Tower section application dummy-flange device
Technical field
The utility model relates to tower section application dummy-flange device, belongs to wind-power tower and manufactures field.
Background technology
Tower section needs to be placed on application roller moulding bed carries out rotation spray paint, roller and tower section outer wall one will certainly be affected enclose contact portion and cannot spray paint, carry out secondary again after also needing to wait paint curing to spray paint, namely delay the duration, again reduce production efficiency and add cost.
Existing solution adopts pseudo-flange fixture to improve, but existing pseudo-flange fixture easily causes flange hole to be out of shape to flange hole extruding for the bolt of fixing dummy-flange and flange in implementation process; Secondly, the size of the dummy-flange that the tower section due to different size requires is not all consistent, and dummy-flange is cast-in-block part, and this just causes the input cost of dummy-flange higher.
Utility model content
For overcoming the above problems, the purpose of this utility model is to provide a kind of tower section application dummy-flange device, can solve the problem preferably.
The technical scheme that the utility model provides is as follows:
Tower section application dummy-flange device, the dummy-flange comprising roller moulding bed, be located at the flange at tower section two ends, interfixed by bolt with flange, it is characterized in that: described dummy-flange is welded by 6 or 8 sections of fanning strips according to required size, be provided with a through hole in the middle of each fanning strip, and in dummy-flange, the difference of outer radius is greater than 400mm, thickness >=40mm; Described flange is provided with some flange holes corresponding with the through hole on fanning strip, and described bolt sleeve is connected to sleeve pipe and is fixed after being through flange hole and through hole.
Described casing length is less than length and wall thickness that flange hole and through hole be added at more than 2mm, and sleeve pipe tube wall two ends are circular arc.
Dummy-flange external diameter must be greater than tower section two ends flange outer diameter and have more than 100mm spacing between roller on tower section outer surface and roller moulding bed.
From foregoing description, the utility model has the advantage of: first, dummy-flange adopts point 6 or 8 sections of weldings to form, and has saved cost of manufacture, and adapts to the versatility of dummy-flange designing requirement, is applicable to the tower section painting operation of multiple diameter; Secondly, adopt barrel forms to be enclosed within bolt and be through inside flange hole, utilizing sleeve pipe and the direct contact protection flange hole of flange hole, prevent flange hole to be out of shape; Sleeve pipe two arc transition is avoided causing scuffing to flange hole surface in rotation process in addition.Therefore, the utility model has stronger practicality and comparatively cost-saving.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
Detailed description of the invention
The most basic a kind of embodiment of the present utility model, as shown in Figure 1, tower section application dummy-flange device, the dummy-flange 2 comprising roller moulding bed, be located at the flange 1 at tower section two ends, interfixed by bolt 3 with flange 1, described dummy-flange 2 is welded by 6 or 8 sections of fanning strips according to required size, be provided with a through hole 21 in the middle of each fanning strip, and in dummy-flange 2, the difference of outer radius is greater than 400mm, thickness >=40mm; Described flange 1 is provided with some flange holes 11 corresponding with the through hole 21 on fanning strip, described bolt 3 is socketed with sleeve pipe 4 and is fixed after being through flange hole 11 and through hole 21, described sleeve pipe 4 length is less than length and wall thickness that flange hole 11 and through hole 21 be added at more than 2mm, and sleeve pipe 4 tube wall two ends are circular arc 41.
The utility model has the advantage of: first, dummy-flange 1 adopts point 6 or 8 sections of weldings to form, and has saved cost of manufacture, and adapts to the versatility of dummy-flange 1 designing requirement, is applicable to the tower section painting operation of multiple diameter; Secondly, adopt sleeve pipe 4 form to be enclosed within bolt 3 and be through inside flange hole 11, utilizing sleeve pipe 4 and flange hole 11 directly contact protection flange hole 11, prevent flange hole 11 to be out of shape; Sleeve pipe 4 two arc transition is avoided causing scuffing to flange hole 11 surface in rotation process in addition.Therefore, the utility model has stronger practicality and comparatively cost-saving.
Above are only a specific embodiment of the present utility model, but the utility model is not limited thereto, all equalizations done according to the utility model claim change and modify, and all should belong to covering scope of the present utility model.