CN205805152U - Tool-type temporary construction fence - Google Patents

Tool-type temporary construction fence Download PDF

Info

Publication number
CN205805152U
CN205805152U CN201620619113.4U CN201620619113U CN205805152U CN 205805152 U CN205805152 U CN 205805152U CN 201620619113 U CN201620619113 U CN 201620619113U CN 205805152 U CN205805152 U CN 205805152U
Authority
CN
China
Prior art keywords
steel pipe
enclosing
temporary construction
tool
construction fence
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620619113.4U
Other languages
Chinese (zh)
Inventor
吴琼
季方
冯金鑫
康在东
马爱民
杨冬冬
毕研朋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai No 7 Construction Co Ltd
Original Assignee
Shanghai No 7 Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai No 7 Construction Co Ltd filed Critical Shanghai No 7 Construction Co Ltd
Priority to CN201620619113.4U priority Critical patent/CN205805152U/en
Application granted granted Critical
Publication of CN205805152U publication Critical patent/CN205805152U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

This utility model provides a kind of tool-type temporary construction fence, and by scaffold support system, including the horizontal steel pipe interconnected and longitudinal steel pipe, described longitudinal steel pipe support is in ground;Hang over the enclosing module on described horizontal steel pipe, described enclosing module includes rectangle enclosing framework, the zinc-plated sheet iron being fixed on described enclosing framework side and is fixed on the hook of described enclosing framework opposite side, the quantities that this utility model can overcome prior art to exist is relatively big, assembling bothers and the problem of component poor universality, have the most prefabricated processing, set up convenient and swift, good endurance, the outward appearance coordinating and unifying, elegant in appearance, securely, effective shorten enclosing construction period, reduce construction cost, can the advantage such as recycling.

Description

Tool-type temporary construction fence
Technical field
This utility model relates to a kind of tool-type temporary construction fence.
Background technology
Temporary construction fence generally uses masonry panel, short for the duration, and construction surrounding is complicated, and construction image requires high Engineering, compared with tool-type temporary construction fence, there is long construction period in traditional brick enclosure wall, and operating expenses is big, constructs not convenient Shortcoming.Short for some durations, construction image requires that height, tradition temporary construction fence cannot meet construction requirement, need to use novel Construction method.
Utility model content
The purpose of this utility model is to provide a kind of tool-type temporary construction fence, it is possible to overcome the engineering that prior art exists Amount is relatively big, assembling bothers and the problem of component poor universality.
For solving the problems referred to above, this utility model provides a kind of tool-type temporary construction fence, including:
Scaffold support system, including the horizontal steel pipe interconnected and longitudinal steel pipe, described longitudinal steel pipe support is in ground Face;
Hang over the enclosing module on described horizontal steel pipe, described enclosing module include rectangle enclosing framework, be fixed on described The zinc-plated sheet iron of enclosing framework one side and be fixed on the hook of described enclosing framework another side.
Further, in above-mentioned tool-type temporary construction fence, described scaffold support system uses the steel pipe of diameter 48mm Set up.
Further, in above-mentioned tool-type temporary construction fence, described enclosing framework is welded by the zinc-plated square tube of 40 × 40 × 2mm Connecing and form, the width of enclosing framework is 1250mm, and height is 2500mm, sets according to 800mm spacing in enclosing frame height direction It is equipped with twice stull.
Further, in above-mentioned tool-type temporary construction fence, the size of described zinc-plated sheet iron is 1250 × 2500mm, thickness Degree is 0.7mm.
Further, in above-mentioned tool-type temporary construction fence, described hook is No. 65 zinc-plated channel-section steels.
Further, in above-mentioned tool-type temporary construction fence, described scaffold support system scaffolding height 2100~ Between 2300mm, longitudinal steel pipe is 700~1000mm in the spacing of the width of temporary construction fence, and longitudinal steel pipe is at temporary construction fence The spacing of length direction is 800~1000mm.
Further, in above-mentioned tool-type temporary construction fence, also include described hook together with horizontal steel pipe colligation Steel wire rope.
Compared with prior art, this utility model pass through scaffold support system, including interconnect horizontal steel pipe and Longitudinal steel pipe, described longitudinal steel pipe support is in ground;Hanging over the enclosing module on described horizontal steel pipe, described enclosing module includes Rectangle enclosing framework, it is fixed on the zinc-plated sheet iron of described enclosing framework side and is fixed on the extension of described enclosing framework opposite side Hook, enclosing module can be assembled in the most prefabricated, field, and processing and fabricating outside the venue, standardization and tool degree are high, scaffold support body After system puts up, directly enclosing module can be hung over by described hook the horizontal steel pipe of scaffold support system, it addition, according to The length of scaffold support system, hangs over scaffold support body by polylith enclosing module according to the length direction of scaffold support system Fastening, ultimately form temporary construction fence, the most zinc-plated sheet iron, in the outside of temporary construction fence, plays the effect with external environment, foot Hand cradle support system is positioned at the inner side of temporary construction fence, plays the effect of support, and this utility model can overcome prior art to exist Quantities is relatively big, assembling trouble and the problem of component poor universality, have the most prefabricated processing, set up convenient and swift, durable Property good, the outward appearance coordinating and unifying, elegant in appearance, securely, effective shorten enclosing construction period, reduce construction cost, energy The advantages such as recycling.
Accompanying drawing explanation
Fig. 1 is the structure chart of the tool-type temporary construction fence of the present utility model of this utility model one embodiment;
Fig. 2 is the structure chart of the scaffold support system of this utility model one embodiment;
Fig. 3 is the side view of the enclosing module of this utility model one embodiment;
Fig. 4 is the front view of the enclosing module of this utility model one embodiment;
Fig. 5 is the installation procedure figure of the tool-type temporary construction fence of this utility model one embodiment.
Detailed description of the invention
Understandable for enabling above-mentioned purpose of the present utility model, feature and advantage to become apparent from, below in conjunction with the accompanying drawings and tool This utility model is described in further detail by body embodiment.
As shown in Figures 1 to 4, this utility model provides a kind of tool-type temporary construction fence, including:
Scaffold support system 1, including the horizontal steel pipe 2 interconnected and longitudinal steel pipe 3, described longitudinal steel pipe 3 supports In ground;
Hanging over the enclosing module 4 on described horizontal steel pipe 2, described enclosing module 4 includes rectangle enclosing framework 5, is fixed on The zinc-plated sheet iron 6 of described enclosing framework 5 one side and be fixed on the hook 7 of described enclosing framework 5 another side.Concrete, enclosing Module can be assembled in the most prefabricated, field, and processing and fabricating outside the venue, standardization and tool degree are high, and scaffold support system is built After Hao, directly enclosing module can be hung over by described hook the horizontal steel pipe of scaffold support system, it addition, according to scaffold The length of support system, hangs on scaffold support system by polylith enclosing module according to the length direction of scaffold support system, Ultimately forming temporary construction fence, the most zinc-plated sheet iron, in the outside of temporary construction fence, plays the effect with external environment, and scaffold props up Support body system is positioned at the inner side of temporary construction fence, plays the effect of support, and this utility model can overcome the engineering that prior art exists Amount is relatively big, assembling trouble and the problem of component poor universality, has the most prefabricated processing, sets up convenient and swift, good endurance, outer See the coordinating and unifying, elegant in appearance, securely, effective shorten enclosing construction period, reduce construction cost, can reuse Etc. advantage.
Preferably, described scaffold support system uses the steel pipe of diameter 48mm to set up.Concrete, scaffold support system φ 48mm steel pipe is used to set up, it is ensured that its supporting degree.
Preferably, as it is shown on figure 3, described enclosing framework is formed by the zinc-plated square tubes soldering of 40 × 40 × 2mm, enclosing framework Width be 1250mm, height be 2500mm, in enclosing frame height direction, 800mm spacing is provided with twice stull, guarantor The fastness of card enclosing framework.
Preferably, the size of described zinc-plated sheet iron be 1250 × 2500mm, thickness be 0.7mm.Concrete, zinc-plated thin ferrum Plate is welded on the outside of enclosing framework.After temporary construction fence has been set up, outside zinc-plated sheet iron, extension advertising cloth or poster can be pasted Deng ornament materials.
Preferably, described hook is No. 65 zinc-plated channel-section steels, concrete, as shown in Figures 2 and 3, can be inside enclosing framework on Respectively it is welded in 90mm width at lower two as hook, directly hangs on the horizontal steel pipe in steel pipe scaffold support system, such as Fig. 1 Shown in, it is possible to inside enclosing framework, at upper, middle and lower three, respectively weld hook.
Preferably, described scaffold support system scaffolding height is between 2100~2300mm, and longitudinal steel pipe encloses temporarily The spacing of width of gear is 700~1000mm, longitudinal steel pipe the spacing of temporary construction fence length direction be 800~ 1000mm.Concrete, enclosing scaffold building, use φ 48mm steel pipe to set up, scaffolding height preferably controls 2100~2300mm Between, set up width 700~1000mm, standpipe spacing 800~1000mm.Set up width 700~1000mm, foot can not only be prevented Hand cradle support system topples, and it is the biggest to be avoided that scaffold support system takes up an area.
Preferably, fixing described hook and the steel wire rope of horizontal steel pipe are also included.
Detailed, as it is shown in figure 5, the installation method of above-mentioned tool-type temporary construction fence is as follows:
Step S1, before temporary construction fence is set up, survey crew is to owner and the red line of local mapping administration section offer and has Effect beasurement base carries out repetition measurement, after the poor demand limit of corresponding points position, lays the horizontal control network of temporary construction fence;
Step S2, carries out the levelling construction of construction site in horizontal control network, foundation construction;
Step S3, sets up scaffold support system 1 in described construction site;Use φ 48mm steel pipe to set up, set up height Degree preferably controls between 2100~2300mm, sets up width 700~1000mm, standpipe spacing 800~1000mm;
Step S4, on construction ground outside processing factory in, some enclosing modules 4 are machined, and be transported to construction Place;
Step S5, is hung over each enclosing module 4 on the horizontal steel pipe of described scaffold support system by hook.
Preferably, step S5, each enclosing module is hung over by hook the horizontal steel pipe of described scaffold support system On step after, also include:
Step S6, use steel wire rope by described hook 7 together with the colligation of horizontal steel pipe 2, thus ensure described hook and Laterally the connection between steel pipe is more reliable.
Preferably, step S5, each enclosing module is hung over by hook the horizontal steel pipe of described scaffold support system On step after, also include:
Outside the zinc-plated sheet iron of enclosing module, hang up advertising cloth or catch-phrase, whole temporary construction fence can be made attractive in appearance Generous.
Preferably, step S5, each enclosing module is hung over by hook the horizontal steel pipe of described scaffold support system On step after, also include:
Use horizontal steel tube that with the fixture in temporary construction fence, scaffold support system is carried out reliable drawknot, it is ensured that whole The stability of temporary construction fence, the fixture in described temporary construction fence can be building or trees.
Preferably, step S5, each enclosing module is hung over by hook the horizontal steel pipe of described scaffold support system On step after, also include:
Scaffold support system away from described zinc-plated sheet iron side stack weight.If here, horizontal drawknot is more difficult Realize, it is possible to stack weight in the inner side of scaffold support system, in case enclosing entirety is toppled.
In sum, this utility model passes through scaffold support system, including the horizontal steel pipe interconnected and longitudinal steel Pipe, described longitudinal steel pipe support is in ground;Hanging over the enclosing module on described horizontal steel pipe, described enclosing module includes rectangle Keep off framework, be fixed on the zinc-plated sheet iron of described enclosing framework side and be fixed on the hook of described enclosing framework opposite side, enclose Gear module can be assembled in the most prefabricated, field, and processing and fabricating outside the venue, standardization and tool degree are high, and scaffold support system is taken After building up, directly enclosing module can be hung over by described hook the horizontal steel pipe of scaffold support system, it addition, according to foot hands The length of frame support system, hangs over scaffold support system by polylith enclosing module according to the length direction of scaffold support system On, ultimately forming temporary construction fence, the most zinc-plated sheet iron, in the outside of temporary construction fence, plays the effect with external environment, foot hands Frame support system is positioned at the inner side of temporary construction fence, plays the effect of support, and this utility model can overcome prior art to exist Quantities is relatively big, assembling bothers and the problem of component poor universality, has the most prefabricated processing, sets up convenient and swift, durability Good, the outward appearance coordinating and unifying, elegant in appearance, securely, effective shorten enclosing construction period, reduce construction cost, can be heavily The advantages such as multiple utilization.
In this specification, each embodiment uses the mode gone forward one by one to describe, and what each embodiment stressed is and other The difference of embodiment, between each embodiment, identical similar portion sees mutually.
Obviously, those skilled in the art can carry out various change and modification without deviating from this practicality newly to utility model The spirit and scope of type.So, if of the present utility model these amendment and modification belong to this utility model claim and Within the scope of equivalent technologies, then this utility model is also intended to change and including modification include these.

Claims (10)

1. a tool-type temporary construction fence, it is characterised in that including:
Scaffold support system, including the horizontal steel pipe interconnected and longitudinal steel pipe, described longitudinal steel pipe support is in ground;
Hanging over the enclosing module on described horizontal steel pipe, described enclosing module includes rectangle enclosing framework, is fixed on described enclosing The zinc-plated sheet iron of framework one side and be fixed on the hook of described enclosing framework another side.
2. tool-type temporary construction fence as claimed in claim 1, it is characterised in that described scaffold support system uses diameter The steel pipe of 48mm is set up.
3. tool-type temporary construction fence as claimed in claim 1, it is characterised in that described enclosing framework is by 40 × 40 × 2mm's Zinc-plated square tubes soldering forms.
4. tool-type temporary construction fence as claimed in claim 1, it is characterised in that the width of described enclosing framework is 1250mm, It is highly 2500mm, in enclosing frame height direction, 800mm spacing is provided with twice stull.
5. tool-type temporary construction fence as claimed in claim 1, it is characterised in that the size of described zinc-plated sheet iron is 1250 × 2500mm, thickness are 0.7mm.
6. tool-type temporary construction fence as claimed in claim 1, it is characterised in that described hook is No. 65 zinc-plated channel-section steels.
7. tool-type temporary construction fence as claimed in claim 1, it is characterised in that described scaffold support system scaffolding height exists Between 2100~2300mm.
8. tool-type temporary construction fence as claimed in claim 1, it is characterised in that described longitudinal steel pipe is at the width of temporary construction fence The spacing in direction is 700~1000mm.
9. tool-type temporary construction fence as claimed in claim 1, it is characterised in that described longitudinal steel pipe is in temporary construction fence length side To spacing be 800~1000mm.
10. the tool-type temporary construction fence as described in any one of claim 1 to 9, it is characterised in that also include described hook and Laterally steel pipe colligation steel wire rope together.
CN201620619113.4U 2016-06-22 2016-06-22 Tool-type temporary construction fence Expired - Fee Related CN205805152U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620619113.4U CN205805152U (en) 2016-06-22 2016-06-22 Tool-type temporary construction fence

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620619113.4U CN205805152U (en) 2016-06-22 2016-06-22 Tool-type temporary construction fence

Publications (1)

Publication Number Publication Date
CN205805152U true CN205805152U (en) 2016-12-14

Family

ID=57505331

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620619113.4U Expired - Fee Related CN205805152U (en) 2016-06-22 2016-06-22 Tool-type temporary construction fence

Country Status (1)

Country Link
CN (1) CN205805152U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106088808A (en) * 2016-06-22 2016-11-09 上海建工七建集团有限公司 Tool-type temporary construction fence and installation method thereof
CN107119980A (en) * 2017-05-18 2017-09-01 无锡市汤成机电配件厂 Carry the enclosure of buildings plate of function landing slab

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106088808A (en) * 2016-06-22 2016-11-09 上海建工七建集团有限公司 Tool-type temporary construction fence and installation method thereof
CN107119980A (en) * 2017-05-18 2017-09-01 无锡市汤成机电配件厂 Carry the enclosure of buildings plate of function landing slab

Similar Documents

Publication Publication Date Title
CN102433955B (en) Assembling prefabricated light steel composite load-bearing wall panel
CN204126230U (en) Assembly scaffold unit
US20160168844A1 (en) Structural Arrangement
CN104847020A (en) Limb type circular tube node transferring structure and manufacturing method thereof
CN205805152U (en) Tool-type temporary construction fence
CN205444984U (en) Pin -connected panel sanitation room
CN203961021U (en) A kind of prefabricated panel and precast beam rapid installing connection structure
CN106088808A (en) Tool-type temporary construction fence and installation method thereof
CN104372923B (en) Scaffolding
CN103541733A (en) Shield vertical shaft assembling type concrete-filled steel tube inner support system and construction method thereof
CN103255837B (en) A kind of removable modular combination room
CN204626657U (en) The syndeton of house brace summer
CN107558608B (en) Lattice steel frame connecting node and construction method
CN102561731B (en) Module constructed one-layer villa and construction method thereof
CN206769085U (en) A kind of wall connecting point structure of assembled architecture
CN203034615U (en) Novel outer sleeve tube type connecting node of cold-bending rectangular steel tube column and H-shaped steel girder
CN205637139U (en) Support flat push formula multicavity steel pipe -concrete composite post braced frame system
CN206722155U (en) A kind of attachment structure of modular aluminum facade
CN205557825U (en) Novel steel construction bracket and steel structure support structure
CN105909006A (en) Prefabricated splicing-combined transformer substation
CN206846097U (en) A kind of Men Gangyu frameworks separately-loaded pipeline support structure
CN206376514U (en) Tool climbing scaffold
CN207484792U (en) A kind of metal wire casing
CN105544896A (en) Outdoor stair for double-layer portable house
CN105040897B (en) A kind of assembled house wallboard produces installation method and wallboard connecting structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161214