CN205656282U - Whole group's test bench of electromagnetic type relay - Google Patents

Whole group's test bench of electromagnetic type relay Download PDF

Info

Publication number
CN205656282U
CN205656282U CN201620430655.7U CN201620430655U CN205656282U CN 205656282 U CN205656282 U CN 205656282U CN 201620430655 U CN201620430655 U CN 201620430655U CN 205656282 U CN205656282 U CN 205656282U
Authority
CN
China
Prior art keywords
relay
power supply
inspection
seat
normally closed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620430655.7U
Other languages
Chinese (zh)
Inventor
***
孙天城
贾宏
郭大胜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changchun No2 Co-Generation Power Co Ltd
Original Assignee
Changchun No2 Co-Generation Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changchun No2 Co-Generation Power Co Ltd filed Critical Changchun No2 Co-Generation Power Co Ltd
Priority to CN201620430655.7U priority Critical patent/CN205656282U/en
Application granted granted Critical
Publication of CN205656282U publication Critical patent/CN205656282U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Testing Electric Properties And Detecting Electric Faults (AREA)

Abstract

The utility model provides a whole group's test bench of electromagnetic type relay, belongs to the inspection machine field. The utility model aims at providing a whole set of automatic check's whole group's test bench of electromagnetic type relay can carry out the electromagnetic type relay. The utility model discloses a constitute by relay protection action definite value test section and relay protection operate time test section. The utility model discloses simple structure, convenient to use. The test bench of a permanence of preparation satisfies mobility and the accuracy to the direct current relay inspection. Reduce the overlap joint work of experimental each components and parts, made things convenient for the checking of direct current relay. Be applicable to the opening the node, close basic test operation such as node measurement of electromagnetic type relay operation voltage, return voltage, sustain voltage, time relay timing and relay of direct current 110V and following electric pressure.

Description

Electromagnetic relay total group test platform
Technical field
This utility model belongs to inspection apparatus field.
Background technology
Currently, along with the development of power system grows, every transformation increases the most increasingly, in order to preferably realize various electric function, as: operating system AC and DC is isolated, and the logic overlap joint etc. of electric loop is required for realizing this series function by electromagnetic relay, therefore, the importance of work is checked also to become increasingly conspicuous for relay.At present, also not having the test apparatus of special work relay inspection, according to traditional work pattern, be all the various loops of interim overlap joint, after having inspected relay, then remove assay device, next time, inspection overlapped the most again, the most repeatedly, and waste of manpower, material resources.
Summary of the invention
The purpose of this utility model is to provide a kind of electromagnetic relay total group test platform that electromagnetic relay can carry out a whole set of inspection automatically.
This utility model is to be made up of relay protection action setting examination part and relay protection detection movement time part;
Relay protection action setting examination part: power sources in parallel slide rheostat; the slide plate of slide rheostat multivoltmeter in parallel with power cathode; a number normally opened relay inspection seat and a normally closed relay inspection seat are on a termination slide plate respectively, and another terminates power cathode;
Relay protection detects part movement time: power positive cathode is respectively and di-normally opened relay checks seat and No. two normally closed relays inspection seats, No. two normally opened relays inspection seats and No. two normally closed relays inspection seats to be both connected on time set;
Time set and the detailed annexation of No. two normally opened relay inspection seats: positive source is connected on No. two normally opened relay inspection seats through resistance, reconnects on K1 relay, and power cathode is connected directly between on K1 relay;
Time set and the detailed annexation of No. two normally closed relay inspection seats: positive source connects on the normally closed node of K1 relay through resistance, reconnect on adjustable switch 2 feet in flakes, adjustable switch 1 foot in flakes is connected on timer, and power cathode is connected directly between on timer;One end of No. two normally closed relay inspection seats is connected on adjustable switch 2 feet in flakes, and the other end is connected on adjustable switch 1 foot in flakes.
This utility model simple in construction, easy to use.Make a permanent testing stand, meet the mobility to DC relay inspection and accuracy.Decrease the overlap joint work testing each components and parts, facilitate the inspection work of DC relay.Be applicable to the electromagnetic relay operation voltage of direct current 110V and following electric pressure thereof, return voltage, holding voltage, time relay timing and relay opens the operation of the basic test such as node, close node measurement.
Accompanying drawing explanation
Fig. 1 is this utility model relay protection action definite value test portion annexation schematic diagram;
Fig. 2 is this utility model relay protection test portion movement time annexation schematic diagram;
Fig. 3 is this utility model relay protection time set movement time part annexation schematic diagram.
Detailed description of the invention
This utility model is to be made up of relay protection action setting examination part and relay protection detection movement time part;
Relay protection action setting examination part: power supply 1 slide rheostat 2 in parallel; the slide plate 3 of slide rheostat 2 and power supply 1 negative pole multivoltmeter in parallel 4; a number normally opened relay inspection seat 6 and a normally closed relay inspection seat 5 are on a termination slide plate 3 respectively, another termination power 1 negative pole;
Relay protection detects part movement time: power supply 1 both positive and negative polarity is respectively and di-normally opened relay checks seat 11 and No. two normally closed relays inspection seats 10, No. two normally opened relays inspection seats 11 and No. two normally closed relays inspection seats 10 to be both connected on time set 12;
Time set 12 and the detailed annexation of No. two normally opened relay inspection seats 11: power supply 1 positive pole is connected on No. two normally opened relay inspection seats 11 through resistance 1201, reconnects on K1 relay 1205, and power supply 1 negative pole is connected directly between on K1 relay 1205;
Time set 12 checks the detailed annexation of seats 10 with No. two normally closed relays: power supply 1 positive pole is connected on the normally closed node of K1 relay 1202 through resistance 1201, reconnect adjustable switch in flakes 1203 2 feet on, adjustable switch in flakes 1203 1 foot be connected on timer 1204, power supply 1 negative pole is connected directly between on timer 1204;One end of No. two normally closed relays inspection seats 10 be connected to adjustable switch in flakes 1203 2 feet on, the other end be connected to adjustable switch in flakes 1203 1 foot on.
This utility model is the inspection principle according to relay, utilizes 2.5mm2Copper cash, power supply sky is opened, the element such as slide rheostat, voltage pointer table, timer, relay base couples together, it is achieved the checking function of relay.
This utility model solves its technical problem and be the technical scheme is that
According to the inspection principle of relay, utilize the copper cash of 2.5mm2, power supply sky is opened, the element such as slide rheostat, voltage pointer table, relay base couples together, it is achieved the checking function of relay.
Make the testing stand being specifically designed to electromagnetic relay inspection, the base of relay is fixed on guidance panel, at the trial, only need to relay be inserted in base, it is ensured that the horizontal positioned of relay.Utilize the characteristic of slide rheostat, can quickly, at random apply voltage.The needle dc voltmeter of one piece 0.5 grade in parallel, can read test data more accurately.Pass through above method, it is ensured that the standard-required to relay inspection.
With embodiment, this practical principle is further illustrated below in conjunction with the accompanying drawings.
This device is that tested device (voltage relay) is installed on relay base, switches on power, automatic Verification relay definite value and time.
When need calibrating voltage relay output node be open type time, relay connects and relay base, the slide plate of slide rheostat is slided to positive pole by the negative pole of power supply, thus change relay base and access the access voltage of tested relay coil, when arriving working value, normal opened contact closes, and bulb is luminous, and now the numerical value on multivoltmeter is exactly the working value of relay.
When need calibrating voltage relay output node be closed type time, relay connects and relay base, the slide plate of slide rheostat is slided to positive pole by the negative pole of power supply, thus change relay base and access the access voltage of tested relay coil, when arriving working value, normally closed contact is opened, and relay lead-out wire can be measured with circuit tester conducting shelves and disconnect, and now the numerical value on multivoltmeter is exactly the working value of relay.
When the voltage relay needing calibrating output node be open type movement time time, relay connects and relay base, timer device be connected to 1-2 foot in flakes, switch on power moment, timer starts in time, when the tested actuating of relay when, tested relay drives relay K 1 action, and at this moment K1 actuating of relay contact K1 opens, and disconnects timing loop, timer stops timing, and at this moment the time above timer is exactly tested pull up time.
When need calibrating voltage relay output node be closed type time, relay connects and relay base, timer device be connected to 2-3 foot in flakes, switching on power moment, timer starts timing, when the tested actuating of relay when, tested relay is normally closed to be opened, disconnecting timing loop, timer stops timing, and at this moment the time above timer is exactly tested pull up time.
As shown in CAD schematic diagram 1,110V DC voltage is connected with the coil terminals of slide rheostat, relay base, a block pointer formula voltmeter in parallel at the coil terminals of relay base.Work signal: after by 110V direct current sky folding, DC voltage is delivered to (can arbitrarily be changed the DC voltage being added in electromagnetic relay coil two ends by slide rheostat) at slide rheostat, the magnitude of voltage being added in relay coil two ends can be read by needle dc voltmeter, thus read the operation voltage of relay.
As shown in CAD schematic diagram 1, at the node terminal of relay base, it is connected to a signal circuit being made up of the set of cells that constitutes of No. 1 aneroid battery and 1 low-power lamp bead of a joint 1.5V, when after the actuating of relay of CAD schematic diagram 1, open node ought to close, link up signal circuit: lamp bead is the most shinny, it was demonstrated that relay to open node action result good;Otherwise, by signal circuit as close node at, when, after the actuating of relay of CAD schematic diagram 1, close node ought to disconnect, link up signal circuit: lamp bead is become not working from bright suddenly, it was demonstrated that the close node the result of the action of relay is good.
As shown in CAD schematic diagram 3, the Inner Constitution of timer, when relay uses normally opened node, by figure attachment means, pressing plate (adjustable switch is in flakes) puts into 1-2 foot, and when starting power up, timer starts timing, when the time actuating of relay, the K1 actuating of relay, K1 node disconnects timing loop, and timing terminates.When using normally closed node, by figure attachment means, pressing plate (adjustable switch is in flakes) puts into 3-2 foot, and when starting power up, timer starts timing, and when the time actuating of relay, normally closed node disconnects timing loop, and timing terminates.

Claims (1)

1. an electromagnetic relay total group test platform, it is characterised in that: it is to be made up of relay protection action setting examination part and relay protection detection movement time part;
Relay protection action setting examination part: power supply (1) slide rheostat (2) in parallel; the slide plate (3) of slide rheostat (2) and power supply (1) negative pole multivoltmeter in parallel (4); number normally opened relay inspection seat (6) and normally closed relay inspection seat (5) are on a termination slide plate (3) respectively, another termination power (1) negative pole;
Relay protection detects part movement time: power supply (1) both positive and negative polarity is respectively and di-normally opened relay checks seat (11) and No. two normally closed relays inspection seat (10), No. two normally opened relays inspection seat (11) and No. two normally closed relays inspection seat (10) to be both connected on time set (12);
Time set (12) and No. two normally opened relays check the detailed annexation of seat (11): power supply (1) positive pole is connected on No. two normally opened relays inspection seat (11) through resistance (1201), reconnecting on K1 relay (1205), power supply (1) negative pole is connected directly between on K1 relay (1205);
Time set (12) checks the detailed annexation of seat (10) with No. two normally closed relays: power supply (1) positive pole is connected on the normally closed node of K1 relay (1202) through resistance (1201), reconnect on 2 feet of adjustable switch (1203) in flakes, 1 foot of adjustable switch (1203) in flakes is connected on timer (1204), and power supply (1) negative pole is connected directly between on timer (1204);One end of No. two normally closed relays inspection seat (10) is connected on 2 feet of adjustable switch (1203) in flakes, and the other end is connected on 1 foot of adjustable switch (1203) in flakes.
CN201620430655.7U 2016-05-13 2016-05-13 Whole group's test bench of electromagnetic type relay Expired - Fee Related CN205656282U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620430655.7U CN205656282U (en) 2016-05-13 2016-05-13 Whole group's test bench of electromagnetic type relay

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620430655.7U CN205656282U (en) 2016-05-13 2016-05-13 Whole group's test bench of electromagnetic type relay

Publications (1)

Publication Number Publication Date
CN205656282U true CN205656282U (en) 2016-10-19

Family

ID=57403656

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620430655.7U Expired - Fee Related CN205656282U (en) 2016-05-13 2016-05-13 Whole group's test bench of electromagnetic type relay

Country Status (1)

Country Link
CN (1) CN205656282U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108445387A (en) * 2018-05-30 2018-08-24 江苏七维测试技术有限公司 A kind of electromagnetic relay reliability test box
CN111132189A (en) * 2019-10-31 2020-05-08 广西华南通信股份有限公司 Three-step multi-carrier wireless forwarding station resource optimization configuration strategy

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108445387A (en) * 2018-05-30 2018-08-24 江苏七维测试技术有限公司 A kind of electromagnetic relay reliability test box
CN108445387B (en) * 2018-05-30 2023-09-19 江苏七维测试技术有限公司 Electromagnetic relay reliability test box
CN111132189A (en) * 2019-10-31 2020-05-08 广西华南通信股份有限公司 Three-step multi-carrier wireless forwarding station resource optimization configuration strategy
CN111132189B (en) * 2019-10-31 2022-07-29 广西华南通信股份有限公司 Three-step multi-carrier wireless forwarding station resource optimal configuration method

Similar Documents

Publication Publication Date Title
CN202676832U (en) Distribution network feeder line monitoring terminal integrated testing device
CN205656282U (en) Whole group's test bench of electromagnetic type relay
CN202886592U (en) Virtual load device of single-phase electric energy meter
CN107576906A (en) A kind of portable relay checking platform and its application method
CN202815146U (en) Polarity detector for mutual inductor
CN205749738U (en) Portable microcomputer busbar protective device tester
CN205333776U (en) Combined current and potential transformer's secondary winding point polarity detection device
CN208860929U (en) Intermediate relay checking table
CN102478630A (en) Relay function testing device and testing method thereof
CN207601285U (en) A kind of ups power test device
CN206906432U (en) A kind of electric energy meter pressure test rapid wiring device
CN203037783U (en) On-off detection apparatus for secondary cable core of current transformer
CN205720637U (en) A kind of check standard device for electric energy meter Withstand test device
CN109521311A (en) Relay protection multiple exit pressing plate measuring instrument
CN212229071U (en) Instrument aging testing cabinet
CN105242522B (en) The test device and method of testing of separating mechanism disengaging time
CN205941823U (en) Specified surplus switch -on breaking capacity testing arrangement
CN209496093U (en) Relay protection multiple exit pressing plate measuring instrument
CN208537608U (en) A kind of quiescent current test circuit with charging system product
CN209514950U (en) Instrument uses training and examination device
CN209417140U (en) A kind of power end disturbance voltage detection circuit
CN207571204U (en) A kind of counter voltage test smelting tool
CN105954626B (en) Portable microcomputer busbar protective device tester
CN206132892U (en) Explosion -proof earth -leakage detection tool
CN206710560U (en) Voltage-time type logic tester

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161019