and to mine huge economic damage is caused Lose, and seriously threaten the safety in production of mine.
With the increase of mining depth, pit shaft is more and more deeper, and ground pressure is increasing, if shaft wall structure is propped up using traditional Protection structure form, calculates according to the code requirement borehole wall by 1.0 hydrostatic pressings are born, and thickness of shaft wall is too thick, the deep-well borehole wall of major diameter Thickness is even more than 3m, and not only increase is freezed, block difficulty dug, while also increasing investment cost.
The content of the invention
The purpose of this utility model is to provide a kind of freezing wells with high strength RC new steel plate shaft wall structure, with the depth for solving presently, there are Items problem caused by well thickness of shaft wall is larger.
To achieve these goals, this utility model provides technical scheme below:
A kind of freezing wells with high strength RC new steel plate shaft wall structure, it includes:Plastic plate, located at borehole wall inner side;Bar-mat reinforcement, located at described Plastic plate inner side;Steel plate cylinder, and the setting of pit shaft diameter parallel, and positioned at wellbore centre position;Concrete, pours in the plastics Between plate, steel plate cylinder.
Preferably, in above-mentioned freezing wells with high strength RC new steel plate shaft wall structure, the steel plate barrel thickness be 10mm, 16mm, 20mm, 25mm or 35mm.
Preferably, in above-mentioned freezing wells with high strength RC new steel plate shaft wall structure, the steel plate cylinder welded by each circular arc steel plate and Into the circular arc steel plate outside is welded with anchor clamp, and the anchor clamp is by the band steel that specification is wide by 80 × long 800mm × thickness 20mm Bending machining is formed.
Preferably, in above-mentioned freezing wells with high strength RC new steel plate shaft wall structure, the plastic plate is double-deck polyethylene panel.
Preferably, in above-mentioned freezing wells with high strength RC new steel plate shaft wall structure structure, the bar-mat reinforcement includes the ring muscle being arranged circumferentially With longitudinally disposed vertical muscle.
Preferably, in above-mentioned freezing wells with high strength RC new steel plate shaft wall structure, a diameter of 22~32mm of the ring muscle, the vertical muscle A diameter of 20~28mm, the adjacent ring muscle spacing and the adjacent longitudinal bar spacing is 200~300mm.
Preferably, in above-mentioned freezing wells with high strength RC new steel plate shaft wall structure, the strength grade of concrete adopts C80~C90.
Preferably, in above-mentioned freezing wells with high strength RC new steel plate shaft wall structure, the steel plate cylinder is provided with multiple-anticorrosion coating.
Preferably, in above-mentioned freezing wells with high strength RC new steel plate shaft wall structure, the multiple-anticorrosion coating includes:The steel plate cylinder Surface reaches Sa2.5 levels using blasting treatment;Subbing adopts epoxy zinc rich primer;Intermediate layer coating is using in epoxy micaceous iron Between paint;Investment precoat adopts epoxy finish.
Preferably, in above-mentioned freezing wells with high strength RC new steel plate shaft wall structure, in the multiple-anticorrosion coating, subbing is applied Thickness degree is 60 μm;Intermediate layer coating coating layer thickness is 60 μm;Investment precoat coating layer thickness is 80 μm.
Analysis understands that this utility model provides a kind of steel plate cylinder and concrete composite shaft lining structure, and in the borehole wall specification is met Hydraulic pressure is calculated while require, moreover it is possible to the significantly thickness of the thinning borehole wall, reduce difficulty of construction, improve speed of application, saved Great amount of investment, therefore, the composite shaft lining that steel plate cylinder is constituted with armored concrete (steel fiber reinforced concrete) is to huge thick alluvium And highland pressure freezing shaft wall structure design has promotional value with application aspect.
Description of the drawings
The cross-sectional structure schematic diagram of the supporting construction embodiment that Fig. 1 is provided for this utility model;
Fig. 2 is the cross section structure diagram of A-A along the line in Fig. 1;
Fig. 3 is the cross section structure diagram of B-B along the line in Fig. 1;
Fig. 4 is the structural representation after plane steel plate welding anchor clamp;
Fig. 5 is the structural representation of anchor clamp.
Specific embodiment
This utility model is described in further details with reference to the accompanying drawings and detailed description.
In order to solve a supporting difficult problem for the current pit shaft borehole wall, as shown in Figure 1 and Figure 2, pit shaft is adopted in the inner side of the borehole wall 1 Composite support form, the wherein borehole wall 1 are the former borehole wall, and it includes concrete 11, the steel plate 12 on the outside of concrete 11, in short It:In the inner side of the borehole wall 1, using circular arc steel plate 2, the outside of circular arc steel plate 2 welding anchor clamp 3, and cast-in-place mixed armored concrete Or the composite support form of steel fiber reinforced concrete (being referred to as concrete 6).
It is new to this practicality below in conjunction with the supporting construction shown in Fig. 1-Fig. 3 in order to understand and not producing the sense for repeating The freeze-wellboring pit shaft borehole wall supporting construction that type is provided is described simultaneously with construction method, and not independent description supporting knot Structure or construction method.
As shown in Figure 1-Figure 3, the construction method that this utility model is provided is comprised the following steps:
First, plane steel plate is made into steel plate in the arc-shaped 2 on ground, and spilled water hole 20 is reserved on circular arc steel plate 2; Again the anchor clamp 3 as shown in Figure 5 for processing is welded on into the outside of circular arc steel plate 2 (side of the borehole wall 1), as Figure 1-Figure 4.
The thickness of above-mentioned plane steel plate circular arc steel plate 2 in other words has as needed a multiple choices, such as 10mm, 16mm, 20mm、25mm、35mm.The height of every block of circular arc steel plate 2 may be selected to be 500~2000mm, length, and for 3~5m, (bending is circle Before curved plate).
Preferably, this utility model is made at anti-corrosion also before the processing of circular arc steel plate 2 or before being transported into down-hole to it Reason.For example, Sa2.5 levels are reached using blasting treatment to surface of steel plate, is then painted, wherein, subbing adopts epoxy zinc-rich Priming paint, coating layer thickness is 60 μm;Intermediate layer coating adopts epoxy micaceous iron intermediate coat, and coating layer thickness is 60 μm;Investment precoat is adopted Epoxy finish, 80 μm of coating layer thickness.It is highly preferred that weld seam between circular arc steel plate 2 and anchor clamp 3 and in each circular arc in down-hole Weld seam between steel plate 2 is also adopted by the multiple-anticorrosion coating system.
As shown in figure 5, band steel bending machining of the anchor clamp 3 by specification for width 80mm × long 800mm × thickness 20mm is formed, bow Depending on sight, anchor clamp 3 takes the shape of the letter U.Certainly, the specification of anchor clamp 3 is not limited thereto, in fact, the effect of anchor clamp 3 is:Make coagulation Is formed effectively integrally between soil 6 and the steel plate cylinder that is welded into by circular arc steel plate 2, it is seen then that the shape of anchor clamp 3, specification have no Limit, meet the similar effect of " anchor pole or anchor cable " in Geotechnical Engineering.
Then, in the inner side of the borehole wall 1, it is preferred that be close to the inner side of the borehole wall 1, lay at least one of which plastic plate 5, and in plastics The inner side assembling reinforcement net of plate 5.
Preferably, plastic plate 5 is the bilayer of stacking, and plastic plate 5 is polyethylene panel.The reinforcing bar of the inner side of plastic plate 5 Net includes ring muscle 41, vertical muscle 42, wherein, ring muscle 41 is indulged muscle 42 and is adopted 20~28mm of diameter using the reinforcing bar of 22~32mm of diameter Reinforcing bar, spacing is 200~300mm between adjacent ring muscle 41 or adjacent vertical muscle 42, and intersecting ring muscle 41, vertical muscle 42 are then tied up Bundle is integrated.
Then, the circular arc steel plate 2 for being welded anchor clamp 3 is transported to into down-hole, assembly, centering, are then welded as in down-hole Steel plate cylinder.
Preferably, the splicing gap of the vertical and ring of each circular arc steel plate 2 adopts solder design, and weld seam is using machinery Automatic welding, further, vertical weldquality is two grades.To improve speed of welding, can be using electro-gas (enclosed) welding and carbon dioxide Gas shielded arc welding technique.The parallel operations between vertical position welding and horizontal position welding can be realized, the speed of welding of steel plate is greatly speeded up.
Each circular arc steel plate 2 is welded as after steel plate cylinder, and due to the effect of steel plate cylinder, in application process, it can change Become the stress of concrete 6, improve the overall intensity of the borehole wall.
After steel plate cylinder has been welded, between the outside of circular arc steel plate 2 and the inner side of the borehole wall 1, segmentation one-piece casting high intensity is high Performance concrete 6.
That is, above-mentioned welding steel cylinder is also segmentation carrying out, not the steel plate cylinder in the inner side of the borehole wall 1 is all welded After the completion of, in casting concrete 6, but steel plate cylinder completes one section, and concrete 6 pours one section, section construction.
Preferably, each section of a height of 500mm~1240mm, the strength grade of concrete 6 adopts C80~C90, segment section height to pour Build steel fiber reinforced concrete.Wherein, steel fiber reinforced concrete is to add appropriate steel fibre in armored concrete, can be had Effect improves the tensile property of concrete 6, the overall safety for improving supporting construction.
In work progress, because the strength grade requirement to concrete 6 is higher, need special messenger to prepare, thing is done before pouring Reason performance test, then recirculation next one section is high.
As shown in Fig. 2 circular arc steel plate 2 and the reserved 4 contour, Grouting Pipe 7 that ring is uniform in concrete 6, along The longitudinal direction of pit shaft, the spacing of Grouting Pipe 7 is not more than 30m.The effect of Grouting Pipe 7 is in 1 set of appropriate time built after terminating of the borehole wall Carry out wall clearance grouting.Therefore, circular arc steel plate 2 reserve at Grouting Pipe 7 position a through hole arranging, when Grouting Pipe 7 is laid with Circular arc steel plate 2 is welded.
Preferably, after the completion of slip casting, for mortar leakage prevention, one pipe plug 71 is set in the outer end termination of Grouting Pipe 7.Enter one Step ground, material selection Φ 60X7 seamless steel pipes (YB231-70) of Grouting Pipe 7, the long 100mm of screw thread of pipe plug 71.
To sum up, this utility model provides one kind in freeze-wellboring shaft construction, and the borehole wall is using steel plate cylinder and cast-in-place steel Reinforced concrete composite shaft lining or steel plate cylinder and steel fiber reinforced concrete composite shaft lining structural support form.Work progress includes: Be welded with the circular arc steel plate cylinder of anchor clamp not only as the borehole wall bearing structure but also as concrete-pouring template, the circle circular arc of the borehole wall one After steel plate is to connecting, circular arc steel plate ring and vertical abutment joint are welded, steel plate cylinder is formed, then to circular arc steel plate cylinder The cast-in-place high intensity in outside, high performance steel or steel fiber reinforced concrete, complete the high steel plate docking of section, welding and a coagulation After soil is poured, then carry out the high construction of next section.
Analysis and field test show that this utility model can be widely applied in all kinds of mine constructions, and composite shaft lining is not It is only capable of structure and bears larger Water And Earth Pressures, and thickness of shaft wall, shaft excavation section and freezing engineering amount etc. can be reduced, so as to drops Low mine construction total cost.
As known by the technical knowledge, this utility model can be by other essence without departing from its spirit or the reality of essential feature Apply scheme to realize.Therefore, embodiment disclosed above, for each side, is all merely illustrative, and is not only 's.It is all in the range of this utility model or in the change being equal in the range of this utility model by this utility model bag Contain.

Claims (10)

1. a kind of freezing wells with high strength RC new steel plate shaft wall structure, it is characterised in that include:
Plastic plate, located at borehole wall inner side;
Bar-mat reinforcement, located at plastic plate inner side;
Steel plate cylinder, and the setting of pit shaft diameter parallel, and positioned at wellbore centre position;
Concrete, pours between the plastic plate, steel plate cylinder.
2. freezing wells with high strength RC new steel plate shaft wall structure according to claim 1, it is characterised in that the steel plate barrel thickness is 10mm, 16mm, 20mm, 25mm or 35mm.
3. freezing wells with high strength RC new steel plate shaft wall structure according to claim 1, it is characterised in that the steel plate cylinder is by each circular arc Shape steel plate is welded, and the circular arc steel plate outside is welded with anchor clamp, and the anchor clamp is wide by 80 × long 800mm × thickness by specification The band steel bending machining of degree 20mm is formed.
4. freezing wells with high strength RC new steel plate shaft wall structure according to claim 1, it is characterised in that the plastic plate is double-deck Polyethylene panel.
5. freezing wells with high strength RC new steel plate shaft wall structure according to claim 1, it is characterised in that the bar-mat reinforcement includes ring The ring muscle of setting and longitudinally disposed vertical muscle.
6. freezing wells with high strength RC new steel plate shaft wall structure according to claim 5, it is characterised in that the ring muscle is a diameter of 22~ 32mm, a diameter of 20~28mm of the vertical muscle, the adjacent ring muscle spacing and the adjacent longitudinal bar spacing be 200~ 300mm。
7. freezing wells with high strength RC new steel plate shaft wall structure according to claim 1, it is characterised in that the strength grade of concrete Using C80~C90.
8. freezing wells with high strength RC new steel plate shaft wall structure according to claim 1, it is characterised in that the steel plate cylinder is provided with many Anticorrosion coat.
9. freezing wells with high strength RC new steel plate shaft wall structure according to claim 8, it is characterised in that the multiple-anticorrosion coating bag Include:The steel plate cylinder surface reaches Sa2.5 levels using blasting treatment;Subbing adopts epoxy zinc rich primer;Intermediate layer coating Using epoxy micaceous iron intermediate coat;Investment precoat adopts epoxy finish.
10. freezing wells with high strength RC new steel plate shaft wall structure according to claim 9, it is characterised in that apply in the multiple-anticorrosion In layer, subbing coating layer thickness is 60 μm;Intermediate layer coating coating layer thickness is 60 μm;Investment precoat coating layer thickness is 80 μm.
CN201620846100.0U 2016-08-05 2016-08-05 Freeze novel steel sheet wall of a well structure of well Expired - Fee Related CN206111181U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620846100.0U CN206111181U (en) 2016-08-05 2016-08-05 Freeze novel steel sheet wall of a well structure of well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620846100.0U CN206111181U (en) 2016-08-05 2016-08-05 Freeze novel steel sheet wall of a well structure of well

Publications (1)

Publication Number Publication Date
CN206111181U true CN206111181U (en) 2017-04-19

Family

ID=58512270

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620846100.0U Expired - Fee Related CN206111181U (en) 2016-08-05 2016-08-05 Freeze novel steel sheet wall of a well structure of well

Country Status (1)

Country Link
CN (1) CN206111181U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106121658A (en) * 2016-08-05 2016-11-16 煤炭工业合肥设计研究院 Freeze-wellboring pit shaft borehole wall supporting construction and construction method thereof
CN108412499A (en) * 2018-03-11 2018-08-17 吕琳 A kind of vertical reparation shaft wall structure
CN108775241A (en) * 2018-05-23 2018-11-09 北京中煤矿山工程有限公司 Enable to slurries equally distributed filling process between freezing shaft inside and outside wall
CN109723087A (en) * 2018-12-26 2019-05-07 中国矿业大学 A kind of double-layer wall of well and construction technique of outer wall assembly steel member

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106121658A (en) * 2016-08-05 2016-11-16 煤炭工业合肥设计研究院 Freeze-wellboring pit shaft borehole wall supporting construction and construction method thereof
CN106121658B (en) * 2016-08-05 2020-03-27 煤炭工业合肥设计研究院 Freezing method sinking shaft well wall supporting structure and construction method thereof
CN108412499A (en) * 2018-03-11 2018-08-17 吕琳 A kind of vertical reparation shaft wall structure
CN108775241A (en) * 2018-05-23 2018-11-09 北京中煤矿山工程有限公司 Enable to slurries equally distributed filling process between freezing shaft inside and outside wall
CN109723087A (en) * 2018-12-26 2019-05-07 中国矿业大学 A kind of double-layer wall of well and construction technique of outer wall assembly steel member

Similar Documents

Publication Publication Date Title
CN206111181U (en) Freeze novel steel sheet wall of a well structure of well
CN104533446B (en) Construction method and its structure that a kind of big cross section Support System in Soft Rock Tunnels bilayer pre- Geological disaster prevention of preliminary bracing occurs
CN106090450B (en) The box pipeline connected with circumferential obtuse angle
CN106121658A (en) Freeze-wellboring pit shaft borehole wall supporting construction and construction method thereof
CN106351670B (en) A kind of closed pre support tunnel structure
CN102734556B (en) Trenchless construction method for power pipes
CN103410161B (en) Oblique control slip casting steel anchor tube framework and construction method thereof
CN203669880U (en) Assembly type tunnel lining segment
CN103643966A (en) Prefabricated tunnel lining segment
CN105386443A (en) FRP pipe and thick-wall steel pipe compounding hollow recycled concrete pile
CN104295814A (en) Underground steel mixed structure pipeline with spiral composite reinforcing rings on inner wall and production method thereof
CN206035500U (en) Adopt prestressing steel's section of jurisdiction connecting device
CN105297708A (en) Compound recycled concrete pile of carbon fibers and steel tube
CN105200983A (en) PVC pipe and thick wall steel tube composite hollow recycled concrete pile
CN105862990A (en) Prefabricated assembly well wall structure and construction method thereof
CN108104121A (en) For improving the structure and method of pressure anchor wire cement grout body compression strength
CN206346737U (en) A kind of supporting major diameter curve pipe curtain
CN101899831B (en) Active variable-stiffness leveling pile and construction method thereof
CN105605335A (en) Large-caliber prestressed steel cylinder concrete pipe for jacking construction
CN210917394U (en) Foundation pit support pile
CN107060778A (en) Pass through high-rise building group back filled region method for tunnel construction
CN206626283U (en) A kind of new concrete push pipe
CN105133646A (en) Underground steel and concrete structure pipeline and manufacturing method thereof
CN110924990A (en) Advanced supporting structure assembled by corrugated steel pipe sheets and supporting method
CN208105923U (en) A kind of existing pond increases the connecting joint structure of water string

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170419

Termination date: 20190805

CF01 Termination of patent right due to non-payment of annual fee