A kind of fixing device between cursory ball and frame rope
Technical field
This utility model belongs to mariculture technology field, specifically refers to the fixing device between a kind of cursory ball and frame rope.
Background technology
Cursory ball is one of indispensable equipment in sea-farming production process, especially when building culture raft frame, it is necessary to fix multiple cursory ball on frame rope to ensure that whole raft frame is positioned on sea level.The structure of current cursory ball is shown in that shown in accompanying drawing 1 and accompanying drawing 2, it includes spheroid 1, is arranged over two hangers 2 at spheroid 1, and hanger 2 is respectively equipped with two fixing holes 3.At present will be mostly to adopt the mode tied up to carry out time fixing with frame rope for cursory ball, require to rotate between cursory ball and frame rope after tying up, slide, more can not cause separating between cursory ball with frame rope, therefore effect is tied up for guarantee, mostly it is utilize auxiliary support bar to be connected by two hangers then hanger and support bar to be tied up with frame rope respectively, its complicated operation, tie up efficiency low, and it cannot be guaranteed that connect reliability, have substantial amounts of cursory ball in process of production every year to be come off by frame rope, cause a large amount of loss of cursory ball.
Summary of the invention
For solving to be connected fixing technical problem between current cursory ball and frame rope, this utility model provides the fixing device between a kind of cursory ball and frame rope.
For realizing above-mentioned technical purpose, the technical solution adopted in the utility model is: the fixing device between a kind of cursory ball and frame rope, it includes hanger folder, it is characterized in that: described hanger folder is in inverted u-shaped, hanger folder inner width and cursory ball hanger consistency of thickness, with the camber line identical with cursory ball sphere bottom hanger folder double wall, the double wall of hanger folder both sides is provided with the through hole corresponding with fixing hole on cursory ball hanger, through hole is consistent with fixing hole diameter, after cursory ball hanger is positioned at hanger folder inside, through hole is through with fixing hole, hanger folder inner space above cursory ball hanger forms frame rope passage;Also include the expandable nail through through hole, fixing hole, described expandable nail includes nail rod, it is provided with taper nail tip in nail rod front end, nail rod rear end is provided with tailstock, nail rod front end and taper nail tip have the contraction notch of radially hollow out, when after taper nail tip stress can elastic shrinkage deformation, described nail rod diameter and through hole, fixing hole diameter are consistent, and cone centre rear end diameter and tailstock diameter are more than nail rod diameter.
Further, described hanger presss from both sides, and is provided with some projections protruded inwardly from the top double wall within its clamp.
Further, the top double wall of described hanger folder has some fixing nail through holes;Also include fixing nail arc plate, the radian of described fixing nail arc plate is consistent with hanger ogival sections radian, the inner surface of fixing nail arc plate is provided with the fixing nail consistent with fixing nail quantity, the nail wall of described fixing nail is provided with non-return boss, the fixing nail rivet nut of non-return boss correspondence position has notch, when can elastic shrinkage after non-return boss stress, after fixing nail arc plate cover is buckled in hanger ogival sections, fixing nail is after fixing nail through hole, and it is internal that the fixing non-return boss nailed on and front end rivet nut thereof are positioned at hanger folder.
A kind of above-mentioned fixing device is utilized to carry out being connected between cursory ball with frame rope fixing method, it is characterised in that the method comprises the following steps:
(1), by hanger clip on frame rope, frame rope is positioned at hanger folder inner top;
(2), the hanger on cursory ball is sent into hanger folder inside and firmly to the internal jack-up of hanger folder until the through hole on hanger folder aligns with the fixing hole on cursory ball hanger;
(3), expandable nail is inserted by the through hole of the upper side of hanger folder, and beat expandable nail with hammer body, until the through hole that the taper nail tip of expandable nail is pressed from both sides opposite side by hanger passes.
Further, in above-mentioned connection fixing means, the top double wall of described hanger folder has some fixing nail through holes;Also include fixing nail arc plate, the radian of described fixing nail arc plate is consistent with hanger ogival sections radian, the inner surface of fixing nail arc plate is provided with the fixing nail consistent with fixing nail quantity, the nail wall of described fixing nail is provided with non-return boss, the fixing nail rivet nut of non-return boss correspondence position has notch, when can elastic shrinkage after non-return boss stress, after fixing nail arc plate cover is buckled in hanger ogival sections, fixing nail is after fixing nail through hole, and it is internal that the fixing non-return boss nailed on and front end rivet nut thereof are positioned at hanger folder;The installation of fixing nail arc plate is also included before described step (1), the installation steps of described fixing nail arc plate are: select appropriate length to fix the fixing nail arc plate of nail according to the size of frame rope diameter, fixing nail arc plate cover is buckled in hanger ogival sections, fixing nail is alignd with fixing nail through hole, fixing nail arc plate is exerted a force downwards till the fixing non-return boss nailed on and front end rivet nut thereof press from both sides double wall through hanger.
The beneficial effects of the utility model are: fixture structure is simple, easy to make, when being attached fixing with this fixing device simple to operate, operating efficiency can be significantly improved, ensure that stablizing between cursory ball with frame rope is firmly connected simultaneously, effectively prevent the loss of cursory ball.
Accompanying drawing explanation
Accompanying drawing 1 is the structural front view of cursory ball.
Accompanying drawing 2 is the structure left view of cursory ball.
Accompanying drawing 3 is the structural front view of hanger folder in first embodiment.
Accompanying drawing 4 looks for, for first embodiment, the structure left view that hanger presss from both sides.
Accompanying drawing 5 is the structural representation of expandable nail.
Accompanying drawing 6 presss from both sides the structure sectional view being connected with frame rope, cursory ball hanger for the provided hanger of first embodiment.
Accompanying drawing 7 is the structure left view of the second embodiment hanger folder.
Accompanying drawing 8 presss from both sides the structure sectional view being connected with frame rope, cursory ball hanger for the second provided hanger of embodiment.
Accompanying drawing 9 is the structural front view of the 3rd the provided hanger folder of embodiment.
Accompanying drawing 10 is the structural representation of fixing nail arc plate.
The structure sectional view that accompanying drawing 11 is connected with fixing nail arc plate, frame rope, cursory ball for the 3rd embodiment provided hanger folder.
Detailed description of the invention
Below in conjunction with drawings and Examples, this utility model is described further.
Embodiment 1
As shown in accompanying drawing 3 and accompanying drawing 4, a kind of fixing device between cursory ball and frame rope, it includes hanger folder 4, this hanger folder is in inverted u-shaped, hanger folder inner width and cursory ball hanger consistency of thickness, with the camber line 5 identical with cursory ball sphere bottom hanger folder double wall, the double wall of hanger folder both sides is provided with the through hole 6 corresponding with fixing hole on cursory ball hanger, and through hole 6 is consistent with fixing hole 3 diameter.
As shown in Figure 5, also including expandable nail 7, described expandable nail includes nail rod 71, is provided with taper nail tip 72 in nail rod front end, and nail rod rear end is provided with tailstock 73, has the contraction notch 74 of radially hollow out on nail rod front end and taper nail tip.Expandable nail adopts highstrenghtpiston to be made, not only it has corrosion resistance but also have certain elasticity, when can elastic shrinkage deforming after taper nail tip 72 stress.During making.Nail rod 71 diameter and through hole 6, fixing hole 3 diameter are consistent, and cone centre 72 rear end diameter and tailstock 73 diameter are more than nail rod diameter.
As shown in Figure 6, when carrying out cursory ball and being connected with frame rope fixing, cursory ball hanger 2 is positioned at after hanger presss from both sides 4 inside, and through hole is through with fixing hole, and the hanger folder inner space above cursory ball hanger forms frame rope passage 8.Concrete method of attachment is: (1), pressed from both sides by hanger and 4 be buckled on frame rope 9, and frame rope 9 is positioned at hanger folder inner top;(2), the hanger 2 on cursory ball is sent into hanger folder 4 inside and firmly to the internal jack-up of hanger folder until the through hole on hanger folder aligns with the fixing hole on cursory ball hanger, in process upwardly, frame rope stress deformation, is clipped solid jam-packed by hanger and hanger;(3), expandable nail 7 is inserted by the through hole of the upper side of hanger folder, and beat expandable nail with hammer body, until the through hole that the taper nail tip 72 of expandable nail is pressed from both sides opposite side by hanger passes.After completing above-mentioned steps, cursory ball is securely joined together by hanger folder with frame rope, can effectively prevent between cursory ball with frame rope, separating the loss causing cursory ball, after cursory ball damages, with instrument, the tailstock 73 of expandable nail is cut down, take off expandable nail residue rivet nut, the cursory ball more renewed smoothly, be fixed again with expandable nail.
Embodiment 2
Although the hanger that embodiment 1 provides is clipped in frame rope 9 when using is subject to the extruding of hanger folder 4 and hanger 2, but in stormy waves environment, cursory ball still can rotate by frame rope, and this rotation can aggravate the abrasion of frame rope 9 and hanger folder 4, reduces its service life.For solving this technical problem, in the present embodiment, the structure of hanger folder is made further improvements.
As shown in Figure 7, the hanger folder 4 that the present embodiment provides is further improved on the basis of the provided hanger folder of embodiment 1.Press from both sides at hanger and the top double wall within clamp is provided with some projections 10 protruded inwardly from.
After projection 10 is set, as shown in Figure 8, after hanger folder 4, frame rope 9, hanger 2 connection are fixed, it is internal that projection 10 is inserted into frame rope 9, stop due to projection 10, being formed between hanger folder 4 and frame rope 9 and be stably connected with, it will not occur frame rope to rotate, and can not horizontally slip along frame rope simultaneously, in stormy waves environment, cursory ball remains the stable fastness being connected between frame rope, greatly extends service life, it is prevented that separate between cursory ball with frame rope.
Embodiment 3
Owing to individual manufacturer standard differs, frame rope diameter is inconsistent, on cursory ball, hanger height is also difficult to ensure that unanimously, when producing bigger space between frame rope passage 8 and frame rope 9, even if there being the existence of projection 10 in embodiment 2 to be also difficult to frame rope 9 is formed effectively stable clamping, cause the changing of the relative positions between hanger folder 4 and frame rope.
For solving above-mentioned technical problem, in the present embodiment hanger folder is made further improvements.
As shown in Figure 9, the hanger folder 4 provided in the present embodiment, its top double wall has some fixing nail through holes 11.
As shown in Figure 10, also include fixing nail arc plate 12, the radian of this fixing nail arc plate 12 is consistent with hanger ogival sections radian, the inner surface of fixing nail arc plate is provided with the fixing nail 13 consistent with fixing nail quantity, the nail wall of described fixing nail is provided with non-return boss 14, the fixing nail rivet nut of non-return boss correspondence position has notch 15, when can elastic shrinkage after non-return boss 14 stress.
This fixing nail arc plate 12 is when making, and the length of fixing nail 13 and diameter can be adjusted making, to produce the fixing nail arc plate of multiple specifications and models.Material selection highstrenghtpiston makes, and existing anti-corrosive properties have again certain toughness and elasticity.
As shown in Figure 11, during use, size according to frame rope 9 diameter selects appropriate length to fix the fixing nail arc plate 12 of nail, fixing nail arc plate 12 cover is buckled in hanger and presss from both sides 4 tops, fixing nail 13 is alignd with fixing nail through hole 11, fixing nail arc plate 12 is exerted a force downwards till the fixing non-return boss 14 nailed on and front end rivet nut thereof press from both sides double wall through hanger.Follow-up operational approach is consistent with the mode of operation of the hanger folder provided in embodiment 1.
As shown in Figure 11, after frame rope 9 is clamped, frame rope and hanger are picked up fixation after lunging frame rope 9 inside by fixing nail 13.Simultaneously because select the fixing nail arc plate 12 of different size to can adapt to differing heights hanger and the needs of different-diameter frame rope installation, when frame rope is relatively large in diameter, the length optional of fixing nail is selected short, and when frame rope diameter diminishes, optional long fixing nail is attached fixing, thus reaching flexible collocation, the convenient technical purpose installed.