CN205678675U - Rubbish energy-conserving and environment-protective pyrolysis installation - Google Patents

Rubbish energy-conserving and environment-protective pyrolysis installation Download PDF

Info

Publication number
CN205678675U
CN205678675U CN201620149364.0U CN201620149364U CN205678675U CN 205678675 U CN205678675 U CN 205678675U CN 201620149364 U CN201620149364 U CN 201620149364U CN 205678675 U CN205678675 U CN 205678675U
Authority
CN
China
Prior art keywords
water pipe
ash chute
conserving
protective
environment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620149364.0U
Other languages
Chinese (zh)
Inventor
李启仁
曹文波
明永刚
舒志强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SINOBIOWAY ENVIRONMENTAL GROUP Co Ltd
Original Assignee
SINOBIOWAY ENVIRONMENTAL GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SINOBIOWAY ENVIRONMENTAL GROUP Co Ltd filed Critical SINOBIOWAY ENVIRONMENTAL GROUP Co Ltd
Application granted granted Critical
Publication of CN205678675U publication Critical patent/CN205678675U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Processing Of Solid Wastes (AREA)
  • Gasification And Melting Of Waste (AREA)

Abstract

The utility model discloses a kind of rubbish energy-conserving and environment-protective pyrolysis installation.In order to overcome conventional garbage pyrolysis installation ash discharge not smooth, easily blocking, affect quality, the efficiency of incineration firing, the high deficiency of operation maintenance cost, the utility model is provided with at least two water pipes passing through this pyrolysis chamber connection water cavity in described pyrolysis chamber, is provided with wind chamber the above of this water pipe or outside, is provided with ash chute in the lower section of this water pipe, the two ends of this ash chute have ash hole, are provided with cinder conveyer structure at described ash chute.The utility model is pyrolyzed for waste incineration, it can make incineration firing ash discharge smooth and easy, be conducive to that the links such as garbage pre-heating, drying, burning, sinking ash discharge is smooth and easy, stable, equilibrium, persistently, desirably prevent waste incineration and produce the harmful substances such as two English, the follow-up harmless treatment making cigarette, vapour, water, ash that garbage pre-heating drying and incinerating produces etc. is easy, operation maintenance cost can be significantly reduced, improve efficiency, the benefit of refuse pyrolysis.

Description

Rubbish energy-conserving and environment-protective pyrolysis installation
Technical field
The utility model relates to a kind of garbage harmless processing means, is specially a kind of rubbish energy-conserving and environment-protective pyrolysis installation.
Background technology
The processing method of conventional garbage has burning pyrolysis, concentrates landfill etc..Landfill is concentrated to need the arable land taking many, thus Most countries is pyrolyzed waste incineration as main garbage harmless processing method.
Waste incineration pyrolytic process requires height to pyrolysis installation.The weak point of conventional garbage pyrolysis installation is: monolateral go out Ash, ash discharge is smooth, easily blocks, and affect the continuation of incineration firing, stability, harmony, not only increases operation maintenance one-tenth This, and easily produce the harmful substances such as two English, makes the follow-up nothing of cigarette, vapour, water, ash etc. that garbage pre-heating drying and incinerating produces Evilization intractability increases, and efficiency reduces, and cost increases.
Utility model content
The purpose of this utility model is aiming at above-mentioned deficiency, provides a kind of rubbish energy-conserving and environment-protective pyrolysis installation, and it can Make incineration firing ash discharge smooth and easy, beneficially the links such as garbage pre-heating, drying, burning, sinking ash discharge smooth and easy, stable, equilibrium, Continue, desirably prevent waste incineration and produce the harmful substance such as two English, make cigarette, vapour, water that garbage pre-heating drying and incinerating produces, The follow-up harmless treatment of ash etc. is easy, can significantly reduce operation maintenance cost, improves efficiency, the benefit of refuse pyrolysis.
For reaching above-mentioned purpose, the technical solution of the utility model is, this rubbish energy-conserving and environment-protective pyrolysis installation, including have The pyrolysis chamber of rubbish input mechanism, is provided with water cavity in the outside in this pyrolysis chamber, is provided with at least two in described pyrolysis chamber and passes through this The water pipe of pyrolysis chamber connection water cavity, is provided with the wind chamber with air inlet, air outlet, at this above of this water pipe or outside The lower section of water pipe or ash chute is arranged below.
The two ends of described ash chute have ash hole, are provided with cinder conveyer structure at described ash chute.
The two ends of described ash chute have ash hole, are provided with spiral conveying mechanism in described ash chute, this spiral transferring Mechanism is sent to have the contrary flight of conveying direction.
Axially axial consistent with water pipe of described ash chute.
The cell wall of described ash chute is connected with water pipe, at the water pipe being arranged over connection water cavity of described ash chute.
The cell wall of described ash chute is connected with the following of water pipe.
The cell wall of described ash chute is connected with the sidewall of water pipe.
Described water pipe interval is arranged, and the two ends of described ash chute have ash hole, are provided with spiral in described ash chute Conveying mechanism, this spiral conveying mechanism has the contrary flight of conveying direction.
Axially axial consistent with water pipe of described ash chute, the cell wall of described ash chute is connected with water pipe, described ash discharge The bottom land of groove is positioned at the lower section at the interval of water pipe or water pipe.
Described water pipe interval is arranged, and is communicated with apoplexy chamber between wind chamber at the middle part at the interval of described each water pipe, between being somebody's turn to do Apoplexy chamber middle air outlet between having.
Comparing with prior-art devices, the utility model is provided with wind chamber the above of spaced water pipe, between described Being provided with ash chute every the lower section of the water pipe arranging or water pipe interval, the two ends of this ash chute are respectively provided with ash hole, described Being provided with spiral conveying mechanism in ash chute, this spiral conveying mechanism has the contrary flight of conveying direction, described ash chute Cell wall (sidewall) be connected with water pipe, be communicated with apoplexy chamber between wind chamber at the middle part at the interval of described each water pipe, should between in Wind chamber middle air outlet between having, enables the utility model smooth and easy equilibrium persistently air-supply oxygen supply, the unobstructed efficient ash discharge in two sides, preferably Achieve the utility model purpose.
The utility model is pyrolyzed for waste incineration, and it can make incineration firing ash discharge smooth and easy, beneficially garbage pre-heating, dry The links such as dry, burning, sinking ash discharge are smooth and easy, stable, equilibrium, continue, and desirably prevent waste incineration and produce two English etc. Harmful substance, the follow-up harmless treatment making cigarette, vapour, water, ash etc. that garbage pre-heating drying and incinerating produces is easy, can significantly drop Low operation maintenance cost, improves efficiency, the benefit of refuse pyrolysis.
Brief description
Fig. 1 is the utility model cross-sectional schematic.
In figure, 1. be pyrolyzed chamber, 2. water cavity, 3. water pipe, 4. wind chamber, 5. ash chute, 6. spiral conveying mechanism, 7. between Apoplexy chamber, 8. between middle air outlet.
Detailed description of the invention
As it is shown in figure 1, the utility model rubbish energy-conserving and environment-protective pyrolysis installation, including there is the pyrolysis chamber of rubbish input mechanism 1, it is provided with water cavity 2 in the outside in this pyrolysis chamber 1, be provided with at least two in described pyrolysis chamber 1 and connect water cavity 2 through this pyrolysis chamber 1 Water pipe 3, be provided with the wind chamber 4 with air inlet, air outlet the above of this water pipe 3 or outside, in the lower section of this water pipe 3 Or ash chute 5 is arranged below.This ash chute can be upper uncovered square or arc.This is simple a kind of embodiment party Formula.
Based on above-mentioned another embodiment, the two ends of described ash chute 5 have ash hole, set at described ash chute 5 There is cinder conveyer structure, can be by the middle part of ash chute 5 to the ash hole ash-slag delivery at its two ends.
Further, the two ends of described ash chute 5 have ash hole, are provided with spiral conveying mechanism in described ash chute 5 6, this spiral conveying mechanism 6 has the contrary flight of conveying direction.Axially axial consistent with water pipe 3 of described ash chute 5. The cell wall of described ash chute 5 is connected with water pipe 3, at the water pipe 3 being arranged over connection water cavity 2 of described ash chute 5.
Further, the cell wall of described ash chute 5 is connected with the following of water pipe 3.
Another kind is, the cell wall of described ash chute 5 is connected with the sidewall of water pipe 3.
Based on above-mentioned another kind of enforcement, described water pipe 3 interval is arranged, and the two ends of described ash chute 5 have ash hole, Being provided with spiral conveying mechanism 6 in described ash chute 5, this spiral conveying mechanism 6 has the contrary flight of conveying direction, permissible By the middle part of ash chute 5 to the ash hole ash-slag delivery at its two ends.Axially axial consistent with water pipe 3 of described ash chute 5, institute The cell wall stating ash chute 5 is connected with water pipe 3, and the bottom land of described ash chute 5 is positioned at the lower section at the interval of water pipe 3 or water pipe 3.
Based on above-mentioned another kind of enforcement, described water pipe 3 interval is arranged, and is provided with at the middle part at the interval of described each water pipe 3 Even apoplexy chamber 7 between vented cavity 4, this apoplexy chamber 7 middle air outlet 8 between having.

Claims (10)

1. a rubbish energy-conserving and environment-protective pyrolysis installation, including have the pyrolysis chamber (1) of rubbish input mechanism, in this pyrolysis chamber (1) Outside be provided with water cavity (2), it is characterized in that, described pyrolysis chamber (1) be provided with at least two pass through this pyrolysis chamber (1) connect water cavity (2) water pipe (3), is provided with the wind chamber (4) with air inlet, air outlet, at this water in the above or outside of this water pipe (3) Manage the lower section of (3) or ash chute (5) is arranged below.
2. rubbish energy-conserving and environment-protective pyrolysis installation according to claim 1, is characterized in that, the two ends tool of described ash chute (5) There is ash hole, be provided with cinder conveyer structure at described ash chute (5).
3. rubbish energy-conserving and environment-protective pyrolysis installation according to claim 1, is characterized in that, the two ends tool of described ash chute (5) Having ash hole, being provided with spiral conveying mechanism (6) in described ash chute (5), this spiral conveying mechanism (6) has conveying direction Contrary flight.
4. the rubbish energy-conserving and environment-protective pyrolysis installation according to any one of claim 1, is characterized in that, described ash chute (5) Axially axial consistent with water pipe (3).
5. rubbish energy-conserving and environment-protective pyrolysis installation according to claim 4, is characterized in that, the cell wall of described ash chute (5) with Water pipe (3) connects, at the water pipe (3) being arranged over connection water cavity (2) of described ash chute (5).
6. rubbish energy-conserving and environment-protective pyrolysis installation according to claim 4, is characterized in that, the cell wall of described ash chute (5) with The following connection of water pipe (3).
7. rubbish energy-conserving and environment-protective pyrolysis installation according to claim 4, is characterized in that, the cell wall of described ash chute (5) with The sidewall of water pipe (3) connects.
8. rubbish energy-conserving and environment-protective pyrolysis installation according to claim 1, is characterized in that, described water pipe (3) interval is arranged, institute The two ends stating ash chute (5) have ash hole, are provided with spiral conveying mechanism (6), this helical feed in described ash chute (5) Mechanism (6) has the contrary flight of conveying direction.
9. rubbish energy-conserving and environment-protective pyrolysis installation according to claim 8, is characterized in that, described ash chute (5) axially with Water pipe (3) axially consistent, the cell wall of described ash chute (5) is connected with water pipe (3), and the bottom land of described ash chute (5) is positioned at water The lower section at the interval of pipe (3) or water pipe (3).
10. rubbish energy-conserving and environment-protective pyrolysis installation according to claim 1, is characterized in that, described water pipe (3) interval is arranged, Be communicated with apoplexy chamber (7) between wind chamber (4) at the middle part at the interval of described each water pipe (3), this apoplexy chamber (7) have between in Air outlet (8).
CN201620149364.0U 2015-12-31 2016-02-26 Rubbish energy-conserving and environment-protective pyrolysis installation Expired - Fee Related CN205678675U (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN2015211431097 2015-12-31
CN201521143109 2015-12-31

Publications (1)

Publication Number Publication Date
CN205678675U true CN205678675U (en) 2016-11-09

Family

ID=57438244

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620149364.0U Expired - Fee Related CN205678675U (en) 2015-12-31 2016-02-26 Rubbish energy-conserving and environment-protective pyrolysis installation

Country Status (1)

Country Link
CN (1) CN205678675U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106931447A (en) * 2015-12-31 2017-07-07 未名生物环保集团有限公司 Rubbish energy-conserving and environment-protective pyrolysis installation

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106931447A (en) * 2015-12-31 2017-07-07 未名生物环保集团有限公司 Rubbish energy-conserving and environment-protective pyrolysis installation

Similar Documents

Publication Publication Date Title
CN208840195U (en) A kind of life refuse high temperature cracking treatment system
CN101618954B (en) Process for processing municipal domestic waste by cement rotary kiln
CN103626409A (en) Method and device for treatment in feeding household garbage into cement kiln in three routes
CN107461746B (en) A kind of small-sized domestic garbage pyrolysis gasification oven and purification system
CN205678675U (en) Rubbish energy-conserving and environment-protective pyrolysis installation
CN204923427U (en) High -efficient biomass boiler
CN206591021U (en) A kind of municipal sludge processing system
CN108613194A (en) A kind of method and device for villages and small towns consumer waste incineration
CN206648038U (en) A kind of garbage cracking no-smoke furnace
CN107013916B (en) Dust-free smokeless and power-free automatic circulation carbonization combustion furnace
CN106931447A (en) Rubbish energy-conserving and environment-protective pyrolysis installation
CN211551608U (en) Garbage pyrolysis device
CN205299536U (en) Automatic environmental protection pyrolysis device that sieves of rubbish
CN106468434B (en) Rubbish row sieves the mixed combustion pyrolysis installation of whirlwind
CN205717226U (en) Rubbish high-efficiency environment friendly pyrolysis installation
CN204611788U (en) A kind of Organic Sludge mixes burning recycling system
CN204494414U (en) Hot pan burner burner
CN205825048U (en) Refuse pyrolysis extruding sewage environment-friendly processing unit
CN103438431B (en) A kind of biomass solid fuel boiler
CN106838968A (en) A kind of light Fuel air conveying device
CN204368943U (en) A kind of material conveying structure of destructive distillation device
CN203718793U (en) Environment-friendly combustion furnace
CN205825037U (en) Prevent lime-ash from blocking up refuse pyrolysis plant
CN206069768U (en) A kind of interior-heat drying integrated carbonization furnace apparatus
CN103739215B (en) A kind of technique utilizing cement clinker production line process domestic refuse

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161109

Termination date: 20200226

CF01 Termination of patent right due to non-payment of annual fee