CN205969481U - Open broken line prestressing force precast beam stretch -draw pedestal earlier - Google Patents
Open broken line prestressing force precast beam stretch -draw pedestal earlier Download PDFInfo
- Publication number
- CN205969481U CN205969481U CN201620933911.4U CN201620933911U CN205969481U CN 205969481 U CN205969481 U CN 205969481U CN 201620933911 U CN201620933911 U CN 201620933911U CN 205969481 U CN205969481 U CN 205969481U
- Authority
- CN
- China
- Prior art keywords
- precast beam
- stretch
- gravity base
- steel
- column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Rod-Shaped Construction Members (AREA)
Abstract
The utility model discloses an open broken line prestressing force precast beam stretch -draw pedestal earlier, including transmission column, gravity base, precast beam and stretch -draw crossbeam. Transmission column places at the top precast beam, and both ends are connected with the gravity base, and the anti - stand of steel case is installed at gravity base top, and the welding of the anti - stand left end of steel case has the stretch -draw crossbeam, and the space of walking that has broken line prestressing force steel hinge line is reserved to the stretch -draw crossbeam. The anti - stand of steel case stretches into the gravity base and joins as an organic wholely through crab -bolt and gravity base, the anti - stand of steel case adopt the steel construction, the microdilatancy concrete is filled to inside. Transmission column is equipped with a plurality of provided groove mouths, conduct simultaneously according to 2 meters modulus the die block of precast beam. The utility model discloses satisfy multiple elder generation of striding the footpath and open the stretch -draw of broken line prestressing force precast beam, and satisfy multi -disc roof beam prefabricated construction simultaneously, simultaneously the utility model discloses but reuse can effectively reduce the roof beam body and build the cost, save the time limit for a project, guarantee roof beam physique volume and durability.
Description
Technical field
This utility model is related to a kind of precast beam stretching bed seat and in particular to one kind first opens folding prestressed prefabricated girder tensioning
Pedestal.
Background technology
At present, the across footpath of Bridges in Our Country pre-tension prestressed concrete beam is mostly below 20 meters, more than 25 meters of across footpaths
First Zhang Liang does not almost have, and its main cause is that the arrangement of presstressed reinforcing steel adopts straight line Distribution form s, folding prestressed first opens
The construction technology of beam does not also have the technology of maturation.
In recent years, some R&D institutions also were setting about studying the construction technology of broken line cloth muscle, achieved some achievements, Qinghai-Tibet
Railroad bridge employs 24 meters of broken lines and first opens simply supported beam.But stretching bed seat can only produce a piece of beam, and broken line muscle is at turner
The stress loss producing is larger, and concentrates on turnover at, stretching bed seat is required higher, need to arrange uplift pile and pull out with meeting
The requirement of power is it is more difficult to large scale application.
Utility model content
The purpose of this utility model is to overcome the deficiencies in the prior art, provides one kind first to open folding prestressed precast beam and opens
Draw pedestal, solve stretching bed seat and can only produce a piece of beam, the larger problem of the stress loss that broken line muscle produces at turner.
For achieving the above object, this utility model adopts following technical proposals:
One kind first opens folding prestressed precast beam stretching bed seat, horizontal including force-transmitting pole, gravity base, precast beam and tensioning
Beam, described power transmission column top is provided with multiple reserved notches, and precast beam is placed in described power transmission column top.
Described force-transmitting pole two ends are connected with gravity base, and described gravity base top is provided with the anti-column of steel case, institute
The steel case anti-column left end stated is welded with stretch-drawing beam, and what described stretch-drawing beam was reserved with folding prestressed steel hinge line walks sky
Between.
The described anti-column of steel case is stretched into gravity base and is integrated with gravity base link by crab-bolt;Described steel case
Anti- column adopts steel construction, internal perfusion microdilatancy concrete.
Described force-transmitting pole is a kind of axis compression member, using concrete structure;Described force-transmitting pole sets according to 2 meters of modulus
There are multiple reserved notches, described reserved notch is folding prestressed steering gear installation notch;Described force-transmitting pole simultaneously as
The bed die of described precast beam.
Described gravity base is a kind of concrete structure relying on own wt to offset moment of flexure caused by prestressed stretch-draw, and with
Described force-transmitting pole connects as one.
The anti-column of two steel casees is had on described gravity base.
The beneficial effects of the utility model:
This utility model meets the tensioning first opening folding prestressed precast beam, be assume responsibility for folding prestressed by gravity base
The larger moment of flexure that stretching force causes, reserves installation notch in power transmission column top and meets the need first opening folding prestressed steering
Ask, notch is pressed modulus and reserved, and can meet multiple across footpaths first opens folding prestressed prefabricated girder tensioning, and can meet multi-disc beam simultaneously
Prefabricated construction, this utility model is repeatable simultaneously utilizes, and can effectively reduce beam body construction costs, saves the duration, ensures beam body matter
Amount and durability.
Brief description
Fig. 1 is a kind of 1/2 stretching bed seat elevation first opening folding prestressed precast beam stretching bed seat;
Fig. 2 is a kind of 1/2 stretching bed seat plane graph first opening folding prestressed precast beam stretching bed seat;
In figure, 1- stretch-drawing beam, 2- gravity base, 3- precast beam, the anti-column of 4- steel case, the folding prestressed steel hinge line of 5-,
6- force-transmitting pole, 7- reserves notch.
Specific embodiment
Below in conjunction with the accompanying drawings this utility model is described in detail:
As shown in Figure 1, 2, one kind first opens folding prestressed precast beam stretching bed seat, including force-transmitting pole 6, gravity base 2, pre-
Beam 3 processed and stretch-drawing beam 1, described force-transmitting pole 6 top is provided with multiple reserved notches 7, and described force-transmitting pole 6 top is placed prefabricated
Beam 3.Described force-transmitting pole 6 two ends are connected with gravity base 2, and described gravity base 2 top is provided with the anti-column of steel case 4, institute
The anti-column of steel case 4 left end stated is welded with stretch-drawing beam 1, and described stretch-drawing beam 1 is reserved with wearing of folding prestressed steel hinge line 5
Row space.
The described anti-column of steel case 4 is stretched into gravity base 2 and is integrated with gravity base 2 link by crab-bolt;Described
The anti-column of steel case 4 adopts steel construction, internal perfusion microdilatancy concrete.
Described force-transmitting pole 6 is a kind of axis compression member, using concrete structure;Described force-transmitting pole 6 is according to 2 meters of modulus
It is provided with multiple reserved notches 7, described reserved notch 7 is folding prestressed steering gear installation notch;Described force-transmitting pole 6 is simultaneously
Bed die as described precast beam 3.
Described gravity base 2 is a kind of concrete structure relying on own wt to offset moment of flexure caused by prestressed stretch-draw, and
Connect as one with described force-transmitting pole 6.
When first opening the construction of folding prestressed precast beam, first the reserved notch 7 at force-transmitting pole 6 top install folding prestressed
Steel bundle steering gear, the folding prestressed steel strand wires of arrangement 5 tensioning, after assembling reinforcement, with force-transmitting pole 6 as bed die, install precast beam
The after-pouring concrete of side form, finally puts folding prestressed 5 one-tenth beams of steel strand wires.
Although the above-mentioned accompanying drawing that combines is described to specific embodiment of the present utility model, not new to this practicality
The restriction of type protection domain, one of ordinary skill in the art should be understood that on the basis of the technical solution of the utility model, ability
Field technique personnel do not need to pay the various modifications that creative work can make or deformation still in protection model of the present utility model
Within enclosing.
Claims (5)
1. one kind first opens folding prestressed precast beam stretching bed seat it is characterised in that including force-transmitting pole, gravity base, precast beam
And stretch-drawing beam, described power transmission column top is provided with multiple reserved notches, and precast beam is placed in described power transmission column top;
Described force-transmitting pole two ends are connected with gravity base, and described gravity base top is provided with the anti-column of steel case, described
Steel case anti-column left end is welded with stretch-drawing beam, and what described stretch-drawing beam was reserved with folding prestressed steel hinge line walks space.
2. a kind of as claimed in claim 1 first open folding prestressed precast beam stretching bed seat it is characterised in that described steel case
Anti- column is stretched into gravity base and is integrated with gravity base link by crab-bolt;The described anti-column of steel case adopts steel construction,
Internal perfusion microdilatancy concrete.
3. a kind of as claimed in claim 1 first open folding prestressed precast beam stretching bed seat it is characterised in that described power transmission
Post is a kind of axis compression member, using concrete structure;Described force-transmitting pole is provided with multiple reserved notches, institute according to 2 meters of modulus
The reserved notch stated is folding prestressed steering gear installation notch;Described force-transmitting pole is simultaneously as the bed die of described precast beam.
4. a kind of as claimed in claim 1 first open folding prestressed precast beam stretching bed seat it is characterised in that described gravity
Base is a kind of concrete structure relying on own wt to offset moment of flexure caused by prestressed stretch-draw, and is connected as with described force-transmitting pole
Integrally.
5. a kind of as claimed in claim 1 first open folding prestressed precast beam stretching bed seat it is characterised in that described gravity
The anti-column of two steel casees is had on base.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620933911.4U CN205969481U (en) | 2016-08-24 | 2016-08-24 | Open broken line prestressing force precast beam stretch -draw pedestal earlier |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620933911.4U CN205969481U (en) | 2016-08-24 | 2016-08-24 | Open broken line prestressing force precast beam stretch -draw pedestal earlier |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205969481U true CN205969481U (en) | 2017-02-22 |
Family
ID=58033901
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620933911.4U Active CN205969481U (en) | 2016-08-24 | 2016-08-24 | Open broken line prestressing force precast beam stretch -draw pedestal earlier |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205969481U (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109571747A (en) * | 2018-11-23 | 2019-04-05 | 上海市政预制技术开发有限公司 | A kind of double T beam construction methods of broken line pretensioned prestressing |
CN109577212A (en) * | 2019-01-23 | 2019-04-05 | 中水电第十工程局(郑州)有限公司 | A kind of pretensioned prestressing Precasting Pedestal Construction method |
CN111636286A (en) * | 2020-05-12 | 2020-09-08 | 济南市市政工程设计研究院(集团)有限责任公司 | Pretensioned broken line prestressed I-beam bridge and construction method |
CN111663434A (en) * | 2020-05-13 | 2020-09-15 | 济南市市政工程设计研究院(集团)有限责任公司 | Mixed-tension prestress prefabricated cover beam tensioning assembly and method for connecting cover beam and upright column |
CN112518983A (en) * | 2020-12-11 | 2021-03-19 | 保利长大工程有限公司 | Pre-tensioning method precast beam slab tensioning pedestal structure |
CN112590000A (en) * | 2020-12-11 | 2021-04-02 | 保利长大工程有限公司 | Prestressed integral tensioning and releasing method for broken line pre-tensioning method beam plate |
CN112936578A (en) * | 2021-01-26 | 2021-06-11 | 中建八局第一建设有限公司 | Precast beam system roof beam pedestal |
-
2016
- 2016-08-24 CN CN201620933911.4U patent/CN205969481U/en active Active
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109571747A (en) * | 2018-11-23 | 2019-04-05 | 上海市政预制技术开发有限公司 | A kind of double T beam construction methods of broken line pretensioned prestressing |
CN109571747B (en) * | 2018-11-23 | 2021-07-06 | 上海市政预制技术开发有限公司 | Construction method of broken line pretensioning prestressed double T-beam |
CN109577212A (en) * | 2019-01-23 | 2019-04-05 | 中水电第十工程局(郑州)有限公司 | A kind of pretensioned prestressing Precasting Pedestal Construction method |
CN111636286A (en) * | 2020-05-12 | 2020-09-08 | 济南市市政工程设计研究院(集团)有限责任公司 | Pretensioned broken line prestressed I-beam bridge and construction method |
CN111663434A (en) * | 2020-05-13 | 2020-09-15 | 济南市市政工程设计研究院(集团)有限责任公司 | Mixed-tension prestress prefabricated cover beam tensioning assembly and method for connecting cover beam and upright column |
CN111663434B (en) * | 2020-05-13 | 2022-03-25 | 济南市市政工程设计研究院(集团)有限责任公司 | Mixed-tension prestress prefabricated cover beam tensioning assembly and method for connecting cover beam and upright column |
CN112518983A (en) * | 2020-12-11 | 2021-03-19 | 保利长大工程有限公司 | Pre-tensioning method precast beam slab tensioning pedestal structure |
CN112590000A (en) * | 2020-12-11 | 2021-04-02 | 保利长大工程有限公司 | Prestressed integral tensioning and releasing method for broken line pre-tensioning method beam plate |
CN112936578A (en) * | 2021-01-26 | 2021-06-11 | 中建八局第一建设有限公司 | Precast beam system roof beam pedestal |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205969481U (en) | Open broken line prestressing force precast beam stretch -draw pedestal earlier | |
CN206859408U (en) | A kind of prefabricated assembled concrete pole steel beam node | |
CN203270457U (en) | Suspension bar anchoring structure capable of initiatively reinforcing concrete tied-arch bridge | |
CN107083808A (en) | A kind of prefabricated assembled concrete pole steel beam node | |
CN203923924U (en) | No. 0 section bracket prepressing device | |
CN202248298U (en) | Node of steel reinforced concrete framework | |
CN105926775A (en) | Novel concrete-filled steel tube beam column joint | |
CN202323717U (en) | Cantilever type pre-stress hoop and special tensioning device thereof | |
CN208293400U (en) | A kind of ultra-high performance concrete-part girder steel combination bent cap | |
CN206190458U (en) | Prestressing force antifatigue combination steel construction wind tower of qxcomm technology | |
CN210766207U (en) | Assembly type vibration reduction upright post structure for inspection pit section in garage | |
CN202064276U (en) | Cable-girder anchorage structure of railway steel truss cable stayed bridge | |
CN204753819U (en) | Take tree -like supporting grid structure of secondary branching of prestressing force | |
CN106704107A (en) | Omni-directional prestress antifatigue combined steel structure wind tower and construction method thereof | |
CN204644869U (en) | Drag-line bridge tower anchoring structure | |
CN203334182U (en) | Structure used for connecting railway concrete retaining wall with steel bridge panel | |
CN202401384U (en) | Ballasting structure of steel-truss cable-stayed bridge | |
CN204753341U (en) | Assembled wave form steel web combination precast beam | |
CN204780642U (en) | Beam bridge I shaped steel makes up reinforced structure | |
CN204000562U (en) | The compound rigid frame bridge of a kind of vertical prestressing steel-concrete | |
CN209837825U (en) | Comb rack structure of three-dimensional parking equipment | |
CN104652249B (en) | A kind of load transfer device of drag-line and girder | |
CN203684115U (en) | Concrete box girder with widened thin wall | |
CN208472944U (en) | The bolt of partial precast connects node structure | |
CN203346803U (en) | Novel strengthening device of reinforced concrete bridge pier |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |