CN205369197U - Self -elevating drilling unit cantilever beam heavy load testing system - Google Patents

Self -elevating drilling unit cantilever beam heavy load testing system Download PDF

Info

Publication number
CN205369197U
CN205369197U CN201620019774.3U CN201620019774U CN205369197U CN 205369197 U CN205369197 U CN 205369197U CN 201620019774 U CN201620019774 U CN 201620019774U CN 205369197 U CN205369197 U CN 205369197U
Authority
CN
China
Prior art keywords
barge
cantilever beam
self
drilling platform
suspension centre
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620019774.3U
Other languages
Chinese (zh)
Inventor
曹凤丽
吴正峰
林海桥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong Zhenhua Heavy Equipment Manufacturing Co Ltd
Original Assignee
Nantong Zhenhua Heavy Equipment Manufacturing Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nantong Zhenhua Heavy Equipment Manufacturing Co Ltd filed Critical Nantong Zhenhua Heavy Equipment Manufacturing Co Ltd
Priority to CN201620019774.3U priority Critical patent/CN205369197U/en
Application granted granted Critical
Publication of CN205369197U publication Critical patent/CN205369197U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model relates to a self -elevating drilling unit cantilever beam heavy load testing system, include the main hull, the level that lie in the sea level top that support by the spud leg lie in on the main hull and extend to the cantilever beam on the sea level, the drilling platform who lies in the cantilever beam tip and derrick, but the top that lies in derrick upper portion drives and drives the continuous ballast ability of swimming barge on the sea level that floats with the top, the last upright root zone who is provided with the simulation actual weight of drilling platform, the top is driven and is linked to each other with the barge through wire rope. The utility model has the advantages of: the utility model discloses in, regard as the counter weight through the barge with specific, cooperate reasonable frock installation order, experimental allupweight passes through the barge ballast water and realizes convenient and fast, and through the frock universalization, it is applicable experimental in other similar drilling platform system reloads, effective reduce cost.

Description

A kind of self-elevating drilling platform cantilever beam heavy-duty test system
Technical field
This utility model relates to a kind of self-elevating drilling platform, particularly to a kind of self-elevating drilling platform cantilever beam heavy-duty test system.
Background technology
Along with development and the scientific and technological progress of society, the mankind are also increasing for the demand of the energy.Offshore oil drilling platform is built quantity and is got more and more, and beam type drilling platforms enjoys great popularity owing to can carry out the probing of many mouthfuls of cluster wells a position.
In the whole debugging process of drilling platforms system, cantilever beam heavy-duty test is very crucial, it may determine that cantilever beam is in the load capacity of diverse location, specifies the operating load that platform is later, concerns the safety of whole platform.
Owing to this test causes that cantilever beam and hull reach design maximum moment of flexure, shearing and deflection, any trickle carelessness can result in whole platform and destroys greatly, therefore participate in test everyone all must keep in mind the safety problem of test.
Utility model content
The technical problems to be solved in the utility model is to provide one can shorten the test period, and adopts unitized Fixture Design to reduce the self-elevating drilling platform cantilever beam heavy-duty test system of cost.
For solving above-mentioned technical problem, the technical solution of the utility model is: a kind of self-elevating drilling platform cantilever beam heavy-duty test system, and its innovative point is in that: include by spud leg support be positioned at the main hull above sea level, be positioned horizontally on main hull and the cantilever beam extending on sea level, the drilling platforms being positioned at cantilever beam end and derrick, be positioned at the top of upper derrick drive and drive with top be connected swim on sea level can ballast ability of swimming barge;Described drilling platforms is provided with the thribble district of simulation actual weight;Described top is driven and is connected with barge by steel wire rope.
Further, described barge having the suspension centre of eight equalization settings, described suspension centre is in along symmetrically arranged two rows of barge long axis direction, and described barge and top are provided with the specific frock that 8 liftings are converted to two ends lifting between driving.
Further, described top is driven lower end and is connected to hook, and described hook lower end is connected with steel wire rope.
Further, it is characterised in that: described top is driven also has a set of weight sensor bearing pin on the steel wire rope of lower end, described weight sensor bearing pin is arranged on special gusset piece;Described special gusset piece includes upper junction plate and lower connecting plate, described upper junction plate includes two pieces of symmetrically arranged risers, described lower connecting plate is the riser that a upper end is arranged between upper junction plate, and namely described weight sensing bearing pin is horizontally set on upper junction plate and lower connecting plate junction.
Further, described specific frock is be arranged on the middle otic placode that top is driven between hook and barge suspension centre;Described middle otic placode includes a plate and is perpendicular to connecting plate and is symmetricly set on the side plate of connecting plate both sides;Described connecting plate top has two and connects the suspension centre hole that top is driven, and biside plate bottom is respectively provided with two suspension centre holes connecting barge;Described steel wire rope is interspersed in middle otic placode suspension centre hole.
The utility model has the advantage of:
(1) in this utility model, by using specific barge as counterweight, coordinating rational frock erection sequence, test maximum load is realized by barge ballast water, convenient and swift;And by frock generalization, be applicable to the test of other similar drilling platforms system reloads, effectively reduce cost.
(2) derrick top is driven as two points stress, and counterweight barge is 8 stress, changes to successfully realize this stress, and in conjunction with virtual condition, otic placode transition and conversion in design, by Modeling Calculation, this otic placode can bear 1000T.
(3) mounting means of suspension ring is disclosed, it is to avoid directly hang steel wire rope and drive both sides otic placode interference with top, improve safety coefficient;
(4) except intrinsic dead line anchor weight sensor counting, still need to include the equipment of measurable weight below hook, to examine hook heavy duty stress further, purchase a set of weight sensor bearing pin, detection certificate is provided by third party, and designing one group of special gusset piece, it is ensured that sensor bearing pin is provided with effect.
(5) top is driven as two points stress, and barge is 8 stress, and in order to ensure stress equalization, centre needs otic placode transition and conversion in design;In conjunction with virtual condition, devising middle otic placode, top is " two " suspension centre, and bottom is for inserting plate design, " four " suspension centre.For through Modeling Calculation, 1000T can be born.
Accompanying drawing explanation
Fig. 1 is this utility model one self-elevating drilling platform cantilever beam heavy-duty test system schematic.
Fig. 2 is hook schematic diagram in this utility model one self-elevating drilling platform cantilever beam heavy-duty test system.
Fig. 3 is barge in this utility model one self-elevating drilling platform cantilever beam heavy-duty test system, middle otic placode and gusset piece assembling schematic diagram.
Fig. 4 is middle otic placode assembling schematic diagram in this utility model one self-elevating drilling platform cantilever beam heavy-duty test system.
Fig. 5 is gusset piece and shaft coupling assembling schematic diagram in this utility model one self-elevating drilling platform cantilever beam heavy-duty test system.
Detailed description of the invention
This utility model one self-elevating drilling platform cantilever beam heavy-duty test system, as it is shown in figure 1, include by spud leg 13 support be positioned at the main hull 12 above sea level, be positioned horizontally on main hull 12 and extend to the cantilever beam 11 on sea level, be positioned at the drilling platforms 10 of cantilever beam 11 end and derrick 1, be positioned at the top on derrick 1 top drive 2 and drive with top 2 be connected swim on sea level can ballast ability of swimming barge 8;Drilling platforms 10 is provided with the thribble district of simulation actual weight;Top is driven 2 and is connected with barge 8 by steel wire rope.
As it is shown on figure 3, have the suspension centre of eight equalization settings on barge 8, suspension centre is in along symmetrically arranged two rows of barge 8 long axis direction, and barge 8 and top are driven and be provided with the specific frock that 8 liftings are converted to two ends lifting between 2.Top is driven 2 lower ends and is connected to hook 3, and hook 3 lower end is connected with steel wire rope.As figure 5 illustrates, top is driven also has a set of weight sensor bearing pin 92 on 2 lower end steel wire ropes, weight sensor bearing pin 92 is arranged on special gusset piece;Special gusset piece includes upper junction plate 91 and lower connecting plate 93, upper junction plate 91 includes two pieces of symmetrically arranged risers, lower connecting plate 93 is the riser that a upper end is arranged between upper junction plate, and namely weight sensing bearing pin 92 is horizontally set on upper junction plate 91 and lower connecting plate 93 junction.As shown in Figure 4, specific frock is be arranged on the middle otic placode 7 that top is driven between hook 3 and barge 8 suspension centre;Middle otic placode 7 includes a plate 71 and is perpendicular to connecting plate 71 and is symmetricly set on the side plate 72 of connecting plate 71 both sides;Connecting plate 71 top has two connection tops and drives the suspension centre hole of 2, and biside plate 72 bottom is respectively provided with two suspension centre holes connecting barges 8;Steel wire rope is interspersed in middle otic placode 7 suspension centre hole.
Utilize the test that this system carries out as follows:
Test load includes heavy duty and hangs thing (hook counterweight) and thribble counterweight: hook 3 empty-weight and ballast amount combination weight at least can reach 1967 kips (892mt), hangs thing weight and will be loaded into top and drive hook 3;The test weight of 646 kips (293mt) will be arranged in thribble district, thribble weight with maximum 646 kips (293mt) of equivalence, or 2712 combination weights (this weight is estimated value, it is contemplated that the equipment lacked, and is likely to need weight strengthened during test) of kip (1230mt).
First all tool parts related in this being tested are weighed, and are witnessed by third party:
1000TLINK (suspension ring and hook 3) is hung top processed and drives both sides, as shown in Figure 1, it is to avoid hang steel wire rope and drive 2 both sides otic placodes interference with top, improve safety coefficient;
Gusset piece assembly assembled in advance is put in place (comprising sensor bearing pin, axle and axle sleeve), has pierced wire line thimble ¢ 172*12m simultaneously.By drilling platforms lifting and transporting equipment, it is transported to top and drives lower section, adopt 2-500T shackle, as shown in Fig. 3, Fig. 5, steel wire rope and suspension ring are connected;
Existing barge 8 is increased " eight " suspension centre, by otic placode 7 in design specialized, " 8 points " lifting is converted to " 2 points " lifting, by four groups of wire line thimble ¢ 135*35m transition.Middle otic placode 7, by wire line thimble ¢ 172*52m and 1250T shackle, drives less than 2 gusset piece combinations and couples, as shown in Figure 3, Figure 4 with top;
Require to arrange in thribble district 567+79 kip (257+36=293mt) test weight, complete by loading finished product counterweight;
In whole heavy-duty test process, will be monitored and observe at any time.If any problem occurs in process of the test, test should be suspended, release test load (if necessary), be ready to fall platform.
Concrete test procedure is as follows:
(1) pretest inspection: guarantee drilling platforms 10 hull level, confirm slide device in order, open cantilever beam 11 sliding lock, cantilever beam 11 is slid onto rotating disk 6 centre-to-centre spacing stern transom plate 75ft place, and rig floor 10 slides onto rotating disk 6 centre-to-centre spacing hull 12 centrage 0ft place, read deflection initial reading;Rig floor 10 is aport slid onto rotating disk 6 center and leaves hull 12 centrage 15ft, and read deflection;Rig floor 10 astarboard is slid onto rotating disk 6 center and leaves hull centrage 15ft, read deformation values;Regain cantilever beam 11 and arrive the rotating disk 6 suitable distance of centre distance stern transom plate;Platform is made to get out load counterweight in thribble district;567+79 kip equivalence thribble load is loaded in rig floor 10 superstructure thribble district;Afterwards, lifting hull 12, to the air gap required, pins fastening system;Sliding gib beam 11 is until rotating disk 6 centre distance stern transom plate 75ft, and when rotating disk 6 center reaches predetermined testing position, locking cantilever 11 beam sliding is locked;
(2) test one: determine that barge 8 is loaded into specific drainage amount, barge 8 of having good positioning, by hoisting rope, barge 8 is connected with platform hook 3;Sling barge 8 with winch;It is gradually increased hook load until reaching test load with the increment of test weight 50%/25%/25%;Barge 8 is not hung the water surface;After increasing weight, check well drilling winch brake every time;Record deflection after increasing weight every time;After reading final deflection under test load, release winch is until barge 8 swims in water completely slowly;Record deflection;
(3) test two: sling barge 8 with winch;Increase load until reaching test load;Band thribble counterweight slip rig floor, makes rotating disk 6 centre distance hull 12 longitudinal centre line aport 15ft;Test load records deflection after reaching, and reads final deflection under test load, and release winch is until barge swims in water completely slowly, records deflection;
(4) test three: slip rig floor 10, makes center of turntable distance hull 12 longitudinal centre line be moved to astarboard 15ft winch by larboard 15ft and slings barge 8;Increase load until reaching test load;Test load reach after record after deflection reads final deflection under test load, release winch brake slowly is until barge swims in water completely;Record deflection;
Barge 8 is transformed, and wherein barge specification is 4m(moldeed depth) * 56.2m(length) * 14m(width), its empty-weight reaches 440 tons, and ballast amount can more than 1000 tons.Inside barge 8, increase by eight " plug-in type " eye plates, each eye plate allowable load 150T, carry 1200T altogether.
Specific frock is be arranged on the middle otic placode 7 that top is driven between hook 3 and barge 8 suspension centre;Middle otic placode 7 top has two connection tops and drives the suspension centre of hook 3, and bottom has four suspension centres connecting barges 8;Top drives 2 for two points stress, and barge 8 is 8 stress, and in order to ensure stress equalization, centre needs otic placode 7 transition and conversion in design.In conjunction with virtual condition, devising middle otic placode 7, top is " two " suspension centre, and bottom is for inserting plate design, " four " suspension centre.For through Modeling Calculation, 1000T can be born;
Top is driven hook 3 lower end and is had a set of weight sensor bearing pin, and weight sensor bearing pin 92 is arranged on special gusset piece;Sensor bearing pin 92 requires that induction point straight down, and requires uniform load on axle, and otherwise read untrue causes that result of the test lost efficacy by shearing force;The intensity of gusset piece 9 is under the premise meeting cantilever beam heavy-duty test maximum load, and its thickness is not more than the width of each segmentation stress of sensor bearing pin 92, it is ensured that its uniform load.
Counterweight frame is adopted during thribble district counterweight;For installation thribble district efficient, quick counterweight, newly purchase finished product balancing weight, monolithic-150X1000X1500, weight about 1.5 tons, by the crane gear of drilling platforms self configuration, in conjunction with its elevating capacity, devise counterweight frame simultaneously, once can transport 6, be greatly improved work efficiency.
Of the present utility model ultimate principle and principal character have more than been shown and described.Skilled person will appreciate that of the industry; this utility model is not restricted to the described embodiments; described in above-described embodiment and description is that principle of the present utility model is described; under the premise without departing from this utility model spirit and scope; this utility model also has various changes and modifications, and these changes and improvements both fall within the scope of claimed this utility model.This utility model claims scope and is defined by appending claims and equivalent thereof.

Claims (5)

1. a self-elevating drilling platform cantilever beam heavy-duty test system, it is characterised in that: include by spud leg support be positioned at the main hull above sea level, be positioned horizontally on main hull and the cantilever beam extending on sea level, the drilling platforms being positioned at cantilever beam end and derrick, be positioned at the top of upper derrick drive and drive with top be connected swim on sea level can ballast ability of swimming barge;Described drilling platforms is provided with the thribble district of simulation actual weight;Described top is driven and is connected with barge by steel wire rope.
2. a kind of self-elevating drilling platform cantilever beam heavy-duty test system according to claim 1, it is characterized in that: described barge has the suspension centre of eight equalization settings, described suspension centre is in along symmetrically arranged two rows of barge long axis direction, and described barge and top are provided with the specific frock that 8 liftings are converted to two ends lifting between driving.
3. a kind of self-elevating drilling platform cantilever beam heavy-duty test system according to claim 1, it is characterised in that: described top is driven lower end and is connected to hook, and described hook lower end is connected with steel wire rope.
4. a kind of self-elevating drilling platform cantilever beam heavy-duty test system according to claim 1, it is characterised in that: described top is driven also has a set of weight sensor bearing pin on the steel wire rope of lower end, described weight sensor bearing pin is arranged on special gusset piece;Described special gusset piece includes upper junction plate and lower connecting plate, described upper junction plate includes two pieces of symmetrically arranged risers, described lower connecting plate is the riser that a upper end is arranged between upper junction plate, and namely described weight sensing bearing pin is horizontally set on upper junction plate and lower connecting plate junction.
5. a kind of self-elevating drilling platform cantilever beam heavy-duty test system according to claim 2, it is characterised in that: described specific frock is be arranged on the middle otic placode that top is driven between hook and barge suspension centre;Described middle otic placode includes a plate and is perpendicular to connecting plate and is symmetricly set on the side plate of connecting plate both sides;Described connecting plate top has two and connects the suspension centre hole that top is driven, and biside plate bottom is respectively provided with two suspension centre holes connecting barge;Described steel wire rope is interspersed in middle otic placode suspension centre hole.
CN201620019774.3U 2016-01-11 2016-01-11 Self -elevating drilling unit cantilever beam heavy load testing system Active CN205369197U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620019774.3U CN205369197U (en) 2016-01-11 2016-01-11 Self -elevating drilling unit cantilever beam heavy load testing system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620019774.3U CN205369197U (en) 2016-01-11 2016-01-11 Self -elevating drilling unit cantilever beam heavy load testing system

Publications (1)

Publication Number Publication Date
CN205369197U true CN205369197U (en) 2016-07-06

Family

ID=56275512

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620019774.3U Active CN205369197U (en) 2016-01-11 2016-01-11 Self -elevating drilling unit cantilever beam heavy load testing system

Country Status (1)

Country Link
CN (1) CN205369197U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105464064A (en) * 2016-01-11 2016-04-06 南通振华重型装备制造有限公司 System and method for cantilever beam heavy-duty test of self-elevating drilling platform
CN107101882A (en) * 2016-02-23 2017-08-29 烟台中集来福士海洋工程有限公司 A kind of method of machine utilization experiment
CN109738139A (en) * 2018-12-26 2019-05-10 大连中远海运重工有限公司 Water tank chute type cantilever beam load test method
CN109738215A (en) * 2018-12-20 2019-05-10 大连中远海运重工有限公司 The test method of self-elevating drilling platform application harbour water tank progress endurance test

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105464064A (en) * 2016-01-11 2016-04-06 南通振华重型装备制造有限公司 System and method for cantilever beam heavy-duty test of self-elevating drilling platform
CN105464064B (en) * 2016-01-11 2017-06-23 南通振华重型装备制造有限公司 A kind of self-elevating drilling platform cantilever beam heavy-duty test system and method
CN107101882A (en) * 2016-02-23 2017-08-29 烟台中集来福士海洋工程有限公司 A kind of method of machine utilization experiment
CN109738215A (en) * 2018-12-20 2019-05-10 大连中远海运重工有限公司 The test method of self-elevating drilling platform application harbour water tank progress endurance test
CN109738215B (en) * 2018-12-20 2020-09-15 大连中远海运重工有限公司 Test method for endurance test of self-elevating drilling platform by applying wharf water tank
CN109738139A (en) * 2018-12-26 2019-05-10 大连中远海运重工有限公司 Water tank chute type cantilever beam load test method

Similar Documents

Publication Publication Date Title
CN105464064B (en) A kind of self-elevating drilling platform cantilever beam heavy-duty test system and method
CN205369197U (en) Self -elevating drilling unit cantilever beam heavy load testing system
US4714382A (en) Method and apparatus for the offshore installation of multi-ton prefabricated deck packages on partially submerged offshore jacket foundations
CN105523477B (en) A kind of method that spud leg pile extension is carried out using 3000t crane barges
CN110656890B (en) Deepwater geological drilling casing, casing hoisting system and casing hoisting method
CN202547962U (en) Load test device for derrick system of drilling platform
CN104088307A (en) Method for detecting vertical bearing capacity of pile foundation
CN208393602U (en) It is a kind of for detecting the diving cage of operation under water
CN202030434U (en) Large-span whole-section hoisting sling for steel box girder
CN204827251U (en) Novel suit derrick upright
ES2668024B1 (en) EFFICIENT ASSEMBLY SYSTEM OF A LARGE SCALE COUNTERWEIGHT FOR A VERTICAL BOAT ELEVATOR AND ASSEMBLY METHOD
CN104234636B (en) Jack-up unit derrick installation method
CN101332962B (en) Waterpower inserting plate balancing hoisting machine
CN103556626A (en) Hanging structure for hoisting large-diameter hole drilling filling pile steel bar cage
CN217808286U (en) Self-balancing hoisting device for building construction
CN114718479A (en) Testing method for drilling system hook
CN206488934U (en) Avoid the Suspension Attachment of Offshore Platform load test stabilization device by face external force
CN201250067Y (en) Hydraulic flashboard balance crane
CN203625891U (en) Hanging structure for large-diameter hole drilling cast pile reinforcement cage hanging
CN205634613U (en) A balanced hanging beam for hoisting steel bridge box girder
CN211078164U (en) Hoisting adjusting structure of crane
CN108438177A (en) A kind of diving cage for underwater detection operation
CN103196688A (en) Lever type dynamic load test platform with loads adjustable
CN209554634U (en) A kind of caisson lifting structure
CN204778268U (en) A special lifting device for hoist and mount of large -tonnage precast box girder

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant