CN205975707U - Glass fiber prestressed anchorage pole anchor structure, its loading device - Google Patents

Glass fiber prestressed anchorage pole anchor structure, its loading device Download PDF

Info

Publication number
CN205975707U
CN205975707U CN201621031415.6U CN201621031415U CN205975707U CN 205975707 U CN205975707 U CN 205975707U CN 201621031415 U CN201621031415 U CN 201621031415U CN 205975707 U CN205975707 U CN 205975707U
Authority
CN
China
Prior art keywords
cylindrical
type connector
anchor
anchor pole
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201621031415.6U
Other languages
Chinese (zh)
Inventor
赵时运
程涛
戴良军
陈刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Water Resources Development Co Ltd
Original Assignee
ANHUI CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ANHUI CONSTRUCTION ENGINEERING GROUP Co Ltd filed Critical ANHUI CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority to CN201621031415.6U priority Critical patent/CN205975707U/en
Application granted granted Critical
Publication of CN205975707U publication Critical patent/CN205975707U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a glass fiber prestressed anchorage pole anchor structure, its loading device, characterized by set up the cylinder connector, above that along fixed crooked reinforcing bar and the GFRP stock of setting up of circumference evenly distributed and interval, the bottom deepening of crooked reinforcing bar is provided with cylinder connector down in the pile body in the pile body, evenly fixed centre gripping is on cylinder connector down along the circumference for the body of rod of stock, and the outer periphery upper band of cylinder connector has the ascending barb of slope under, the utility model discloses a set up prestressing force load mechanism in the top of last cylinder connector, utilize prestressing force load mechanism to pass and do all can in last cylinder connector to implement the prestressing force loading to the GFRP stock. The utility model discloses can effectively avoid the GFRP stock to receive shear failure, guarantee the stock and be connected with the effective of base plate reinforcing bar, ensure that the bottom plate can obtain great resistance to plucking bearing capacity to guarantee anti -floating anchor rod's anchor and strut the effect.

Description

Glass fibre prestressed anchor anchor structure, its charger
Technical field
This utility model is related to the underground engineering technical field of civil engineering, relates in particular to a kind of glass fibre and in advance should The anchor rod anchored structure of power, its charger.
Background technology
With the exploitation of urban underground space, substantial amounts of building basis is embedded in the higher ground of level of ground water In, the attention of anti-floating problem causes engineering construction all the more person, compared to fall row's subsoil water, load the anti-floating skills such as ballast, anti-floating pile Art measure, anti-float anchor rod is due to having that ground adaptability is strong, dispersive stress, easy construction, the low advantage of cost, therefore in engineering On be widely applied.
Anti-float anchor rod of the prior art is mainly steel strand prestress anchor cable and fining twisted steel anchor pole.Due to prestressing force Anti-float anchor rod needs guiding through base plate in construction and is anchored at base plate top, straight joint easily and causes base surface infiltration phenomenon;And Steel anchor rod is perishable in underground environment, is also easy to produce larger creeping during tension, and these unfavorable factors all greatly limit steel anchor Application in underground engineering for the bar.
Fiberglass reinforced plastics Glass Fiber Reinforced Polymer abbreviation GFRP, is using multiply glass After fiber is glued with base materials such as poly- phthalein ammonia resin, polyvinyl resin or epoxy resin, through mould extruding, drawing moulding process The composite producing, contains 70%~80% glass fibre and 20%~30% resin, nominal diameter in composite 10mm~36mm.Glass fiber-reinforced polymer anchor pole has obtained certain application at present in mine, anti-float anchor rod, slope retaining.With steel Muscle anchor pole is compared, and the glass fibre anchor pole under equal conditions is applied to underground engineering and has tensile strength height, strong, the low pine of durability The advantages of relaxation.But its horizontal shear resistance is relatively poor, such as using produced horizontal when conventional brace anchoring and interlayer dislocation Shearing easily makes glass fiber-reinforced polymer anchor pole be subject to horizontal failure by shear;Greatly have impact on the anchoring support effect of anti-float anchor rod Really.Simultaneously because the anchor force between GFRP anchor pole and mortar and concrete is less, its anti-floating bearing capacity is limited, especially on China edge The Soft Soil Foundation Pit engineering in Haiti area.Therefore, seek to design a kind of glass fibre prestressed anchor and its charger, can obtain Obtain larger anti-pulling capacity, and reduce the shear stress that GFRP anchor pole is born, to China's soft clay area deep foundation anti-float anchor rod Design and construction have highly important society and economic implications.
Utility model content
This utility model is for avoiding the deficiency existing for above-mentioned prior art, providing a kind of glass fibre prestressed anchor Anchor structure, its charger, to avoid GFRP anchor pole to produce failure by shear it is ensured that the effectively connection of anchor pole and baseplate reinforcing bar, Guarantee that base plate is obtained in that larger anti-pulling capacity, thus ensureing the anchoring support effect of anti-float anchor rod.
This utility model is to solve technical problem to adopt the following technical scheme that:
The feature of this utility model glass fibre prestressed anchor anchor structure is:
Cylindrical-type connector in setting, be circumferentially uniformly distributed thereon and the inverted truncated cone-shaped through hole of interval setting three and Three cylindrical holes, described inverted truncated cone-shaped through hole refers to that its aperture is up big and down small;It is clamped with each truncated cone-shaped through hole Upper core body, and anchor pole is clamped by upper core body, in described cylindrical hole, sliding sleeve has moment reinforcement, and described anchor pole is GFRP anchor Bar;
It is provided with adjusting nut in the epimere of described moment reinforcement, the top end face of described adjusting nut is that above cylinder connects The bottom surface of device is locking end face, and described moment reinforcement sequentially passes through downwards lower locking nut, carries backing plate, modified asphalt layer and bottom Plate bed course, the bottom of moment reinforcement is embedded in pile body, and lower locking nut is with the upper surface that carries backing plate for locking end face;Described Modified asphalt layer is in bottom cushion, is located at and carries the bottom surface of backing plate, the closure being formed around moment reinforcement and anchor pole Waterproof layer;
It is provided with lower cylindrical-type connector in described pile body, described lower cylindrical-type connector is circumferentially evenly distributed with three Individual positive truncated cone-shaped through hole, described positive truncated cone-shaped through hole refers to that its aperture is up-small and down-big, is clamped with lower core in positive truncated cone-shaped through hole Body, the body of rod of described anchor pole is clamped in lower core body, is evenly distributed with inclination on the outer circumference surface of described lower cylindrical-type connector Agnail upwards.
The feature of this utility model glass fibre prestressed anchor anchor structure lies also in:
Described upper core body is a pair of intermediate plate of half slide structure, and its external shape epimere is and truncated cone-shaped in upper cylindrical-type connector Cone that through hole inner chamber matches, hypomere be convexedly stretch in cylindrical-type connector bottom surface with externally threaded cylinder, justifying Utilize its external screw thread that locking nut is set on cylinder, described locking nut is the bottom surface of above cylindrical-type connector is locking end face; There is cylindrical hole inside upper core body, through-hole wall has screw thread, clamp anchor pole using screw thread;
Described lower core body has the version contrary up and down with upper chip;Externally threaded cylinder is carried convex in lower core body Stretch in lower cylindrical-type connector top surface, and using the clamp nut locking on lower cylindrical-type connector top surface;Have inside lower core body Cylindrical hole, through-hole wall has screw thread, clamps anchor pole using screw thread.
The feature of this utility model glass fibre prestressed anchor anchor structure lies also in:Described lower cylindrical-type connector is on edge The axial direction of anchor pole has multiple tracks with the distance of 0.5m for arranged for interval, and described agnail is evenly distributed in three along lower cylindrical-type connector Root, with the horizontal 40 ° of angle, agnail is the Ribbed Bar of diameter 10cm to agnail, and length is 50cm.
The feature of this utility model glass fibre prestressed anchor anchor structure lies also in:Described moment reinforcement is embedded in stake Length in body is not less than 30cm.
Being structurally characterized in that of the charger of this utility model glass fibre prestressed anchor anchor structure:Circle on described The top setting prestressing force load maintainer of column connector, using described prestressing force load maintainer power transmission in upper cylindrical-type connector, leads to Cross described upper cylindrical-type connector and implement prestressing force loading to GFRP anchor pole.
The construction featuress of the charger of this utility model glass fibre prestressed anchor anchor structure lie also in:Described pre- Stress loading mechanism is supported loading plate above upper cylindrical-type connector by reaction frame, installs punching thousand on upper loading plate Jin top, load bar is fixedly connected with upper cylindrical-type connector, passes through load bar power transmission in upper by the loading force that punching jack provides Cylindrical-type connector, and implement prestressing force loading to GFRP anchor pole;Described reaction frame is fixed with annular base, described annular bottom Seat is placed on bottom cushion, is in the periphery of GFRP anchor pole.
Compared with the prior art, this utility model has the beneficial effect that:
1st, this utility model passes through bottom cushion using moment reinforcement and is embedded in pile body, greatly reduces interlayer dislocation Shearing force suffered by caused GFRP anchor pole, substantially increases dependability.
2nd, this utility model is connected with anchor pole by cylinder shape connector, can make being subject to of GFRP anchor pole applying prestressing force Power uniformity, it is to avoid anchor pole produces because of excessive shear stress to destroy and larger draws the power of dialling it is ensured that obtaining.
3rd, in this utility model, GFRP anchor pole is provided by the cohesion between lower cylindrical-type connector, agnail, anchor pole and pile body Counteracting force, so that it is guaranteed that base plate obtain larger draw the power of dialling, improve the anchoring effect of anti-float anchor rod,
4th, this utility model is after loading is complete, is connected it is ensured that anchor pole and base plate with baseplate reinforcing bar using moment reinforcement Connection between reinforcing bar, it is to avoid traditional prestressed anchor is because base plate easily straight joint thus causing base plate sweat phenomenon.
5th, in this utility model in addition to consolidating between agnail and lower cylindrical-type connector, it is screw thread between other components even Connect, its easy accessibility, the charger including upper connecting rod, upper loading plate and counter-force bar etc. can Reusability, be conducive to control Construction cost processed, shortens the construction period.
6th, glass fiber-reinforced polymer anchor pole is replaced traditional steel strand anchor rod by this utility model, solves traditional reinforcing bar corrosion resistance Difference, stress are crept larger shortcoming, have given full play to the high characteristic of glass fiber-reinforced polymer tensile strength, thus ensure that anti-float anchor rod Accurate prestressing force can be provided, be that GFRP muscle large-scale application provides technical guarantee in underground engineering.
Brief description
Fig. 1 is glass fibre prestressed anchor and its charger structural representation in this utility model;
Fig. 2 is anchor rod anchored structural representation in this utility model;
Fig. 3 is anchor pole and charger main structure diagram in this utility model;
Fig. 4 is A-A view in Fig. 3;
Fig. 5 is B-B view in Fig. 3;
Fig. 6 is C-C view in Fig. 3;
Fig. 7 is D-D view in Fig. 3;
Fig. 8 is E-E view in Fig. 3.
In figure label:1 pile body, 2 anchor poles, 3 times core bodys, 4 times cylindrical-type connectors, 5 agnails, 6 clamp nuts, 7 batholith layers, 8 Bottom cushion, 9 moment reinforcements, 10 carrying backing plates, 11 lower locking nuts, 12 adjusting nuts, 13 modified asphalt layer, 14 annular bottoms Seat, 15 locking nuts, cylindrical-type connector on 16, core body on 17,18 load bars, 19 reaction frames, loading plate on 20,21 punchings are very heavy Top, 22 pads, 23 fixing nuts.
Specific embodiment
Referring to Fig. 1, Fig. 2 and Fig. 3, in the present embodiment, glass fibre prestressed anchor anchor structure is
Cylindrical-type connector 16 in setting, are circumferentially uniformly distributed and the inverted truncated cone-shaped through hole of interval setting three thereon With three cylindrical holes (as shown in Figure 5 and Figure 6), inverted truncated cone-shaped through hole refers to that its aperture is up big and down small;In each round platform It is clamped with core body 17 in shape through hole, and anchor pole 2 is clamped by upper core body 17, anchor pole 2 is prevented effectively from by pinch off with this;In cylinder In shape through hole, sliding sleeve has moment reinforcement 9 it is ensured that on moment reinforcement 9 is free in cylindrical hole when prestressing force loads Lower slider, anchor pole 2 is GFRP anchor pole.
It is provided with adjusting nut 12 in the epimere of moment reinforcement 9, the top end face of adjusting nut 12 is above cylindrical-type connector 16 bottom surface is locking end face it is ensured that anchor pole 2 will not produce contraction distortion because of the prestressing force loading;Moment reinforcement 9 downwards according to Secondary through lower locking nut 11, carry backing plate 10, modified asphalt layer 13 and bottom cushion 8;The bottom of moment reinforcement 9 is embedded in In pile body 1, it is to avoid the shearing force suffered by GFRP anchor pole caused by interlayer dislocation;Lower locking nut 11 is to carry the upper of backing plate 10 Surface is locking end face so that moment reinforcement 9 bears the prestressing force of loading together with carrying backing plate 10, without stress concentration And the bending of reinforcing bar occurs, the phenomenon such as moves down;Modified asphalt layer 13 be in bottom cushion 8, be located at carry backing plate 10 bottom surface, The closure waterproof layer being formed around moment reinforcement 9 and anchor pole 2, thus avoid subsoil water to pass through between anchor pole and bottom cushion Gap penetration is to backplane level.
It is provided with lower cylindrical-type connector 4 in pile body 1, lower cylindrical-type connector 4 is circumferentially being evenly distributed with three just Truncated cone-shaped through hole (as shown in Figure 8), positive truncated cone-shaped through hole refers to that its aperture is up-small and down-big, under being clamped with positive truncated cone-shaped through hole Core body 3, the body of rod of anchor pole 2 is clamped in lower core body 3, it is to avoid anchor pole 2 is by pinch off;Outer circumference surface in lower cylindrical-type connector 4 On be evenly distributed with the agnail 5 tilting upward so that lower cylindrical-type connector 4 can provide bigger loading counter-force.
As depicted in figs. 1 and 2, upper core body 17 is a pair of intermediate plate of half slide structure, and its external shape epimere is and upper cylinder Cone that in adapter 16, truncated cone-shaped through hole inner chamber matches, hypomere be convexedly stretch in cylindrical-type connector 16 bottom surface with outer The cylinder of screw thread, utilizes its external screw thread to arrange locking nut 15, locking nut 15 is above cylindrical-type connector on the cylinder 16 bottom surface is locking end face it is ensured that the firm connection of anchor pole 2 and upper cylindrical-type connector 16;There is cylinder inside upper core body 17 Through hole, through-hole wall has screw thread, clamps anchor pole 2 using screw thread.
Lower core body 3 has the version contrary about 17 with upper chip;Externally threaded cylinder is carried convex in lower core body 3 Stretch in lower cylindrical-type connector 16 top surface, and locked using the clamp nut 6 on lower cylindrical-type connector 16 top surface;Lower core body 3 There is cylindrical hole inside, and through-hole wall has screw thread, clamps anchor pole 2 using screw thread.
Lower cylindrical-type connector 4 has multiple tracks with the distance of 0.5m for arranged for interval in the axial direction along anchor pole 2, and agnail 5 is along lower circle Column connector 4 be evenly distributed in three, with the horizontal 40 ° of angle, agnail 5 is the Ribbed Bar of diameter 10cm to agnail 5, Length is 50cm;The length that moment reinforcement 9 is embedded in pile body 1 is not less than 30cm, it is to avoid GFRP anchor pole caused by interlayer dislocation Suffered shearing force.
The charger of glass fibre prestressed anchor anchor structure referring to Fig. 1 and Fig. 3, is set in the present embodiment, be The top setting prestressing force load maintainer of upper cylindrical-type connector 16, using prestressing force load maintainer power transmission in upper cylindrical-type connector 16, prestressing force is implemented to GFRP anchor pole 2 by upper cylindrical-type connector 16 and loads.
Prestressing force load maintainer supports loading plate 20 by reaction frame 19 above upper cylindrical-type connector 16, holds upper Punching jack 21 is installed on support plate 20, load bar 18 is fixed in punching jack 21 (such as by fixing nut 23 and pad 22 Shown in Fig. 4), the lower end of load bar 18 is fixedly connected (as shown in Figure 5) with upper cylindrical-type connector 16, can freely tear open between the two Unload, easy to operate;Load bar 18 power transmission is passed through in upper cylindrical-type connector 16 by the loading force that punching jack 21 provides, and to GFRP anchor pole 2 is implemented prestressing force and is loaded;Reaction frame 19 is fixing (as shown in Figure 7) with annular base 14, and annular base 14 is put Put on bottom cushion 8, be in the periphery of GFRP anchor pole 2, because bottom cushion is flatter and intensity is higher it can be ensured that loading Prestressing force vertically downward and stress relaxation phenomenon will not be produced.
In the present embodiment, the loading method of glass fibre prestressed anchor anchor structure charger is to enter as follows OK:
Step 1:By the lower cylindrical-type connector 4 with agnail 5 on the body of rod of anchor pole 2 in the axial direction with the interval of 0.5m Be uniformly distributed so that anchor pole 2 with the lower firm fixation of cylindrical-type connector 4 so that each lower cylindrical-type connector 4 can equably provide plus Carry counter-force.
Step 2:In batholith layer 7, pile body 1 is become using high pressure jet grouting, stake footpath is φ 50~φ 80cm, drilling rod is vertical Pore-forming, depth of pore forming is more than the design length 0.5m of anchor pole, it is to avoid anchor pole can not be buried and put in place;Do not solidify it in pile body cement Before, bury anchor pole in stake bottom in grouting pile-forming in the hole.
Step 3:After pile body thes cement solidifies, by the thickness earth excavation of bottom cushion, so that anchor pole epimere is exposed, clear up stake Head simultaneously lays moment reinforcement, pours bottom cushion concrete, when pouring it is ensured that moment reinforcement vertical, and with upper cylindrical-type connector circle Cylindricality through hole corresponds.
Step 4:When bottom cushion concrete strength reaches 70%, cut concrete bed course, filling-modified asphaltic sealing waterproof, curved Bent reinforcing bar upper sliding sleeve carries backing plate, with locking nut stationary curved reinforcing bar;Cylindrical-type connector in arrangement;By upper cylindrical-type connector with The firm fixation of anchor pole, and sliding sleeve is on moment reinforcement.
Step 5:Prestressed load maintainer, using prestressing force load maintainer to upper cylindrical-type connector and by upper circle Implement prestressing force to anchor pole 2 under the power transmission of column connector to load;When reaching the loading force of setting, using adjusting nut by upper circle Column connector is fixed with moment reinforcement.
Step 6:Remove prestressing force load maintainer, by colligation baseplate reinforcing bar after moment reinforcement tip flexion, and then complete bottom The pouring construction of board concrete, thus provide larger anchor force to base plate.

Claims (6)

1. a kind of glass fibre prestressed anchor anchor structure, is characterized in that:
Cylindrical-type connector (16) in setting, be circumferentially uniformly distributed thereon and the inverted truncated cone-shaped through hole of interval setting three and Three cylindrical holes, described inverted truncated cone-shaped through hole refers to that its aperture is up big and down small;It is clamped with each truncated cone-shaped through hole Upper core body (17), and anchor pole (2) is clamped by upper core body (17), in described cylindrical hole, sliding sleeve has moment reinforcement (9), institute Stating anchor pole (2) is GFRP anchor pole;
It is provided with adjusting nut (12) in the epimere of described moment reinforcement (9), the top end face of described adjusting nut (12) is above The bottom surface of cylindrical-type connector (16) is locking end face, and described moment reinforcement (9) sequentially passes through downwards lower locking nut (11), carries Backing plate (10), modified asphalt layer (13) and bottom cushion (8), the bottom of moment reinforcement (9) is embedded in pile body (1), lower locking Nut (11) is with the upper surface that carries backing plate (10) for locking end face;Described modified asphalt layer (13) be in bottom cushion (8), It is located at and carry the bottom surface of backing plate (10), the closure waterproof layer being formed around moment reinforcement (9) and anchor pole (2);
It is provided with lower cylindrical-type connector (4) in described pile body (1), described lower cylindrical-type connector (4) is circumferentially uniformly divided It is furnished with three positive truncated cone-shaped through holes, described positive truncated cone-shaped through hole refers to that its aperture is up-small and down-big, clamp in positive truncated cone-shaped through hole There is lower core body (3), the body of rod of described anchor pole (2) is clamped in lower core body (3), in the excircle of described lower cylindrical-type connector (4) The agnail (5) tilting upward is evenly distributed with face.
2. glass fibre prestressed anchor anchor structure according to claim 1, is characterized in that:
Described upper core body (17) is a pair of intermediate plate of half slide structure, and its external shape epimere is and circle in upper cylindrical-type connector (16) Cone that platform shape through hole inner chamber matches, hypomere be convexedly stretch in cylindrical-type connector (16) bottom surface with externally threaded cylinder Body, utilizes its external screw thread setting locking nut (15), described locking nut (15) is above cylindrical-type connector on the cylinder (16) bottom surface is locking end face;There is cylindrical hole inside upper core body (17), through-hole wall has screw thread, clamp anchor using screw thread Bar (2);
Described lower core body (3) has the version contrary up and down with upper chip (17);Externally threaded circle is carried in lower core body (3) Cylinder convexedly stretches in lower cylindrical-type connector (16) top surface, and using the clamp nut (6) on lower cylindrical-type connector (16) top surface Locking;There is cylindrical hole, through-hole wall has screw thread, using screw thread clamping anchor pole (2) inside lower core body (3).
3. glass fibre prestressed anchor anchor structure according to claim 1, is characterized in that:Described lower cylindrical-type connector (4) axially having multiple tracks with the distance of 0.5m for arranged for interval along anchor pole (2), described agnail (5) is along lower cylindrical-type connector (4) Be evenly distributed in three, with the horizontal 40 ° of angle, agnail (5) is the Ribbed Bar of diameter 10cm to agnail (5), length For 50cm.
4. glass fibre prestressed anchor anchor structure according to claim 1, is characterized in that:Described moment reinforcement (9) The length being embedded in pile body (1) is not less than 30cm.
5. a kind of charger of glass fibre prestressed anchor anchor structure described in claim 1, is characterized in that:On described The top setting prestressing force load maintainer of cylindrical-type connector (16), is connected in upper cylinder using described prestressing force load maintainer power transmission Device (16), implements prestressing force by described upper cylindrical-type connector (16) to GFRP anchor pole (2) and loads.
6. the charger of glass fibre prestressed anchor anchor structure according to claim 5, is characterized in that:Described pre- Stress loading mechanism is by loading plate (20) in reaction frame (19) support in the top of upper cylindrical-type connector (16), in upper loading plate (20) upper installation punching jack (21), load bar (18) is fixedly connected with upper cylindrical-type connector (16), by punching jack (21) loading force providing passes through load bar (18) power transmission in upper cylindrical-type connector (16), and implements in advance should to GFRP anchor pole (2) Power loads;Described reaction frame (19) is fixing with annular base (14), and described annular base (14) is placed on bottom cushion (8) Periphery that is upper, being in GFRP anchor pole (2).
CN201621031415.6U 2016-08-30 2016-08-30 Glass fiber prestressed anchorage pole anchor structure, its loading device Withdrawn - After Issue CN205975707U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621031415.6U CN205975707U (en) 2016-08-30 2016-08-30 Glass fiber prestressed anchorage pole anchor structure, its loading device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621031415.6U CN205975707U (en) 2016-08-30 2016-08-30 Glass fiber prestressed anchorage pole anchor structure, its loading device

Publications (1)

Publication Number Publication Date
CN205975707U true CN205975707U (en) 2017-02-22

Family

ID=58039431

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621031415.6U Withdrawn - After Issue CN205975707U (en) 2016-08-30 2016-08-30 Glass fiber prestressed anchorage pole anchor structure, its loading device

Country Status (1)

Country Link
CN (1) CN205975707U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106223368A (en) * 2016-08-30 2016-12-14 安徽建工集团有限公司 Glass fibre prestressed anchor anchor structure, its charger and loading method
CN107419725A (en) * 2017-08-28 2017-12-01 山东大学 A kind of system and method for strengthening trans reaction frame tensile property
CN108018890A (en) * 2018-01-23 2018-05-11 安徽省(水利部淮河水利委员会)水利科学研究院(安徽省水利工程质量检测中心站) A kind of anchor pole pullout tests system
CN109899097A (en) * 2019-03-22 2019-06-18 李静娴 Mechanical linkage Pulling-Resistant Anchor Rod

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106223368A (en) * 2016-08-30 2016-12-14 安徽建工集团有限公司 Glass fibre prestressed anchor anchor structure, its charger and loading method
CN107419725A (en) * 2017-08-28 2017-12-01 山东大学 A kind of system and method for strengthening trans reaction frame tensile property
CN107419725B (en) * 2017-08-28 2019-01-25 山东大学 A kind of system and method enhancing trans- reaction frame tensile property
CN108018890A (en) * 2018-01-23 2018-05-11 安徽省(水利部淮河水利委员会)水利科学研究院(安徽省水利工程质量检测中心站) A kind of anchor pole pullout tests system
CN109899097A (en) * 2019-03-22 2019-06-18 李静娴 Mechanical linkage Pulling-Resistant Anchor Rod

Similar Documents

Publication Publication Date Title
CN106223368B (en) Glass fibre prestressed anchor anchor structure, its loading device and loading method
CN205975707U (en) Glass fiber prestressed anchorage pole anchor structure, its loading device
US11976431B2 (en) Methods for constructing tensionless concrete pier foundations and foundations constructed thereby
CN106968245A (en) The uplift pile of prestress anchorage cable manually digging hole and its construction method
CN106193615B (en) A kind of glass fiber-reinforced polymer prestressed anti-floating anchor rod loading device and its construction method
CN101942833A (en) Frameless unbonded post-tensioned prestressed uplift filling pile and construction method thereof
CN102493476A (en) Post-tensioned prestressing pier foundation structure
CN212104064U (en) Anchor cable tensioning and installing device based on anchor rod
CN113550348A (en) Land large-plate foundation anchor rod reinforcing structure, construction method and fan foundation structure
CN210562163U (en) Prefabricated prestressed anchor rod piece
CN102363957B (en) A kind of post-tensioned prestressing composite uplift pile
CN102561212A (en) Method for strengthening vertical crack of single-pillar concrete pier
CN107435293A (en) Pre-stress FRP bar stretching and anchoring device and its construction method for precast assembly bridge pier
CN113338279A (en) Anticorrosive stagnant water stock
CN206693220U (en) Artificial digging pile resistance to plucking structure
CN110359755B (en) Consolidation inhaul cable system of wind tower with mixed structure and manufacturing and mounting method thereof
CN214574126U (en) Anti-floating device of power communication combined pipeline
CN205976542U (en) Glass fiber reinforced prestressing force anti -floating anchor rod loading device
CN214993804U (en) Glass fiber composite anchor rod
CN213773506U (en) Anti structure of floating of prestressed anchorage pole
CN202323991U (en) Post-tensioned prestressing pier foundation structure
CN110541355B (en) FRP constraint concrete hollow self-resetting-mild steel extrusion energy dissipation pier structure
CN103938626B (en) A kind of post jacking pressure type anchor rod and its construction method
CN208363089U (en) The steel strand reinforced structure of Pulling-Resistant Anchor Rod in a kind of stake
CN207448750U (en) A kind of U-shaped girder prefabricated pedestal of peg board formula track traffic pre-tensioning system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20170428

Address after: 233000 Anhui City, East China Sea Road, Cheung Shan Road South

Patentee after: Anhui Water Resources Development Co., Ltd.

Address before: 230001 Anhui City, Hefei Province, No. 459 Mount Huangshan Road, International Building

Patentee before: Anhui Construction Engineering Group Co., Ltd.

TR01 Transfer of patent right
AV01 Patent right actively abandoned

Granted publication date: 20170222

Effective date of abandoning: 20180629

AV01 Patent right actively abandoned