CN205475709U - A scalable stores pylon for high -rise, super high -rise building jacking platform - Google Patents

A scalable stores pylon for high -rise, super high -rise building jacking platform Download PDF

Info

Publication number
CN205475709U
CN205475709U CN201620290789.3U CN201620290789U CN205475709U CN 205475709 U CN205475709 U CN 205475709U CN 201620290789 U CN201620290789 U CN 201620290789U CN 205475709 U CN205475709 U CN 205475709U
Authority
CN
China
Prior art keywords
rise
lifting platform
walkway board
chain
rise building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620290789.3U
Other languages
Chinese (zh)
Inventor
李可柏
周洪涛
裴鸿斌
柯子平
王宜彬
崔爱珍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201620290789.3U priority Critical patent/CN205475709U/en
Application granted granted Critical
Publication of CN205475709U publication Critical patent/CN205475709U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model provides a scalable stores pylon for high -rise, super high -rise building jacking platform hangs and locates upper stores pylon bottom, the upper strata stores pylon including hang a plurality of pole settings of locating jacking platform truss bottom and set up in the first guidance tape of walking of pole setting, scalable stores pylon includes: correspond to hang and locate the chain of pole setting bottom, set up in the guidance tape is walked to the second of chain, and be fixed in the supporting beam of guidance tape bottom is walked to the second. The utility model provides a stores pylon relapse the dismouting scheduling problem because of the barrier in the work progress.

Description

For high-rise, the scalable hanger of high-rise building lifting platform
Technical field
This utility model relates to high level, construction of super highrise building field, be specifically related to a kind of for high-rise, The scalable hanger of high-rise building lifting platform.
Background technology
Along with scientific and technological progress and the raising of construction technology, high-rise, Super High heavy construction gets more and more, High-rise, Super High core wall structure horizontal structure often separates construction with vertical structure, and Core Walls Structure is vertically tied Structure uses the formwork system-integral jacking platform that can certainly climb.
Below integral jacking platform girder truss, it is attached with multistep hanger, provides some for construction operation activity Individual working place.Conventional hanger is to be assembled by vertical rod, cross bar, scaffold board etc., after assembling Maintain static, when running into barrier during construction and jacking, need to remove support body, the most temporarily Install, expend substantial amounts of manpower and time.It is therefore desirable to propose what the easy operation of a kind of energy can be stretched Hanger, it is to avoid repeatedly it installed and remove.
Utility model content
For overcoming the defect existing for prior art, existing offer one is for high-rise, high-rise building jacking The scalable hanger of platform, with solve hanger in work progress because of barrier the problem such as repeated disassembled and assembled.
It is for achieving the above object, a kind of for high-rise, the scalable hanger of high-rise building lifting platform, Hanging on bottom the hanger of upper strata, it is multiple vertical that described upper strata hanger includes hanging on bottom lifting platform truss Bar and be erected on the first walkway board of described vertical rod, described scalable hanger includes: correspondence hang on institute State the chain of bottom of upright rod;It is erected on the second walkway board of described chain;And be fixed on described second and walk Support beam bottom guidance tape.
This utility model is used for changing further of the scalable hanger of high level, high-rise building lifting platform Enter to be, also include that soft protecting net, the quantity of described vertical rod and described chain are four, described soft Property protection network two ends be separately fixed at outside two described chains on.
This utility model is used for changing further of the scalable hanger of high level, high-rise building lifting platform Entering to be, described soft protecting net is flameproof fabric.
This utility model is used for changing further of the scalable hanger of high level, high-rise building lifting platform Entering to be, described support beam includes two shaped steel being welded in described second walkway board side by side.
This utility model is used for changing further of the scalable hanger of high level, high-rise building lifting platform Enter to be, also include: chain block, hang on bottom described first walkway board;And stay cord, connect In described chain block and described support beam.
This utility model is used for changing further of the scalable hanger of high level, high-rise building lifting platform Entering to be, described second walkway board is provided with the perforating worn for described stay cord.
This utility model is used for changing further of the scalable hanger of high level, high-rise building lifting platform Entering to be, described stay cord is galvanized steel wire rope.
This utility model is used for changing further of the scalable hanger of high level, high-rise building lifting platform Enter to be, also include: turnover panel, be articulated with in described second walkway board the one end being positioned at inner side;And rope Rope, drawknot is in described turnover panel and described chain.
The beneficial effects of the utility model are, by hanging chain at bottom of upright rod and arranging the second aisle Plate and support beam, when high-rise, high-rise building Core Walls Structure run into barrier during construction and jacking, Chain block is hung on bottom described first walkway board, and stay cord drawknot in described support beam and is worn Crossing described chain block, then, promote support beam by described stay cord, described support sill bolt moves described the Two walkway boards and described chain rise to certain altitude with avoiding obstacles, after having constructed, by described Two walkway boards and described chain put down, and then are not required to repeatedly hanger be carried out peace and tear open, it is possible to extension Frame carries out extension and contraction control within a certain height, regulates its height, facilitates simple and direct, solve hanger and exist In work progress because of barrier the problem such as repeated disassembled and assembled, improve efficiency of construction.
Accompanying drawing explanation
What Fig. 1 was this utility model for the scalable hanger of high-rise, high-rise building lifting platform is flat Face schematic diagram.
Fig. 2 is that this utility model is for high level, the side of the scalable hanger of high-rise building lifting platform Face schematic diagram.
What Fig. 3 was this utility model for the scalable hanger of high-rise, high-rise building lifting platform is vertical Face schematic diagram.
Fig. 4 is the enlarged diagram in region, Fig. 3 middle and lower part.
Fig. 5 is the enlarged diagram in S1 region in Fig. 3.
Fig. 6 is the enlarged diagram in S2 region in Fig. 3.
Fig. 7 is the enlarged diagram in S3 region in Fig. 2.
Fig. 8 is the enlarged diagram in S4 region in Fig. 2.
Detailed description of the invention
Below by way of specific instantiation, embodiment of the present utility model, those skilled in the art are described Other advantages of the present utility model and effect can be understood easily by the content disclosed by this specification.This reality Can also be carried out by the most different detailed description of the invention with novel or apply, in this specification Every details can also be carried out under without departing from spirit of the present utility model based on different viewpoints and application Various modifications or change.
It should be noted that structure depicted in this specification institute accompanying drawings, ratio, size etc., the most only In order to coordinate the content disclosed in description, understand for those skilled in the art and read, not using To limit the enforceable qualifications of this utility model, therefore do not has technical essential meaning, any structure Modification, the change of proportionate relationship or the adjustment of size, do not affecting the merit that this utility model can be generated by Under the purpose imitated and can reach, all should still fall and obtain can contain at the technology contents disclosed in this utility model In the range of.Meanwhile, in this specification cited as " on ", D score, "left", "right", The term of " middle " and " one " etc., is merely convenient to understanding of narration, and is not used to limit this practicality Novel enforceable scope, being altered or modified of its relativeness, changing under technology contents without essence, When being also considered as the enforceable category of this utility model.
Refer to Fig. 1, Fig. 2 and Fig. 3, Fig. 1 is that this utility model is for high-rise, high-rise building top Rising the floor map of the scalable hanger of platform, Fig. 2 is that this utility model is for high-rise, Super High The side schematic view of scalable hanger of building lifting platform, Fig. 3 be this utility model for high-rise, The elevational schematic view of the scalable hanger of high-rise building lifting platform.
As shown in Figure 1, Figure 2 and Figure 3, this utility model provides and a kind of builds for high-rise, Super High Building the scalable hanger of lifting platform, described upper strata hanger includes: hang on bottom lifting platform truss 6 Four vertical rods 10, four described vertical rods 10 one group two-by-two, often the described vertical rod of two in group 10 is erected Straight Parallel Symmetric is arranged;It is connected to be located at the first walkway board 11 of described vertical rod 10, described first aisle Between two the described vertical rods 10 in the vertical rod of described often group of the end of plate 11, this utility model kind is used Include in high-rise, the described scalable hanger of high-rise building lifting platform: hang on respectively described in four Four chains 21 bottom vertical rod 10, one group two-by-two of four described chains 21, often two institutes in group State the vertical Parallel Symmetric of chain 21 to arrange;It is connected to be located at the second walkway board 22 of described chain 21, The end of described second walkway board 22 is positioned at two described chains 21 vertical rod 10 in described often group chain Between;And it is fixed on the support beam 23 bottom described second walkway board 22.This utility model is using Time, when running into barrier, it is provided that chain block 41 and stay cord 42, described chain block 41 is hung Bottom described first walkway board 11, and described stay cord 42 drawknot in described support beam 23 and is passed Described chain block 41, then, promotes support beam 23, described support beam 23 by described stay cord 42 Described second walkway board 22 and described chain 21 is driven to rise to certain altitude with avoiding obstacles, construction After completing, described second walkway board 22 and described chain 21 are put down.This utility model is not required to instead Again hanger is carried out peace to tear open, hanger can be carried out within a certain height extension and contraction control, regulate it high Degree, facilitates simple and direct, solve hanger in work progress because of barrier the problem such as repeated disassembled and assembled, improve Efficiency of construction.
Hereinafter said modules is described in detail.
As shown in Figure 2, Figure 3 and Figure 4, Fig. 4 is the enlarged diagram in region, Fig. 3 middle and lower part, vertical Bar 10 is hung on the truss 6 times of described lifting platform side by side, bottom the truss 6 of described lifting platform also Row is fixed with two skid beams, and two groups of vertical rod correspondences are hung under two skid beams.Skid beam can be I-beam, Both sides, vertical rod 10 top are folded with supporting plate, and supporting plate top has upwardly extended riser, is provided with cunning inside riser It is located at the roller of the lower wing plate of described I-beam, and then vertical rod 10 can be hung on skid beam.As Fig. 2, Shown in Fig. 3 and Fig. 4, vertical rod 10 both sides are folded with multipair clamping plate, and vertical rod 10 includes multiple body of rod, often Clamping plate are located in the end of adjacent two body of rod, and clamping plate are provided with corresponding bolt hole with the body of rod.Vertical The length of bar 10, according to construction needs, can adapt to the length of construction demand by the increase and decrease body of rod, for Convenience dismounting or install the body of rod, the junction of adjacent two bodies of rod, is folded with a pair clamping plate, i.e. two Clamping plate lay respectively at the both sides of adjacent two body of rod junction, and the two ends up and down of clamping plate are connected to phase Two adjacent bodies of rod.
As depicted in figs. 1 and 2, two end correspondences of described first walkway board 11 are positioned at two groups of vertical rods In two described vertical rods 10 between.Described first walkway board 11 can be to be directly welded in described vertical rod 10, it is also possible to be to be spaced connection between the described vertical rod 10 of two in two groups of vertical rods to have connecting rod, described Two end correspondences of the first walkway board 11 are fixed in described connecting rod.In described first walkway board 11 Between one end and described vertical rod 10 of inner side, drawknot has the first chain 12, described first chain 12 The first end fix one first fixed plate, described first fixed plate is provided with the first corresponding spiral shell with vertical rod 10 Keyhole, described first fixed plate is additionally provided with the first hanging hole that the first end for the first chain 12 wears; Second end of described first chain 12 fixes one second fixed plate, and described second fixed plate sets with vertical rod 10 There is the second bolt hole of correspondence, described second fixed plate is additionally provided with the second end for the first chain 12 and wears If the second hanging hole.
As in figure 2 it is shown, one group two-by-two of four described chains 21, often the described chain of two in group 21 erects Straight Parallel Symmetric is arranged, four described chains 21 hang on bottom four described vertical rods 10 respectively.Described Being folded with two clamping plate bottom vertical rod 10, the upper end of two clamping plate is located in vertical rod 10 both sides, two folders The lower end of plate is exposed to described vertical rod 10, and the lower end of two clamping plate is provided with the bolt hole of correspondence, two folders Being equipped with bolt between plate, described chain 21 hang on described bolt.As shown in Figure 2 and Figure 8, Fig. 8 is the enlarged diagram in S4 region in Fig. 2, and the second walkway board 22 is connected to described chain 21, The end of described second walkway board 22 is positioned at two described chains 21 vertical rod in described often group chain 21 Between 10.Can according to job site situation, the quantity of described second walkway board 22 can be one also Can be multiple.Described second walkway board 22 can be attached in the following manner with described chain 21, Fixing otic placode on described second walkway board 22, described otic placode is provided with earhole, and described chain 21 is arranged in Described earhole.In described second walkway board 22, between one end and described chain 21 of inner side, drawknot has Second chain.Closer, the one end being positioned at inner side in described second walkway board 22 is hinged with turnover panel 51, between described turnover panel 51 and described chain 21, drawknot has rope 52.
As shown in Figure 4, Figure 5 and Figure 6, in order to ensure that operator is in described first walkway board 11 or institute State the safety of operation on the second walkway board 22, it is provided that facade protection network 71, by described facade protection network The two ends of 71 are separately fixed in two described vertical rods 10 in outside;And soft protecting net 72 is provided, The two ends of described soft protecting net 72 are separately fixed on two described chains 21 in outside, described soft Property protection network 72 can be flameproof fabric.As shown in Figure 2 and Figure 8, solid bottom described second walkway board 22 Surely having support beam 23, when the quantity of described second walkway board 22 is multiple, described support beam 23 can To be affixed to bottom one of them described second walkway board 22, such as, it is fixed on described the of bottom Bottom two walkway boards 22;Described support beam can also be respectively and fixedly provided with bottom each described second walkway board 22 23;Can also be wherein to be fixed with support beam 23 bottom certain several described second walkway board 22.Described hold Joist 23 includes two shaped steel being welded in described second walkway board 22 side by side, it is preferred that described shaped steel For channel-section steel.
Closer, as shown in Figure 7 and Figure 8, this utility model also includes: chain block 41, It hang on bottom described first walkway board 11;And stay cord 42, it is connected to described chain block 41 He Described support beam 23.Wherein, described stay cord 42 can be galvanized steel wire rope.Described first walkway board 11 It is provided with the perforating worn for described stay cord 42 with described second walkway board 22.Described stay cord 42 After one end is connected to described chain block 41, the other end of described stay cord 42 wears described the most successively Perforating on one walkway board 11 and described second walkway board 22, up through described the second of bottommost Walkway board 22, and be connected with the described support beam 23 under described second walkway board 22 of bottommost.
After having said structure feature, in conjunction with Fig. 1 and Fig. 2, this utility model can be real by procedure below Execute:
First, four vertical rods 10 are hung on bottom lifting platform truss 6, and be spaced connection and first walk Guidance tape 11;
Secondly, bottom four described vertical rod 10, hang chain 21, and be spaced connection the second walkway board 22, Support beam 23 is fixed on bottom described second walkway board 22;
Then, when high-rise, high-rise building Core Walls Structure run into barrier during construction and jacking, Chain block 41 is hung on bottom described first walkway board 11, and by stay cord 42 drawknot in described Support beam 23 also passes described chain block 41;
Then, promoting support beam 23 by described stay cord 42, described support beam 23 drives described second Walkway board 22 and described chain 21 rise to certain altitude with avoiding obstacles, after having constructed, by institute State the second walkway board 22 and described chain 21 puts down.
The beneficial effects of the utility model are:
By hanging chain at bottom of upright rod and arranging the second walkway board and support beam, when high-rise, Super High When building core cylinder runs into barrier during construction and jacking, chain block is hung on described first Bottom walkway board, and by stay cord drawknot in described support beam and through described chain block, then, logical Crossing described stay cord and promote support beam, described support sill bolt moves described second walkway board and described chain rises to Certain altitude is with avoiding obstacles, after having constructed, described second walkway board and described chain is put down i.e. Can, and then be not required to repeatedly hanger be carried out peace and tear open, it is possible to hanger is stretched within a certain height Contracting controls, and regulates its height, facilitates simple and direct, solves hanger in work progress because of barrier repeatedly The problems such as dismounting, improve efficiency of construction.
Above in association with accompanying drawing embodiment, this utility model is described in detail, ordinary skill in this area This utility model can be made many variations example by personnel according to the above description.Thus, some in embodiment Details should not constitute restriction of the present utility model, and this utility model will define with appended claims Scope is as protection domain.

Claims (8)

1., for high-rise, a scalable hanger for high-rise building lifting platform, it hang on upper strata and hang Bottom frame, described upper strata hanger includes the multiple vertical rods hanging on bottom lifting platform truss and is erected on First walkway board of described vertical rod, it is characterised in that described scalable hanger includes:
Correspondence hang on the chain of described bottom of upright rod;
It is erected on the second walkway board of described chain;And
It is fixed on the support beam bottom described second walkway board.
The most according to claim 1 for high-rise, the scalable extension of high-rise building lifting platform Frame, it is characterised in that also include that soft protecting net, the quantity of described vertical rod and described chain are four, The two ends of described soft protecting net are separately fixed on two described chains in outside.
The most according to claim 2 for high-rise, the scalable extension of high-rise building lifting platform Frame, it is characterised in that described soft protecting net is flameproof fabric.
The most according to claim 1 for high-rise, the scalable extension of high-rise building lifting platform Frame, it is characterised in that described support beam includes two shaped steel being welded in described second walkway board side by side.
The most according to claim 1 for high-rise, the scalable extension of high-rise building lifting platform Frame, it is characterised in that also include:
Chain block, hang on bottom described first walkway board;And
Stay cord, is connected to described chain block and described support beam.
The most according to claim 5 for high-rise, the scalable extension of high-rise building lifting platform Frame, it is characterised in that described second walkway board is provided with the perforating worn for described stay cord.
The most according to claim 5 for high-rise, the scalable extension of high-rise building lifting platform Frame, it is characterised in that described stay cord is galvanized steel wire rope.
The most according to claim 1 for high-rise, the scalable extension of high-rise building lifting platform Frame, it is characterised in that also include:
Turnover panel, is articulated with in described second walkway board the one end being positioned at inner side;And
Rope, drawknot is in described turnover panel and described chain.
CN201620290789.3U 2016-04-08 2016-04-08 A scalable stores pylon for high -rise, super high -rise building jacking platform Expired - Fee Related CN205475709U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620290789.3U CN205475709U (en) 2016-04-08 2016-04-08 A scalable stores pylon for high -rise, super high -rise building jacking platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620290789.3U CN205475709U (en) 2016-04-08 2016-04-08 A scalable stores pylon for high -rise, super high -rise building jacking platform

Publications (1)

Publication Number Publication Date
CN205475709U true CN205475709U (en) 2016-08-17

Family

ID=56643615

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620290789.3U Expired - Fee Related CN205475709U (en) 2016-04-08 2016-04-08 A scalable stores pylon for high -rise, super high -rise building jacking platform

Country Status (1)

Country Link
CN (1) CN205475709U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109736595A (en) * 2018-12-29 2019-05-10 中国建筑第五工程局有限公司 A kind of assembled steel stair
CN110550529A (en) * 2019-09-19 2019-12-10 上海宝冶集团南京建筑有限公司 Super high-rise telescopic lifting platform

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109736595A (en) * 2018-12-29 2019-05-10 中国建筑第五工程局有限公司 A kind of assembled steel stair
CN110550529A (en) * 2019-09-19 2019-12-10 上海宝冶集团南京建筑有限公司 Super high-rise telescopic lifting platform
CN110550529B (en) * 2019-09-19 2023-07-28 上海宝冶集团南京建筑有限公司 Super high-rise telescopic lifting platform

Similar Documents

Publication Publication Date Title
CN106958346B (en) Intelligent attached lifting scaffold equipment for curved surface super high-rise building and construction method
CN206053274U (en) The external scaffolding device of the perpendicular BAIYE outer visor of skyscraper and glass curtain wall dual-purpose
CN104763109B (en) Quick construction method for pressed bottom tile of large-span steel structure factory building roof
CN101775896B (en) Rigid suspended scaffold for installing pipeline of steel roof equipment
CN106193568A (en) Mobile steel truss operating platform
CN105298099A (en) Modular suspension type steel tube fastener scaffold operating platform and erecting method thereof
CN105350759A (en) Suspended scaffold
CN205475709U (en) A scalable stores pylon for high -rise, super high -rise building jacking platform
WO2023208250A1 (en) Curtain wall construction platform
CN115538792A (en) Residential building machine installation construction method and structure
CN205134919U (en) Modularization suspension type steel tubes clamps scaffold operation platform
CN205475706U (en) Hanging rack system
CN105839907A (en) Suspension type steel platform scaffold foundation and method for mounting same
CN201635377U (en) Rigid suspended type scaffold provided with large-span steel roof equipment pipeline
CN206784958U (en) A kind of encorbelmented across metal greatly decorates prefabricated roof and air translation splicing structure
CN209780190U (en) Hanging platform for large-span beam string beam daylighting roof construction
CN105649209B (en) Applied to the hanging rack system in lifting platform small space
CN115306137A (en) Operation platform structure for mounting suspended ceiling at bottom of overhead corridor and construction method thereof
CN207553565U (en) A kind of crosshead of truss
CN201649607U (en) Overhung-type outer wall scaffold
CN214301281U (en) Construction platform for connecting steel truss girder and bridge deck slab
CN212867550U (en) Assembled subway subsurface excavation construction is overhead pedestrian passageway device for vertical well
CN205475707U (en) A jacking platform for super high -rise building
CN107035037A (en) High building top layer curtain wall frame and its installation method
CN208310158U (en) Construction protection crosshead

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160817

CF01 Termination of patent right due to non-payment of annual fee