CN205604168U - Cut short silt dyke of tide - Google Patents

Cut short silt dyke of tide Download PDF

Info

Publication number
CN205604168U
CN205604168U CN201620213758.8U CN201620213758U CN205604168U CN 205604168 U CN205604168 U CN 205604168U CN 201620213758 U CN201620213758 U CN 201620213758U CN 205604168 U CN205604168 U CN 205604168U
Authority
CN
China
Prior art keywords
dam body
dam
tide
layer
facing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620213758.8U
Other languages
Chinese (zh)
Inventor
金国旗
郑基桓
陈锡栋
俞小华
胡金水
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Lingyun Water Conservancy And Hydropower Building Co Ltd
Original Assignee
Zhejiang Lingyun Water Conservancy And Hydropower Building Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Lingyun Water Conservancy And Hydropower Building Co Ltd filed Critical Zhejiang Lingyun Water Conservancy And Hydropower Building Co Ltd
Priority to CN201620213758.8U priority Critical patent/CN205604168U/en
Application granted granted Critical
Publication of CN205604168U publication Critical patent/CN205604168U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Landscapes

  • Revetment (AREA)

Abstract

The utility model relates to a hydraulic engineering technical field, concretely relates to cut short silt dyke of tide. Setting up geotechnological non -woven fabrics layer on the mud flat, setting up the flat bottom protection of throwing layer on the geotechnological non -woven fabrics layer, flatly set up left dam body and right dam body on throwing the bottom protection layer, it has core mud to fill between left dam body and the right dam body, and left dam body and right dam body fill by the braided bag of the different external diameters of a plurality of layers of outsourcing nonwovens geotechnique cloth and form, left side dam body and right dam body are formed with the dam facing of locating basic dam crest portion by trapezoidal ji ba, and the dam facing of left dam body forms the step for its basic dam adduction, and the dam facing of right dam body is unanimous rather than jiba's side. The structural strength of this dyke is high, satisfies the high strength requirement of rough swell tidal zone, the main part is stable, the soft basic condition of adaptation silt.

Description

A kind of tide that cuts promotees silt dike
Technical field
This utility model relates to hydraulic engineering technical field, is specifically related to a kind of tide that cuts and promotees silt dike.
Background technology
China's rivers are numerous, founding of New is over more than 50 year, especially through the practice of more than 20 years large and medium water power station engineering, water conservancy diversion dams and the design of coffering and construction level improve rapidly, as Ge Zhou Ba, the Changjiang river, damming the Yangtze River of Three Gorges Projects the most all indicate that China dams on great rivers and builds cofferdam technology and ranked among the international rank of advanced units.But the dam project that mountain area rivers are mainly implemented by above-mentioned engineering, they have individual feature, basis is rock, belong to hard basis, although damming, Longkou flow velocity is bigger, but substrate scour depth will not be aggravated, construction section keeps certain, use the vertical stifled method effect of branched dike in an opposite direction notable, and it is the most few to the successful experience of Plain Soft Soil river cut-off, such as Yangtze River Delta silt area, particularly Hangzhou Wan tidal bore zone, basis is the soft base of silt being easily washed, need plus because of urban development and hydraulic engineering construction, cofferdam construction is implemented in Tidal flat lower ground district, straight stifled method is the most inapplicable.
Concrete, after Longkou is formed, near dike Longkou, there is a deeper scour hole in an opposite direction, preferred plan is that in using, block up method in cofferdam.Interior cofferdam is divided into three limits totally three back levee line, left side dike length is generally 120~150m, opposite, dike Longkou dike line length is generally 200~250m in an opposite direction, right side dike length is generally 120~150m, the characteristic easily formed inside dike in an opposite direction according to trend ditch, is set to the side dike line by tidewater frontal impact Longkou, interior cofferdam, also referred to as blocks up and cut Chao Di, the side dike line being formed trend ditch by tidewater backflow is referred to as cutting tide rush silt dike, and opposite, dike Longkou dike line is referred to as general section dike in an opposite direction.And the tide that cuts for being applied at present on the soft base of the silt of tidal bore zone promotees silt dike, structure exists service life and intensity defect.Therefore, the dykes and dams on a kind of soft base of silt being applicable to tidal bore zone are needed badly to meet the requirement of real work.
Summary of the invention
The purpose of this utility model is the problem in order to solve current above-mentioned existence, it is provided that a kind of tide that cuts promotees silt dike.
In order to reach foregoing invention purpose, this utility model by the following technical solutions:
A kind of tide that cuts promotees silt dike, beach arranges geotechnique's nonwoven layer, in geotechnique's nonwoven layer, bedding course layer is set, left dam body and right dam body are set on bedding course layer, it is filled with core mud between left dam body and right dam body, forms if left dam body and right dam body are filled by the woven bag of the various outer diameter of dried layer outsourcing non-woven geotextile;Left dam body and right dam body are by trapezoidal Ji Ba and the dam facing composition being located at base dam crest portion, and the dam facing of left dam body forms step relative to receiving in its base dam, and the dam facing of right dam body is consistent with the side of its Ji Ba.
As preferably, it is provided with a cubic metre of earth back-up coat outside left dam body, bottom earthwork back-up coat, is provided with casing.
As preferably, the outer slope of the Ji Ba of left dam body is 1:3, and the inner side gradient is 1:0.77;The outer slope of the dam facing of left dam body is 1:1.5.
As preferably, the Ji Ba of right dam body and the outer slope of dam facing are 1:1.5;The inner side gradient of Ji Ba is 1:1.5.
As preferably, described bedding course layer be thickness be the river bottom protection stone of 2-3m.
As preferably, described geotechnique's nonwoven layer uses steel nail to fix.
As preferably, the lateral surface of right dam body is provided with ripple glaze, and described ripple glaze matches with its layer structure.
As preferably, less than bottom left dam body bottom right dam body.
This utility model compared with prior art, provides the benefit that: structural strength is high, meets the high intensity requirement of tidal bore zone;Soil stability, adapts to silt soft base condition.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
In figure: 1 geotechnique's nonwoven layer, 2 bedding course layers, 3 left dam bodys, 4 right dam bodys, 5 core mud, 6 Ji Ba, 7 dam facings, 8 steps, 9 cubic metres of earth of back-up coats, 10 casings, 11 ripple glazes.
Detailed description of the invention
Below by specific embodiment, the technical solution of the utility model is further described explanation.
Embodiment:
A kind of tide that cuts promotees silt dike, as shown in Figure 1, beach arranges geotechnique's nonwoven layer 1, geotechnique's nonwoven layer 1 uses steel nail to fix, in geotechnique's nonwoven layer 1, bedding course layer 2 is set, bedding course layer 2 is the river bottom protection stone that thickness is 2-3m, and bedding course layer 2 arranges left dam body 3 and right dam body 4, less than bottom left dam body bottom right dam body;It is filled with core mud 5 between left dam body 3 and right dam body 4, forms if left dam body 3 and right dam body 4 are filled by the woven bag of the various outer diameter of dried layer outsourcing non-woven geotextile;Left dam body 3 and right dam body 4 are formed by trapezoidal base dam 6 and the dam facing 7 being located at top, base dam 6, and the dam facing 7 of left dam body 3 forms step 8 relative to receiving in its base dam 6, and the dam facing 7 of right dam body 4 is consistent with the side on its base dam 6.The lateral surface of right dam body 4 is provided with ripple glaze 11, and described ripple glaze 11 matches with its layer structure;It is provided with cubic metre of earth back-up coat 9 outside left dam body 3, bottom earthwork back-up coat 9, is provided with casing 10.The outer slope on the base dam 6 of left dam body 3 is 1:3, and the inner side gradient is 1:0.77;The outer slope of the dam facing 7 of left dam body 3 is 1:1.5;The base dam 6 of right dam body 4 and the outer slope of dam facing 7 are 1:1.5;The inner side gradient on base dam 6 is 1:1.5.

Claims (7)

1. one kind is cut tide rush silt dike, it is characterized in that, beach arranges geotechnique's nonwoven layer (1), on geotechnique's nonwoven layer (1), bedding course layer (2) is set, left dam body (3) and right dam body (4) are set on bedding course layer (2), core mud (5), left dam body (3) and right dam body (4) it is filled with if being filled by the woven bag of the various outer diameter of dried layer outsourcing non-woven geotextile and forming between left dam body (3) and right dam body (4);Left dam body (3) and right dam body (4) are by trapezoidal Ji Ba (6) and dam facing (7) composition of being located at Ji Ba (6) top, the dam facing (7) of left dam body (3) forms step (8) relative to receiving in its Ji Ba (6), and the dam facing (7) of right dam body (4) is consistent with the side of its Ji Ba (6).
One the most according to claim 1 is cut tide and is promoted silt dike, it is characterised in that left dam body (3) outside is provided with a cubic metre of earth back-up coat (9), and earthwork back-up coat (9) bottom is provided with casing (10).
One the most according to claim 1 is cut tide and is promoted silt dike, it is characterised in that the outer slope of the Ji Ba (6) of left dam body (3) is 1:3, and the inner side gradient is 1:0.77;The outer slope of the dam facing (7) of left dam body (3) is 1:1.5.
One the most according to claim 1 is cut tide and is promoted silt dike, it is characterised in that the Ji Ba (6) of right dam body (4) and the outer slope of dam facing (7) are 1:1.5;The inner side gradient of Ji Ba (6) is 1:1.5.
One the most according to claim 1 cut tide promote silt dike, it is characterised in that described bedding course layer (2) be thickness be the river bottom protection stone of 2-3m.
One the most according to claim 1 is cut tide and is promoted silt dike, it is characterised in that described geotechnique's nonwoven layer (1) uses steel nail to fix.
One the most according to claim 1 is cut tide and is promoted silt dike, it is characterised in that the lateral surface of right dam body (4) is provided with ripple glaze (11), and described ripple glaze (11) matches with its layer structure.
CN201620213758.8U 2016-03-18 2016-03-18 Cut short silt dyke of tide Expired - Fee Related CN205604168U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620213758.8U CN205604168U (en) 2016-03-18 2016-03-18 Cut short silt dyke of tide

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620213758.8U CN205604168U (en) 2016-03-18 2016-03-18 Cut short silt dyke of tide

Publications (1)

Publication Number Publication Date
CN205604168U true CN205604168U (en) 2016-09-28

Family

ID=56963341

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620213758.8U Expired - Fee Related CN205604168U (en) 2016-03-18 2016-03-18 Cut short silt dyke of tide

Country Status (1)

Country Link
CN (1) CN205604168U (en)

Similar Documents

Publication Publication Date Title
CN104612104B (en) A kind of flexible coast protection structure and method of construction thereof
CN108193606B (en) A kind of means of defence of local scour near pier
CN105464056A (en) Anti-seepage structure capable of adapting to settlement of earth and rockfill dam
CN203782664U (en) Anti-scour structure of sandy foundation water gate
CN111472326A (en) Method and structure for building gravity dam on deep covering layer
CN104060619A (en) Construction method and structure of hydraulic core-wall rockfill dam without cofferdams
CN108797631A (en) A kind of more negative well bore pressure bucket anemometer tower foundation scour protection methods of jacket
CN104790410A (en) Foundation pit excavation supporting method suitable for watercourse with shallow water and sludge
CN110804957A (en) Protection method for local scouring of bridge pier
CN107761668B (en) Coastal shore reservoir land-building type revetment structure and construction method thereof
CN203939036U (en) A kind of steel sheet pile cofferdam structure that is applicable to river course
CN212203372U (en) Immersed tube pipeline covering protection layer
CN112854144A (en) Construction structure of earth-rock dam on deep sludge layer and construction method thereof
CN205604167U (en) Block up and cut chao di
CN205604168U (en) Cut short silt dyke of tide
CN204825787U (en) Gabion barricade protective structure
CN102808394B (en) Construction method for fine sand ultra-long interception embankment closure gap bottom guard with deep covering layer
CN207794060U (en) A kind of Ecotype Concrete support pile
CN203383193U (en) Core-wall rockfill dam structure without cofferdams
CN206800314U (en) Rubble-mound foundation gravity type quay
CN210459099U (en) Seawall structure on soft soil foundation
CN106930242A (en) Pile foundation overfall dam and galvanized wire gabion protection-apron
CN208055980U (en) A kind of permeable erosion control wall construction of hydraulic engineering
CN108798589B (en) Modification method of aquifer
CN206570772U (en) A kind of ecological earth and rockfill dam

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160928

Termination date: 20170318

CF01 Termination of patent right due to non-payment of annual fee