CN205474859U - Bridge bent cap construction safety protection platform - Google Patents

Bridge bent cap construction safety protection platform Download PDF

Info

Publication number
CN205474859U
CN205474859U CN201620174754.3U CN201620174754U CN205474859U CN 205474859 U CN205474859 U CN 205474859U CN 201620174754 U CN201620174754 U CN 201620174754U CN 205474859 U CN205474859 U CN 205474859U
Authority
CN
China
Prior art keywords
protection platform
safety protection
channel
guardrail
construction safety
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620174754.3U
Other languages
Chinese (zh)
Inventor
刘立贵
李伟泉
余绍江
陈正聪
林峰垚
王小通
杨鼎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 14 Co Ltd
Original Assignee
Sinohydro Bureau 14 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 14 Co Ltd filed Critical Sinohydro Bureau 14 Co Ltd
Priority to CN201620174754.3U priority Critical patent/CN205474859U/en
Application granted granted Critical
Publication of CN205474859U publication Critical patent/CN205474859U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model relates to a bridge bent cap construction safety protection platform. This safety protection platform makes up into the safety protection platform by preceding, back, left and right four bibliographic categories part unit platform, the safety protection platform pass through the platform lifting rope and install on the punching rod iron, and arrange around the pier stud. The utility model discloses braced system installation (demolising) in -process operation safety in the time of guarantee adopting the rod iron method to pour bridge bent cap (binder) plays the second and says the protective action in the time of simultaneously can be in the overall process of bent cap (binder) construction. Its processing, assemble, demolish etc. Convenient, swift, use safe and reliable, but manifold cycles uses.

Description

A kind of bridge coping construction safety protection platform
Technical field
This utility model belongs to technical field of bridge engineering, is specifically related to a kind of construction safety protection platform when using rod iron method to pour bridge coping (binder).
Background technology
At present, when using rod iron method to pour bridge coping (binder), main employing is set up temporary steel pipe support or directly uses lifting appliance to arrange the cage mounting platform as support system, after secondary beam installation terminates, then laying construction platform and safe protective railing on secondary beam.Temporary steel pipe support is set up in employing need to carry out based process, and the most time-consuming;Directly use lifting appliance that cage is set and the support system bigger security risk of existence is installed.
Summary of the invention
The purpose of this utility model is to provide one and is easy to dismounting, can reuse, can guarantee that the protective platform of safety operation during using rod iron method support system installing (dismounting) when pouring bridge coping (binder), while can in the overall process that bent cap (binder) constructs time play the protective platform of second protective action.
The technical solution of the utility model is: a kind of bridge coping construction safety protection platform is combined into security protection platform by front, rear, left and right four part unit platforms, described security protection platform is arranged on punching rod iron by platform lifting rope, and is arranged in around pier stud.
The structure of described front, rear, left and right four part unit platforms all includes channel-section steel girder, channel-section steel secondary beam, expanded steel diamond mesh, standing screw, guardrail inserted link, guardrail, skirting board, close mesh safety net, channel-section steel Main Girder Welding becomes a rectangular outer frame, weld multiple channel-section steel secondary beams in rectangular outer frame and form multiple rectangle inside casing, expanded steel diamond mesh is installed in rectangular inner frames, guardrail inserted link and guardrail are installed in the outside of rectangular frame, and guardrail is provided with skirting board and close mesh safety net.
The utility model has the advantages that: during can guarantee that employing rod iron method support system installing (dismounting) when pouring bridge coping (binder), operate safety, while can in the overall process that bent cap (binder) constructs time play second protective action.It processes, assemble, dismounting etc. is convenient, fast, safe and reliable, can be recycled for multiple times.
Accompanying drawing explanation
Fig. 1 is the structural representation of unit platforms of the present utility model.
Fig. 2 is security protection platform structure schematic diagram (plane graph) of the present utility model.
Fig. 3 is security protection platform structure schematic diagram (front view) of the present utility model.
Fig. 4 is security protection platform structure schematic diagram (side view) of the present utility model.
In figure: 1-channel-section steel girder, 2-channel-section steel secondary beam, 3-expanded steel diamond mesh, 4-standing screw, 5-guardrail inserted link, 6-guardrail, 7-skirting board, 8-close mesh safety net, 9-security protection platform, 10-platform lifting rope, 11-punching rod iron, 12-steel cattle foot, 13-adjusting means, 14-bent cap (binder) support system, 15-pier stud, 16-bent cap (binder).
Detailed description of the invention
As shown in Figure 2,3, 4, bridge coping construction safety protection platform 9 of the present utility model is combined by front, rear, left and right four part unit platforms, described security protection platform 9 is arranged on punching rod iron 11 (part that punching rod iron, steel corbel belong to support system) by platform lifting rope 10, and it is arranged in pier stud 15 around, two ends and each one piece of both sides.
The structure of described front, rear, left and right four part unit platforms all includes channel-section steel girder 1, channel-section steel secondary beam 2, expanded steel diamond mesh 3, standing screw 4, guardrail inserted link 5, guardrail 6, skirting board 7, close mesh safety net 8, channel-section steel girder 1 is welded into a rectangular frame, weld multiple channel-section steel secondary beams 2 in rectangular frame and form multiple rectangle inside casing, its effect is to reduce span, improve expanded steel diamond mesh bearing capacity, expanded steel diamond mesh 3 is installed in rectangular frame, guardrail inserted link 5 and guardrail 6 are installed in the outside of rectangular frame, and guardrail is provided with skirting board 7 and close mesh safety net 8.
Security protection platform is interior empty more than the pier stud the least 10cm of 15 each sizes after assembling, in order to lifting.Channel-section steel girder 1 uses that [16 channel-section steels processing, channel-section steel secondary beam 2 uses ∠ 50 × 50mm angle steel process, secondary case bay 100cm of channel-section steel.Expanded steel diamond mesh 3 thickness of slab δ=0.4mm, mesh is 20 × 30mm.Standing screw 4 uses M20 bolt, adjustable length 15cm.Guardrail inserted link 5 uses Φ 28 reinforcement welding in channel-section steel girder 1 outer side edges, and appear 10cm, installing space 150cm;Guardrail 6 uses φ 48 steel-pipe welding to process, highly 120cm, steel pipe spacing 150cm, and on guardrail 6, surrounding completely spreads and hangs close mesh safety net 8, inserts in guardrail inserted link 5 when guardrail 6 is installed.Skirting board 7 uses plank or bamboo springboard to install, and highly 30cm uses galvanized wire colligation on guardrail 6.
Installation method:
The with bolts assembling on ground of security protection platform 9 is processed into four module unit platforms, lift with truck crane, hang on punching rod 11 with steel wire rope 10, finally use standing screw 4 to be fixed on pier stud to prevent from moving, as installation, the security protection platform of dismounting of bent cap (binder) support system.After use terminates, entirety is put on ground dismounting, is transported to next work surface and uses.

Claims (8)

1. a bridge coping construction safety protection platform, it is characterized in that this security protection platform is combined into security protection platform by front, rear, left and right four part unit platforms, described security protection platform is arranged on punching rod iron by platform lifting rope, and is arranged in around pier stud.
Bridge coping construction safety protection platform the most according to claim 1, it is characterized in that the structure of described front, rear, left and right four part unit platforms all includes channel-section steel girder, channel-section steel secondary beam, expanded steel diamond mesh, standing screw, guardrail inserted link, guardrail, skirting board, close mesh safety net, channel-section steel Main Girder Welding becomes a rectangular frame, weld multiple channel-section steel secondary beams in rectangular frame and form multiple rectangle inside casing, expanded steel diamond mesh is installed in rectangle inside casing, guardrail inserted link and guardrail are installed in the outside of rectangular frame, and guardrail is provided with skirting board and close mesh safety net.
Bridge coping construction safety protection platform the most according to claim 1, it is characterised in that security protection platform is interior empty more than each the least 10cm of size of pier stud after assembling, in order to lifting.
Bridge coping construction safety protection platform the most according to claim 2, it is characterised in that [16 channel-section steels process the employing of channel-section steel girder.
Bridge coping construction safety protection platform the most according to claim 2, it is characterised in that channel-section steel secondary beam uses ∠ 50 × 50mm angle steel to process, channel-section steel time case bay 100cm.
Bridge coping construction safety protection platform the most according to claim 2, it is characterised in that expanded steel diamond mesh thickness of slab δ=0.4mm, mesh is 20 × 30mm.
Bridge coping construction safety protection platform the most according to claim 2, it is characterised in that guardrail inserted link uses Φ 28 reinforcement welding in channel-section steel girder outer side edges, and appear 10cm, installing space 150cm.
Bridge coping construction safety protection platform the most according to claim 2, it is characterised in that guardrail uses the processing of φ 48 steel-pipe welding, highly 120cm, steel pipe spacing 150cm.
CN201620174754.3U 2016-03-08 2016-03-08 Bridge bent cap construction safety protection platform Expired - Fee Related CN205474859U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620174754.3U CN205474859U (en) 2016-03-08 2016-03-08 Bridge bent cap construction safety protection platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620174754.3U CN205474859U (en) 2016-03-08 2016-03-08 Bridge bent cap construction safety protection platform

Publications (1)

Publication Number Publication Date
CN205474859U true CN205474859U (en) 2016-08-17

Family

ID=56658561

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620174754.3U Expired - Fee Related CN205474859U (en) 2016-03-08 2016-03-08 Bridge bent cap construction safety protection platform

Country Status (1)

Country Link
CN (1) CN205474859U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105603884A (en) * 2016-03-08 2016-05-25 中国水利水电第十四工程局有限公司 Safety protection platform for bridge cap beam construction
CN111535199A (en) * 2020-05-27 2020-08-14 中交路桥建设有限公司 Integral type edge-facing protection device and structure for pier column, middle tie beam and bent cap construction
CN114808723A (en) * 2022-05-10 2022-07-29 中交第二航务工程局有限公司 Concrete pouring platform for ultrahigh and overlong steel pipes

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105603884A (en) * 2016-03-08 2016-05-25 中国水利水电第十四工程局有限公司 Safety protection platform for bridge cap beam construction
CN111535199A (en) * 2020-05-27 2020-08-14 中交路桥建设有限公司 Integral type edge-facing protection device and structure for pier column, middle tie beam and bent cap construction
CN114808723A (en) * 2022-05-10 2022-07-29 中交第二航务工程局有限公司 Concrete pouring platform for ultrahigh and overlong steel pipes
CN114808723B (en) * 2022-05-10 2023-04-18 中交第二航务工程局有限公司 Concrete pouring platform for ultrahigh and overlong steel pipes

Similar Documents

Publication Publication Date Title
CN105603884A (en) Safety protection platform for bridge cap beam construction
CN205474859U (en) Bridge bent cap construction safety protection platform
CN204386197U (en) The horizontal protective platform of a kind of Super High alien invasion steel work
CN105257009B (en) Device for anti-falling partition in elevator shaft
CN101265748B (en) Tools type section steel fastener steel tube outer scaffold
CN203961276U (en) High-building construction steel form and handling frame Integral lifting stage apparatus
CN204781887U (en) Prefabricated assembly type structure's no outrigger construction platform
CN107524284A (en) A kind of regularization pylon protection system and installation method
CN206571130U (en) A kind of outside the pale of civilization protective frame of sizing for Fabricated balcony
CN206722368U (en) One kind is used to protect frame system outside the working regularization of assembled architecture
CN103603491A (en) Beam plate post-cast strip template support frame and erection method thereof
CN203947756U (en) Exterior wall protective frame
CN102425123B (en) Combined type protection shed frame and construction method thereof
CN201778479U (en) Detachable high-altitude working platform
CN201190408Y (en) Tool type exterior scaffolding of section steel fastening tube
CN103132640A (en) Detachable steel-concrete composite floor
CN203640257U (en) Support of overhanging type scaffold
CN203145273U (en) Dismountable steel-concrete composite floor
CN205840289U (en) A kind of suspension type vertical operating platform
CN205243058U (en) Horizontal safety device of elevartor shaft
JP6534938B2 (en) Lining plate installation and rain curing jig and lining plate installation method using the jig
CN204940916U (en) A kind of Super High Core Walls Structure emergency escape passage
CN204038917U (en) Detachable external hanging type operating platform
CN204059589U (en) A kind of shaped steel combination formula supporting and the cantilevered structure of going along with sb. to guard him
CN102913007A (en) Steel reinforcement processing shed and construction method therefor

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160817

CF01 Termination of patent right due to non-payment of annual fee