CN205665917U - 一种盾构掘进机仿真培训*** - Google Patents
一种盾构掘进机仿真培训*** Download PDFInfo
- Publication number
- CN205665917U CN205665917U CN201520841134.6U CN201520841134U CN205665917U CN 205665917 U CN205665917 U CN 205665917U CN 201520841134 U CN201520841134 U CN 201520841134U CN 205665917 U CN205665917 U CN 205665917U
- Authority
- CN
- China
- Prior art keywords
- shield
- examiner
- station
- machine
- main driver
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
本实用新型涉及盾构掘进机技术领域,公开一种盾构掘进机仿真培训***,包括:盾构培训服务器、生产网内客户端工作站、考官评价站,所述盾构培训服务器通过互联网与生产网内客户端工作站、考官评价站相连,生产网内客户端工作站由客户端PC机与学员用盾构机主操控台连接组成,考官评价站为考官用考官评价PC机。本实用新型能够使盾构主司机不用进入施工现场即可进行理论及实践学习,大大减小了主司机的培养过程,而通过考试认证上岗,有助于提高盾构主司机自身专业素质以及主司机行业的整体质量。
Description
技术领域
本实用新型涉及盾构掘进机技术领域,尤其涉及一种盾构掘进机仿真培训***。其具有开挖切削土体、运送土碴、拼装隧道衬砌、丈量导向纠偏等功能。
背景技术
随着国家基础建设的持续发展,隧道工程越来越多, 盾构法施工在铁路行业逐渐推广,例如狮子洋隧道、北京直径线、中天山隧道、长株潭、珠三角等城际铁路隧道施工均采用盾构法。据统计,我国目前共有三十多个城市正在进行轨道交通前期规划、设计、筹备和建设等工作。今后10 年间将建设各类盾构法隧道5000 余公里,因此盾构机将会得到广泛的应用。但盾构设备结构复杂、自动化程度高,而且常常根据不同的要求进行专门设计制造。因此如何保障施工过程的质量和安全是广大隧道施工单位优先考虑的问题。
为了保障对建设质量以及人员和设备的安全,在隧道开工前必须对盾构机主司机进行专业培训。目前盾构主要采用传统的培训方式,即通过集中上课的方式。但出于安全考虑,学员不能进入到施工现场观看设备内部结构和运转操作情况,因此培训效果并不理想。在竞争日益激烈的今天,如何弥补传统培训的缺点,提高培训效率,降低培训成本,快速培养出合格的盾构机主司机,是众多企业需要解决的一个重要的技术问题。为此急需一套盾构机培训***势在必行。
发明内容
为解决上述技术问题,本实用新型的目的是提出一种盾构掘进机仿真培训***。其集机、电、液、传感、信息技能于一体,并且具有开挖切削土体、运送土碴、拼装隧道衬砌、丈量导向纠偏等功能。
为实现上述发明目的实用新型采用如下技术方案:
一种盾构掘进机仿真培训***,包括:盾构培训服务器、生产网内客户端工作站、考官评价站,所述盾构培训服务器通过互联网与生产网内客户端工作站、考官评价站相连,生产网内客户端工作站由客户端机与学员用盾构机主操控台连接组成,考官评价站为考官用考官评价机。
一种盾构掘进机仿真培训***,所述盾构机主操控台为仿真的操控台,包括:四个显示屏、盾构机功能机组键盘、操控台体,操控台体立面设置有四个显示屏,左下和右下两个屏模拟显示盾构机操作的实际主控界面,右上屏显示仿真的全站仪,左上屏显示主司机的考试界面;操控台体平面设置有盾构机功能机组键盘,盾构机功能机组键盘包括:按钮F1至按钮F8。
由于采用如上所述的技术方案,本实用新型具有如下优越性:
一种盾构掘进机仿真培训***,为盾构主司机培证***,能够使盾构主司机不用进入施工现场即可进行理论及实践学习,大大减小了主司机的培养过程,有助于提高盾构主司机自身专业素质以及主司机行业的整体质量。通过主司机培证***的开发与应用,逐步形成了规范化和产业化盾构主司机的培证体系,将产生较好的经济效益。
当前国家对设备操作人员的管理越来越严格,从起重吊装等特种设备操作到机动车驾驶等普通设备操作都需要进行考核,持证上岗。而盾构机造价昂贵,盾构主司机作为一个特殊岗位,其岗位的重要性类似于焊接、高空作业等国家规定的特种作业,但目前国内相关的盾构机操作***尚处于空白状态,急需形成业内认可度较高的职业的盾构机操作***技能,以填补这方面空白,丰富特种设备的盾构机操作***,使盾构机操作规范化、服务于国家工程建设。
在国家大力推动基础建设的形势下,盾构隧道使用的盾构机已成为隧道建设的主流前提,盾构机操作***具有非常重要的实际意义,并且有利于提升企业核心竞争力,有利于树立科技领先的企业形象,具有良好的社会效益。
附图说明
图1 为盾构掘进机仿真培训***方框图。
图2为盾构掘进机仿真培训***结构图。
具体实施方式
结合附图和具体实施例对本发明加以说明:
如图1、2所示,一种盾构掘进机仿真培训***,包括:盾构培训服务器、生产网内客户端工作站、考官评价站,所述盾构培训服务器通过互联网与生产网内客户端工作站、考官评价站相连,生产网内客户端工作站由客户端机与学员用盾构机主操控台连接组成,考官评价站为考官用考官评价机。所述盾构机主操控台为仿真的操控台,包括:四个显示屏、盾构机功能机组键盘、操控台体,操控台体立面设置有四个显示屏、若干指示灯2和插排6,左下显示屏4和右下显示屏两个显示屏模拟显示盾构机操作的实际主控界面,右上显示屏显示仿真的全站仪,左上显示屏3显示主司机的考试界面;操控台体平面设置有盾构机功能机组键盘5和若干开关1,盾构机功能机组键盘包括:按钮F1至按钮F8。
盾构掘进机仿真培训***的盾构培训服务器为IBM小型服务器,500G 的IBM高性能存储***,生产网内客户端工作站:客户端机,网络,显示器。
使用时,采用应用服务器通过互联网与生产网内客户端工作站、考官工作站相连构成盾构掘进机仿真培训***,进行盾构掘进机培训,该盾构掘进机集机、电、液、传感、信息技能于一体,并且具有开挖切削土体、运送土碴、拼装隧道衬砌、丈量导向纠偏的功能。
主操控台,盾构机操作非常繁琐,有作业前检查、盾构推进状态下操作、盾构拼装状态下操作、盾构辅助***操作、气闸***的操作和照明***操作。
该操控台以长株潭海瑞克土压盾构机为原型,所有操控按键及仪表盘均按照1比1制作,操控台有四个显示屏,左下和右下两个屏模拟显示盾构机操作的实际主控界面,右上屏显示仿真的全站仪,左上屏显示主司机的考试界面。
盾构掘进机集机、电、液、传感、信息技能于一体,学员在操控的同时,需要不断检测各个关键部件,当操作不当时,***主会有相应的警告。***显示主界面将采用双屏显示。所有测量值都显示在控制仓内的屏幕上。
Claims (2)
1.一种盾构掘进机仿真培训***,其特征是:包括:盾构培训服务器、生产网内客户端工作站、考官评价站,所述盾构培训服务器通过互联网与生产网内客户端工作站、考官评价站相连,生产网内客户端工作站由客户端机与学员用盾构机主操控台连接组成,考官评价站为考官用考官评价机。
2.如权利要求1所述一种盾构掘进机仿真培训***,其特征是:所述盾构机主操控台为仿真的操控台,包括:四个显示屏、盾构机功能机组键盘、操控台体,操控台体立面设置有四个显示屏,左下和右下两个屏模拟显示盾构机操作的实际主控界面,右上屏显示仿真的全站仪,左上屏显示主司机的考试界面;操控台体平面设置有盾构机功能机组键盘,盾构机功能机组键盘包括:按钮F1至按钮F8。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520841134.6U CN205665917U (zh) | 2015-10-28 | 2015-10-28 | 一种盾构掘进机仿真培训*** |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520841134.6U CN205665917U (zh) | 2015-10-28 | 2015-10-28 | 一种盾构掘进机仿真培训*** |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205665917U true CN205665917U (zh) | 2016-10-26 |
Family
ID=57162300
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520841134.6U Active CN205665917U (zh) | 2015-10-28 | 2015-10-28 | 一种盾构掘进机仿真培训*** |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205665917U (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106652637A (zh) * | 2017-03-02 | 2017-05-10 | 西安电子科技大学 | 一种盾构机协同操作虚拟训练***及方法 |
CN108776997A (zh) * | 2018-08-13 | 2018-11-09 | 中铁工程装备集团技术服务有限公司 | 土压平衡盾构机模拟训练方法及平台 |
CN109191978A (zh) * | 2018-09-27 | 2019-01-11 | 常州工程职业技术学院 | 盾构机操控驾驶模拟*** |
-
2015
- 2015-10-28 CN CN201520841134.6U patent/CN205665917U/zh active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106652637A (zh) * | 2017-03-02 | 2017-05-10 | 西安电子科技大学 | 一种盾构机协同操作虚拟训练***及方法 |
CN108776997A (zh) * | 2018-08-13 | 2018-11-09 | 中铁工程装备集团技术服务有限公司 | 土压平衡盾构机模拟训练方法及平台 |
CN109191978A (zh) * | 2018-09-27 | 2019-01-11 | 常州工程职业技术学院 | 盾构机操控驾驶模拟*** |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205665917U (zh) | 一种盾构掘进机仿真培训*** | |
DE112018003914T5 (de) | Ein Echtzeit-Wahrnehmungssystem und -verfahren für den TBM-Bohrgesteinsmassenzustand | |
CN105513451B (zh) | 一种盾构掘进机仿真培训***及方法 | |
CN103577651B (zh) | 一种智能化的批量生成及处理任意形状截面等值线云图的方法 | |
CN204461463U (zh) | 一种光学三维扫描仪 | |
CN107103078A (zh) | 基于bim的变电站建设全周期数字化管控*** | |
CN104462778A (zh) | 一种基于深度学习的pm2.5污染物测量方法 | |
CN206208251U (zh) | 隧道拱顶沉降监测点快速布置装置 | |
CN205318659U (zh) | 一种课堂互动式计算机教学*** | |
CN104598970B (zh) | 一种爬架组的工作状态检测方法 | |
CN205718761U (zh) | 一种简易张弦梁预应力张拉位移监测装置 | |
CN113094939B (zh) | 一种地铁牵引供电仿真数据可视分析*** | |
CN110469348A (zh) | 基于bim技术的暗挖隧道大曲线转弯处钢格栅布置方法 | |
CN102486089A (zh) | 基于等值线的三维地质构造图的重建*** | |
CN213502859U (zh) | 一种节约空间的船舶驾控台 | |
CN207130620U (zh) | 一种混凝土铁路桥专用检查车 | |
CN206769908U (zh) | 一种基于bim的地铁车站竖井开马头门的防护监控*** | |
Yu et al. | Research and Development of Building Construction Safety Management System Based on BIM Technology | |
CN111383339A (zh) | 一种基于bim+mr的结构钢筋检查方法 | |
Pecci et al. | Residue analysis of some Late Roman amphora coming from the excavations of the historical center of Florence | |
Spoto | Formal psychological assessment theoretical and mathematical foundations | |
Shirazi | Concluding remark: Paradox of citizen participation in Iran | |
Bartolini et al. | Diagnosis of monumental structures considering history-related phenomena: a systematic operating method applied to the Baptistery of Pisa | |
Yang | Exploration and Practice of Standardized Design and Management of Oil and Gas Field Surface Engineering | |
Vitali | Thermodynamic and fluid-dynamic challenges associated with the transport of CO2 via pipelines |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |