CN205663226U CN201620490828.4U CN201620490828U CN205663226U CN 205663226 U CN205663226 U CN 205663226U CN 201620490828 U CN201620490828 U CN 201620490828U CN 205663226 U CN205663226 U CN 205663226U
Authority
CN
China
Prior art keywords
pulley
wire rope
steel construction
steel wire
hoist engine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620490828.4U
Other languages
Chinese (zh)
Inventor
吴攀
张启亭
黄伟
王洪刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Haichuan Construction Group Co Ltd
Original Assignee
Qingdao Haichuan Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Haichuan Construction Group Co Ltd filed Critical Qingdao Haichuan Construction Group Co Ltd
Priority to CN201620490828.4U priority Critical patent/CN205663226U/en
Application granted granted Critical
Publication of CN205663226U publication Critical patent/CN205663226U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a super high -rise building thing top steel construction symmetry is hung and is drawn device, including hoist engine, wire rope and assembly pulley mechanism, wire rope's one end and windlass connected, wire rope's the other end passes through assembly pulley mechanism and is connected with load, assembly pulley mechanism includes first pulley, second pulley and third pulley, wire rope level between wire rope, second pulley and the third pulley between first pulley and the hoist engine sets up, the vertical setting of wire rope between first pulley and the second pulley, and just first pulley is located the below of second pulley, hoist engine, wire rope and assembly pulley mechanism all are provided with two sets ofly, and the symmetry sets up. With the help of scaffold frame and one step last steel construction and utilize two hoist engines to carry out the symmetry to horizontal steel structural member and hang and draw, make the even atress of steel construction, avoided construction load to give the adverse effect that the body of the tower structure was brought. The effectual requirements for quality who satisfies the steel construction.

Description

A kind of super high rise building top steel construction symmetry hangs drawing device
Technical field
This utility model relates to super high rise building top structure installation Technology field, is specially a kind of Super High and builds Build thing top steel construction symmetry and hang drawing device.
Background technology
Because building top, the handling appliance such as tower crane cannot use, and is only capable of each steel beam column split is hoisted to operating surface. Because steel construction perfect aspect height is higher, deadweight is relatively big, even if material split is hoisted to operating surface, does not has suitable hanging device Also cannot be by component installation, it is necessary to the Hoisting Program of operating surface a kind of Simple mechanical of research is being installed, should guarantee to install Complete, ensure the construction safety in installation process again, how to carry out lifting at narrow space and install, be that this steel knot is installed The key of structure.
Summary of the invention
The purpose of this utility model is to provide a kind of super high rise building top steel construction symmetry to hang drawing device, to solve The problem proposed in above-mentioned background technology.
For achieving the above object, the following technical scheme of this utility model offer: a kind of super high rise building top steel construction Symmetry hangs drawing device, including hoist engine, steel wire rope and pulley block mechanism;One end of described steel wire rope is connected with hoist engine, steel wire The other end of rope is connected with load by pulley block mechanism;Described pulley block mechanism includes the first pulley, the second pulley and the 3rd Pulley;The steel wire rope between steel wire rope, the second pulley and the 3rd pulley between described first pulley and hoist engine is horizontally disposed with, Steel wire rope between first pulley and the second pulley is vertically arranged, and the first pulley is positioned at the lower section of the second pulley.
Further, described hoist engine, steel wire rope and pulley block mechanism are provided with two groups, and are symmetrical arranged.
Further, described load adjusts perpendicularity by magnetic line pendant.
Further, described load includes segmentation beam, and segmentation beam connects at levelling some postwelding high intensity screw of each segmentation Method is blue.
Compared with prior art, the beneficial effects of the utility model are: by scaffold and previous step steel construction and utilize Two hoist engines carry out symmetry and hang and draw horizontal steel structure member, make steel construction uniform stressed, it is to avoid construction loads is to tower body The adverse effect that structure is brought.Effectively meet the prescription of steel construction.
Technical elements, the hoisting technology not only economy but also safe ready that this engineering method uses.
Economic aspect, the lifting of steel beam column is lifted by the combination of assembly pulley, steel wire rope and hoist engine, eliminates big The use of type plant equipment, decreases construction cost, improves economic benefit.
Accompanying drawing explanation
Fig. 1 is that hoist engine of the present utility model lifts schematic diagram;
Hoisting structure schematic diagram when Fig. 2 is utility model works.
In figure: 1-hoist engine, 2-steel wire rope, 3-the first pulley, 4-the second pulley, 5-the 3rd pulley, 6-load.
Detailed description of the invention
Below in conjunction with the accompanying drawing in this utility model embodiment, the technical scheme in this utility model embodiment is carried out Clearly and completely describe, it is clear that described embodiment is only a part of embodiment of this utility model rather than whole Embodiment.Based on the embodiment in this utility model, those of ordinary skill in the art are not under making creative work premise The every other embodiment obtained, broadly falls into the scope of this utility model protection.
Refer to Fig. 1-2, a kind of embodiment that this utility model provides: a kind of super high rise building top steel construction is symmetrical Hang drawing device, including hoist engine 1, steel wire rope 2 and pulley block mechanism;One end of described steel wire rope 2 is connected with hoist engine 1, steel wire The other end of rope 2 is connected with load 6 by pulley block mechanism;Described pulley block mechanism includes first pulley the 3, second pulley 4 and 3rd pulley 5;The steel wire between steel wire rope the 2, second pulley 4 and the 3rd pulley 5 between described first pulley 3 and hoist engine 1 Rope 2 is horizontally disposed with, and the steel wire rope 2 between the first pulley 3 and the second pulley 4 is vertically arranged, and the first pulley 3 is positioned at the second pulley The lower section of 4.
As optimisation technique scheme of the present utility model: described hoist engine 1, steel wire rope 2 and pulley block mechanism are provided with Two groups, and be symmetrical arranged.
As optimisation technique scheme of the present utility model: described load 6 adjusts perpendicularity by magnetic line pendant.
As optimisation technique scheme of the present utility model: described load 6 includes segmentation beam, and segmentation beam is levelling in each segmentation Point postwelding is blue by high intensity screw connection method.
Operation principle: using two hoist engines 1 and pulley block mechanism lifting load 6, double-steel wire rope 2 is tied up;Rear spiral shell in place Cap is fixed, and magnetic line pendant adjusts perpendicularity, stoppers column bottom load-bearing correcting block, and spot welding is fixed temporarily.
Lifting requirements:
1, lifting before check component each other, component and pre-buried between relation size, absolute altitude and component installing hole it Between relation, check that component partial whether deforms, between the number of components, length, perpendicularity, joint bolt hole size whether with figure Paper is consistent, and pinpoints the problems, and solves before lifting.
2, link up with position in correct selection load 6, and take appropriate measures, it is to avoid component produces big flexural deformation.Hang Check before dress size between pedestal anchor bolt, expose basis end face size, whether basis end face absolute altitude is consistent with design, checks suspension column Crab-bolt is whether damaged.
3, installed component in place unguyed before can not be welded with other objects in main force part.Note Protection Code Blue connecting end surface, is strictly on guard against electric welding, gas welding equivalent damage.
4, before lifting, Hoisting Program is told somebody what one's real intentions are to all workmens, lift this section of component numbering.High-strength bolt and spiral shell Female supporting, smear a small amount of mineral oil in nut.
5, check before lifting, adjust equipment tool and the theodolite etc. such as hoist engine 1, strand mill, steel wire rope 2, pulley block mechanism Instrument, it is ensured that safe handling.Adjusting complete, examination is hung in advance, checks again for the intact degree of equipment rigging after test specimen is liftoff.
6, using two hoist engines 1 and assembly pulley lifting steel column, double-steel wire rope 2 is tied up;Rear nut in place is fixed, magnetic line Pendant adjusts perpendicularity, stoppers column bottom load-bearing correcting block, and spot welding is fixed temporarily.
It is obvious to a person skilled in the art that this utility model is not limited to the details of above-mentioned one exemplary embodiment, and And in the case of without departing substantially from spirit or essential attributes of the present utility model, it is possible to realize this practicality in other specific forms new Type.Therefore, no matter from the point of view of which point, all should regard embodiment as exemplary, and be nonrestrictive, this practicality is new The scope of type is limited by claims rather than described above, it is intended that by the containing of equivalency in claim that fall All changes in justice and scope are included in this utility model.Should not be considered as any reference in claim limiting Involved claim.

Claims (4)

1. super high rise building top steel construction symmetry hangs a drawing device, including hoist engine (1), steel wire rope (2) and assembly pulley Mechanism;It is characterized in that: one end of described steel wire rope (2) is connected with hoist engine (1), the other end of steel wire rope (2) passes through assembly pulley Mechanism is connected with load (6);Described pulley block mechanism includes the first pulley (3), the second pulley (4) and the 3rd pulley (5);Described The steel wire rope (2) between steel wire rope (2), the second pulley (4) and the 3rd pulley (5) between first pulley (3) and hoist engine (1) Being horizontally disposed with, the steel wire rope (2) between the first pulley (3) and the second pulley (4) is vertically arranged, and the first pulley (3) is positioned at The lower section of two pulleys (4).
A kind of super high rise building top the most according to claim 1 steel construction symmetry hangs drawing device, it is characterized in that: described Hoist engine (1), steel wire rope (2) and pulley block mechanism are provided with two groups, and are symmetrical arranged.
A kind of super high rise building top the most according to claim 1 steel construction symmetry hangs drawing device, it is characterized in that: described Load (6) adjusts perpendicularity by magnetic line pendant.
A kind of super high rise building top the most according to claim 1 steel construction symmetry hangs drawing device, it is characterized in that: described Load (6) includes segmentation beam, and segmentation beam is blue in levelling some postwelding high intensity screw connection method of each segmentation.
CN201620490828.4U 2016-05-25 2016-05-25 Super high -rise building thing top steel construction symmetry is hung and is drawn device Expired - Fee Related CN205663226U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620490828.4U CN205663226U (en) 2016-05-25 2016-05-25 Super high -rise building thing top steel construction symmetry is hung and is drawn device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620490828.4U CN205663226U (en) 2016-05-25 2016-05-25 Super high -rise building thing top steel construction symmetry is hung and is drawn device

Publications (1)

Publication Number Publication Date
CN205663226U true CN205663226U (en) 2016-10-26

Family

ID=57161298

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620490828.4U Expired - Fee Related CN205663226U (en) 2016-05-25 2016-05-25 Super high -rise building thing top steel construction symmetry is hung and is drawn device

Country Status (1)

Country Link
CN (1) CN205663226U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115492387A (en) * 2022-09-15 2022-12-20 中建八局第一建设有限公司 Creeping formwork integrated material hoisting system and construction method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115492387A (en) * 2022-09-15 2022-12-20 中建八局第一建设有限公司 Creeping formwork integrated material hoisting system and construction method thereof
CN115492387B (en) * 2022-09-15 2023-08-11 中建八局第一建设有限公司 Climbing form integrated material hoisting system and construction method thereof

Similar Documents

Publication Publication Date Title
CN100519396C (en) Gin pole integrated dismounting method for tower crane
CN204917648U (en) Turbine rotor lifts by crane instrument
CN214167082U (en) Special lifting device for pressure vessel
CN107954306A (en) Precast stair Lift-on/Lift-off System and hanging method
CN108163694A (en) A kind of body section hanging method with hatch coaming
CN105464456B (en) Go straight up to method and suspender that unit founds UHV transmission steel tower
CN205663226U (en) Super high -rise building thing top steel construction symmetry is hung and is drawn device
CN207346996U (en) A kind of Bridge Erector
CN204454235U (en) A kind of novel many suspension centres equalizing bar device
CN104942564A (en) Mounting method of large-tonnage pin on jib of offshore shipborne jib type crane
CN105952129B (en) Elevator shaft combined type integral lifting operation platform and construction method thereof
CN204371545U (en) A kind of power station impeller apparatus for examination and repair
CN104030176B (en) The equalizer bar of hoisting platform truss and hanging method thereof
CN203959697U (en) The equalizing bar of hoisting platform truss
CN205662256U (en) High rises pergola side and hangs a semi -portal bridge crane
CN202744175U (en) Sling used for hoisting precast concrete columns
CN204689351U (en) A kind of H profile steel structural elements suspender
CN109378767A (en) A kind of lifting engineering method of hoist engine to skyscraper electricity well inner cable
CN209538038U (en) A kind of cable tension device
CN208843629U (en) A kind of crane upper mechanism is from dismantling device and crane
CN106315391B (en) A kind of turbine generator unit shaft watt checks hoisting special purpose tools and hoisting method
CN204702404U (en) Portable suspender
CN205114815U (en) Parallel hoist of diesel engine
CN207276049U (en) A kind of gantry crane
CN205243147U (en) Hoist that uses during special high -tension transmission iron tower of helicopter assemblage

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161026