CN205935407U CN201620428600.2U CN201620428600U CN205935407U CN 205935407 U CN205935407 U CN 205935407U CN 201620428600 U CN201620428600 U CN 201620428600U CN 205935407 U CN205935407 U CN 205935407U
Authority
CN
China
Prior art keywords
steel pipe
gypsum mortar
waste concrete
combination column
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620428600.2U
Other languages
Chinese (zh)
Inventor
吴冬雁
赵俊亮
孙林柱
李桅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wenzhou University
Original Assignee
Wenzhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wenzhou University filed Critical Wenzhou University
Priority to CN201620428600.2U priority Critical patent/CN205935407U/en
Application granted granted Critical
Publication of CN205935407U publication Critical patent/CN205935407U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses a steel pipe gypsum mortar waste concrete combination column, including the steel pipe with fill gypsum mortar and the waste concrete piece in the steel pipe, the steel pipe both ends are sealed by the end plate, a plurality of holes of vibrating of having arranged on the steel pipe lateral wall, steel pipe inner wall circumference evenly distributed has many longitudinal reinforcements. The utility model also discloses a method of preparing steel pipe gypsum mortar waste concrete combination column. The utility model discloses the steel pipe gypsum mortar waste concrete combination column of preparation has fast hard, early strong characteristics, can reach the bearing capacity rapidly, and the intensity of member as follows mainly discarded delayed coagulation soil block skeleton provide, can reduce material cost, the gypsum mortar only is used as cementitious material and sealant in addition, and the outside restraint of steel pipe in addition can weaken the weak sureness in interface between gypsum mortar and the waste concrete piece, greatly improves the intensity and the ductility of member.

Description

Steel pipe gypsum mortar discarded concrete coupled column
Technical field
This utility model is related to a kind of steel pipe gypsum mortar discarded concrete coupled column.
Background technology
With the high speed development of building industry, villages and small towns pull down and remove a building for reconstruction with repair, Urban New District and residential quarters continuous Exploitation and scale construction and public utility newly-built, all can produce substantial amounts of building waste.Additionally, China's part is built Building structure will reach design life.According to statistics, the annual projects of China account for the 40% of construction project total amount, and every The quantity that ten thousand square metres of projects can produce building waste is 7000 tons -12000 tons.To make after construction waste crushing Natural aggregate resource anxiety problem not only can be solved for regenerated aggregate, realize the regeneration of concrete and recycle it is ensured that building The sustainable development of industry.Both at home and abroad substantial amounts of experimental study is done to regeneration concrete performance, shown regeneration concrete items Can be good, can be used in Practical Project construction.Current discarded concrete coupled column is typically all that in steel pipe, filling is discarded to be mixed The materials such as solidifying soil block, cement, coal ash, there is the shortcomings of rate of set is slow, intensity is not good enough in the early time in this coupled column, and fill material The combination dynamics of material and steel pipe is poor.
Utility model content
In view of the deficiency of background technology, technical problem to be solved in the utility model be provide one kind hard soon, early strong, prolong Property good and low cost steel pipe gypsum mortar discarded concrete coupled column.
For this reason, this utility model adopts the following technical scheme that to realize:
A kind of steel pipe gypsum mortar discarded concrete coupled column, including steel pipe and the gypsum mortar that is filled in steel pipe and useless Abandon concrete block, described steel pipe two ends are sealed by end plate.
Described gypsum mortar is made up of water, Gypsum Fibrosum and sand.
Also added with retarder in described gypsum mortar.
The maximum gauge of described waste concrete block is the 1/4-1/3 of diameter of steel tube, the minimum diameter of waste concrete block For 20-30mm.
The ratio of described water, Gypsum Fibrosum and sand is 0.3:1:1-0.5:1:1.
Described retarder is citric acid.
After technique scheme, the intensity of coupled column is mainly provided by discarded slow setting soil block, and gypsum mortar is used only as Binder Materials and pointing, it is plastic that gypsum mortar pours rear 20-30 minute, and its intensity can arrive 20-60MPa, has fast Firmly, early strong feature, and the intensity of component mainly has discarded slow setting soil block skeleton to provide, gypsum mortar is used only as the material that is gelled Material and pointing, the outside constraint also having steel pipe, can weaken interface between gypsum mortar and waste concrete block weak Determine, intensity and the ductility of component not only can be greatly improved, but also material cost can be reduced.
Brief description
This utility model has drawings described below:
The structural representation of the steel pipe gypsum mortar discarded concrete coupled column that Fig. 1 provides for this utility model.
Specific embodiment
Include steel pipe 1 and fill out with reference to the steel pipe gypsum mortar discarded concrete coupled column that shown in Fig. 1, this utility model provides Fill the gypsum mortar 2 in steel pipe 1 and waste concrete block 3, steel pipe 1 two ends are sealed by end plate, and gypsum mortar 2 is by water, Gypsum Fibrosum With sand composition, the ratio of water, Gypsum Fibrosum and sand is 0.3:1:1-0.5:1:1, mixing water amount is bigger, and intensity is lower, and mobility is got over Good, also added with retarder in gypsum mortar 2, retarder is citric acid, for adjusting the flocculation time of gypsum mortar 2, discards mixed The maximum gauge of solidifying soil block 3 is the 1/4-1/3 of steel pipe 1 diameter, and the minimum diameter of waste concrete block 3 is 20-30mm.
With reference to shown in Fig. 1, in order to increase structural strength, described steel pipe side wall is placed with multipair horizontal steel along short transverse Muscle jack 4, transverse steel 5 passes through in steel pipe 1 and two ends insertion transverse steel jack 4, and described transverse steel 5 and steel pipe 1 wall weld Connect fixation.In view of the volume of waste concrete block 3 is larger, if cannot be obtained in steel pipe 1 using common reinforcement cage structure Enough bearing spaces, are therefore contributed in reinforcing bar and coupled column using the structure that transverse steel 5 inserts transverse steel jack 4 Core combines, and improves intensity.
The preparation method of above-mentioned steel pipe gypsum mortar discarded concrete coupled column, comprises the following steps:
(1)Steel pipe one end plate of 1 bottom welding is sealed, then into steel pipe fill diameter of steel tube 1/2-1 it Between thickness gypsum mortar 2, add the retarder of certain metering as needed in gypsum mortar 2, for adjusting gypsum mortar 2 Flocculation time;
(2)To in steel pipe, alternately throw discarded solidifying soil block 3 and/or rubble and/or cobble and filler plaster mortar;
(3)After gypsum mortar 2 condenses, in steel pipe 1 welded top end plate.
In above-mentioned steps(2)In, throw discarded solidifying soil block 3 and/or rubble and/or cobble and filler plaster in steel pipe 1 Often reach a pair of transverse steel jack 4 position during mortar and in transverse steel jack 4, insert transverse steel 5, And by outside steel pipe 1, transverse steel 5 is welded on steel pipe 1 wall.The transverse steel inserted mode that the present embodiment provides can avoid Transverse steel 5 aggregate larger with waste concrete block 3 equal-volume contacts, it is to avoid the loading of impact large volume aggregate, is lifted simultaneously The bulk strength of coupled column.

Claims (1)

1. a kind of steel pipe gypsum mortar discarded concrete coupled column, is characterized in that:Including steel pipe and the Gypsum Fibrosum being filled in steel pipe Mortar and waste concrete block, described steel pipe two ends are sealed by end plate, and the maximum gauge of described waste concrete block is that steel pipe is straight The 1/4-1/3 in footpath, the minimum diameter of waste concrete block is 20-30mm, described steel pipe side wall is placed with many along short transverse To transverse steel jack, transverse steel passes through in steel pipe and two ends insertion transverse steel jack, described transverse steel and steel pipe walls It is welded and fixed.
CN201620428600.2U 2016-05-12 2016-05-12 Steel pipe gypsum mortar waste concrete combination column Expired - Fee Related CN205935407U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620428600.2U CN205935407U (en) 2016-05-12 2016-05-12 Steel pipe gypsum mortar waste concrete combination column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620428600.2U CN205935407U (en) 2016-05-12 2016-05-12 Steel pipe gypsum mortar waste concrete combination column

Publications (1)

Publication Number Publication Date
CN205935407U true CN205935407U (en) 2017-02-08

Family

ID=57934932

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620428600.2U Expired - Fee Related CN205935407U (en) 2016-05-12 2016-05-12 Steel pipe gypsum mortar waste concrete combination column

Country Status (1)

Country Link
CN (1) CN205935407U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105804321A (en) * 2016-05-12 2016-07-27 温州大学 Steel pipe gypsum mortar and waste concrete combined column and preparation method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105804321A (en) * 2016-05-12 2016-07-27 温州大学 Steel pipe gypsum mortar and waste concrete combined column and preparation method thereof

Similar Documents

Publication Publication Date Title
US10087106B2 (en) Method of constructing an axial compression steel tubular column
CN202898930U (en) By-river reinforced roadbed structure
CN104711976B (en) A kind of construction refuse regenerated aggregate complex carrier stake and preparation method thereof
CN103306432B (en) High-strength concrete cushion block and manufacturing method thereof
CN104358356A (en) High-enhanced regenerative mixed steel-tubular concrete-filled anti-shock column with built-in local restraint and construction technology thereof
CN105254195B (en) A kind of Waste tire regeneration concrete composite material and complex and its construction method
CN102995746A (en) Beam slab node of renewable hybrid combined floor slab made of U-shaped steel-encased renewable hybrid beam and construction method thereof
CN105804321B (en) Steel pipe gypsum mortar discarded concrete coupled column and preparation method thereof
CN205935407U (en) Steel pipe gypsum mortar waste concrete combination column
CN208534081U (en) A kind of reconstruction structure of old building constructional column
CN105178511B (en) Section steel flange weakens regeneration concrete energy dissipation coupled column and preparation method thereof
CN104762956A (en) Method for forming novel pile based on construction waste recycled aggregate
CN105064502B (en) Using the regeneration concrete bean column node and construction method of cross-shaped profile steel plate weld edge of a wing stiffener
CN103896539B (en) Prefabricated sial base green cement concrete bidirectional hole hollow template and manufacture method thereof
CN202882164U (en) Member for restraining grouting anchor connection by using two ends of reinforcing steel bar
CN102912928B (en) Structural member for restraining grouting anchoring connection by using two ends of steel bar and connection method
CN108035457A (en) A kind of high ductility concrete shear force wall connection structure of assembled and connection method
CN205242388U (en) Enhancement mode SMW worker method pilework
CN104947948B (en) A kind of reinforcement means of rammed earth body of wall
CN106381956A (en) Concrete prefabricated shell-regenerated mixed concrete combination column and preparation method thereof
CN104314001B (en) Regeneration concrete band U rib dumbbell shape columnar piers
CN206681208U (en) One kind combination constraint double steel plate concrete shear force wall
CN104831706B (en) A kind of reinforcement means of red mud dump
CN114318990A (en) Construction waste resource filling method for road widening
CN205474790U (en) Light -duty arched bridge

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170208

Termination date: 20170512

CF01 Termination of patent right due to non-payment of annual fee