CN205618058U - Building grid deflection control structure - Google Patents

Building grid deflection control structure Download PDF

Info

Publication number
CN205618058U
CN205618058U CN201620213023.5U CN201620213023U CN205618058U CN 205618058 U CN205618058 U CN 205618058U CN 201620213023 U CN201620213023 U CN 201620213023U CN 205618058 U CN205618058 U CN 205618058U
Authority
CN
China
Prior art keywords
grid
control structure
deflection control
shaped channel
drag
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620213023.5U
Other languages
Chinese (zh)
Inventor
沈尧
赵晓晖
方志仁
柳林
杨洪春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Guangtian Group Ltd By Share Ltd
Original Assignee
Shenzhen Grandland Decoration Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Grandland Decoration Group Co Ltd filed Critical Shenzhen Grandland Decoration Group Co Ltd
Priority to CN201620213023.5U priority Critical patent/CN205618058U/en
Application granted granted Critical
Publication of CN205618058U publication Critical patent/CN205618058U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Tents Or Canopies (AREA)

Abstract

The utility model relates to a building grid amount of deflection control structure, including grid frame (1), install a plurality of grids (2) that arrange in proper order on grid frame (1), grid frame (1) is by a set of relative first C type groove (3) and a set of relative second C type groove (4) end to end connection constitution square frame, the both ends of each grid (2) are fixed in on the first C type groove (3) at both ends through first screw (5); the pull cable (6) sequentially penetrates through a through hole (8) matched with each grating (2), and two ends of the pull cable (6) are fixed on second C-shaped grooves (4) at two ends through bolts (9); each grid (2) is clamped between two corresponding hoops (7) on the inhaul cable (6). The utility model has the characteristics of the construction is simple, practice thrift the cost, do not influence pleasing to the eye.

Description

A kind of building grid amount of deflection control structure
Technical field
This utility model relates to building decoration field, especially relates to a kind of building grid amount of deflection control structure.
Background technology
Grid all has been widely used in fields such as construction, design decorations, can be used in the structures such as ceiling, wall or fences, and it at decoration and the most all has characteristic.
Nowadays according to Building Design demand, the dimension of opening installing grid is increasing, thus required grid also does longer and longer, and length-width ratio is done bigger and bigger.But after grid length-width ratio becomes greatly, under the effect in grid deadweight or vertical wind excitation direction, grid can bear bigger power, bear bigger power for a long time and easily make grid produce permanent deformation, affect aesthetics.In prior art, in order to prevent long bar grating amount of deflection not enough, workmen uses after being interrupted by grid, increases reinforcement on grid, and to reduce grid deformation, but the method construction is more complicated, and affects the attractive, decorative effect of grid;It addition, some solutions are the size of grid itself to carry out widen thickening process, to strengthen the ability of anti-deformation of himself, but the method can increase material usage, thus increases cost.
Utility model content
The technical problems to be solved in the utility model is to provide a kind of building grid amount of deflection control structure, has the advantages that construction is simple, cost-effective, do not affect the appearance.
In order to solve above-mentioned technical problem, this utility model provides a kind of building grid amount of deflection control structure, including grid housing, the some grids being arranged in order that are installed on grid housing, described grid housing is to be connected, by the second C-shaped channel that one group of first relative C-shaped channel is relative with a group, the square frame formed from beginning to end, and the two ends of every described grid are fixed in first C-shaped channel at two ends by the first screw;Also including drag-line and some location clip, described drag-line sequentially passes through through hole adaptive on every bar grating, and the two ends of described drag-line are secured by bolts in second C-shaped channel at two ends;Between two clips of correspondence that every described grid (2) is placed on described drag-line.
It is preferred that, described grid is lined with opening cushion film with the centre of clip.
It is preferred that, described cushion film is that anti-corrosion material is made.
It is preferred that, described through hole is positioned at centre or the side of grid.
It is preferred that, described drag-line is can the steel cable of load.
It is preferred that, the quantity of described through hole or drag-line is one or more.
It is preferred that, the opening with two described second C-shaped channel of two described first C-shaped channel is snapped on corresponding the first adaptive hanger and the second hanger, and described first hanger and the second hanger are fixed in the respective face of matrix by the second screw.
It is preferred that, described first C-shaped channel and described second C-shaped channel are aluminum systems.
It is preferred that, the surrounding of described first hanger and described second hanger is filled with for reinforcing and waterproof magma.
This utility model relates to a kind of building grid amount of deflection control structure, compared with existing design, have an advantage in that: first, grid arranges through hole, and penetrates drag-line in through-holes, by the positioning lathe dog of grid upper and lower surface, grid is fixed on drag-line suitably position, drag-line has shared partial grid deadweight and the active force of wind load, thus controls grid amount of deflection, neither affects the attractive in appearance of grid entirety, construction is simple again, cost-effective.
Further, opening cushion film it is lined with between clip and grid, the clip abrasion to grid is avoided on the premise of clip stationary grizzly, add the service life of grid, when opening cushion film serious wear, directly pull down from the opening part interface of opening cushion film, it is convenient for changing, under specific environment, opening cushion film uses anti-corrosion material to make, and prevents it to be corroded.On grid, lead to the hole site can be at middle or other active position, and motility is strong;Drag-line uses steel cable, owing to steel cable hardness is reliable, makes less size and can also meet force request, thus do not affect the attractive in appearance of overall grid;In order to better control over the amount of deflection of grid, multiple through hole can be started on grid and use a plurality of drag-line.Grid housing uses conventional aluminum square tube, draws materials conveniently.
Accompanying drawing explanation
Fig. 1 is this utility model building grid amount of deflection control structure longitudinal cross-section schematic diagram.
Fig. 2 is this utility model building grid amount of deflection control structure transverse sectional view.
Fig. 3 is this utility model building grid amount of deflection control structure partial enlarged drawing.
Fig. 4 is the schematic cross-section of clip in this utility model building grid amount of deflection control structure.
Fig. 5 is cushion film schematic diagram in this utility model building grid amount of deflection control structure.
Reference is as follows:
1-grid housing, 2-grid, 3-the first C-shaped channel, 4-the second C-shaped channel, 5-the first screw, 6-drag-line, 7-clip, 8-through hole, 9-bolt, 10-cushion film, 11-the first hanger, 12-the second hanger, 13-the second screw 13,14-matrix.
Detailed description of the invention
As shown in Figure 1-2, this utility model relates to a kind of building grid amount of deflection control structure, including by the second C-shaped channel 4 that one group of first relative C-shaped channel 3 is relative with a group connect from beginning to end the grid housing 1 formed, the some grids 2 being arranged in order being installed on grid housing 1, through the drag-line 6 of grid through hole 8 and some clips 7 for location grid.
The two ends of every bar grating 2 are fixed in first C-shaped channel 3 at two ends by the first screw 5, every bar grating 2 amount of deflection inadequate centre or other active position, the such as side of grid 2, offer one or more through hole 8, the described drag-line 6 of respective numbers sequentially passes through through hole 8, thus some grids 2 are placed through on drag-line 6, the two ends of described drag-line 6 are fixed in second C-shaped channel 4 at two ends by bolt 9.The grid housing 1 of the first C-shaped channel 3 and the second C-shaped channel 4 composition uses aluminum material, conveniently draws materials, and economical and practical, the shape of the grid housing 1 formed can be square or rhombus or other shapes, with enrichment effect;Drag-line 6 uses steel cable, and intensity is reliable, uses less size can meet load requirement, does not affects the appearance.
As shown in Figure 2-5, multiple clips 7 are placed on drag-line 6, make every bar grating 2 be stuck between two clips 7, opening cushion film 10 is inserted between clip 7 and grid 2, mobile clip 7 so that it is after being close to opening cushion film 10, tighten the bolt on clip 7, grid 2 to be fixed on drag-line 6 suitable position, drag-line 6 has shared partial grid 2 deadweight and the active force of wind load, thus controls grid 2 amount of deflection, neither affects the attractive in appearance of grid entirety, construction is simple again, cost-effective;Opening cushion film 10 can avoid the clip 7 direct abrasion to grid 2, and open design facilitates the replacing of opening cushion film 10, under specific environment, anticorrosive can be used to make.
As shown in Figure 1-2, the opening with two the second C-shaped channel 4 of two the first C-shaped channel 3 is snapped on corresponding first hanger 11 and the second hanger 12 adaptedly, and described first hanger 11 and the second hanger 12 are fixed in the respective face of matrix 14 by the second screw 13.
Filling magma around described first hanger 11 and described second hanger 12, reaches to reinforce and waterproof effect.

Claims (9)

1. a building grid amount of deflection control structure, including grid housing (1), the some grids (2) being arranged in order being installed on grid housing (1), described grid housing (1) is to be connected, by the second C-shaped channel (4) that one group of relative first C-shaped channel (3) is relative with a group, the square frame formed from beginning to end, the two ends of every described grid (2) are fixed in first C-shaped channel (3) at two ends by the first screw (5), it is characterized in that: also include drag-line (6) and some location clip (7), described drag-line (6) sequentially passes through the upper adaptive through hole (8) of every bar grating (2), the two ends of described drag-line (6) are fixed in second C-shaped channel (4) at two ends by bolt (9);Between two clips (7) of correspondence that every described grid (2) is placed on described drag-line (6).
A kind of building grid amount of deflection control structure the most according to claim 1, it is characterised in that: described grid (2) is lined with opening cushion film (10) with the centre of clip (7).
A kind of building grid amount of deflection control structure the most according to claim 2, it is characterised in that: described cushion film (10) is that anti-corrosion material is made.
A kind of building grid amount of deflection control structure the most according to claim 1, it is characterised in that: described through hole (8) is positioned at centre or the side of grid (2).
A kind of building grid amount of deflection control structure the most according to claim 1, it is characterised in that: described drag-line (6) is can the steel cable of load.
A kind of building grid amount of deflection control structure the most according to claim 1, it is characterised in that: the quantity of described through hole (8) or drag-line (6) is one or more.
A kind of building grid amount of deflection control structure the most according to claim 1, it is characterized in that: the opening with two described second C-shaped channel (4) of two described first C-shaped channel (3) is snapped on corresponding adaptive the first hanger (11) and the second hanger (12), and described first hanger (11) and the second hanger (12) are fixed in the respective face of matrix (14) by the second screw (13).
A kind of building grid amount of deflection control structure the most according to claim 1 and 2, it is characterised in that: described first C-shaped channel (3) and described second C-shaped channel (4) they are aluminum systems.
A kind of building grid amount of deflection control structure the most according to claim 7, it is characterised in that: the surrounding of described first hanger (11) and described second hanger (12) is filled with for reinforcing and waterproof magma.
CN201620213023.5U 2016-03-21 2016-03-21 Building grid deflection control structure Active CN205618058U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620213023.5U CN205618058U (en) 2016-03-21 2016-03-21 Building grid deflection control structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620213023.5U CN205618058U (en) 2016-03-21 2016-03-21 Building grid deflection control structure

Publications (1)

Publication Number Publication Date
CN205618058U true CN205618058U (en) 2016-10-05

Family

ID=57031033

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620213023.5U Active CN205618058U (en) 2016-03-21 2016-03-21 Building grid deflection control structure

Country Status (1)

Country Link
CN (1) CN205618058U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108411797A (en) * 2018-02-09 2018-08-17 广西交通科学研究院有限公司 Vault amount of deflection control method in Catenary arch arch springing increasing section strengthening construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108411797A (en) * 2018-02-09 2018-08-17 广西交通科学研究院有限公司 Vault amount of deflection control method in Catenary arch arch springing increasing section strengthening construction

Similar Documents

Publication Publication Date Title
CN205688638U (en) Beam-string structure, beam string and building
CN102619226B (en) Pressure dispersion type yielding anchor cable
CN105040577B (en) A kind of multi-component alloy co-cementation bridge pre-buried steel component
CN202543920U (en) Pressure distributed type yielding anchor cable
CN102776969A (en) Aluminum-coated steel curtain wall section structure
CN101705660B (en) Reaction frame prestress anchoring system and method for vertical rotating steel pipe arch on concrete bridge
CN205618058U (en) Building grid deflection control structure
CN214575056U (en) Pull rod supporting ceiling conversion layer structure
CN205777000U (en) A kind of prestressed steel structure cable support node
CN202390970U (en) Text curtain wall
CN210217152U (en) Wall form split bolt
CN206555564U (en) A kind of suspension rod and fastener applied to antidetonation suspension and support
CN201665956U (en) Prestressed parallel steel stranded wire assembly cable structure in annular closed steel tube
CN212743032U (en) Outer wall bearing wallboard for pre-assembly building installation
CN213015701U (en) Gas film connecting steel cable pulley assembly
CN212078409U (en) Suspended ceiling component
CN205171834U (en) Sealed anti -skidding prestressing force stretch -draw end ground tackle
CN204826867U (en) Building construction protection fence of steel cable structure
KR100785435B1 (en) A water-tank with support-bar connected to hub
CN210687243U (en) Finished product support hanger
CN210927516U (en) Photovoltaic module support and device for preventing purlin from being unstable due to wind-borne suction
CN215414717U (en) Clamp suitable for drawing experiment of check net
KR20120115923A (en) Fixing device of lightweight steel for underground double wall
CN205046523U (en) Assembled ditch
CN208221764U (en) A kind of row's card with cover

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 518000 Guangdong, Shenzhen, Luohu District, Yanhe Road 1003, Beijing capital east 1~2 level.

Patentee after: Shenzhen Guangtian group Limited by Share Ltd

Address before: 518000 Guangdong, Shenzhen, Luohu District, Yanhe Road 1003, Beijing capital east 1~2 level.

Patentee before: Shenzhen Guangtian Decoration Group Co., Ltd.

CP01 Change in the name or title of a patent holder