CN205604272U - Manger plate cofferdam - Google Patents

Manger plate cofferdam Download PDF

Info

Publication number
CN205604272U
CN205604272U CN201620291622.9U CN201620291622U CN205604272U CN 205604272 U CN205604272 U CN 205604272U CN 201620291622 U CN201620291622 U CN 201620291622U CN 205604272 U CN205604272 U CN 205604272U
Authority
CN
China
Prior art keywords
fill
water
clay core
cofferdam
opposite direction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620291622.9U
Other languages
Chinese (zh)
Inventor
黄智文
姚春燕
李燕
李晶晶
黄智献
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Poly Water Conservancy Engineering Co Ltd
Original Assignee
Zhejiang Poly Water Conservancy Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Poly Water Conservancy Engineering Co Ltd filed Critical Zhejiang Poly Water Conservancy Engineering Co Ltd
Priority to CN201620291622.9U priority Critical patent/CN205604272U/en
Application granted granted Critical
Publication of CN205604272U publication Critical patent/CN205604272U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

The utility model relates to a water conservancy construction technical field, concretely relates to manger plate cofferdam. Being included in proper order by upstream face to back side and clashing dyke, clay core and fill, the clay core below is equipped with the concrete cut -pff wall, is equipped with the rock revetment layer on the upstream face of dyke, clay core and fill in an opposite direction. Cost is reduced the time, guaranteed the structure in cofferdam, it provides the safety guarantee to construct for low reaches.

Description

A kind of water-retaining cofferdam
Technical field
This utility model relates to water conservancy construction technical field, is specifically related to a kind of water-retaining cofferdam.
Background technology
Cofferdam refers in water conservancy, water transport engineering project, for building permanent water conservancy projects, the provisional building enclosure built.Its effect be prevent water, soil enter building build position, in order at cofferdam internal drainage, excavation pit, build building.
Damming is the key project in construction of hydro project, has certain risk, and cofferdam used in therefore damming needs possess enough safeties.All there is shortcoming in the steadiness in current cofferdam and barrier, for the cofferdam that construction structure is more stable, required materials are complicated, are unfavorable for reducing the cost in water conservancy construction work progress.
Summary of the invention
The purpose of this utility model is to solve described problem, it is provided that a kind of water-retaining cofferdam, for upstream dash, upstream water-retaining cofferdam can provide safety guarantee for the construction in downstream, materials are simple simultaneously, reliable in quality, it is ensured that also reduce construction cost while construction quality.
In order to reach above-mentioned utility model purpose, this utility model by the following technical solutions:
A kind of water-retaining cofferdam, is included dike, clay core wall and fill in an opposite direction by upstream face to back side, is provided with concrete cutoff wall below clay core wall, the upstream face of dike, clay core wall and fill is provided with rock revetment layer in an opposite direction successively.
Preferably, the gradient of dike is 1:2 in an opposite direction, and the gradient of fill is 1:1.2.
Preferably, the thickness of clay core wall is 2-3m.
Preferably, the height of concrete cutoff wall is 3-5m, and thickness is 0.5-2m.
Preferably, dike and fill are excavated material and fill and form in an opposite direction.
Preferably, the thickness of rock revetment layer is 0.5-1m.
Preferably, the width ratio of dike, clay core wall and fill in an opposite direction is 2-2.5:1:3-5.
Preferably, in concrete cutoff wall top embeds clay core wall.
Preferably, it is additionally provided with anti-seepage geotextile layer under the rock revetment layer of fill.
Preferably, concrete cutoff wall is provided with steel sheet pile, and steel sheet pile top is positioned at clay core wall.
This utility model compared with prior art, provides the benefit that: the raw material of cofferdam construction is gathered materials on the spot, and greatly reduces cost.Although cost is reduced, but the structure in this cofferdam is the firmest, provides safety guarantee for downstream construction.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
In figure: 1 clashes dike, 2 clay core walls, 3 fills, 4 concrete cutoff walls, 5 rock revetment layers, 6 anti-seepage geotextile layers, 7 steel sheet piles.
Detailed description of the invention
Below by specific embodiment, the technical solution of the utility model is further described explanation.
Embodiment:
A kind of water-retaining cofferdam, as it is shown in figure 1, included dike 1, clay core wall 2 and fill 3 in an opposite direction successively by upstream face to back side, is provided with concrete cutoff wall 4 below clay core wall 2, concrete cutoff wall 4 top embeds in clay core wall 2.The upstream face of dike 1, clay core wall 2 and fill 3 is provided with rock revetment layer 5 in an opposite direction, and the rock revetment layer of fill 3 is additionally provided with anti-seepage geotextile layer 65 times.The gradient of dike 1 is 1:2 in an opposite direction, and the gradient of fill 3 is 1:1.2.The width of clay core wall 2 is 2-3m, and the height of concrete cutoff wall 4 is 3-5m, and thickness is 0.5-2m, and the thickness of rock revetment layer 5 is 0.5-1m;The width ratio of dike 1, clay core wall 2 and fill 3 is 2-2.5:1:3-5 in an opposite direction.Concrete cutoff wall 4 is provided with steel sheet pile 7, and steel sheet pile 7 top is positioned at clay core wall 2.
In an opposite direction dike 1 and fill 3 are excavated material and fill and form, and clay core wall 2 is formed by clay compacting,
The raw material major part of this upstream water-retaining cofferdam is gathered materials on the spot, and greatly reduces cost.Although cost is reduced, but the structure in this cofferdam is the firmest, provides safety guarantee for downstream construction.

Claims (10)

1. a water-retaining cofferdam, it is characterized in that, dike (1), clay core wall (2) and fill (3) in an opposite direction is included successively by upstream face to back side, clay core wall (2) lower section is provided with concrete cutoff wall (4), and the upstream face of dike (1), clay core wall (2) and fill (3) is provided with rock revetment layer (5) in an opposite direction.
A kind of water-retaining cofferdam the most according to claim 1, it is characterised in that the gradient of dike (1) is 1:2 in an opposite direction, and the gradient of fill (3) is 1:1.2.
A kind of water-retaining cofferdam the most according to claim 1, it is characterised in that the width of clay core wall (2) is 2-3m.
A kind of water-retaining cofferdam the most according to claim 1, it is characterised in that the height of concrete cutoff wall (4) is 3-5m, and thickness is 0.5-2m.
A kind of water-retaining cofferdam the most according to claim 1, it is characterised in that dike (1) and fill (3) are excavated material and fill and form in an opposite direction.
A kind of water-retaining cofferdam the most according to claim 1, it is characterised in that the thickness of rock revetment layer (5) is 0.5-1m.
A kind of water-retaining cofferdam the most according to claim 1, it is characterised in that the width ratio of dike (1), clay core wall (2) and fill (3) is 2-2.5:1:3-5 in an opposite direction.
A kind of water-retaining cofferdam the most according to claim 1, it is characterised in that concrete cutoff wall (4) top embeds in clay core wall (2).
A kind of water-retaining cofferdam the most according to claim 1, it is characterised in that be additionally provided with anti-seepage geotextile layer (6) under the rock revetment layer (5) of fill (3).
A kind of water-retaining cofferdam the most according to claim 1, it is characterised in that concrete cutoff wall (4) is provided with steel sheet pile (7), and steel sheet pile (7) top is positioned at clay core wall (2).
CN201620291622.9U 2016-04-07 2016-04-07 Manger plate cofferdam Expired - Fee Related CN205604272U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620291622.9U CN205604272U (en) 2016-04-07 2016-04-07 Manger plate cofferdam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620291622.9U CN205604272U (en) 2016-04-07 2016-04-07 Manger plate cofferdam

Publications (1)

Publication Number Publication Date
CN205604272U true CN205604272U (en) 2016-09-28

Family

ID=56972799

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620291622.9U Expired - Fee Related CN205604272U (en) 2016-04-07 2016-04-07 Manger plate cofferdam

Country Status (1)

Country Link
CN (1) CN205604272U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106368176A (en) * 2016-11-08 2017-02-01 中国电建集团成都勘测设计研究院有限公司 High dam structure built on deep overburden of soil material shortage area
CN106498902A (en) * 2016-11-16 2017-03-15 中国电建集团贵阳勘测设计研究院有限公司 Rapid and efficient slope fixing method
CN106638471A (en) * 2017-01-14 2017-05-10 张众 Slope protection system for water conservancy and hydropower engineering
CN113322904A (en) * 2021-06-04 2021-08-31 中国电建集团成都勘测设计研究院有限公司 High-spraying impervious wall for covering layer foundation concrete dam and construction method thereof

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106368176A (en) * 2016-11-08 2017-02-01 中国电建集团成都勘测设计研究院有限公司 High dam structure built on deep overburden of soil material shortage area
CN106368176B (en) * 2016-11-08 2019-01-01 中国电建集团成都勘测设计研究院有限公司 The high dam structure being built on earth material scarcity area deeply covered layer
CN106498902A (en) * 2016-11-16 2017-03-15 中国电建集团贵阳勘测设计研究院有限公司 Rapid and efficient slope fixing method
CN106638471A (en) * 2017-01-14 2017-05-10 张众 Slope protection system for water conservancy and hydropower engineering
CN113322904A (en) * 2021-06-04 2021-08-31 中国电建集团成都勘测设计研究院有限公司 High-spraying impervious wall for covering layer foundation concrete dam and construction method thereof
CN113322904B (en) * 2021-06-04 2022-08-19 中国电建集团成都勘测设计研究院有限公司 High-spraying impervious wall for covering layer foundation concrete dam and construction method thereof

Similar Documents

Publication Publication Date Title
CN205604272U (en) Manger plate cofferdam
CN204023501U (en) A remove dangerous and consolidate prevention of seepage processing structure for earth and rockfill dam
CN204530633U (en) The soft rock that a kind of subregion is arranged builds rock dam body
CN101644041B (en) Face rockfill dam toe board structure constructed on completely weathered bed rock and construction method thereof
CN103422510B (en) Steel pipe frame type cofferdam structure and construction method
CN103526721B (en) A kind of permeable pile foundation groynes
CN102660936A (en) Method for realizing seepage prevention of bridge wall by means of polyvinyl chloride film
CN204282308U (en) Gabion composite dam adapting to deep covering layer
CN103603335A (en) Winged shelter steel-pipe pile capable of reducing influence of soil surface loading to adjacent pile foundations
CN208949902U (en) A kind of river channel bridge bearing platform foundation pit antiseepage cofferdam
CN101831915B (en) Reinforced structure for foundation with wide defect and construction method thereof
CN203939036U (en) A kind of steel sheet pile cofferdam structure that is applicable to river course
CN106368176A (en) High dam structure built on deep overburden of soil material shortage area
CN101285302B (en) Method for reinforcing caisson of concrete dam
CN108396760B (en) Combined deviation-rectifying construction technology for inclined open caisson
CN202450501U (en) Bricking drainage structure for stilling pool
CN203530921U (en) Water-permeable pile foundation spur dike
CN113338315B (en) Earth-rock cofferdam structure of silt soft soil foundation and construction method thereof
CN105019466A (en) Construction method and structure of earth-rock cofferdam seepage-proofing system
CN214363322U (en) Wave type landscape water passing panel rock-fill dam
CN213390185U (en) Cofferdam structure that earth-rock cofferdam and concrete cofferdam combined together
CN204715304U (en) Cofferdam slope protection structure
CN204849791U (en) Structure of earth-rock cofferdam seepage-proofing system
CN202730719U (en) Rock-fill dam measuring weir
CN211621441U (en) Vertical dike structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160928

Termination date: 20170407

CF01 Termination of patent right due to non-payment of annual fee