CN205318199U - Divide defeated station control room - Google Patents

Divide defeated station control room Download PDF

Info

Publication number
CN205318199U
CN205318199U CN201521068979.2U CN201521068979U CN205318199U CN 205318199 U CN205318199 U CN 205318199U CN 201521068979 U CN201521068979 U CN 201521068979U CN 205318199 U CN205318199 U CN 205318199U
Authority
CN
China
Prior art keywords
plc
room
flow measurement
point
door
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201521068979.2U
Other languages
Chinese (zh)
Inventor
路金才
张帅华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianbao Zhongtian Science and Technology (Tianjin) Co., Ltd.
Original Assignee
Tianbao Zhongtian Science And Technology (tianjin) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianbao Zhongtian Science And Technology (tianjin) Co Ltd filed Critical Tianbao Zhongtian Science And Technology (tianjin) Co Ltd
Priority to CN201521068979.2U priority Critical patent/CN205318199U/en
Application granted granted Critical
Publication of CN205318199U publication Critical patent/CN205318199U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Toilet Supplies (AREA)

Abstract

The utility model discloses a divide defeated station control room, include from between the instrument that the sets gradually control of a left side to the right side, between the rack, between the battery and electricity distribution room, be equipped with the three PLC active station that sets up side by side at least in between instrument control to and set gradually data terminal computer, video terminal equipment and the printer in the PLC active station that lies in one of them side, be equipped with the PLC controller with PLC active station one -to -one in between the rack to and a plurality of flow measurement cabinets, the PLC controller is connected in the flow measurement cabinet, connect in electricity distribution room between the battery, electricity distribution room are between to instrument control and the electric energy of deliveing between the rack. By providing a plurality of PLC active stations and data terminal computer, video terminal equipment and printer in between the instrument control, provide a plurality of PLC controllers and flow measurement cabinet between the rack, can satisfy the defeated user's of a plurality of branches demand, and the spatial layout in above -mentioned control room is equitable, the placing of the newly -increased equipment of being convenient for.

Description

A kind of point defeated station control room
Technical field
This utility model relates to Natural Gas Station association area, particularly relates to a kind of point of defeated station control room.
Background technology
Natural Gas Station is generally built on long-distance transport pipes, it is used for distributing the natural gas of long-distance transport pipes, assign them to downstream user, existing point of defeated station is generally controlled the transport of natural gas by a set of PLC and PLC active station, but during for dividing defeated user more, the said equipment is difficult to meet the demand of multiple points of defeated users, and the space layout of existing point of defeated station control room is not reasonable, make space shared by internal each functional device very few, be unfavorable for the placement of newly added equipment.
Utility model content
The purpose of this utility model is in that to provide one point defeated station control room, it is possible to meet the demand of multiple points of defeated users, and the space layout of above-mentioned control room is reasonable, it is simple to the placement of newly added equipment.
For reaching this purpose, this utility model by the following technical solutions: a kind of point of defeated station control room, between controlling including the instrument set gradually from left to right, between rack room, accumulator and switchgear house, wherein,
Described instrument is provided with, in controlling, the PLC active station that at least three is arranged side by side, and is successively set on and is located therein the data terminal computer of PLC active station side of side, video frequency terminal apparatus and printer;
It is provided with in described rack room and PLC active station PLC one to one, and some flow measurement cabinets, described PLC is connected to flow measurement cabinet;
Being connected to switchgear house between described accumulator, switchgear house is between instrument control and rack room electricity distribution.
As preferably, between described instrument controls, between rack room, accumulator and on switchgear house, be equipped with door, and described instrument control between, between rack room, accumulator and switchgear house be provided with the side of door and be provided with corridor.
As preferably, the side in described corridor is provided with door, and the side of described door is provided with step.
As preferably, being additionally provided with office and toilet between described accumulator and between switchgear house, described office and toilet are equipped with door.
As preferably, described flow measurement cabinet is connected with base, and described base includes the some gripper shoes being positioned at bottom, is installed in the support column above gripper shoe, and is positioned at the horizontal stand of support column upper end, and described flow measurement cabinet is arranged on horizontal stand.
As preferably, described horizontal stand is provided with through hole, and described flow measurement cabinet is arranged on horizontal stand through through hole by bolt.
As preferably, described gripper shoe is provided with some holes.
As preferably, described door is single open-door structure/double swing doors.
The beneficial effects of the utility model: by arranging multiple PLC active station and data terminal computer, video frequency terminal apparatus and printer in instrument control, multiple PLC and flow measurement cabinet are set at rack room, disclosure satisfy that the demand of multiple points of defeated users, and the space layout of above-mentioned control room is reasonable, it is simple to the placement of newly added equipment.
Accompanying drawing explanation
Fig. 1 is the structural representation of this utility model control room;
Fig. 2 is the structural representation of this utility model base.
In figure:
1, between instrument controls; 2, rack room; 3, between accumulator; 4, switchgear house; 5, door; 6, corridor; 7, office; 8, toilet; 9, entrance guard room; 11, PLC active station; 12, data terminal computer; 13, video frequency terminal apparatus; 14, printer; 21, PLC; 22, flow measurement cabinet; 61, step; 231, gripper shoe; 232, support column; 233, horizontal stand; 2311, hole; 2331, through hole.
Detailed description of the invention
The technical solution of the utility model is further illustrated below in conjunction with accompanying drawing and by detailed description of the invention.
This utility model provides one point defeated station control room, as it is shown in figure 1, it instrument including setting gradually from left to right control between 1, rack room 2, between accumulator 3 and switchgear house 4, wherein,
Instrument is provided with the PLC active station 11 that at least three is arranged side by side in 1 between controlling, the present embodiment is set to three, and be successively set on and be located therein the data terminal computer 12 of PLC active station 11 side of side, video frequency terminal apparatus 13 and printer 14, wherein data terminal computer 12 is for receiving the related datas such as the data on flows of the natural gas flowing to each point of defeated user, pressure data, and above-mentioned data are passed to long distance control system, it is simple to remotely control; Video frequency terminal apparatus 13 display flows to the dynamic menu of the natural gas of each point of defeated user; Printer 14 is then for the printing to above-mentioned each data.
It is provided with in rack room 2 and PLC active station 11 PLC 21 one to one, and some flow measurement cabinets 22, this PLC 11 is connected to flow measurement cabinet 22, record flow to a point data on flows for the natural gas of defeated user for gathering each flow measurement cabinet 22, and deliver the data to data terminal computer 12. PLC active station 11 is for carrying out order input and control to PLC 21. In the present embodiment, flow measurement cabinet 22 is set to multiple and is arranged side by side, and is specifically configured to 6, is connected to above-mentioned three PLC 11 respectively between two.
Between accumulator, 3 are connected to switchgear house 4, are used for providing power supply.
PLC 21 in PLC active station 11, data terminal computer 12, video frequency terminal apparatus 13 and printer 14 that switchgear house 4 is connected between instrument control in 1 and rack room 2 and flow measurement cabinet 22 electricity distribution.
In the present embodiment, instrument control between 1, rack room 2, between accumulator 3 and switchgear house 4 on be equipped with door 5, for the turnover of operator.
In the present embodiment, between instrument control 1, between rack room 2, accumulator 3 and switchgear house 4 be provided with the side of door 5 and be provided with corridor 6, for operator's walking in each room, be provided with door 5 in the side in corridor 6, it is provided with step 61 in this side of 5, enters corridor 6 for operator.
Office 7 and toilet 8 it is additionally provided with between 3 and switchgear house 4 between accumulator, for the rest of operator with go to toilet, same, it is equipped with door 5 in the side of office 7 and toilet 8. The present embodiment can also arrange entrance guard room 9 in this control room.
Preferably, it is connected with base (not shown in figure 1) at flow measurement cabinet 22, this base is as shown in Figure 2, they some gripper shoes 231 including being positioned at bottom, it is installed in the support column 232 above gripper shoe 231, and it being positioned at the horizontal stand 233 of support column 232 upper end, flow measurement cabinet 22 is arranged on horizontal stand 233.
Wherein being provided with through hole 2331 on horizontal stand 233, flow measurement cabinet 22 is arranged on horizontal stand 233 through through hole 2331 by bolt.
Gripper shoe 231 is provided with some holes 2311, foundation bolt can be passed through this gripper shoe 231 is fixed on the ground of control room.
In said structure, involved door 5 is single open-door structure or double swing doors, and concrete can be configured according to the size of each room.
Obviously, above-described embodiment of the present utility model is only used to clear this utility model example that illustrates, and is not the restriction to embodiment of the present utility model. For those of ordinary skill in the field, can also make other changes in different forms on the basis of the above description. Here without also cannot all of embodiment be given exhaustive. All any amendment, equivalent replacement and improvement etc. made within spirit of the present utility model and principle, should be included within this utility model scope of the claims.

Claims (8)

1. one kind of point of defeated station control room, it is characterised in that include the instrument that sets gradually from left to right control between (3) and switchgear house (4) between (1), rack room (2), accumulator, wherein,
It is provided with, in (1), the PLC active station (11) that at least three is arranged side by side between the control of described instrument, and is successively set on the data terminal computer (12) of PLC active station (11) side being located therein side, video frequency terminal apparatus (13) and printer (14);
It is provided with in described rack room (2) and PLC active station (11) PLC one to one (21), and some flow measurement cabinets (22), described PLC (21) is connected to flow measurement cabinet (22);
Between described accumulator, (3) are connected to switchgear house (4), and switchgear house (4) is to (1) between instrument control and rack room (2) electricity distribution.
2. according to claim 1 point of defeated station control room, it is characterized in that, described instrument is equipped with door (5) on (3) and switchgear house (4) between (1), rack room (2), accumulator between controlling, and described instrument control between (1), rack room (2), accumulator (3) and switchgear house (4) be provided with the side of door (5) and be provided with corridor (6).
3. according to claim 2 point of defeated station control room, it is characterised in that the side of described corridor (6) is provided with door (5), and the side of described door (5) is provided with step (61).
4. according to claim 1 point of defeated station control room, it is characterized in that, it is additionally provided with office (7) and toilet (8), described office (7) and toilet (8) between described accumulator between (3) and switchgear house (4) and is equipped with door (5).
5. according to claim 1 point of defeated station control room, it is characterized in that, described flow measurement cabinet (22) is connected with base, described base includes the some gripper shoes (231) being positioned at bottom, it is installed in the support column (232) of gripper shoe (231) top, and it being positioned at the horizontal stand (233) of support column (232) upper end, described flow measurement cabinet (22) is arranged on horizontal stand (233).
6. according to claim 5 point of defeated station control room, it is characterized in that, described horizontal stand (233) is provided with through hole (2331), and described flow measurement cabinet (22) is arranged on horizontal stand (233) through through hole (2331) by bolt.
7. according to claim 5 point of defeated station control room, it is characterised in that described gripper shoe (231) is provided with some holes (2311).
8. according to the arbitrary described point defeated station control room of claim 2-4, it is characterised in that described door (5) is single open-door structure/double swing doors.
CN201521068979.2U 2015-12-17 2015-12-17 Divide defeated station control room Expired - Fee Related CN205318199U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201521068979.2U CN205318199U (en) 2015-12-17 2015-12-17 Divide defeated station control room

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201521068979.2U CN205318199U (en) 2015-12-17 2015-12-17 Divide defeated station control room

Publications (1)

Publication Number Publication Date
CN205318199U true CN205318199U (en) 2016-06-15

Family

ID=56186027

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201521068979.2U Expired - Fee Related CN205318199U (en) 2015-12-17 2015-12-17 Divide defeated station control room

Country Status (1)

Country Link
CN (1) CN205318199U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109210380A (en) * 2017-06-07 2019-01-15 北京东方华智石油工程有限公司 Natural gas divides transmission method and system automatically

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109210380A (en) * 2017-06-07 2019-01-15 北京东方华智石油工程有限公司 Natural gas divides transmission method and system automatically

Similar Documents

Publication Publication Date Title
CN103806704B (en) A kind of modular data center machine room with closed channel
CN205318199U (en) Divide defeated station control room
CN206790212U (en) A kind of small busbar electric distribution system of data center
CN204335235U (en) A kind of Joint construction and sharing type base station integrated machine cabinet
CN204668863U (en) 2M cell cube activity reason coil holder
CN104320478A (en) Transformer substation real-time information browsing system based on digital remote centralized management scheme
CN204045951U (en) A kind of arrangement of 220kV power distribution equipment
CN103579921A (en) Comprehensive power distribution device
CN106049914B (en) Communication base station integration method and integrated communication base station
CN204146637U (en) A kind of file management cabinet
CN205724593U (en) Transformer station and a kind of layer fraction transformer station
CN205921860U (en) Miniature data center of modularization
CN203523206U (en) Network cabinet
CN204377268U (en) Multi-functional communications rack
CN203748161U (en) Turnover power-distribution unit for communication cabinet
CN202274247U (en) Bracket for placing remote controllers
CN207118117U (en) Combined outdoor rack
CN204947494U (en) Comprehensive wiring system in a kind of intelligent building
CN207475113U (en) Electric power extra-high voltage station used in communication machine room " mesh " font two-layer wiring slot box
CN203884989U (en) Multifunctional operating table with organized routing
CN204615231U (en) The full indoor substation of a kind of 110kV double winding split transformer
CN205104769U (en) Double -deck built on stilts GIS combined electrical apparatus of being qualified for next round of competitions and distribution lines layout structure thereof
CN103135020A (en) Flexibly configured experimental platform suitable for various distributed type power supply connection modes
CN203150908U (en) Distribution management terminal
CN104754731A (en) Indoor positioning system and positioning method of distributed antenna system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 300308 Huaying Building, Dongli Airport Economic Zone, Tianjin - A

Patentee after: Tianbao Zhongtian Science and Technology (Tianjin) Co., Ltd.

Address before: 300308 Huaying Building, Dongli Airport Economic Zone, Tianjin - A

Patentee before: Tianbao Zhongtian science and Technology (Tianjin) Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160615