CN205634711U CN201620358694.0U CN201620358694U CN205634711U CN 205634711 U CN205634711 U CN 205634711U CN 201620358694 U CN201620358694 U CN 201620358694U CN 205634711 U CN205634711 U CN 205634711U
Authority
CN
China
Prior art keywords
hanging basket
crossbeam
wirerope
overload
movable pulley
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620358694.0U
Other languages
Chinese (zh)
Inventor
李兆龙
王晓琴
杨苏春
黄浩
仇仲颖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Zhuo Yuan Architectural Design Co Ltd
Qingdao Zhongjia Construction Group Co Ltd
Qingdao Jianan Construction Group Co Ltd
Original Assignee
Shandong Zhuo Yuan Architectural Design Co Ltd
Qingdao Zhongjia Construction Group Co Ltd
Qingdao Jianan Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Zhuo Yuan Architectural Design Co Ltd, Qingdao Zhongjia Construction Group Co Ltd, Qingdao Jianan Construction Group Co Ltd filed Critical Shandong Zhuo Yuan Architectural Design Co Ltd
Priority to CN201620358694.0U priority Critical patent/CN205634711U/en
Application granted granted Critical
Publication of CN205634711U publication Critical patent/CN205634711U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Types And Forms Of Lifts (AREA)

Abstract

The utility model discloses a formula construction hanging basket prevents overloading, including guide pulley, crossbeam, overload circuit breaker, steel cable, main tributary post, hanging flower basket and headstock, the upper right end at the wheel bracket is installed to the guide pulley, is located the upside of crossbeam, guide pulley scaffold weldment is at the upper surface left end of crossbeam, the lower surface right side position at the crossbeam is installed to the steel cable fixing base, the junction at steel cable and steel cable fixing base is installed to the overload circuit breaker, move pulley mounting on the movable pulley support, the welding of movable pulley support is in the top right side position of hanging flower basket, the outer wall right side middle part position at the hanging flower basket is installed to the floor inductor, elastic support installs the bottom at the hanging flower basket, the transmission main shaft front end is connected with the capstan winch, rear end and retarder connection, the control chamber welding is at the left end of bottom plate, limit switch installs the upper portion position at the main tributary post, the utility model discloses simple easy operation, convenient to use to the overload circuit breaker is installed, the hanging flower basket overload operation can be effectively prevented.

Description

A kind of anti-overload formula building hanging basket
Technical field
This utility model relates to a kind of hanging basket, a kind of anti-overload formula building hanging basket.
Background technology
Along with developing rapidly of building trade, some Architectural Equipments are also carrying out improvement and development;Existing building hanging basket is not provided with some safety components mostly for ensureing the safety of construction, the particularly overload operation of hanging basket has great danger, and hanging basket operator do not observe the situation within hanging basket, to such an extent as to maloperation, bring danger to material handling personnel in hanging basket.
Utility model content
The purpose of this utility model is to provide a kind of anti-overload formula building hanging basket, with the problem solving to propose in above-mentioned background technology.
For achieving the above object, the following technical scheme of this utility model offer:
A kind of anti-overload formula building hanging basket, including guide wheel, crossbeam, overload circuit breaker, wirerope, main pillar, hanging basket and headstock;Described guide wheel is arranged on the upper right side of wheel bracket, is positioned at the upside of crossbeam;Described wheel bracket is welded on the upper surface left end of crossbeam;Described main pillar is connected with base plate by bolt, is positioned at the upside of base plate;Wirerope is fixed seat and is arranged on the lower surface right positions of crossbeam;Overload circuit breaker is arranged on wirerope and the junction of seat fixed by wirerope;Described movable pulley is arranged on movable pulley bearing;Described movable pulley bearing is welded on the top right positions of hanging basket;Guide roller is arranged on the gap location between hanging basket and main pillar;Floor induction apparatus is arranged on the outer wall right side central position of hanging basket;Photographic head is arranged on hanging basket inner tip, and photographic head is connected with display screen by cable simultaneously;Elastic support is arranged on the bottom of hanging basket;Transmission main shaft front end is connected with capstan winch, and rear end is connected with decelerator;Operating room is welded on the left end of base plate;Motor is arranged on inside headstock, is connected with decelerator by V belt translation;Limit switch is arranged on the upper position of main pillar.
As further program of the utility model: described crossbeam is steel structure beam, two ends, left and right are connected with main pillar by bolt.
As further program of the utility model: described wirerope right-hand member is fixed on wirerope and fixes on seat, and left end is fixed on capstan winch, and centre sequentially passes through movable pulley and guide wheel.
As this utility model further scheme: described capstan winch is arranged on transmission main shaft, section is H-shaped, and material is 45 steel.
Compared with prior art, the beneficial effects of the utility model are:
This utility model is simple to operation, easy to use, and is provided with overload circuit breaker, can effectively prevent hanging cradle overload to run;Limit switch can effectively prevent hanging basket to collide with crossbeam in lifting process;The situation of the loading and unloading arranging personal observations's hanging basket materials inside convenient to operate of photographic head, starts hanging basket in good time.
Accompanying drawing explanation
Fig. 1 is the structural representation of anti-overload formula building hanging basket.
Fig. 2 is the structural representation of operating room in anti-overload formula building hanging basket.
Fig. 3 is the structural representation of anti-overload formula building hanging basket medium power case.
In figure: 1-guide wheel, 2-wheel bracket, 3-crossbeam, seat fixed by 4-wirerope, 5-overload circuit breaker, 6-wirerope, the main pillar of 7-, 8-movable pulley, 9-movable pulley bearing, 10-guide roller, 11-floor induction apparatus, 12-hanging basket, 13-elastic support, 14-base plate, 15-headstock, 16-transmission main shaft, 17-capstan winch, 18-operating room, 19-photographic head, 20-limit switch, 21-motor, 22-decelerator, 23-display screen.
Detailed description of the invention
Below in conjunction with detailed description of the invention, the technical scheme of this patent is described in more detail.
Referring to Fig. 1-3, a kind of anti-overload formula building hanging basket, including guide wheel 1, crossbeam 3, overload circuit breaker 5, wirerope 6, main pillar 7, hanging basket 12 and headstock 15;Described guide wheel 1 is arranged on the upper right side of wheel bracket 2, is positioned at the upside of crossbeam 3, for guiding wirerope 6, is supported wirerope 6 simultaneously;Described wheel bracket 2 is welded on the upper surface left end of crossbeam 3, for being supported guide wheel 1 and fixing;Described crossbeam 3 is steel structure beam, and two ends, left and right are connected with main pillar 7 by bolt, for the pulling force born during hanging basket 12 lifting on wirerope 6;Described main pillar 7 is connected with base plate 14 by bolt, is positioned at the upside of base plate 14, for supporting and fixed cross beam 3, is guided the up and down motion of hanging basket 12 by guide roller 10 simultaneously;Wirerope is fixed seat 4 and is arranged on the lower surface right positions of crossbeam 3, for being fixed the right-hand member of wirerope 6;Overload circuit breaker 5 is arranged on wirerope 6 and the junction of seat 4 fixed by wirerope, and when the load of hanging basket 12 is more than 1 ton hour, then overload circuit breaker 5 will send alarm, and disconnects the supply line of motor 21, can effectively prevent hanging cradle overload to run, substantially increase safety;Described wirerope 6 right-hand member is fixed on wirerope and fixes on seat 4, and left end is fixed on capstan winch 17, and centre sequentially passes through movable pulley 8 and guide wheel 1, for promoting hanging basket 12;Described movable pulley 8 is arranged on movable pulley bearing 9, by with wirerope 6 with the use of, during hanging basket 12 is promoted, reduce the lifting pulling force on wirerope 6;Described movable pulley bearing 9 is welded on the top right positions of hanging basket 12, is used for connecting movable pulley 8 and hanging basket 12;Guide roller 8 is arranged on the gap location between hanging basket 12 and main pillar 7, for guiding the up and down motion of hanging basket 12, it is to avoid hanging basket 12 collides with main pillar 7;Floor induction apparatus 11 is arranged on the outer wall right side central position of hanging basket 12, for sensing the story height residing for hanging basket 12;Photographic head 19 is arranged on hanging basket 12 inner tip, and photographic head 19 is connected with display screen 23 by cable simultaneously, it is simple to operator observe the situation of the internal workers carry's material of hanging basket 12 when hanging basket 12 arrival floor;Elastic support 13 is arranged on the bottom of hanging basket 12, for reducing when hanging basket 12 drops to ground in the face of the impact of hanging basket 12;Capstan winch 17 is arranged on transmission main shaft 16, and section is H-shaped, and material is 45 steel, draws wirerope 6 for strand, is promoted hanging basket 12 by movable pulley 8;Transmission main shaft 16 front end is connected with capstan winch 17, and rear end is connected with decelerator 22, for the power that decelerator 22 exports is delivered to capstan winch 17;Operating room 18 is welded on the left end of base plate 14;It is internal that motor 21 is arranged on headstock 15, is connected with decelerator 22 by V belt translation, provides power for the lifting for hanging basket 12;Limit switch 20 is arranged on the upper position of main pillar 7, for being controlled the upward stroke of hanging basket, prevents hanging basket 12 from bumping against with crossbeam 3.
Above the better embodiment of this patent is explained in detail, but this patent is not limited to above-mentioned embodiment, in the ken that one skilled in the relevant art is possessed, it is also possible to make a variety of changes on the premise of without departing from this patent objective.

Claims (4)

1. an anti-overload formula building hanging basket, including guide wheel, crossbeam, overload circuit breaker, wirerope, main pillar, hanging basket and headstock;It is characterized in that, described guide wheel is arranged on the upper right side of wheel bracket, is positioned at the upside of crossbeam;Described wheel bracket is welded on the upper surface left end of crossbeam;Described main pillar is connected with base plate by bolt, is positioned at the upside of base plate;Wirerope is fixed seat and is arranged on the lower surface right positions of crossbeam;Overload circuit breaker is arranged on wirerope and the junction of seat fixed by wirerope;Movable pulley is arranged on movable pulley bearing;Described movable pulley bearing is welded on the top right positions of hanging basket;Guide roller is arranged on the gap location between hanging basket and main pillar;Floor induction apparatus is arranged on the outer wall right side central position of hanging basket;Photographic head is arranged on hanging basket inner tip, and photographic head is connected with display screen by cable simultaneously;Elastic support is arranged on the bottom of hanging basket;Transmission main shaft front end is connected with capstan winch, and rear end is connected with decelerator;Operating room is welded on the left end of base plate;Motor is arranged on inside headstock, is connected with decelerator by V belt translation;Limit switch is arranged on the upper position of main pillar.
Anti-overload formula building hanging basket the most according to claim 1, it is characterised in that described crossbeam is steel structure beam, two ends, left and right are connected with main pillar by bolt.
Anti-overload formula building hanging basket the most according to claim 1, it is characterised in that described wirerope right-hand member is fixed on wirerope and fixes on seat, and left end is fixed on capstan winch, and centre sequentially passes through movable pulley and guide wheel.
Anti-overload formula building hanging basket the most according to claim 1, it is characterised in that described capstan winch is arranged on transmission main shaft, and section is H-shaped, and material is 45 steel.
CN201620358694.0U 2016-04-22 2016-04-22 Formula construction hanging basket prevents overloading Expired - Fee Related CN205634711U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620358694.0U CN205634711U (en) 2016-04-22 2016-04-22 Formula construction hanging basket prevents overloading

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620358694.0U CN205634711U (en) 2016-04-22 2016-04-22 Formula construction hanging basket prevents overloading

Publications (1)

Publication Number Publication Date
CN205634711U true CN205634711U (en) 2016-10-12

Family

ID=57063663

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620358694.0U Expired - Fee Related CN205634711U (en) 2016-04-22 2016-04-22 Formula construction hanging basket prevents overloading

Country Status (1)

Country Link
CN (1) CN205634711U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112096045A (en) * 2020-08-04 2020-12-18 深圳丰发一诺科技有限公司 Overload-proof hanging basket

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112096045A (en) * 2020-08-04 2020-12-18 深圳丰发一诺科技有限公司 Overload-proof hanging basket

Similar Documents

Publication Publication Date Title
CN204625039U (en) A kind of safe tower crane
CN205590191U (en) Prevent overload formula building tower crane
CN202080836U (en) Material lifting equipment for aerial operation
CN207671388U (en) Inflation film winder quickly up and down winding apparatus
CN114193584B (en) Concrete vibrating rod conveying device with collision prevention function for pouring construction
CN202785364U (en) Movable dual-door-type mast hoisting device
CN205634711U (en) Formula construction hanging basket prevents overloading
CN104453201A (en) Automatic ascending and descending type material platform
CN214989776U (en) Bridge crane with anti-swing function
CN215101557U (en) Multifunctional anti-shaking device of crane
CN205604697U (en) Hook type high -place operation hanging basket
CN205324714U (en) Ladle tilting mechanism
CN101692407B (en) Automatic lifting cable arrangement frame
CN108035530B (en) Oil tank inner wall construction hanging basket
CN205990204U (en) Cable overhauls manhole cover lifting device
CN212101728U (en) Special crane wound by double steel wire ropes for metallurgy
CN204454165U (en) A kind of vehicle for construction material elevator
CN205419582U (en) Floor hoist
CN219906905U (en) Lifting platform for overhauling inside upper end shaft of generator set
CN204508614U (en) Portable kink changing rig
CN205275060U (en) Gantry crane
CN202684364U (en) Loading and balancing device for working beam
CN201864541U (en) Maintenance truck used for hoisting underwater equipments
CN210973782U (en) High-altitude operation equipment for building engineering
CN221318885U (en) Self-balancing guiding lifting device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161012

Termination date: 20180422

CF01 Termination of patent right due to non-payment of annual fee