CN205863657U - 220kV double bus scheme transmission line circuit wiring optimizes structure - Google Patents

220kV double bus scheme transmission line circuit wiring optimizes structure Download PDF

Info

Publication number
CN205863657U
CN205863657U CN201620860091.0U CN201620860091U CN205863657U CN 205863657 U CN205863657 U CN 205863657U CN 201620860091 U CN201620860091 U CN 201620860091U CN 205863657 U CN205863657 U CN 205863657U
Authority
CN
China
Prior art keywords
switch
chopper
bus
transmission line
disconnecting switch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620860091.0U
Other languages
Chinese (zh)
Inventor
蒙家彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Guofu Electric Design Engineering Co Ltd
Original Assignee
Shanghai Guofu Electric Design Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Guofu Electric Design Engineering Co Ltd filed Critical Shanghai Guofu Electric Design Engineering Co Ltd
Priority to CN201620860091.0U priority Critical patent/CN205863657U/en
Application granted granted Critical
Publication of CN205863657U publication Critical patent/CN205863657U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The utility model discloses a kind of 220kV double bus scheme transmission line circuit wiring and optimize structure, including chopper, the first disconnecting switch, the first inspection earthing switch, high speed grounding switch, voltage transformer, current transformer and spark gap, the bus bar side of chopper is sequentially connected with the first inspection earthing switch, the first disconnecting switch to bus, and the outgoing line side of chopper is connected with current transformer, high speed grounding switch, voltage transformer, charged display device, spark gap in turn;Described new arrangement, when 220kV outlet is without T link, removes the second disconnecting switch of breaker outgoing line side, the second inspection earthing switch relative to traditional connection type optimization, and the miscellaneous equipment order of connection is identical with conventional connections.This utility model simplifies wiring, improves equipment dependability, meets the basic design principle of main electrical scheme " reliability is reasonable, and economy is optimum ", it is easy to promote the use of.

Description

220kV double bus scheme transmission line circuit wiring optimizes structure
Technical field
This utility model relates to electrical main connecting wire technical field, particularly relates to a kind of 220kV double bus scheme transmission line circuit Wiring optimizes structure.
Background technology
Electrical main connecting wire is mainly in power plant, electrical power system in substation as to meet predetermined power transmission and operation etc. Requiring and design, it shows the circuit transmitting electric energy of interconnected relationship, the high pressure in circuit between high voltage electric equipment Electrical equipment includes bus, chopper, isolation switch, spark gap etc., and their connected mode is to power supply reliability, flexible operation Property and economic rationality etc. play decisive role (typically when studying Main Wire Connection Scheme and the method for operation, in order to clear and square Just, generally three-phase circuit figure is depicted as line chart).
Electrical main connecting wire should meet the following requirements: (1) reliability of operation: main electrical scheme system should ensure that and supplies user The reliability of electricity, particularly ensures the power supply to important load;(2) motility run: main electrical scheme system should be able to be fitted neatly Answer various working conditions, particularly when a part of overhaul of the equipments or working condition change, it is possible to by switching switch The method of operation, accomplishes scheduling flexibly, does not interrupt the power supply to user, when enlarging should be able to very easily from primary construction to finally Wiring;(3) main electrical scheme system also should ensure that and runs the convenience of operation and under ensureing the requirement that meets the specification, accomplish through Ji rationally, reduces floor space as far as possible, reduces investment outlay.
Double bus scheme is a kind of connection type conventional in power system, and two groups of buses of double-bus work simultaneously, and By bus-tie circuit breaker parallel running, power supply and load are distributed evenly on two groups of buses.China's 220kV distribution dress at present Putting more employing Cubicle Gas-Insulated Switchgear (GIS), the 220kV power distribution equipment in 220kV electric substation, when in system In occupy critical role, transmission line circuit number be 4 times and above time, preferably use double bus scheme.
Fig. 1 is the 220kV transmission line circuit wiring diagram of prior art, according to regulation in " power engineering electrical design handbook ": " both sides of chopper all should configuration isolation switch, in order to the insulating power supply when overhaul of line breaker." GIS combination electric appliance is open circuit Device the 1, first disconnecting switch the 2, second disconnecting switch the 3, first inspection earthing switch the 4, second inspection earthing switch 5, rapid grounding The equipment that switch 6, current transformer 8, voltage transformer 7 are highly integrated, employing gas-insulated, compact conformation, even if chopper 1 First disconnecting switch the 2, second disconnecting switch 3 of both sides is all opened, and only has a disconnecting switch between maintenance part and live part Fracture, can not Disintegration overhaul online;GIS disconnecting switch is only external equipment (bus, main transformer etc.) and internal debugging chopper Offer secured electrical is isolated.Along with the raising of device fabrication level, equipment dependability greatly improves, and therefore designs for switch maintenance Chopper both sides disconnecting switch just lose (the most greatly slackening) exist necessity and actual application value.Double mothers Under line section wiring mode, outgoing line side disconnecting switch always exits with chopper simultaneously, puts into operation, only plays and examines into chopper Repair the effect that security isolation is provided.So, the optimization of 220kV double bus scheme transmission line circuit, to safe operation and investment reduction There is very important meaning.
Therefore, those skilled in the art is devoted to develop a kind of 220kV double bus scheme transmission line circuit wiring optimization knot Structure.
Utility model content
Because the drawbacks described above of prior art, technical problem to be solved in the utility model is to provide a kind of 220kV Double bus scheme transmission line circuit wiring optimizes structure, simplifies wiring, reasonable in design, improves equipment dependability, meets main The basic design principle of wiring " reliability is reasonable, and economy is optimum ", it is easy to promote the use of.
For achieving the above object, this utility model provides 220kV double bus scheme transmission line circuit wiring and optimizes structure, wraps Include chopper, the first disconnecting switch, the first inspection earthing switch, high speed grounding switch, voltage transformer, current transformer and keep away Thunder device, the bus bar side of chopper is sequentially connected with the first inspection earthing switch, the first disconnecting switch to bus, the outgoing line side of chopper It is connected with current transformer, high speed grounding switch, voltage transformer, charged display device, spark gap in turn.
As preferably, described new arrangement is when 220kV outlet is without T link, excellent relative to traditional connection type Change and remove the second disconnecting switch of breaker outgoing line side, the second inspection earthing switch, new arrangement by chopper, first keep apart Pass, the first inspection earthing switch, high speed grounding switch, voltage transformer, current transformer, spark gap are suitable according to certain connection Sequence connects composition, and its order of connection is identical with conventional connections.
The beneficial effects of the utility model are:
(1) optimization of new arrangement form eliminates disconnecting switch and the earthed switch of breaker outgoing line side, and each GIS is spaced Equipment investment 20-30 ten thousand yuan can be saved, good in economic efficiency;
(2) this kind of connection type simplifies wiring, improves equipment dependability, meet main electrical scheme run safety, simple and flexible, The basic design principle such as easy to operate.
Below with reference to accompanying drawing, the technique effect of design of the present utility model, concrete structure and generation is made furtherly Bright, to be fully understood from the purpose of this utility model, feature and effect.
Accompanying drawing explanation
Fig. 1 is the circuit diagram of background technology;
Fig. 2 is circuit diagram of the present utility model.
Detailed description of the invention
With reference to Fig. 2, this detailed description of the invention by the following technical solutions:
220kV double bus scheme transmission line circuit wiring optimizes structure, examines including chopper the 1, first disconnecting switch 2, first Repairing earthed switch 4, high speed grounding switch 6, voltage transformer 7, current transformer 8 and spark gap 9, the bus bar side of chopper 1 depends on Secondary connection the first inspection earthing switch the 4, first disconnecting switch 2 to bus 10, it is mutual that the outgoing line side of chopper 1 is connected with electric current in turn Sensor 8, high speed grounding switch 6, voltage transformer 7, charged display device 11, spark gap 9.
This detailed description of the invention is a kind of novel 220kV outlet connection type, when 220kV outlet is without T link, relatively Second disconnecting switch the 3, second inspection earthing switch 5 of chopper 1 outgoing line side, Novel connecting is removed in traditional connection type optimization Line is mutual by chopper the 1, first disconnecting switch the 2, first inspection earthing switch 4, high speed grounding switch 6, voltage transformer 7, electric current Sensor 8, spark gap 9 connect composition according to certain order of connection, and its order of connection is identical with conventional connections.
Connection type after this detailed description of the invention optimizes is as shown in table 1 with the technology comparison of traditional wired form:
Table 1
The wiring of this detailed description of the invention is proved through SSRE-TH software, after cancelling outgoing line side disconnecting switch, and power supply reliability More former scheme improves, result of calculation such as table 2, table 3:
Double bus scheme after table 2 improves contrasts with double bus scheme continuity parameter
Failure-frequency Idle time in year Probability
Double-bus (after optimization) 100% 99.34% 99.34%
Double-bus 100% 100% 100%
Double bus scheme after table 3 improves contrasts with double bus scheme adequacy indexes
EPNS EENS
Double-bus (after optimization) 100% 99.63%
Double-bus 100% 100%
This detailed description of the invention connection type simplifies wiring, and each interval current period can save disconnecting switch 1 group, and ground connection is opened Closing 1 group, this allocation plan meets main electrical scheme " reliability ", " economy ", the requirement of " motility ", has raising equipment reliable Property, save the feature such as overall life cycle cost, meeting main electrical scheme, to run safety, simple and flexible, the Basic Design such as easy to operate former Then, there is wide market application foreground.
Preferred embodiment of the present utility model described in detail above.Should be appreciated that the ordinary skill people of this area Member just can make many modifications and variations according to design of the present utility model without creative work.Therefore, all technology neck In territory, technical staff passes through logical analysis, reasoning or limited reality on the basis of existing technology according to design of the present utility model Test available technical scheme, all should be in the protection domain being defined in the patent claims.

Claims (1)

1. the wiring of 220kV double bus scheme transmission line circuit optimize a structure, including chopper (1), the first disconnecting switch (2), First inspection earthing switch (4), high speed grounding switch (6), voltage transformer (7), current transformer (8) and spark gap (9), its It is characterised by: the bus bar side of chopper (1) is sequentially connected with the first inspection earthing switch (4), the first disconnecting switch (2) to bus (10), the outgoing line side of chopper (1) be connected with in turn current transformer (8), high speed grounding switch (6), voltage transformer (7), Charged display device (11), spark gap (9).
CN201620860091.0U 2016-08-10 2016-08-10 220kV double bus scheme transmission line circuit wiring optimizes structure Expired - Fee Related CN205863657U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620860091.0U CN205863657U (en) 2016-08-10 2016-08-10 220kV double bus scheme transmission line circuit wiring optimizes structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620860091.0U CN205863657U (en) 2016-08-10 2016-08-10 220kV double bus scheme transmission line circuit wiring optimizes structure

Publications (1)

Publication Number Publication Date
CN205863657U true CN205863657U (en) 2017-01-04

Family

ID=57658623

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620860091.0U Expired - Fee Related CN205863657U (en) 2016-08-10 2016-08-10 220kV double bus scheme transmission line circuit wiring optimizes structure

Country Status (1)

Country Link
CN (1) CN205863657U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109856436A (en) * 2019-01-09 2019-06-07 国网上海市电力公司 A kind of electric energy metering device
CN111596204A (en) * 2020-05-11 2020-08-28 中国南方电网有限责任公司超高压输电公司检修试验中心 Alternating current field breaker fracture alternating current withstand voltage test system and method
CN114374218A (en) * 2021-12-14 2022-04-19 中国华能集团清洁能源技术研究院有限公司 High-capacity offshore flexible direct-current power transmission system

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109856436A (en) * 2019-01-09 2019-06-07 国网上海市电力公司 A kind of electric energy metering device
CN111596204A (en) * 2020-05-11 2020-08-28 中国南方电网有限责任公司超高压输电公司检修试验中心 Alternating current field breaker fracture alternating current withstand voltage test system and method
CN111596204B (en) * 2020-05-11 2023-12-12 中国南方电网有限责任公司超高压输电公司检修试验中心 Alternating-current field breaker fracture alternating-current withstand voltage test system and method
CN114374218A (en) * 2021-12-14 2022-04-19 中国华能集团清洁能源技术研究院有限公司 High-capacity offshore flexible direct-current power transmission system

Similar Documents

Publication Publication Date Title
CN205863657U (en) 220kV double bus scheme transmission line circuit wiring optimizes structure
CN103580264A (en) Direct current micro-grid system supplying power in looped network mode
CN104124632B (en) Combined intelligent transformer station
CN211375862U (en) Low-voltage intelligent transformer area fault simulation training device
CN203352172U (en) Auxiliary power wiring structure for large thermal power plant
CN106356905A (en) Alternating-current and direct-current double-bus controllable power transmission system
CN204577857U (en) A kind of 110kV transformer station adopting novel wire connecting way
CN203674797U (en) Station power microgrid main wiring system
CN208078653U (en) Double-bus and single busbar mixing wiring high voltage distribution installation
CN205157669U (en) Special condenser ripple current of flexible direct current transmission detects main circuit
CN204144762U (en) Combined intelligent transformer station
CN205863765U (en) Double bus scheme structure based on disconnecting switch segmentation in GIS power distribution equipment
CN203151087U (en) Lightning-protection and energy-saving power transformer with non-harmful output power
CN110224432A (en) A kind of box-type substation and its microgrid system control method
CN212322505U (en) Intelligent practical training system for live-line replacement of electric energy meter
CN203932698U (en) A kind of single busbar connection dual-breaker sectional wiring structure
CN208890370U (en) Direct current house system
CN201927897U (en) Novel 220kV combined electrical-apparatus secondary line-collecting terminal box
CN203481825U (en) Optimized natural gas distribution-type energy main wiring circuit
CN205985758U (en) Novel electric main wiring of 220kV transformer substation
CN205945072U (en) Intelligence reactive power compensation device
CN205693142U (en) A kind of little bus connecting device of Medium Voltage Switchgear
CN205452937U (en) 330kVGIS distribution device based on four angle scheme
CN205160080U (en) Intelligent low tension circuit of drawer type combination
CN204333626U (en) Standby device is mutually moved back in two-way inlet wire list table metering throwing

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170104

Termination date: 20200810

CF01 Termination of patent right due to non-payment of annual fee