CN205907673U - Steel sheet pile structure for bridge main pier bearing platform foundation pit on river channel steep slope bedrock - Google Patents

Steel sheet pile structure for bridge main pier bearing platform foundation pit on river channel steep slope bedrock Download PDF

Info

Publication number
CN205907673U
CN205907673U CN201620849118.6U CN201620849118U CN205907673U CN 205907673 U CN205907673 U CN 205907673U CN 201620849118 U CN201620849118 U CN 201620849118U CN 205907673 U CN205907673 U CN 205907673U
Authority
CN
China
Prior art keywords
steel sheet
sheet pile
cushion cap
foundation ditch
main pier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620849118.6U
Other languages
Chinese (zh)
Inventor
孟利军
刘缉江
许明君
黄志兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 19th Metallurgical Group Co ltd
Original Assignee
China 19th Metallurgical Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 19th Metallurgical Group Co ltd filed Critical China 19th Metallurgical Group Co ltd
Priority to CN201620849118.6U priority Critical patent/CN205907673U/en
Application granted granted Critical
Publication of CN205907673U publication Critical patent/CN205907673U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)

Abstract

The utility model discloses a steel sheet pile structure that is used for bridge owner mound cushion cap foundation ditch on river course abrupt slope basement rock, including the steel sheet pile, the cross-section of steel sheet pile is "C" type structure, and two liang of adjacent steel sheet piles are relative, and the side interlock each other is connected, and on the riverbed rock layer was located to the steel sheet pile, and the steel sheet pile runs through riverbed cobble overburden and cofferdam island filled soil layer, and the junction is equipped with rubber between the steel sheet pile. The utility model discloses can effectively be waterproof, stagnant water to bridge main mound cushion cap foundation ditch, effectively overcome and leaned on complicated geology, hydrology structure and the characteristics of channel one side to the adverse effect of bridge main mound cushion cap construction, solved river water level change, river water pressure and river water and immersed the construction problem that foundation ditch influences bridge main mound cushion cap, the utility model discloses it is current not to influence river course center channel, simple structure, and the preparation is convenient, and the cost is practiced thrift.

Description

A kind of steel plate pilework of the Main Pier of Bridges cushion cap foundation ditch on the basement rock for river course abrupt slope
Technical field
This utility model is related to river course bridge construction technical field, particularly relates to one kind and is used for river course abrupt slope basement rock On Main Pier of Bridges cushion cap foundation ditch steel plate pilework.
Background technology
Constantly develop with China's economic society, the city rural volume of traffic is also increasing, strengthen road and bridge Construction, can preferably meet the requirement of the development to transportation industry for the people, improve the quality of life of people, promote local Economic development.
Apply man-hour requirement in Main Pier of Bridges cushion cap foundation ditch in the face of complicated geology, hydrology construction, difficulty of construction and requirement Relatively higher.As steeper sandstone dirt bed riverbank in the gradient constructs brings difficulty to main pier bearing platform construction, and a part of position of cushion cap On the abrupt slope basement rock on riverbank, another part gos deep into river or river, and side is navigation channel, and its bearing platform construction is necessarily in the face of the water surface SEA LEVEL VARIATION and river immersion pressure, the side slope construction by navigation channel is unstable, faced by hydraulic pressure larger and pressure becomes Change and there is uncertainty, a couple of days at least main pier bearing platform engineering time of bridge, the at most several months, as the boundary in flood season and non-flood period Time, more should pay attention to its working security and quality, but in the construction of prior art, one is that prior art cost is very high High, two is also undesirable to the effect of foundation ditch inner waterproofing, sealing, so needing one kind more preferably to build in river course abrupt slope base The foundation pit supporting construction of the Main Pier of Bridges cushion cap on rock.
Content of the invention
In order to overcome the shortcomings of existing technology, this utility model provides the bridge on a kind of basement rock for river course abrupt slope The steel plate pilework of main pier bearing platform foundation ditch.
Technical solutions of the utility model are as described below:
A kind of steel plate pilework of the Main Pier of Bridges cushion cap foundation ditch on basement rock for river course abrupt slope is it is characterised in that include Steel sheet pile, the section of described steel sheet pile is in that " c " type constructs, and adjacent described steel sheet pile is relative two-by-two, and side is engaged each other Connect, described steel sheet pile is on riverbed lithosphere, and described steel sheet pile runs through riverbed cobble cover layer and cofferdam is built island and banketed Layer.
Further, described steel sheet pile is at 1 meter of described cofferdam Zhu Dao edge.
Further, between described steel sheet pile, junction is provided with rubber.
Further, connected overall structure is curved two-by-two for described steel sheet pile.
Further, described steel sheet pile builds island and the river course water surface higher than described cofferdam.
According to this utility model of such scheme, its advantage is, this utility model can be to Main Pier of Bridges cushion cap The effective waterproof of foundation ditch, sealing, effectively overcome by the complicated geology in navigation channel side, hydrology construction and feature to Main Pier of Bridges cushion cap The adverse effect of construction, solves river water level change, river pressure and river and immerses foundation ditch impact Main Pier of Bridges cushion cap Construction problem, this utility model does not affect river course mid-channel and passes through, and structure is simple, easy to make, cost savings.
Brief description
Fig. 1 is structural representation of the present utility model;
Fig. 2 is that in this utility model, pore cross section figure is drawn in twist bit cutting;
Fig. 3 is top view of the present utility model;
Fig. 4 is embodied as illustration for this utility model.
In in figure, 1, steel sheet pile;2nd, armored concrete arch ring;3rd, auger;4th, island fill stratum is built in cofferdam;5th, stake holes;6、 Riverbed cobble cover layer;7th, riverbed lithosphere;8th, Main Pier of Bridges;9th, urban river water.
Specific embodiment
Below in conjunction with the accompanying drawings and embodiment conducts further description to this utility model:
As Figure 1-4, the steel plate pilework of the Main Pier of Bridges cushion cap foundation ditch on a kind of basement rock for river course abrupt slope, including Steel sheet pile 1, the section of steel sheet pile 1 is in that " c " type constructs, and adjacent steel sheet pile 1 is relative two-by-two, and side is connected each other, Steel sheet pile 1 is on riverbed lithosphere 7, and steel sheet pile 1 runs through riverbed cobble cover layer 6 and island fill stratum 4 is built in cofferdam.
At 1 meter of cofferdam Zhu Dao edge, between steel sheet pile 1, junction is provided with rubber to steel sheet pile 1, prevents urban river water 9 from oozing Enter, connected overall structure is curved two-by-two for steel sheet pile 1, Stability Analysis of Structures is conducive to buffering the surge of urban river water 9, steel sheet pile Build island and urban river water 9 plane higher than cofferdam, prevent from during 9 flood season of urban river water, overflowing cofferdam and build island, impact bridge main pier bearing platform foundation ditch.
This utility model first at 1 meter of the cofferdam Zhu Dao edge by river course side with 3 quarter of auger stake holes 5, stake holes 5 continuously connects Connect formation arc, then steel sheet pile inserting piling entered stake holes 5, adjacent steel sheet pile 1 is relative two-by-two, and side is connected each other, Surround Main Pier of Bridges 8 cushion cap foundation ditch by river course side it is ensured that steel sheet pile 1 passes through riverbed cobble cover layer 6 and cofferdam to build island and fill out Soil layer 4, arrives at riverbed lithosphere 7, is provided with armored concrete arch ring 2, steel sheet pile 1 and armored concrete arch ring inside steel sheet pile 1 2, mutual security Main Pier of Bridges cushion cap foundation ditch, waterproof, sealing.
This utility model can to Main Pier of Bridges cushion cap foundation ditch effective waterproof, sealing, effectively overcome multiple by navigation channel side Miscellaneous geology, the hydrology construction and feature adverse effect to Main Pier of Bridges bearing platform construction, solve river water level change, river pressure Power and river immerse foundation ditch and affect the construction problem of Main Pier of Bridges cushion cap, and this utility model does not affect river course mid-channel and leads to OK, structure is simple, easy to make, cost savings
It should be appreciated that for those of ordinary skills, can be improved according to the above description or be converted, And all these modifications and variations all should belong to the protection domain of this utility model claims.
Above in conjunction with accompanying drawing, exemplary description is carried out to this utility model patent it is clear that the reality of this utility model patent Now it is not subject to the restrictions described above, as long as the method design employing this utility model patent is various with what technical scheme was carried out Improve, or the not improved design by this utility model patent and technical scheme directly apply to other occasions, all in this reality With in new protection domain.

Claims (5)

1. a kind of steel plate pilework of the Main Pier of Bridges cushion cap foundation ditch on basement rock for river course abrupt slope is it is characterised in that include steel Sheet pile, the section of described steel sheet pile is in that " c " type constructs, and adjacent described steel sheet pile is relative two-by-two, and the side company of occlusion each other Connect, described steel sheet pile is on riverbed lithosphere, and described steel sheet pile runs through riverbed cobble cover layer and island fill stratum is built in cofferdam.
2. it is used for the steel plate pilework of the Main Pier of Bridges cushion cap foundation ditch on the basement rock of river course abrupt slope according to claim 1, it is special Levy and be, described steel sheet pile is at 1 meter of described cofferdam Zhu Dao edge.
3. it is used for the steel plate pilework of the Main Pier of Bridges cushion cap foundation ditch on the basement rock of river course abrupt slope according to claim 1, it is special Levy and be, between described steel sheet pile, junction is provided with rubber.
4. it is used for the steel plate pilework of the Main Pier of Bridges cushion cap foundation ditch on the basement rock of river course abrupt slope according to claim 1, it is special Levy and be, connected overall structure is curved two-by-two for described steel sheet pile.
5. it is used for the steel plate pilework of the Main Pier of Bridges cushion cap foundation ditch on the basement rock of river course abrupt slope according to claim 1, it is special Levy and be, described steel sheet pile builds island and the river course water surface higher than described cofferdam.
CN201620849118.6U 2016-08-08 2016-08-08 Steel sheet pile structure for bridge main pier bearing platform foundation pit on river channel steep slope bedrock Expired - Fee Related CN205907673U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620849118.6U CN205907673U (en) 2016-08-08 2016-08-08 Steel sheet pile structure for bridge main pier bearing platform foundation pit on river channel steep slope bedrock

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620849118.6U CN205907673U (en) 2016-08-08 2016-08-08 Steel sheet pile structure for bridge main pier bearing platform foundation pit on river channel steep slope bedrock

Publications (1)

Publication Number Publication Date
CN205907673U true CN205907673U (en) 2017-01-25

Family

ID=57804201

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620849118.6U Expired - Fee Related CN205907673U (en) 2016-08-08 2016-08-08 Steel sheet pile structure for bridge main pier bearing platform foundation pit on river channel steep slope bedrock

Country Status (1)

Country Link
CN (1) CN205907673U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112575777A (en) * 2020-12-15 2021-03-30 杭州京杭运河二通道建设投资有限公司 Frame reinforcing system and method for high-speed railway pier foundation penetrating through under channel
CN114592423A (en) * 2022-04-01 2022-06-07 中国十九冶集团有限公司 Wet joint connection construction method of prefabricated pier stud and bearing platform

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112575777A (en) * 2020-12-15 2021-03-30 杭州京杭运河二通道建设投资有限公司 Frame reinforcing system and method for high-speed railway pier foundation penetrating through under channel
CN114592423A (en) * 2022-04-01 2022-06-07 中国十九冶集团有限公司 Wet joint connection construction method of prefabricated pier stud and bearing platform
CN114592423B (en) * 2022-04-01 2024-01-30 中国十九冶集团有限公司 Wet joint connection construction method for prefabricated pier column and bearing platform

Similar Documents

Publication Publication Date Title
CN1837511B (en) Double-rowed cofferdam and method for manufacturing the same
CN104805854A (en) Method for constructing deep-water ultra-long steel plate pile cofferdam in tide environment
CN104790410B (en) A kind of Support of Foundation Pit Excavation method that is applicable to shallow water mud river course
CN105421500A (en) Basement anti-floating system based on low horizontal grout curtain and depressurization through water drawing
CN105350526A (en) Method for setting up steel platform
CN202559368U (en) Subsidence-reducing pile structure of capped steel pipe of immersed tunnel
CN203939036U (en) A kind of steel sheet pile cofferdam structure that is applicable to river course
CN205907673U (en) Steel sheet pile structure for bridge main pier bearing platform foundation pit on river channel steep slope bedrock
CN111472326A (en) Method and structure for building gravity dam on deep covering layer
CN208949902U (en) A kind of river channel bridge bearing platform foundation pit antiseepage cofferdam
CN107059914A (en) A kind of ring-type for being used for shallow overburden or naked rock area in water is embedded to set basis
CN204551500U (en) Novel cofferdam in a kind of super thick soft foundation
CN101481913A (en) Construction method of rock-socketed underground continuous wall punching slot section
CN205975646U (en) Shallow water territory steel pipe pile holder fortifield village weir structure
CN205776154U (en) A kind of high-strength prestressed concrete flute profile sheet pile
CN106988317A (en) One kind is used for underground pipe gallery method for processing foundation
CN207727514U (en) A kind of library basin antiseepage is anti-to lift structure
CN205907692U (en) Reinforced concrete arch ring structure for bridge main pier bearing platform foundation pit on river channel steep slope bedrock
CN105569055A (en) Structure for preventing mountain landslide
CN204875807U (en) Bridge main pier cushion cap foundation pit supporting structure on river channel abrupt slope basement rock
CN213390185U (en) Cofferdam structure that earth-rock cofferdam and concrete cofferdam combined together
CN204898700U (en) Bridge foundation structure
CN208501613U (en) Nearby Structure depth riverbed quaywall supporting construction
CN209429054U (en) Seepage prevention of dam founda structure in ultra-deep thick-covering
CN107130644A (en) Coffering composite geo-membrane and gravelly clay combination against seepage construction method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170125

Termination date: 20200808

CF01 Termination of patent right due to non-payment of annual fee