CN205688412U - Wall arrangement structure is led to power station factory building tailrace - Google Patents
Wall arrangement structure is led to power station factory building tailrace Download PDFInfo
- Publication number
- CN205688412U CN205688412U CN201620528411.2U CN201620528411U CN205688412U CN 205688412 U CN205688412 U CN 205688412U CN 201620528411 U CN201620528411 U CN 201620528411U CN 205688412 U CN205688412 U CN 205688412U
- Authority
- CN
- China
- Prior art keywords
- wall
- guide wall
- tailrace
- channel
- power station
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 16
- 239000004576 sand Substances 0.000 claims abstract description 9
- 238000006424 Flood reaction Methods 0.000 claims description 2
- 239000004575 stone Substances 0.000 abstract description 5
- 239000003818 cinder Substances 0.000 abstract description 3
- 239000013049 sediment Substances 0.000 abstract description 2
- 230000000903 blocking effect Effects 0.000 abstract 2
- 238000010248 power generation Methods 0.000 abstract 1
- 239000011435 rock Substances 0.000 description 11
- 238000010276 construction Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 241000628997 Flos Species 0.000 description 1
- 230000001934 delay Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000002893 slag Substances 0.000 description 1
- 238000011144 upstream manufacturing Methods 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
- 238000001363 water suppression through gradient tailored excitation Methods 0.000 description 1
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Revetment (AREA)
Abstract
The utility model discloses a wall arrangement structure is led to power station factory building tailrace. The hydropower station workshop tail water channel is positioned on one side of the river channel (6), and a water outlet of the tail water channel is communicated with the river channel; a left guide wall (2) and a right guide wall (3) are respectively arranged on two sides of the tail water channel, a bottom plate (1) is arranged at the bottom between the left guide wall and the right guide wall, and a sand blocking bank (4) is arranged at a water outlet of the bottom plate; a guide wall (5) is arranged in the river channel, an azimuth angle theta is arranged between the guide wall and the sand blocking ridge, and one end of the guide wall is connected with the left guide wall. The utility model discloses mainly be applied to among the long diversion shore formula factory building tailrace building in hilly area, the utility model discloses a structure can not the high low reaches water level of harmony, and then does not influence the unit and exert oneself, and has reached the purpose that prevents the ballast from getting into the tailrace. Can effectively reduce the stone sediment that gets into in the tailrace to reduce the number of times of scarfing cinder in the tailrace, directly reduce the running cost in power station, the indirect power generation benefit that increases the power station.
Description
Technical field
This utility model relates to a kind of powerhouse of hydropower station tailwater channel and leads wall arrangement, belongs to hilly ground head of district's diversion bank
Formula power plant building tailwater channel arranges technical field.
Background technology
River, knob typically uses cascade development mode to utilize waterpower resourses, in order to make full use of head, and power plant
Room tail water mainly considers to be connected with lower reservoir reservoir level, and for not affecting power benefit, tailwater channel sediment trapping bank height will be less than half
Platform machine generating tailwater level, the effect intercepting riverbed rock ballast is limited.
For hilly ground head of district's diversion power house along river bank, between factory dam, in river course, section, isolated block stone is more, and side slope mostly is heap
Long-pending body, construction waste and construction disturbance cause the loosest rock ballast to roll in river course.The several years ago dam inter-plant gone into operation in power station
Rock ballast in river course is extremely difficult to stable, and during dam flood-discharge in flood season, flood carries the loose rock ballast such as substantial amounts of boulder, block stone and enters
Entering tail water river course, owing to tail water river course width delays, part boulder, block stone can not be washed away by flood, cause rock ballast to deposit at tail water
In canal and outlet section downstream river course thereof, and the rock ballast deposited in tailwater channel is relatively big due to tailwater channel base plate counter-slope, its interior stone
Slag rolls under the effect of generating current in tailwater channel, collision tailwater channel and tail water gate pier, damages structure, time serious
Have to close unit tailwater channel is repaired, affect unit generation and cause electric quantity loss.
Summary of the invention
The purpose of this utility model is, it is provided that a kind of powerhouse of hydropower station tailwater channel leads wall arrangement.To reduce entrance
Rock ballast in tailwater channel, thus reduce tailwater channel and gate pier structural damage, reduce the frequency that power station scarfing cinder is shut down, reach to carry
The purpose of high power station economic benefit.
The technical solution of the utility model:
A kind of powerhouse of hydropower station tailwater channel leads wall arrangement, and described powerhouse of hydropower station tailwater channel is positioned at side, river course, tail
The outlet of water channel communicates with river course;Tailwater channel is respectively provided on two sides with left guide wall and the right side is led wall, left guide wall and the right side and led between wall
Bottom is provided with base plate, and the water outlet of base plate is provided with and blocks sand bank;It is provided with in river course and leads wall, lead wall and block and be provided with orientation between sand bank
Angle θ, leads wall one end and is connected with left guide wall.
In aforementioned structure, described in lead wall height be not less than 5 years or 10 years one meet flood time tailwater level elevation.
In aforementioned structure, described in lead wall length less than or equal to tailwater channel width 1/2.
In aforementioned structure, described in lead the azimuth angle theta of wall less than 45 °.
Compared with prior art, this utility model is mainly used in hilly ground head of district's diversion power house along river bank tailwater channel building
In thing, structure of the present utility model will not the harmony high level of tail water, and then do not affect unit output, and reached to prevent rock ballast from entering
The purpose of tailwater channel.It is effectively reduced the rock ballast entered in tailwater channel, thus the number of times of scarfing cinder in reducing tailwater channel, directly reduce
The operating cost in power station, indirectly increases the power benefit in power station.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
Being labeled as in figure: 1 base plate, 2 left guide wall, 3 right sides lead wall, and 4 block sand bank, and 5 lead wall, 6 river courses.
Detailed description of the invention
The utility model is described in further detail with embodiment below in conjunction with the accompanying drawings, but not as new to this practicality
Any restriction of type.
A kind of powerhouse of hydropower station tailwater channel leads wall arrangement, as it is shown in figure 1, powerhouse of hydropower station tailwater channel is positioned at river course 6
Side, the outlet of tailwater channel communicates with river course 6;Tailwater channel is respectively provided on two sides with left guide wall 2 and wall 3 is led on the right side, and left guide wall 2 is with right
Leading the bottom between wall 3 and be provided with base plate 1, the water outlet of base plate 1 is provided with and blocks sand bank 4;Be provided with in river course 6 and lead wall 5, lead wall 5 with
Block and be provided with azimuth angle theta between sand bank 4, lead wall 5 one end and be connected with left guide wall 2.Lead wall 5 and be highly not less than 5 years or 10 years one chance floods
Tailwater level elevation during water.Lead wall 5 length less than or equal to the 1/2 of tailwater channel width.Lead the azimuth angle theta of wall 5 less than 45 °.
Embodiment
This example is as a example by Flos Caryophylli water power station and hair man Hydropower Station.When wall is led in setting, lead wall height with bed load not
Can enter, part suspended load can enter tailwater channel and occupies the principle layout that trade culture is few, it is proposed that uses 5 years one chances or 10
Year one meets flood tailwater level elevation as leading wall rational height.Leading wall length with tailwater channel upstream side barricade as starting point, terminal is pressed
According to build lead wall after do not affect tail water go out stream, rock ballast breach the most downstream roll into tailwater channel be principle, it is proposed that lead wall length little
In or 1/2 being advisable equal to tailwater channel width.Lead wall grid azimuth θ according to lead after wall is built can water conservancy diversion tail the most smoothly
Water enters river course 6, i.e. to reduce the Yong Shuiwei impact on unit generation, the principle occupying river course flood discharge section that again can not be too much
It is arranged.
Arrange that leading wall can reach and do not affecting the premise that power station unit is exerted oneself by above arrangement principle in tailwater channel outer
Under, reduce the purpose of the rock ballast entering tailwater channel.
Claims (4)
1. powerhouse of hydropower station tailwater channel leads a wall arrangement, and described powerhouse of hydropower station tailwater channel is positioned at river course (6) side, tail
The outlet of water channel communicates with river course (6);It is characterized in that: tailwater channel is respectively provided on two sides with left guide wall (2) and wall (3) is led on the right side,
Left guide wall (2) and the right side are led the bottom between wall (3) and are provided with base plate (1), and the water outlet of base plate (1) is provided with and blocks sand bank (4);River course
(6) it is provided with in and leads wall (5), lead wall (5) and block and be provided with azimuth angle theta between sand bank (4), lead wall (5) one end with left guide wall (2) even
Connect.
Structure the most according to claim 1, it is characterised in that lead wall (5) described in: and be highly not less than 5 years or 10 years one chance floods
Time tailwater level elevation.
Structure the most according to claim 2, it is characterised in that lead wall (5) length described in: less than or equal to tailwater channel width
1/2。
Structure the most according to claim 3, it is characterised in that lead the azimuth angle theta of wall (5) described in: less than 45 °.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620528411.2U CN205688412U (en) | 2016-06-02 | 2016-06-02 | Wall arrangement structure is led to power station factory building tailrace |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620528411.2U CN205688412U (en) | 2016-06-02 | 2016-06-02 | Wall arrangement structure is led to power station factory building tailrace |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205688412U true CN205688412U (en) | 2016-11-16 |
Family
ID=57261405
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620528411.2U Active CN205688412U (en) | 2016-06-02 | 2016-06-02 | Wall arrangement structure is led to power station factory building tailrace |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205688412U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110131089A (en) * | 2019-05-17 | 2019-08-16 | 天津天发总厂机电设备有限公司 | Power station tail water cyclic utilization system |
CN117230819A (en) * | 2023-07-27 | 2023-12-15 | 中国水利水电第三工程局有限公司 | Hydropower station factory building foundation pit under stage cofferdam diversion working condition and tail water channel construction method thereof |
-
2016
- 2016-06-02 CN CN201620528411.2U patent/CN205688412U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110131089A (en) * | 2019-05-17 | 2019-08-16 | 天津天发总厂机电设备有限公司 | Power station tail water cyclic utilization system |
CN110131089B (en) * | 2019-05-17 | 2024-02-13 | 天津天发总厂机电设备有限公司 | Tail water recycling system of power station |
CN117230819A (en) * | 2023-07-27 | 2023-12-15 | 中国水利水电第三工程局有限公司 | Hydropower station factory building foundation pit under stage cofferdam diversion working condition and tail water channel construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204112294U (en) | Dual channel formula flow velocity controlled ecological fish pass | |
CN103410130A (en) | Multi-purpose tunnel arrangement structure | |
CN103882838A (en) | Sediment releasing method for water intake of low-head river channel pivotal power station | |
CN203256706U (en) | Underflow energy dissipation structure of broken slope in hydraulic and hydroelectric projects | |
CN101294380A (en) | Secondary continuous step generator of hydraulic power plant | |
CN112281770A (en) | Flood discharge structure adopting bottom hole and surface hole combined flood discharge and energy dissipation | |
CN205688412U (en) | Wall arrangement structure is led to power station factory building tailrace | |
CN103882839A (en) | Sediment releasing system for water intake of low-head river channel pivotal power station | |
CN203021973U (en) | Sand intercepting groove | |
KR101419520B1 (en) | Hydro power generating apparatus using additional dam installed in upper stream of watercourse and control method thereof | |
CN204875721U (en) | Diversion tunnel outlet energy dissipation device | |
CN103290804A (en) | Method and structure for providing downstream ecological flow after gate locking of stream guidance water release structure | |
CN104099909B (en) | Based on the flood discharge generating sync energy dissipater of flood-discharge tunnel | |
CN204491545U (en) | The sediment outflow structure of tailrace | |
CN204023523U (en) | Internal gate valve chamber structure of dam body | |
CN206752427U (en) | A kind of power station ground power house tailrace outlet structure and its power station | |
CN104099908B (en) | Gravity type sand obstructing and guiding structure | |
CN107893406B (en) | Diversion tunnel group lower brake plugging program | |
CN103114565B (en) | River-closure water-diversion system suitable for slope torrent watercourse water-diversion generation and hydropower stations | |
CN102352617B (en) | Bulb-tubular hydropower station plant diverting constructing method | |
CN104775964A (en) | Splitting type water turbine chamber | |
CN211849316U (en) | Ecological flow facility of formula power station behind dam of compromise benefit and monitoring demand | |
CN108360472A (en) | Sluice " L " type trash rack pier and its " zigzag " arrangement | |
CN205662903U (en) | Water conservancy diversion water -retaining structure that by stages sluices | |
CN203393688U (en) | Multipurpose tunnel arrangement structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |