CN205977150U - Punching cable logging carries technology tubular column in horizontal well coiled tubing - Google Patents

Punching cable logging carries technology tubular column in horizontal well coiled tubing Download PDF

Info

Publication number
CN205977150U
CN205977150U CN201620985574.3U CN201620985574U CN205977150U CN 205977150 U CN205977150 U CN 205977150U CN 201620985574 U CN201620985574 U CN 201620985574U CN 205977150 U CN205977150 U CN 205977150U
Authority
CN
China
Prior art keywords
coiled tubing
short circuit
logging
horizontal well
punching
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620985574.3U
Other languages
Chinese (zh)
Inventor
刘华臣
宋立成
张兰江
夏竹君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Tongsheng Petroleum Technology Co Ltd
Original Assignee
Tianjin Tongsheng Petroleum Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Tongsheng Petroleum Technology Co Ltd filed Critical Tianjin Tongsheng Petroleum Technology Co Ltd
Priority to CN201620985574.3U priority Critical patent/CN205977150U/en
Application granted granted Critical
Publication of CN205977150U publication Critical patent/CN205977150U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • A Measuring Device Byusing Mechanical Method (AREA)

Abstract

The utility model discloses a punching cable logging carries technology tubular column in horizontal well coiled tubing, from the top down comprises coiled tubing (1), logging cable (2), test blanking plug (3), one -way joint (4), rotatory short circuit (5), flexible short circuit (6), tension short circuit (7), release short circuit (8) and production logging instrument cluster (9). The utility model discloses a go into the operation under the punching cable logging operating tool string in the horizontal well coiled tubing of oil and natural gas engineering in, can make the production logging instrument cluster of operating tool string tubular column foot can go into the target zone smoothly down, carry out normal horizontal well production logging operation to reach improved level well production logging efficiency, reduce horizontal well production logging accident rate's purpose.

Description

Punching wireline logging conveying process pipe string in horizontal well coiled tubing
Technical field
This utility model belongs to petroleum gas engineering field, specifically, is to be related to the well logging of horizontal well coiled tubing to survey Study industry and and downhole tool making field.
Background technology
The method of horizontal wellbore logging testing tool conveying mainly adopts down-hole electric traction device (crawl device) conveying method, oil pipe Conveying method, coiled tubing conveying method and Hydraulic transportation method etc..This several carrying method is every kind of have respective pluses and minuses it is adaptable to The horizontal well of different well logging purposes.
According to literature survey, in terms of net horizontal section logger conveying technology, be summed up can be divided into following several:
(1) oil pipe (drilling rod) conveying technology:Logger is transported to by drilling rod or oil pipe using rig or working rig Test purpose depth, and using mud circulation power, well cable butting instrument is combined with logger.This technology is current Conveying technology the most ripe, but may not apply to Production Logging in Horizontal Wells, and fragile production logging instrument.The method simultaneously Need rig or workover rig and drilling rod or oil pipe carry out logging operation, high cost, under enter slow, workload is big, labor intensity Height, the time is long, and efficiency is low.
(2) Hydraulic transportation technology:Using the motive force of water, logger is pushed into horizontal segment after High angle section is hampered End, due to being to be conveyed in sleeve pipe, construction operation is safe and reliable for Hydraulic transportation method.But this technology can only adopt Oil pipe logging method is it is impossible to measure the oil of horizontal interval, gas and water percentage ratio, and easily oil reservoir is polluted, and fed distance is short, It is not suitable for well logging with pressure.
(3) electric traction device (crawl device) conveying technology:Connect logger using crawl device, after High angle section is hampered Powered to crawl device by ground system, logger is transported to by interval of interest by crawl device.The method is subject to instruments weight Impact, crawl device maximum thrust in (200~300) kg, be not therefore suitable for open hole well, heavy oil wells, slim hole well well logging.With When the method not only power is low, and high cost, and there is certain risk.
(4) coiled tubing conveying technology:In advance cable (optical fiber) is penetrated in coiled tubing, logger is mounted directly In the lower end of coiled tubing, injection head promotes coiled tubing to be lowered in well, promotes logger to be lowered into measurement well section, to not With the logger wide adaptability of size, cased well, annular space, through tubing log operation can be carried out.
In above-mentioned several logger conveying technology, coiled tubing logging technique has other in horizontal well performance testing It is considered to be most rising production logging technology, its advantage is as follows for the incomparable advantage of logging method:
(1) in the conveying underground logging instrument instrument of horizontal well middle and long distance and short-range spiral twisted tube can be passed through Section;
(2) when logger is in down-hole, mud conditioning can be carried out by coiled tubing, assessment result on the spot;
(3) logging tool removes steadily, can achieve multiple logging speed follow-on tests;
(4) logging cable reliability is higher, and can replacing logging tool quickly and easily;
(5) with pressure or have operation in the case of liquor stream, and pressure can be maintained constant, reduce blowout dangerous.
Abroad, coiled tubing well logging becomes a kind of new horizontal wellbore logging Technology, but should in CHINESE REGION With less.At home, oil-water well dynamic monitoring production logging with pressure and coiled tubing are worn to the kit of cable, domestic Scientific research personnel then also need to further study.
Content of the invention
This utility model is directed to punching wireline logging conveying process pipe string in horizontal well coiled tubing, redesigns, and is protecting On the premise of card original function can be realized, improve stability and the suitability of conveying process pipe string, increased horizontal well The safety of punching cable production logging construction in coiled tubing, decreases punching wireline logging conveying in horizontal well coiled tubing The weak link of process pipe string, meets the construction requirement of punching wireline logging production logging in horizontal well coiled tubing, solves The problem being difficult to reach purpose pay interval is entered under horizontal well horizontal segment production logging instrument.
In order to solve above-mentioned technical problem, this utility model is achieved by following technical scheme:
Punching wireline logging conveying process pipe string in a kind of horizontal well coiled tubing, this process pipe string is from top to bottom by continuous Oil pipe, logging cable, test blanking plug, one-way joint, rotation short circuit, flexible short circuit, tension force short circuit, release short circuit and production are surveyed Well instrument string is constituted.
Wherein said logging cable is located inside coiled tubing, and logging cable afterbody is connected with test blanking plug top, surveys Examination blanking plug is connected with coiled tubing by shear pin, and material used by shear pin is No. 45 steel matter.
Described test blanking plug and can be locked in production work cylinder, coiled tubing of leaving moves up and down, in production test Can unlock easily after finishing, leave seating nipple, and be suggested ground together with coiled tubing.
Described one-way joint is located at the top of described rotation short circuit, makes the liquid in sleeve pipe can not enter into coiled tubing Interior, ground is suppressed in the liquid sleeve pipe that can make in coiled tubing, may be implemented in test function in particular cases.
Described rotation short circuit is located at the top of described flexibility short circuit, lays down produce due to the rotation of coiled tubing anti-twisted Square.Thus avoiding the rotation due to coiled tubing, leading to the quick rotation of logger string, causing production logging instrument described in bottom The damage of device string.
Described flexibility short circuit is connected to the top of described tension force short circuit, during coiled tubing conveying well measuring instrument. Can prevent from causing production logging instrument string described in bottom to meet card due to due to hole deviation;Improve in whole horizontal well coiled tubing Punching wireline logging convey process pipe string in sleeve pipe by property.
Described tension force short circuit is connected to the top of described release short circuit, ground real-time monitoring go into the well logger string with continuous Feed status in cased well for the oil pipe;When occur being hampered, meet card when remind drumman to stop decentralization coiled tubing in time, prevent Only coiled tubing damages logger string by pressure.
Described release short circuit is connected to the logger string top gone into the well, the surface power supply cut-out when logger string meets card The connection of coiled tubing and instrument, proposes coiled tubing, go into the well logger string stay convenient in well salvaging.
Described production logging instrument string can need to select logger to be combined accordingly according to production logging project, can With flexible configuration, it is selected to complete the subfunction production logging instrument module of production logging task, to meet logging tasks Need.
It is the 31.75mm (coiled tubing of 1.25 ") that described coiled tubing refers exclusively to external diameter.
In this utility model horizontal well coiled tubing punching wireline logging conveying process pipe string pass through by described coiled tubing, Described logging cable, described test blanking plug, described one-way joint, described rotation short circuit, described flexibility short circuit, described tension force are short Connect, described release short circuit and described production logging instrument string are attached according to shown in accompanying drawing, can make operating tool string tubing string The described production logging instrument string of bottom can smoothly under enter target zone, meet the requirement of Production Logging in Horizontal Wells project, thus Normal Production Logging in Horizontal Wells operation can be carried out, reach well production logging efficiency of improving the standard, reduce horizontal wellbore logging thing Therefore the purpose of incidence rate, and then sea, land horizontal well logging operation totle drilling cost can be reduced.
Brief description
Fig. 1 structural representation of the present utility model.
In figure:1:Coiled tubing, 2:Logging cable, 3:Test blanking plug, 4:One-way joint, 5:Rotation short circuit, 6:Flexible Short circuit, 7:Tension force short circuit, 8:Release short circuit, 9:Production logging instrument string.
Specific embodiment
As shown in figure 1, the utility model discloses in a kind of horizontal well coiled tubing being applied to petroleum gas engineering Punching wireline logging conveys process pipe string, and specific embodiment is in horizontal well horizontal completion section, if there are production logging item Purpose needs, and connects punching wireline logging conveying process pipe string tool combinations in horizontal well coiled tubing as follows:
Short by coiled tubing 1, logging cable 2, test blanking plug 3, one-way joint 4, rotation short circuit 5, flexibility from top to bottom Connect 6, tension force short circuit 7, release short circuit 8 and production logging instrument string 9 to constitute, wherein said logging cable 2 is located in coiled tubing 1 Portion, logging cable 2 afterbody is connected with test blanking plug 3 top, and test blanking plug 3 is connected with coiled tubing 1 by shear pin, Described one-way joint 4 is located at the top of described rotation short circuit 5, and described rotation short circuit 5 is located at the top of described flexibility short circuit 6, institute State the top that flexible short circuit 6 is connected to described tension force short circuit 7, described tension force short circuit 7 is connected to the top of described release short circuit 8, Described release short circuit 8 is connected to the logger string top gone into the well.
Described test blanking plug 3 is connected with described coiled tubing 1 by shear pin;Under enter during by instrument positioning Step judges whether it puts in place;Pushed by described coiled tubing 1, the closing piece entrance of described test blanking plug 3 is matching The expanding position of production work cylinder, is interacted with seating nipple and realizes locking;Described coiled tubing 1 continues to press to pin to be cut Cut design load, the pin that described test blanking plug 3 is connected with described coiled tubing 1 is sheared, described test blanking plug 3 with described Coiled tubing 1 separates, and now described test blanking plug 3 is locked at seating nipple, and described coiled tubing 1 can freely drag up and down Dynamic, carry out Production Logging in Horizontal Wells operation;The Production Logging in Horizontal Wells end of job, described coiled tubing 1 above carries to design load, institute State the safetied pin shearing of test blanking plug 3, closing piece reclaims, described test blanking plug 3 unlocks, and with described coiled tubing 1 one Rise and propose to ground.
During Specific construction, in horizontal well coiled tubing, the speed that removes of punching wireline logging conveying is maintained at 8-10m/min. Prevent the occurrence of block that be hampered, it is to avoid punching wireline logging conveying process pipe string in the horizontal well coiled tubing therefore bringing Damage or fracture.
Application of the present utility model, under can enabling the production logging instrument string of operating tool string tubing string foot smooth Enter target zone, meet the requirement of Production Logging in Horizontal Wells project, such that it is able to carry out normal Production Logging in Horizontal Wells operation, reach To well production logging working performance of improving the standard, reduce the purpose of Production Logging in Horizontal Wells work accident incidence rate, and then can Reduce sea, land Production Logging in Horizontal Wells operating assembly originally.
Although being described to preferred embodiment of the present utility model above in conjunction with accompanying drawing, this utility model is not It is confined to above-mentioned specific embodiment, above-mentioned specific embodiment is only schematically, is not restricted, ability The those of ordinary skill in domain under the enlightenment of the present invention, without departing from this utility model objective and scope of the claimed protection In the case of, the concrete conversion of a lot of forms can also be made, these belong within protection domain of the present utility model.

Claims (4)

1. in horizontal well coiled tubing punching wireline logging conveying process pipe string it is characterised in that from top to bottom by coiled tubing (1), logging cable (2), test blanking plug (3), one-way joint (4), rotation short circuit (5), flexible short circuit (6), tension force short circuit (7), release short circuit (8) and production logging instrument string (9) are constituted, and wherein said logging cable (2) is located in coiled tubing (1) Portion, logging cable (2) afterbody is connected with test blanking plug (3) top, and shear pin and coiled tubing are passed through in test blanking plug (3) (1) it is connected, described one-way joint (4) is located at the top of described rotation short circuit (5), described rotation short circuit (5) is located at described flexibility The top of short circuit (6), described flexibility short circuit (6) is connected to the top of described tension force short circuit (7), and described tension force short circuit (7) connects On the top of described release short circuit (8), described release short circuit (8) is connected to the logger string top gone into the well.
2. in horizontal well coiled tubing according to claim 1 punching wireline logging conveying process pipe string it is characterised in that Described coiled tubing (1) external diameter is 31.75mm.
3. in horizontal well coiled tubing according to claim 1 punching wireline logging conveying process pipe string it is characterised in that The material used by shear pin that described test blanking plug (3) is connected with described coiled tubing (1) is No. 45 steel matter.
4. in horizontal well coiled tubing according to claim 1 punching wireline logging conveying process pipe string it is characterised in that Described production logging instrument string (9) can be adjusted flexibly according to production logging project, is selected to complete production logging task Subfunction production logging instrument module.
CN201620985574.3U 2016-08-29 2016-08-29 Punching cable logging carries technology tubular column in horizontal well coiled tubing Expired - Fee Related CN205977150U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620985574.3U CN205977150U (en) 2016-08-29 2016-08-29 Punching cable logging carries technology tubular column in horizontal well coiled tubing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620985574.3U CN205977150U (en) 2016-08-29 2016-08-29 Punching cable logging carries technology tubular column in horizontal well coiled tubing

Publications (1)

Publication Number Publication Date
CN205977150U true CN205977150U (en) 2017-02-22

Family

ID=58041417

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620985574.3U Expired - Fee Related CN205977150U (en) 2016-08-29 2016-08-29 Punching cable logging carries technology tubular column in horizontal well coiled tubing

Country Status (1)

Country Link
CN (1) CN205977150U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112211614A (en) * 2020-11-18 2021-01-12 大庆科力远石油装备制造有限公司 Comprehensive tester for injection section
CN112360433A (en) * 2020-11-11 2021-02-12 中石化石油工程技术服务有限公司 Method for arranging monitoring optical fibers in horizontal well
CN114293973A (en) * 2021-12-31 2022-04-08 杰瑞能源服务有限公司 Logging tool string and manufacturing process thereof
CN115075782A (en) * 2021-03-10 2022-09-20 中国石油天然气股份有限公司 Depth correction method for oil pipe transmission perforation

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112360433A (en) * 2020-11-11 2021-02-12 中石化石油工程技术服务有限公司 Method for arranging monitoring optical fibers in horizontal well
CN112360433B (en) * 2020-11-11 2023-11-07 中石化石油工程技术服务有限公司 Method for arranging monitoring optical fiber in horizontal well
CN112211614A (en) * 2020-11-18 2021-01-12 大庆科力远石油装备制造有限公司 Comprehensive tester for injection section
CN115075782A (en) * 2021-03-10 2022-09-20 中国石油天然气股份有限公司 Depth correction method for oil pipe transmission perforation
CN115075782B (en) * 2021-03-10 2023-09-26 中国石油天然气股份有限公司 Depth correction method for oil pipe transmission perforation
CN114293973A (en) * 2021-12-31 2022-04-08 杰瑞能源服务有限公司 Logging tool string and manufacturing process thereof
CN114293973B (en) * 2021-12-31 2024-03-12 杰瑞能源服务有限公司 Logging tool string and manufacturing process thereof

Similar Documents

Publication Publication Date Title
CN205977150U (en) Punching cable logging carries technology tubular column in horizontal well coiled tubing
US9976407B2 (en) Logging tool and method of use
US7249629B2 (en) Multi-function well servicing vehicle
Tan et al. In situ investigations of failure zone of floor strata in mining close distance coal seams
US6179058B1 (en) Measuring method and system comprising a semi-rigid extension
MX2012004587A (en) Instrumented disconnecting tubular joint.
CN112097726B (en) Device and method for measuring expansion deformation of protected layer
CN201148847Y (en) Oil pipe elevator
CN103993879A (en) Boom-type roadheader mounted tunneling anchor-along drilling integrated drilling machine
CN104989272A (en) Upward inverse well drilling process
CN102691520A (en) Monitoring system for heading face
CN209927122U (en) Remote protected layer expansion deformation and top and bottom plate separation layer measuring device
CN105089629A (en) Horizontal well rod conveying well-logging method
CN205477590U (en) Hydraulic drive horizontal well test draw gear
CN207436950U (en) Coiled tubing crosses cable hydraulic releasing tool
CN102691521A (en) Installation method for driving working face monitoring system
US9719329B2 (en) Downhole tool string buoyancy apparatus
CN203248106U (en) Multi-purpose lifting and unfreezing pipe pulling device
RU2603322C1 (en) Method of downhole tools delivery to bottoms of drilled wells with complex profile, carrying out geophysical survey and complex for its implementation
Shi et al. The underground directional drilling technology and equipments for kilometer deep borehole with MWD in coalmine
US20130119207A1 (en) Cable tool safety support
CN212614674U (en) Shearing type horizontal directional drilling geological prospecting in-hole logging instrument protection device
CN205532653U (en) A demolish device for anchor rope
CN215894066U (en) Telescopic device for mine geological measurement
US20130146362A1 (en) Oil and Gas Enhancement System - Radial Drilling Method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Zhang Lanjiang

Inventor after: Xia Zhujun

Inventor before: Liu Huachen

Inventor before: Song Licheng

Inventor before: Zhang Lanjiang

Inventor before: Xia Zhujun

CU03 Correction of utility model patent gazette
CU03 Correction of utility model patent gazette

Correction item: Inventor

Correct: Liu Huachen|Song Licheng|Zhang Lanjiang|Xia Zhujun

False: Zhang Lanjiang|Xia Zhujun

Number: 22

Volume: 33

CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Zhang Lanjiang

Inventor after: Xia Zhujun

Inventor before: Liu Huachen

Inventor before: Song Licheng

Inventor before: Zhang Lanjiang

Inventor before: Xia Zhujun

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170222