CN205472729U - Water treatment component and water pipe assembly thereof - Google Patents

Water treatment component and water pipe assembly thereof Download PDF

Info

Publication number
CN205472729U
CN205472729U CN201620102818.9U CN201620102818U CN205472729U CN 205472729 U CN205472729 U CN 205472729U CN 201620102818 U CN201620102818 U CN 201620102818U CN 205472729 U CN205472729 U CN 205472729U
Authority
CN
China
Prior art keywords
assembly
water
water treatment
joint
installation portion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620102818.9U
Other languages
Chinese (zh)
Inventor
邓雁青
王林双
魏璇
舒春明
耿庆松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Midea Group Co Ltd
Original Assignee
Midea Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Midea Group Co Ltd filed Critical Midea Group Co Ltd
Priority to CN201620102818.9U priority Critical patent/CN205472729U/en
Application granted granted Critical
Publication of CN205472729U publication Critical patent/CN205472729U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Water Treatment By Sorption (AREA)

Abstract

The utility model discloses a water treatment component and water pipe assembly thereof, water pipe assembly includes: a joint Assembly, the 2nd joint Assembly and pipeline subassembly, first passageway and second channel have in the joint Assembly, third passageway and four -channel have in the 2nd joint Assembly, the pipeline subassembly is connected a joint Assembly with between the 2nd joint Assembly, so that first passageway with third passageway intercommunication, and make the second channel with the four -channel intercommunication, wherein, the raw water flows into first passageway from the third passageway through the pipeline subassembly and filters, flows into four -channel and discharges through the pipeline subassembly from the second channel again. According to the utility model discloses a water treatment component's water pipe assembly, simple structure, ingenious can realize water treatment component's water treatment facilities and tap's high -speed joint, it is high to connect the reliability.

Description

Water treatment component and conduit assembly thereof
Technical field
This utility model relates to technical field of water purification, especially relates to a kind of water treatment component and conduit assembly thereof.
Background technology
At present, people generally use tap water to wash one's face, but, hardness of water is likely to harm users skin from the beginning, causes use Family skin damage.It addition, the structure complexity of the water treatment facilities in correlation technique, when being connected with faucet, installation process is multiple Miscellaneous, connection reliability is poor, and the later stage is changed, safeguards inconvenience, and the attachment structure of complexity also can increase difficulty of processing, reduces Production efficiency, draws high production cost.
Utility model content
This utility model is intended at least to solve one of technical problem present in prior art.To this end, this utility model is to carry Going out the conduit assembly of a kind of water treatment component, it is excellent that described conduit assembly has simple in construction, low cost and connection reliability height etc. Point.
This utility model also proposes a kind of water treatment component with above-mentioned conduit assembly.
The conduit assembly of the water treatment component according to this utility model first aspect, including: the first adapter assembly, described first There is in adapter assembly first passage and second channel;Second adapter assembly, has third channel in described second adapter assembly And fourth lane;Pipeline assembly, described pipeline assembly is connected between described first adapter assembly and described second adapter assembly, So that described first passage connects with described third channel, and described second channel is made to connect with described fourth lane, wherein, Former water flows into first passage from third channel through described pipeline assembly and filters, then from second channel through described pipeline group Part flows into fourth lane and discharges.
According to the conduit assembly of water treatment component of the present utility model, simple in construction, ingenious, it is possible to achieve water treatment component Water treatment facilities is quickly connected with faucet, and connection reliability is high.
In certain embodiments, described pipeline assembly includes: the first water pipe and the second water pipe, and described first cross current is in institute Stating between first passage and described third channel, described second cross current is between described second channel and described fourth lane.
In certain embodiments, described first water pipe is located at the side on described second water pipe vertical direction or horizontal direction side by side On side.
In certain embodiments, described pipeline assembly farther includes: display pipe, described display pipe wrap up in be enclosed within the first water pipe and Outside described second water pipe.
In certain embodiments, described conduit assembly, it is characterised in that farther include: support member, described support member sets To support described pipeline assembly on described pipeline assembly.
In certain embodiments, described support member includes: sleeve pipe, and described casing pipe sleeve is located on described pipeline assembly;And sucker Part, described sucker part is located on described connection sleeve pipe.
In certain embodiments, it is provided with bubbler in described fourth lane.
In certain embodiments, described first adapter assembly includes: the first joint;And first installation portion, described first peace Dress portion is detachably connected by the first attachment structure with described first joint, and described pipeline assembly is connected to described first and installs Portion.
In certain embodiments, described second adapter assembly includes: the second joint;And second installation portion, described second peace Dress portion is detachably connected by the second attachment structure with described second joint, and described pipeline assembly is connected to described second and installs Portion.
According to the water treatment component of this utility model second aspect, including: water treatment facilities, described water treatment facilities includes filter Core and base assembly, described filter element includes outer filter housing and the interior filter housing being accommodated in described outer filter housing, and described interior filter housing is with described Outer filter housing limits the outer flow passage that connect internal with described interior filter housing jointly, is provided with filter material to carry out former water in described interior filter housing Filter, described base assembly is formed the first water flowing runner being communicated within described interior filter housing and is communicated to described outer flow passage The second water flowing runner;With the conduit assembly of the water treatment component according to this utility model first aspect, described first joint group Part is connected to described water treatment facilities, so that described first passage is communicated to described first water flowing runner and described second water flowing stream One of them in road, and make that described second channel is communicated in described first water flowing runner and described second water flowing runner another One.
According to water treatment component of the present utility model, by arranging the conduit assembly of the water treatment component of above-mentioned first aspect, from And improve the overall performance of water treatment component.
Additional aspect of the present utility model and advantage will part be given in the following description, and part will become from the following description Obtain substantially, or recognized by practice of the present utility model.
Accompanying drawing explanation
Fig. 1 is the explosive view of the water treatment component according to this utility model embodiment;
Fig. 2 is the installation diagram of the water treatment component shown in Fig. 1;
Fig. 3 is the sectional view of the first adapter assembly according to this utility model embodiment;
Fig. 4 is the schematic diagram of the first adapter assembly shown in Fig. 3;
Fig. 5 is the sectional view of the second adapter assembly according to one embodiment of this utility model;
Fig. 6 is the explosive view of the conduit assembly that the second adapter assembly shown in Fig. 5 is constituted;
Fig. 7 is the explosive view of the conduit assembly according to another embodiment of this utility model;
Fig. 8 is the sectional view of the second adapter assembly shown in Fig. 7;
Fig. 9 is the sectional view of another second adapter assembly close with Fig. 8;
Figure 10 is the schematic diagram of the second adapter assembly according to this utility model further embodiment;
Figure 11 is the explosive view of the second adapter assembly shown in Figure 10;
Figure 12 is the sectional view of the second adapter assembly shown in Figure 11;
Figure 13 is the top partial view diagram of the second adapter assembly shown in Figure 12;
Figure 14 is the schematic diagram of the conduit assembly according to one embodiment of this utility model;
Figure 15 is the sectional view of the conduit assembly shown in Figure 14.
Reference:
Water treatment component 1000;
Water treatment facilities 100;Housing 1;Filter element 2;Base assembly 3;
Conduit assembly 200;
Pipeline assembly 1000a;First water pipe 1001;Second water pipe 1002;Display pipe 1003;
Support member 1100;Sleeve pipe 1101;Sucker part 1102;Bubbler 1200;
First passage 200a;Second channel 200b;Third channel 200c;Fourth lane 200d;
First adapter assembly 7;First installation portion 71;First joint 72;
Second adapter assembly 4,5,6;Second installation portion 41,51,61;Second joint 42,52,62;
Perforation 711;Enter water adapter 34;Water outlet adapter 35;Guiding surface 721;First attachment structure 73;Stopper slot 731; Buckle 732b;First paragraph portion 7321;Second segment portion 7322;Throwout sleeve 733;Elastic component 734;
First main part 411;First connecting portion 412;End wall 4121;Surrounding wall portion 4122;First sub-attachment structure 410; Second main part 421;Second connecting portion 422;Second sub-attachment structure 420;Sealing member 43;
Hole 511;Guiding surface 521 is installed;Second attachment structure 53;Locating slot 531;Dismounting guiding surface 531a;Ball Body 532a;Elastic buckles 532b;3rd section of portion 5321;4th section of portion 5322;Sliding axle sleeve 533;Elastomeric element 534; Sealing ring 54
Position retaining plate 611;Second attachment structure 63;Press section 631;Fastener 631a;Card-bit part 632;Screens ring 633; Arc snap ring 6330;Guide section 6331;Spring part 634;Cylindrical member 64.
Detailed description of the invention
Of the present utility model embodiment is described below in detail, and the example of described embodiment is shown in the drawings, the most from start to finish Same or similar label represents same or similar element or has the element of same or like function.Below with reference to attached The embodiment that figure describes is exemplary, it is intended to be used for explaining this utility model, and it is not intended that to limit of the present utility model System.
Following disclosure provides many different embodiments or example for realizing different structure of the present utility model.For letter Changing disclosure of the present utility model, hereinafter parts and setting to specific examples are described.Certainly, they are the most merely illustrative, And it is not intended to limit this utility model.Additionally, this utility model can in different examples repeat reference numerals and/or Letter.This repetition is for purposes of simplicity and clarity, between itself not indicating discussed various embodiment and/or arranging Relation.Additionally, the various specific technique that provides of this utility model and the example of material, but ordinary skill Personnel are it can be appreciated that the property of can be applicable to of other techniques and/or the use of other materials.
Below with reference to Fig. 1-Figure 15, the water treatment component according to this utility model embodiment is described.
According to the water treatment component of this utility model embodiment, including: water treatment facilities 100 and conduit assembly 200.
With reference to Fig. 1, water treatment facilities 100 may include that housing 1, filter element 2 and base assembly 3, wherein, filter element 2 In being each provided at housing 1 with base assembly 3 and base assembly 3 is positioned at the bottom of filter element 2, filter element 2 includes that shape is similar and interior The interior filter housing of outer nesting and outer filter housing, be provided with the filter material for filtering former water in interior filter housing, limits between interior filter housing and outer filter housing Go out outer flow passage and outer flow passage is communicated to interior filter housing, base assembly 3 has the first water flowing runner connected with interior filter housing and with outward Second water flowing runner of flow passage.
With reference to Fig. 1, conduit assembly 200 has first flow and the second runner, conduit assembly 200 and water treatment facilities 100 It is connected so that first flow is communicated to the first water flowing runner, and makes the second runner be communicated to the second water flowing runner.So, from the beginning Water can be flowed in the first water flowing runner on water treatment facilities 100 by the first flow on conduit assembly 200, and flows into Filter material filters, and the water purification after filtration can pass sequentially through outer flow passage and the second water flowing runner is expelled on conduit assembly 200 The second runner in, then give off from the second runner, for user apply.Thus, the structure letter of water treatment component 1000 Single, it is simple to produce, filter efficiency is high, and functional reliability is good.Main to realize the water treatment component of this kind of filter process Illustrate as a example by 1000.
Certainly, this utility model is not limited to this, and above-mentioned water treatment procedure can also inversely be carried out, now, and conduit assembly 200 It is connected with water treatment facilities 100 so that first flow is communicated to the second water flowing runner, and makes the second runner be communicated to the first water flowing Runner.So, tap water can be led to by second on the first flow inflow water treatment facilities 100 on conduit assembly 200 In water flow passage, and flowing into filter material and filter, the water purification after filtration can pass sequentially through outer flow passage and the first water flowing runner is discharged In the second runner to conduit assembly 200, then give off from the second runner, apply for user.Thus, water processes The simple in construction of assembly 1000, it is simple to produce, filter efficiency is high, and functional reliability is good.Describe for simplifying, the most detailed State the technical scheme of the water treatment component 1000 realizing this kind of filter process.
Here, it should be noted that the kind of filter material can select flexibly according to actual filtration demand, for example, it is possible to Select the common filter material only filtered out by target grain size pollutant, it is also possible to select the special filter material with ion exchanging function. Preferably, the filter material that the oxidation-reduction potential value of water is filtered into negative value can be selected, so, when user uses this kind of filter material During the soft water cleaning face filtered, not only can be effectively improved cleaning effect, it is also possible to play the effect of skin protection.This area Technical staff, it is understood that have the filter material of various filtering function, the most no longer describes in detail.
Below with reference to Fig. 1-Figure 15, the conduit assembly 200 according to this utility model embodiment is described.
As it is shown in figure 1, according to the conduit assembly 200 of this utility model embodiment, including: the first adapter assembly, the second joint Assembly and pipeline assembly 1000a.
Specifically, there is in the first adapter assembly first passage 200a and second channel 200b, in the second adapter assembly, have Triple channel 200c and fourth lane 200d, pipeline assembly 1000a is connected between the first adapter assembly and the second adapter assembly, So that first passage 200a and third channel 200c connects to limit above-mentioned first flow, and make second channel 200b and Four-way 200d connects to limit above-mentioned second runner.Here, it should be noted that first passage 200a, second channel 200b, third channel 200c, fourth lane 200d concrete forming position can be with shown in below figure 1-Figure 15.
Wherein, the first adapter assembly is for being connected with above-mentioned water treatment facilities 100, and first passage 200a and the first water flowing stream Road is connected so that first flow and the first water flowing flow passage, second channel 200b and the second water flowing runner are connected so that second Road and the second water flowing flow passage, the second adapter assembly is used for receiving former water and discharge water purification, such as, the second adapter assembly with Faucet is connected so that third channel 200c connects so that former water can flow in first flow with described former water, fourth lane 200d is connected with air so that the second runner outwards discharges water purification.Preferably, it is provided with bubbler in fourth lane 200d.By This, can reduce discharge purified water pressure, makes user can more cosily use water purification, thus improves customer experience.
Conduit assembly 200 according to this utility model embodiment, simple in construction, ingenious, it is possible to achieve water treatment facilities 100 With being quickly connected of faucet, connection reliability height.
In an embodiment of the present utility model, pipeline assembly 1000a includes: the first water pipe 1001 and the second water pipe 1002, First water pipe 1001 connects between first passage 200a and third channel 200c, and the second water pipe 1002 connects and leads to second Between road 200b and fourth lane 200d.Thus, the simple in construction of pipeline assembly 1000a, it is simple to produce and connect.
Further, the first water pipe 1001 and the second water pipe 1002 are arranged side by side, such as, and the first water pipe 1001 and the second water Pipe 1002 can be the most horizontally extending, and the first water pipe 1001 is located at the surface of the second water pipe 1002, the most such as, First water pipe 1001 and the second water pipe 1002 can be the most horizontally extending, and the first water pipe 1001 is located at the second water pipe Side in 1002 horizontal directions.Thus, pipeline assembly 1000a's is rationally distributed, takes up room little, and functional reliability is high. Preferably, the first water pipe 1001 is identical with the structure of the second water pipe 1002, thus, and convenient processing, and cleaning water Stable.
Further, pipeline assembly 1000a farther includes: display pipe 1003, and display pipe 1003 is wrapped up in and is enclosed within the first water pipe 1001 and second outside water pipe 1002.Thus, display pipe 1003 can protect the first water pipe 1001 and the second water pipe effectively 1002, improve the functional reliability of pipeline assembly 1000a, and pipeline assembly 1000a can be improved by arranging display pipe 1003 Structure integration, it is simple to cleaning, install, and make pipeline assembly 1000a more elegant in appearance.Preferably, display pipe The axial length of 1003 and the axial length of the first water pipe 1001 and the second water pipe 1002 are the most equal, and in display pipe 1003 There is the first installing hole for installing the first water pipe 1001 and for installing the second installing hole of the second water pipe 1002.
Further, pipeline assembly 1000a can also include that support member 1100, support member 1100 are located at pipeline assembly 1000a On to support pipeline assembly 1000a.Specifically, during water treatment component 1000 works, pipeline assembly 1000a Water purification after flowing through former water to be clean and purifying, will be applied to pipeline assembly 1000a huge when the water yield is big when Pressure, easily bends pipeline assembly 1000a, when pipeline assembly 1000a deforms, will destroy the first joint group Connection between part and the second adapter assembly so that junction leaks and even ruptures, and, as pipeline assembly 1000a May be subject to crushing during long-time pressurized.Thus, support pipeline assembly 1000a by arranging support member 1100, can be effectively Improve the functional reliability of pipeline assembly 1000a, extend pipeline assembly 1000a or even the use of water treatment component 1000 entirety Life-span.
Preferably, support member 1100 includes that sleeve pipe 1101 and sucker, sleeve pipe 1101 are set on pipeline assembly 1000a, example As, can be set on the central part of pipeline assembly 1000a, sucker part 1102 is located on connection sleeve pipe 1101 and can inhale It is attached on installed surface, such as, can adsorb in ceramic tile wall.Thus, the installation of support member 1100 is facilitated to position, to implement The support member 1100 support to pipeline assembly 1000a.
Below with reference to Fig. 3 and Fig. 4, the first adapter assembly 7 according to this utility model embodiment is described.
Specifically, the first adapter assembly 7 includes: the first joint 72 and the first installation portion 71, wherein, the first joint 72 is used In the water treatment facilities 100 of connection water treatment component 1000, such as, the first joint 72 can be attached to water treatment facilities Entering water adapter 34 and water outlet adapter 35 on 100, the first installation portion 71 and the first joint 72 are by the first attachment structure 73 Being detachably connected, pipeline assembly 1000a is connected to the first installation portion 71.Thus, the simple in construction of the first adapter assembly 7, It is easy to the fast assembling-disassembling of conduit assembly 200 and water treatment facilities 100.
As it is shown on figure 3, the first attachment structure 73 includes the first locating part (such as stopper slot 731), the second locating part (such as Buckle 732b) and sliding component (such as throwout sleeve 733).First locating part is located on the first joint 72, the second locating part Being located on the first installation portion 71, sliding component is located on the first installation portion 71, and makes the second locating part and the first locating part join Close spacing primary importance (position as shown in Figure 3) and make the second locating part and the separable second of the first locating part Slip between putting.Thus sliding component sliding between the first location and the second location can realize the first locating part and second spacing The cooperation of part and separation, thus realize the installation and removal between the first installation portion 71 and the first joint 72, and then simplify water Processing means 100 and the installation and removal process of conduit assembly 200, it is achieved water treatment facilities 100 and conduit assembly 200 It is rapidly assembled and disassembled.
Alternatively, as it is shown on figure 3, sliding component is to be set in outside the first installation portion 71 and axially may be used along the first installation portion 71 The throwout sleeve 733 of sliding.It is to say, throwout sleeve 733 can be along the left and right directions of the first installation portion 71 (such as Fig. 3 Shown left and right directions) sliding, when throwout sleeve 733 is positioned at limit on the left position, throwout sleeve 733 is in primary importance, When throwout sleeve 733 is positioned at limit on the right-right-hand limit position, throwout sleeve 733 is in the second position.Thus can simplify the first joint The structure of assembly 7, it is simple to the first installation portion 71 and installation and removal of the first joint 72.
Preferably, as it is shown on figure 3, the first attachment structure 73 farther includes elastic component 734, elastic component 734 is set in Often to promote throwout sleeve 733 to be positioned at primary importance between one installation portion 71 and throwout sleeve 733.When the first installation portion 71 Being assembled on the first joint 72 and time elastic component 734 often promotes throwout sleeve 733 to be positioned at primary importance, throwout sleeve 733 can To lock the first locating part and the cooperation of the second locating part, thus the connection improving the first installation portion 71 and the first joint 72 can By property.
As it is shown on figure 3, have multiple perforation 711 of circumferentially spaced distribution on the sidewall of the first installation portion 71, second is spacing It is interior to coordinate with the first locating part that the part of part stretches into the first installation portion 71 by perforation 711.Thus can strengthen the first peace The axial limiting in dress portion 71, prevents the first installation portion 71 from axial direction moving, thus increases by the first joint 72 and the first peace The reliability connected between dress portion 71.
Alternatively, the second locating part includes the multiple spheroids (not shown this example) the most corresponding with multiple perforation 711.Also That is, spheroid coordinates with the first locating part through perforation 711 with the enhancing axial limiting to the first installation portion 71, prevents the One installation portion 71 in axial direction moves, and realizes the connection between the first joint 72 and the first installation portion 71, the most simultaneously But the first attachment structure 73 can be simplified, but also can increase be connected between the first joint 72 with the first installation portion 71 can By property.
In other embodiments of the present utility model, as it is shown on figure 3, the second locating part includes with multiple perforation 711 respectively Corresponding multiple buckle 732b.It is to say, buckle 732b coordinates with the first locating part with enhancing the through perforation 711 The axial limiting of one installation portion 71, prevents the first installation portion 71 from axial direction moving, and realizes the first joint 72 and simultaneously Connection between one installation portion 71, the most not only can simplify the first attachment structure 73, but also can increase by the first joint The reliability being connected between 72 with the first installation portion 71.
Further, as it is shown on figure 3, buckle 732b includes first paragraph portion 7321 and second segment portion 7322, first paragraph portion 7321 Being positioned at outside the first installation portion 71, the one end in second segment portion 7322 is connected and second segment portion with the one end in first paragraph portion 7321 The other end of 7322 penetrates perforation 711.The other end and the first locating part that thus can make second segment portion 7322 coordinate to strengthen Axial limiting to the first installation portion 71, prevents the first installation portion 71 from axial direction moving, realizes the first joint 72 simultaneously And the connection that first between installation portion 71, the most not only can simplify the first attachment structure 73, but also first can be increased The reliability being connected between joint 72 with the first installation portion 71.
Alternatively, as it is shown on figure 3, the first locating part is the stopper slot 731 being formed on the first joint 72.Thus can enter The simplification structure of one step, thus save the production cycle, reduce production cost.Further, the first joint 72 has The part of two locating parts imports the guiding surface 721 in stopper slot 731.Thus it is easy to the second locating part is imported the first joint In the stopper slot 731 of 72, it is simple to the installation of the first installation portion 71.
When assembling the first adapter assembly 7, first by throwout sleeve 733 along the first installation portion 71 axially to the right to right Extreme position, now the left end of throwout sleeve 733 is positioned at the right side at center of perforation 711, then by the first installation portion 71 edge First joint 72 axially pushing sleeve is on the first joint 72 to the left, when the guiding surface 721 on the first joint 72 touches ball After body or buckle 732b, spheroid or buckle 732b being moved radially outward towards the first installation portion 71 can be promoted, when first Joint 72 move the spheroid to stopper slot 731 thereon and the first installation portion 71 or buckle 732b position just pair time, spheroid Or buckle 732b can spring in stopper slot 731 automatically, now, discharging throwout sleeve 733, throwout sleeve 733 is the most permissible Under the effect of elastic component 734, the axial direction along the first installation portion 71 is moved to the left limit on the left position, and locking first is spacing Part and the cooperation of the second locating part, complete the first joint 72 and assembling of the first installation portion 71.
When dismantling the first adapter assembly 7, first by throwout sleeve 733 along the first installation portion 71 axially to the right to right Extreme position, now the left end of throwout sleeve 733 may be located at the right side at center of perforation 711, then by the first installation portion 71 axially pulling to the right along the first joint 72, after the diapire of stopper slot 731 touches spheroid or buckle 732b, can push away Dynamic spheroid or buckle 732b being moved radially outward towards the first installation portion 71, when the first installation portion 71 moves to stopper slot After 731 are kept completely separate with spheroid or buckle 732b, the first joint 72 can be left the most to the right, now, discharge throwout sleeve 733, after the first fully out spheroid of joint 72 or buckle 732b, throwout sleeve 733 just can be at the work of elastic component 734 It is moved to the left limit on the left position with the lower axial direction along the first installation portion 71, and by the part of spheroid or buckle 732b again Head in perforation 711, complete the first joint 72 and dismounting of the first installation portion 71.
Below with reference to Fig. 5 and Fig. 6, the second adapter assembly 4 according to one embodiment of this utility model is described.
Specifically, the second adapter assembly 4 includes: the second joint 42 and the second installation portion 41, wherein, the second joint 42 is used In the joint (such as faucet, such as, the second joint 42 can be threadeded with faucet) of the former water of connection, the second installation portion 41 are detachably connected by the second attachment structure 4a with the second joint 42, and pipeline assembly 1000a is connected to the second installation portion 41.Thus, the simple in construction of the second adapter assembly 4, it is simple to conduit assembly 200 and the fast assembling-disassembling of water treatment facilities 100.
Specifically, the second attachment structure includes: the first sub-attachment structure 410 and the second sub-attachment structure 420, and the first son connects Structure 410 is located on the second installation portion 41, and the second sub-attachment structure 420 is located on the second joint 42 and is connected with the first son Structure 410 threaded engagement.Thus, it is possible to easily and quickly realize the assembling of the second attachment structure.
Specifically, the first sub-attachment structure 410 can be for being formed at axial one end (institute in such as Fig. 5 of the second installation portion 41 The upper end shown) external screw thread, the second sub-attachment structure 420 can be that the axial one end being formed at the second joint 42 (is such as schemed Lower end shown in 5) female thread.With reference to Fig. 5, the first sub-attachment structure 410 can be to be formed at the second installation portion 41 The external screw thread of upper axial end, the second sub-attachment structure 420 can be the female thread of the lower axial end being formed at the second joint 42, By external screw thread and the cooperation of female thread, can make together with the second installation portion 41 is closely attached with the second joint 42.
In embodiments more of the present utility model, with reference to Fig. 5, the second installation portion 41 includes: the first main part 411 and the A junction 412.Further, with reference to Fig. 5, the second joint 42 includes the second main part 421 and the second connecting portion 422, Second connecting portion 422 part is positioned at the downside of the second main part 421 and is set on the second main part 421.
With reference to Fig. 5, the first connecting portion 412 is located at the top of the first main part 411, and external screw thread can be formed at the first connecting portion On the outer peripheral face of 412, with reference to Fig. 5, the second connecting portion 422 is set on the second main part 421 and is at least partially disposed at second The downside of main part 421, female thread is formed on the inner peripheral surface of the second connecting portion 422.Thus, by the second connecting portion 422 Inner peripheral surface on female thread and the first connecting portion 412 outer peripheral face on external screw thread be connected, can make first son connect knot Together with structure 410 is closely attached with the second sub-attachment structure 420, and then ensure the second installation portion 41 and the second joint 42 Steadily and reliably link together.
Specifically, the first connecting portion 412 can include end wall 4121 and around the end wall surrounding wall portion of 4,121 1 weeks 4122, End wall 4121 is located on the upper surface of the first main part 411, and external screw thread is formed on the outer peripheral face of surrounding wall portion 4122, this Sample, the first connecting portion 412 simple in construction, it is simple to remove and install.The lower surface of end wall 4121 and the second main part 421 it Between be provided with sealing member 43, thus the sealing of water knockout drum assembly 200 can be increased, and by arranging sealing member 43, it is also possible to have Avoid water to flow between the first sub-attachment structure 410 and the second sub-attachment structure 420 to effect, such as, avoid water to make screw thread get rusty, So that it is guaranteed that the first sub-attachment structure 410 and service life of the second sub-attachment structure 420, facilitate the first sub-attachment structure 410 Dismounting with the second sub-attachment structure 420 and installation, it is simple to maintenance.
Further, with reference to Fig. 5, the inner peripheral surface of surrounding wall portion 4122 is only against the outside of sealing member 43 and surrounding wall portion 4122 Top is higher than the upper surface of sealing member 43, such that it is able to the most only propped up by sealing member 43, it is ensured that sealing member 43 is at liquid Percussion under be still held in the correct position, the job stability of the sealing member 43 of raising, and surrounding wall portion 4122 Can avoid spilling over outside the water inside surrounding wall portion 4122 outside of surrounding wall portion 4122 further, thus avoid water to damage further First sub-attachment structure 410 and the second sub-attachment structure 420, to improve the first sub-attachment structure 410 and the second son further The service life of attachment structure 420, it is ensured that the dismounting smoothly of the first sub-attachment structure 410 and the second sub-attachment structure 420 and Connection reliability.In addition, it is necessary to explanation, the installation site of sealing member 43 is not limited to this, as long as install sealing member After 43, it can be ensured that the junction of the second installation portion 41 and the second joint 42 is water-tight, and water will not overflow into the first son and connect Between structure 410 and the second sub-attachment structure 420.
Below with reference to Fig. 7-Fig. 9, the second adapter assembly 5 according to another embodiment of this utility model is described.
Shown in Fig. 7-Fig. 9, the second attachment structure 53 includes the first keeper (such as locating slot 531), the second keeper (example Such as ball 532a or elastic buckles 532b) and sliding parts (such as sliding axle sleeve 533).First keeper is located at the second joint On 52, the second keeper is located on the second installation portion 51, and sliding parts are located on the second installation portion 51, and makes second to determine Position part and the first keeper coordinate first extreme position (position shown in Fig. 8 and Fig. 9) of location and make the second keeper And slip between separable second extreme position of the first keeper.Thus sliding parts are in the first extreme position and the second pole Between extreme position, sliding can realize the first keeper and the cooperation of the second keeper and separate, thus realizes the second joint 52 and Installation and removal between two installation portions 51, and then second installation portion 51 and the installation and removal process of the second joint 52 of simplification, Realize being rapidly assembled and disassembled of the second joint 52 and the second installation portion 51.
Alternatively, shown in Fig. 8 and Fig. 9, sliding parts are to be set in outside the second installation portion 51 and along the second installation portion 51 The axially sliding axle sleeve 533 of slip.It is to say, sliding axle sleeve 533 can be along the above-below direction (figure of the second installation portion 51 Above-below direction shown in 8) sliding, when sliding axle sleeve 533 be positioned at upper pole location put time, sliding axle sleeve 533 is in the first pole Extreme position, when sliding axle sleeve 533 be positioned at lower pole location put time, sliding axle sleeve 533 is in the second extreme position.The most permissible Simplify the structure of water knockout drum assembly 200, it is simple to the second joint 52 and installation and removal of the second installation portion 51.
Preferably, shown in Fig. 8 and Fig. 9, the second attachment structure 53 farther includes elastomeric element 534, elastomeric element 534 It is set between the second installation portion 51 and sliding parts (such as sliding axle sleeve 533) often to promote sliding parts (such as sliding axle sleeve 533) the first extreme position (as above location, pole is put) it is positioned at.Thus, by arranging elastomeric element 534, sliding axle sleeve 533 The first keeper and the reliable fit of the second keeper can be locked, thus avoid the second joint 52 upwardly away from the second installation portion 51。
In embodiments more of the present utility model, shown in Fig. 8 and Fig. 9, the sidewall of the second installation portion 51 has between circumference Spaced multiple holes 511, it is interior with first that the part of the second keeper stretches into the second installation portion 51 by hole 511 Keeper coordinates.Thus can strengthen the axial location to the second joint 52, prevent the second joint 52 from axial direction moving, Thus increase the reliability being connected between the second installation portion 51 with the second joint 52.
Alternatively, as shown in Figure 8, the second keeper includes the multiple spheroplast 532as the most corresponding with multiple holes 511. It is to say, spheroplast 532a coordinates with the first keeper to strengthen the axial location to the second joint 52 through hole 511, Prevent the second joint 52 from axial direction moving, realize the connection between the second installation portion 51 and the second joint 52 simultaneously, by This not only can simplify the second attachment structure 53, but also can increase and be connected between the second installation portion 51 with the second joint 52 Reliability.
In other embodiments of the present utility model, as it is shown in figure 9, the second keeper can also include and multiple holes 511 The most corresponding multiple elastic buckles 532b.It is to say, elastic buckles 532b through hole 511 coordinate with the first keeper with Strengthen the axial location to the second joint 52, prevent the second joint 52 from axial direction moving, realize the second installation portion simultaneously 51 and second connections between joint 52, the most not only can simplify the second attachment structure 53, but also can increase by second The reliability being connected between installation portion 51 with the second joint 52.
Further, as shown in Figure 8 and Figure 9, elastic buckles 532b includes the 3rd section of portion 5321 and the 4th section of portion 5322, the Three sections of portions 5321 are positioned at outside the second installation portion 51, and the one end in the 4th section of portion 5322 is connected with the one end in the 3rd section of portion 5321 And the other end in the 4th section of portion 5322 penetrates hole 511.Thus can make the other end and first location in the 4th section of portion 5322 Part coordinates to strengthen the axial location to the second joint 52, prevents the second joint 52 from axial direction moving, and realizes the simultaneously Connection between two installation portions 51 and the second joint 52, the most not only can simplify the second attachment structure 53, but also permissible Increase the reliability being connected between the second installation portion 51 with the second joint 52.
Alternatively, shown in Fig. 8 and Fig. 9, the first keeper is the locating slot 531 being formed on the outer peripheral face of the second joint 52. Thus can further simplify structure, thus save the production cycle, reduce production cost.Further, the second joint 52 On have the part of the second keeper imported the installation guiding surface 521 in locating slot 531, shown in Fig. 8, install and guide Inclined-plane 521 is increasingly towards the centroclinal circular slanting downwardly extended of the second joint 52 on the above-below direction of the second joint 52 Face.Thus it is easy to import the second keeper in the locating slot 531 of the second joint 52, it is simple to the installation of the second joint 52.
Further, the diapire of locating slot 531 is configured to derive the part of the second keeper the dismounting guiding of locating slot 531 Inclined-plane 531a.Such as, shown in Fig. 8, dismounting guiding surface 531a is increasingly towards the on the above-below direction of the second joint 52 The centroclinal upwardly extending annular slope of two joints 52.Thus, convenient dismounting the second joint 52 and the second installation portion 51.
Preferably, in the present embodiment, be provided with between periphery wall and the internal perisporium of the second installation portion 51 of the second joint 52 close Seal 54, it is preferable that sealing ring 54 may be mounted in the cannelure on the internal perisporium of the second installation portion 51, thus plays Reliably and effectively sealing effectiveness.
When assembling the second adapter assembly 5, first by sliding axle sleeve 533 along water knockout drum body the second installation portion 51 axial to Lower movement is put to location, limit inferior position, and now the upper end of sliding axle sleeve 533 then will be able to be divided less than the center of hole 511 Hydrophone joint the second joint 52 axially downwardly pushes water knockout drum body the second installation portion along water knockout drum body the second installation portion 51 In 51, when the assembling guiding surface 521 on water knockout drum joint the second joint 52 touches spheroplast 532a or elastic buckles 532b After, spheroplast 532a or elastic buckles 532b being moved radially outward towards water knockout drum body the second installation portion 51 can be promoted, When water knockout drum joint the second joint 52 moves to spacing locating slot 531 thereon and water knockout drum body the second installation portion 51 Spheroplast 532a or elastic buckles 532b position just pair time, it is spacing fixed that spheroplast 532a or elastic buckles 532b can spring into automatically Position groove 531 in, now, discharge sliding axle sleeve 533, sliding axle sleeve 533 just can under the effect of elastomeric element 534 edge The axial direction of water knockout drum body the second installation portion 51 is moved upward to location, limit superior position and puts, and locks the first locating part first fixed Position part and the cooperation of second locating part the second keeper, complete water knockout drum joint the second joint 52 and install with water knockout drum body second The assembling in portion 51.
When dismantling the second adapter assembly 5, first by throwout sleeve sliding axle sleeve 533 along the second installation portion 51 axially downwardly Mobile location to lower pole is put, and the upper end of now throwout sleeve sliding axle sleeve 533 can connect less than the center of perforated holes 511 The second joint 52 mentioning axially upwards along the second installation portion 51, the dismounting guiding surface 531a of the diapire of locating slot 531 After touching spherical ball body 532a or buckle elastic buckles 532b, spherical ball body 532a or buckle elastic buckles can be promoted 532b is moved radially outward towards the second installation portion 51, when the second joint 52 moves to locating slot 531 and second thereon After spherical ball body 532a on installation portion 51 or buckle elastic buckles 532b is kept completely separate, can the most upward out second peace Dress portion 51, now, discharge throwout sleeve sliding axle sleeve 533, treat the second joint 52 fully out spherical ball body 532a or After buckle elastic buckles 532b, throwout sleeve sliding axle sleeve 533 just can be along second under the effect of elastic component elastomeric element 534 The axial direction of installation portion 51 moves up location, supreme pole and puts, and by spherical ball body 532a's or buckle elastic buckles 532b Part heads in perforated holes 511 again, completes the second joint 52 and dismounting of the second installation portion 51.
Below with reference to Figure 10-Figure 15, the second adapter assembly 6 according to another embodiment of this utility model is described.
Second attachment structure 63 includes press section 631, card-bit part 632 and screens ring 633.Card-bit part 632 is located at second and connects On 62.For example, referring to Figure 11, card-bit part 632 is positioned at the lower end of the second joint 62.Screens ring 633 includes being located at Multiple arc snap rings 6330 on two installation portions 61, multiple arc snap rings 6330 are in the closing position being spliced into a complete annular Put and split into be interrupted between annular division position and may move, with a pressing between two the most adjacent arc snap rings 6330 Relatively, when press section 631 is not pressed, multiple arc snap rings 6330 are positioned at detent position, and press section 631 is pressed in portion 631 After pressure, multiple arc snap rings 6330 move to divide position.
Such as, when press section 631 is not pressed, multiple arc snap rings 6330 are positioned at detent position, and card-bit part 632 is stuck in card In the ring 633 of position.When needs dismounting water knockout drum assembly 200, available finger etc. presses press section 631 so that multiple arcs Snap ring 6330 moves to divide position, and the most multiple arc snap rings 6330 split into interruption annular, and card-bit part 632 is from screens Ring 633 is deviate from.Thus, the second installation portion 61 can be disassembled from the second joint 62, simple in construction, connect skilful Wonderful.
Further, the two ends of each arc snap ring 6330 are respectively provided with guide section 6331, two adjacent guide section 6331 courts To each other away from direction tilt extend.For example, referring to Figure 11, arc snap ring 6330 be two and structure identical.Guide Section 6331 is four, and the lateral cross section of two adjacent guide sections 6331 is formed generally as V-arrangement.When press section 631 quilt During pressing, two adjacent guide sections 6331 of one end extruding of press section 631 so that two arc snap rings 6330 split into It is interrupted annular.Thus, the second installation portion 61 can be disassembled, simple in construction, connect ingenious and facilitate implementation.
According to embodiments more of the present utility model, the second attachment structure 63 farther includes spring part 634, spring part 634 Such as springs etc. are connected between the second installation portion 61 and screens ring 633 often promote multiple arc snap rings 6330 to be positioned at closing Position.Specifically, multiple arc snap rings 6330 are located on the end face of the second installation portion 61.For example, referring to Figure 11, multiple Arc snap ring 6330 is located on the upper surface of the second installation portion 61.On the end face of the second installation portion 61, there is position retaining plate 611, With reference to Figure 11, position retaining plate 611 is vertically extending, and position retaining plate 611 is positioned at the edge of upper surface of the second installation portion 61. The two ends of spring part 634 are the most only against between arc snap ring 6330 and position retaining plate 611.Thus, spring part can be made The position of 634 is stable, thus spring part 634 can be made often to promote multiple arc snap ring 6330 to be frequently located in detent position, improves The reliability of water knockout drum assembly 200.
According to embodiments more of the present utility model, spring part 634 is with the central part on the arc length direction of arc snap ring 6330 only Support.Such as, in the example of fig. 11, the outer peripheral face of the central part on the arc length direction of arc snap ring 6330 has face of only supporting, And face of only supporting is formed as plane.One end of spring part 634 is only against only to be supported on face, thus, can make the position of spring part 634 Put more stable, thus further increasing the reliability of water knockout drum assembly 200.
Further, with reference to Figure 11, water knockout drum assembly 200 also includes that cylindrical member 64, cylindrical member 64 are set in the second installation Outside portion 61 and the second joint 62, one end of press section 631 passes the perisporium of cylindrical member 64 and is movably arranged at cylindrical member On 64.Thus, card-bit part 632 and screens ring 633 can be played a protective role, thus extend water knockout drum assembly 200 Service life.The outward appearance that it also allows water knockout drum assembly 200 is more attractive in appearance.
Specifically, above-mentioned one end of press section 631 has the fastener 631a preventing deviating from cylindrical member 64.Thus, Above-mentioned one end of press section 631 can be limited in cylindrical member 64 so that the position of press section 631 is stable.
In description of the present utility model, it is to be understood that term " " center ", " on ", D score, " top ", Orientation or the position relationship of the instruction such as " end ", " interior ", " outward ", " axially ", " radially ", " circumferential " are base In orientation shown in the drawings or position relationship, be for only for ease of description this utility model and simplify describe rather than instruction or Hint indication device or element must have specific orientation, with specific azimuth configuration and operation, therefore it is not intended that To restriction of the present utility model.
Additionally, term " first ", " second " are only used for describing purpose, and it is not intended that instruction or imply relatively important Property or the implicit quantity indicating indicated technical characteristic.Thus, define " first ", " second " feature permissible Express or implicitly include one or more this feature.In description of the present utility model, " multiple " are meant that Two or more, unless otherwise expressly limited specifically.In this utility model, unless otherwise clear and definite regulation and limit Fixed, fisrt feature second feature " on " or D score can be that the first and second features directly contact, or first and second Feature passes through intermediary mediate contact.
In the description of this specification, reference term " embodiment ", " some embodiments ", " example ", " tool Body example " or the description of " some examples " etc. means to combine this embodiment or example describes specific features, structure, material Material or feature are contained at least one embodiment of the present utility model or example.In this manual, to above-mentioned term Schematic representation is necessarily directed to identical embodiment or example.And, the specific features of description, structure, material or Person's feature can be to combine in one or more embodiments in office or example in an appropriate manner.Additionally, in the most conflicting feelings Under condition, those skilled in the art can be by the different embodiments described in this specification or example and different embodiment or show The feature of example is combined and combines.
Embodiment the most of the present utility model, it will be understood by those skilled in the art that: not These embodiments can be carried out multiple change in the case of departing from principle of the present utility model and objective, revise, replace and become Type, scope of the present utility model is limited by claim and equivalent thereof.

Claims (10)

1. the conduit assembly of a water treatment component, it is characterised in that including:
First adapter assembly, has first passage and second channel in described first adapter assembly;
Second adapter assembly, has third channel and fourth lane in described second adapter assembly;
Pipeline assembly, described pipeline assembly is connected between described first adapter assembly and described second adapter assembly, so that institute State first passage to connect with described third channel, and make described second channel connect with described fourth lane,
Wherein, former water flows into first passage from third channel through described pipeline assembly and filters, then passes through from second channel Described pipeline assembly flows into fourth lane and discharges.
The conduit assembly of water treatment component the most according to claim 1, it is characterised in that described pipeline assembly includes: First water pipe and the second water pipe, described first cross current between described first passage and described third channel, described second Cross current is between described second channel and described fourth lane.
The conduit assembly of water treatment component the most according to claim 2, it is characterised in that described first water pipe sets side by side Side on described second water pipe vertical direction or the side in horizontal direction.
The conduit assembly of water treatment component the most according to claim 3, it is characterised in that described pipeline assembly is further Including: display pipe, described display pipe is wrapped up in and is enclosed within outside described first water pipe and described second water pipe.
The conduit assembly of water treatment component the most according to claim 1, it is characterised in that farther include: support member, Described support member is located on described pipeline assembly to support described pipeline assembly.
The conduit assembly of water treatment component the most according to claim 5, it is characterised in that described support member includes:
Sleeve pipe, described casing pipe sleeve is located on described pipeline assembly;With
Sucker part, described sucker part is located on described connection sleeve pipe.
The conduit assembly of water treatment component the most according to claim 1, it is characterised in that be provided with in described fourth lane Bubbler.
8. according to the conduit assembly of the water treatment component according to any one of claim 1-7, it is characterised in that described first Adapter assembly includes:
First joint;And
First installation portion, described first installation portion is detachably connected by the first attachment structure with described first joint, described Pipeline assembly is connected to described first installation portion.
9. according to the conduit assembly of the water treatment component according to any one of claim 1-7, it is characterised in that described second Adapter assembly includes:
Second joint;And
Second installation portion, described second installation portion is detachably connected by the second attachment structure with described second joint, described Pipeline assembly is connected to described second installation portion.
10. a water treatment component, it is characterised in that including:
Water treatment facilities, described water treatment facilities includes that filter element and base assembly, described filter element include outer filter housing and be accommodated in institute Stating the interior filter housing in outer filter housing, described interior filter housing jointly limits the outflow that connect internal with described interior filter housing with described outer filter housing Road, is provided with filter material to filter former water, described base assembly is formed and is communicated to described interior filter housing in described interior filter housing The first internal water flowing runner and the second water flowing runner being communicated to described outer flow passage;With
According to the conduit assembly of the water treatment component according to any one of claim 1-9, described first adapter assembly is connected to Described water treatment facilities, so that described first passage is communicated to its in described first water flowing runner and described second water flowing runner In one, and make that described second channel is communicated in described first water flowing runner and described second water flowing runner another.
CN201620102818.9U 2016-02-01 2016-02-01 Water treatment component and water pipe assembly thereof Active CN205472729U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620102818.9U CN205472729U (en) 2016-02-01 2016-02-01 Water treatment component and water pipe assembly thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620102818.9U CN205472729U (en) 2016-02-01 2016-02-01 Water treatment component and water pipe assembly thereof

Publications (1)

Publication Number Publication Date
CN205472729U true CN205472729U (en) 2016-08-17

Family

ID=56672225

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620102818.9U Active CN205472729U (en) 2016-02-01 2016-02-01 Water treatment component and water pipe assembly thereof

Country Status (1)

Country Link
CN (1) CN205472729U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109058630A (en) * 2018-09-20 2018-12-21 珠海善德济办公设备有限公司 The pump housing passes in and out water swivel

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109058630A (en) * 2018-09-20 2018-12-21 珠海善德济办公设备有限公司 The pump housing passes in and out water swivel

Similar Documents

Publication Publication Date Title
US11331612B2 (en) Filter cartridge arrangements and assemblies; preferred features; methods of assembly and use
CN105054864A (en) Cyclone separation device, dust collection assembly and dust collector
CN106746144A (en) A kind of filter
CN107821104A (en) A kind of ornamental plantation sections skin growing dendrobium removal of impurities irrigation device
US20170028328A1 (en) Water filter and manifold
CN205472729U (en) Water treatment component and water pipe assembly thereof
KR20130048427A (en) Water purifying filter assembly
CN106267954A (en) A kind of water purification catridge of adjustable water quality
CN204798963U (en) Pipeline filter
CN202605869U (en) Filtering component and external water pump with same
CN103889558A (en) Hollow fiber membrane module
CN103343631B (en) For the siphon head of clean swimming pool
CN205461184U (en) Composite filter element
CN211864006U (en) Diatomite filtering device
CN104190016A (en) Invisible adhesive filtering nasal plug
CN208526026U (en) A kind of multi-stage filtering water purifier
CN205472728U (en) Water knockout drum subassembly and water treatment component who has it
CN109005663A (en) filter core and gravity water purifier
CN205461300U (en) Water knockout drum subassembly and water treatment component who has it
CN205073772U (en) Integrated filter core
CN205516842U (en) Water treatment component
CN105521647A (en) Water treatment assembly
CN103334600B (en) Siphon head for cleaning swimming pool
CN206404409U (en) Filter core and the purifier with it
CN209302311U (en) Multicore fore filter

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant