CN205617634U - Constructional steel structure floor - Google Patents
Constructional steel structure floor Download PDFInfo
- Publication number
- CN205617634U CN205617634U CN201620342078.6U CN201620342078U CN205617634U CN 205617634 U CN205617634 U CN 205617634U CN 201620342078 U CN201620342078 U CN 201620342078U CN 205617634 U CN205617634 U CN 205617634U
- Authority
- CN
- China
- Prior art keywords
- floor
- steel
- top layer
- plate
- steel structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Floor Finish (AREA)
Abstract
The utility model relates to a constructional steel structure floor, by the precast concrete bottom plate, middle fossil fragments and cast in situ concrete top layer are constituteed, on middle fossil fragments longitudinal separation setting and the precast concrete bottom plate, cast in situ concrete top layer on precast concrete bottom plate and the middle fossil fragments, inlay many steel pipes in the concrete top layer, the steel pipe is the cavity form, can lay wire or settle the required water pipe of factory building in the steel pipe, can play the guard action to electric wire and water pipe, be equipped with a plurality of locating pins and locating hole on two curb plates of floor respectively, adjacent floor is when the concatenation, locating hole block on the locating pin on the curb plate of a floor and the curb plate of adjacent floor, locating pin and locating hole mainly play the effect of two the concatenation floors in location.
Description
Technical field
This utility model relates to construction steel structure field, especially a kind of construction steel structure floor.
Background technology
Floor includes cast-in-situ floor and precast floor slab, cast-in-situ floor good integrity, but needs on-the-spot formwork, casting concrete,
Long construction period, difficulty are big, template consume is big, cost is high, and precast floor slab is not required to on-the-spot formwork, short construction period, and cost is low, but
Prefabricated components are from great, and lifting difficulty, component assembly position is easily generated crack, and globality is poor, along with the development of industry, existing
Factory Building be on the increase, the floor of present common Factory Building be typically all replaced by steel plate, can exist insufficient strength and every
The phenomenon that sound is bad, and, present floor all exists quality, and greatly or splicing gap is big, needs cast, causes construction to bother,
Cost is high, and present floor is substantially unsuitable for Factory Building and uses.
Utility model content
The purpose of this utility model is to solve in prior art the defect existing for floor, it is provided that a kind of construction(al)steel
Structure floor.
To achieve these goals, the technical solution adopted in the utility model is:
A kind of construction steel structure floor, by concrete prefabricated base plate, middle Os Draconis and cast-in-place concrete top layer composition, mixed
Solidifying soil prefabricated panel is made up of hot-galvanized steel silk screen, horizontal draw-in groove steel band, side plate and casting concrete layer, and side plate is a pair right angle
Base plate, is arranged on concrete prefabricated base plate longitudinal direction dual-side, and steel wire is arranged between pair of side plates and is connected with bottom surface, right angle, horizontal
It is connected on steel wire to the interval setting of draw-in groove steel band;
The middle longitudinally spaced setting of Os Draconis is with on concrete prefabricated base plate, and concrete prefabricated base plate is cast-in-place with on middle Os Draconis
Concrete top layer, inlays many steel pipes in concrete top layer, steel pipe is hollow form, and it is multiple fixed that said two side plate is respectively equipped with
Position pin and location hole, adjacent floor splicing time, the alignment pin on the side plate of a floor and determining on the side plate of adjacent floor deck
Location hole card closes.
Above-mentioned a kind of construction steel structure floor, described middle Os Draconis are C-type steel.
Above-mentioned a kind of construction steel structure floor, the rubber-coated set in outside of described floor, band at the periphery of rubber sleeve
There is sealing strip.
Above-mentioned a kind of construction steel structure floor, described rubber sleeve and sealing strip are one-body molded.
The beneficial effects of the utility model are: inlay many steel pipes in the concrete top layer of this construction steel structure floor,
Steel pipe is hollow form, can connect up or dispose the water pipe needed for Factory Building in steel pipe, electric wire and water pipe can play protection and make
With, two side plates of floor are respectively equipped with multiple alignment pin and location hole, adjacent floor splicing time, the side of a floor
Alignment pin on plate engages with the hole, location on the side plate of adjacent floor deck, and alignment pin and hole, location primarily serve two splicings in location
The effect of floor, it is ensured that on one wire, and the rubber-coated set in the outside of floor, rubber sleeve is equivalent at floor spliced floor
Carpet is laid on surface, plays anti-skidding and is easy to the effect cleaned, with sealing strip at the periphery of rubber sleeve, splicing at floor
Time, sealing strip plays the effect sealing piece, easy to use.
Accompanying drawing explanation
Fig. 1 is schematic diagram of the present utility model;
Fig. 2 is schematic side view of the present utility model.
Detailed description of the invention
As shown in Figure 1 and Figure 2, a kind of construction steel structure floor, by concrete prefabricated base plate 1, middle Os Draconis 2 and cast-in-place
Concrete top layer 3 forms, and concrete prefabricated base plate 1 is by hot-galvanized steel silk screen 4, horizontal draw-in groove steel band 5, side plate 6 and casting coagulation
Soil layer forms, and side plate 6 is a pair right angle base plate, is arranged on the longitudinal dual-side of concrete prefabricated base plate 1, and steel wire 4 is arranged on one
Being connected with bottom surface, right angle between side plate 6, horizontal draw-in groove steel band 5 is spaced setting and is connected on steel wire 4;
In the middle longitudinally spaced setting of Os Draconis 2 and concrete prefabricated base plate 1, on concrete prefabricated base plate 1 and middle Os Draconis 2
Cast-in-place concrete top layer 3, inlays many steel pipes 7 in concrete top layer 3, steel pipe 7, in hollow form, two side plates 6 is respectively equipped with
Multiple alignment pins 8 and hole 9, location, adjacent floor when splicing, the alignment pin 8 on the side plate 6 of a floor and adjacent floor deck
Hole, location 9 on side plate engages.
In this utility model, middle Os Draconis 2 are C-type steel, the rubber-coated set in outside of floor, band at the periphery of rubber sleeve
There are sealing strip 10, rubber sleeve and sealing strip 10 one-body molded.
Inlaying many steel pipes 7 in the concrete top layer 3 of this construction steel structure floor, steel pipe 7 is in hollow form, in steel pipe 7
Can connect up or dispose the water pipe needed for Factory Building, electric wire and water pipe can be played a protective role, on two side plates 6 of floor
Be respectively equipped with multiple alignment pin 8 and hole 9, location, adjacent floor when splicing, the alignment pin 8 on the side plate of a floor and phase
Hole, location 9 on the side plate of adjacent floor engages, and alignment pin 8 and hole 9, location primarily serve the effect of two spliced floors in location, protect
Demonstrate,prove spliced floor on one wire, and the rubber-coated set in the outside of floor, rubber sleeve is equivalent to lay carpet in slab surfaces,
Play anti-skidding and be easy to the effect cleaned, with sealing strip 10 at the periphery of rubber sleeve, when floor splices, sealing strip 10
To the effect of sealing piece, easy to use.
Of the present utility model ultimate principle, principal character and of the present utility model advantage have more than been shown and described.One's own profession
Skilled person will appreciate that of industry, this utility model is not restricted to the described embodiments, described in above-described embodiment and description
Simply principle of the present utility model, on the premise of without departing from this utility model spirit and scope, this utility model also has respectively
Planting changes and improvements, these changes and improvements both fall within the range of claimed this utility model.This utility model requirement
Protection domain defined by appending claims and equivalent thereof.
Claims (4)
1. a construction steel structure floor, by concrete prefabricated base plate, middle Os Draconis and cast-in-place concrete top layer composition, coagulation
Soil prefabricated panel is made up of hot-galvanized steel silk screen, horizontal draw-in groove steel band, side plate and casting concrete layer, and side plate is at the bottom of a pair right angle
Plate, is arranged on concrete prefabricated base plate longitudinal direction dual-side, and steel wire is arranged between pair of side plates and is connected with bottom surface, right angle, laterally
The interval setting of draw-in groove steel band is connected on steel wire;
It is characterized in that, middle Os Draconis are longitudinally spaced is arranged on concrete prefabricated base plate, concrete prefabricated base plate and centre dragon
Cast-in-place concrete top layer on bone, inlays many steel pipes in concrete top layer, steel pipe is hollow form, and said two side plate sets respectively
Have multiple alignment pin and hole, location, adjacent floor when splicing, the side of the alignment pin on the side plate of a floor and adjacent floor deck
Hole, location engaging on plate.
A kind of construction steel structure floor the most according to claim 1, it is characterised in that described middle Os Draconis are C-type steel.
A kind of construction steel structure floor the most according to claim 1, it is characterised in that the outside cladding rubber of described floor
Gum cover, with sealing strip at the periphery of rubber sleeve.
A kind of construction steel structure floor the most according to claim 3, it is characterised in that described rubber sleeve and sealing strip one
Body formed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620342078.6U CN205617634U (en) | 2016-04-21 | 2016-04-21 | Constructional steel structure floor |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620342078.6U CN205617634U (en) | 2016-04-21 | 2016-04-21 | Constructional steel structure floor |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205617634U true CN205617634U (en) | 2016-10-05 |
Family
ID=57026975
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620342078.6U Expired - Fee Related CN205617634U (en) | 2016-04-21 | 2016-04-21 | Constructional steel structure floor |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205617634U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109322410A (en) * | 2018-11-06 | 2019-02-12 | 辽宁福瑞达建筑科技有限公司 | Low-rise Lightweight Steel structural construction floor connect engineering method with metope node |
CN109322411A (en) * | 2018-11-06 | 2019-02-12 | 辽宁福瑞达建筑科技有限公司 | Multiple-story Lightweight Steel building floor connect engineering method with metope node |
-
2016
- 2016-04-21 CN CN201620342078.6U patent/CN205617634U/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109322410A (en) * | 2018-11-06 | 2019-02-12 | 辽宁福瑞达建筑科技有限公司 | Low-rise Lightweight Steel structural construction floor connect engineering method with metope node |
CN109322411A (en) * | 2018-11-06 | 2019-02-12 | 辽宁福瑞达建筑科技有限公司 | Multiple-story Lightweight Steel building floor connect engineering method with metope node |
CN109322410B (en) * | 2018-11-06 | 2020-07-24 | 辽宁福瑞达建筑科技有限公司 | Low-rise light steel structure building floor and wall surface joint connection construction method |
CN109322411B (en) * | 2018-11-06 | 2020-07-24 | 辽宁福瑞达建筑科技有限公司 | Construction method for connecting multi-layer light steel structure building floor slab and wall surface node |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206486820U (en) | Repair fixing device in a kind of road and bridge crack | |
CN104032869B (en) | A kind of Prefabricated stacking floor and precast construction method thereof | |
CN205617634U (en) | Constructional steel structure floor | |
CN105442629A (en) | Construction method for T-shaped platform vibration-isolating base of large-scale equipment | |
CN204112860U (en) | Detachable enclosure wall | |
CN207130569U (en) | A kind of pavement laying structure with inspection shaft cover plate | |
CN204960002U (en) | Novel assembled coincide floor bottom piece structure | |
CN204266150U (en) | A kind of hard isolated column for old bridge dividing strip | |
CN203782515U (en) | Highway pavement structure | |
CN210085961U (en) | Porous concrete water-permeable floor tile | |
CN104074354A (en) | Plate-insertion type cast-in-place staircase template and use method of plate-insertion type cast-in-place staircase template | |
CN202430939U (en) | Splicing structure of stone floor and wood floor | |
CN207672616U (en) | A kind of outdoor cable penetration pipe is passed by one's way laying structure | |
CN203007827U (en) | Bridge gap filling device | |
CN206233564U (en) | Drop plate formwork erection structure | |
CN204803750U (en) | Waterproof type bridge expansion joint | |
CN205224252U (en) | Sump pit construction mould | |
CN204825561U (en) | Chain function hidden concrete road curbing | |
CN204826374U (en) | Waterproof wall brick | |
CN203347221U (en) | Concrete pouring formwork | |
CN205577374U (en) | Pavement device is prevented trampling by floor reinforcing bar | |
CN104120827B (en) | Ship rail type bare concrete wallboard and construction method thereof | |
CN205012197U (en) | Imitative brick with high water permeability ability | |
CN203188084U (en) | In-field shoulder-stone-free secondary concrete road | |
CN204151766U (en) | A kind of Pure-Concrete-Pile Composite Subgrade |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20161005 Termination date: 20190421 |
|
CF01 | Termination of patent right due to non-payment of annual fee |