CN205189411U - Formwork support is striden to building height - Google Patents

Formwork support is striden to building height Download PDF

Info

Publication number
CN205189411U
CN205189411U CN201521041166.4U CN201521041166U CN205189411U CN 205189411 U CN205189411 U CN 205189411U CN 201521041166 U CN201521041166 U CN 201521041166U CN 205189411 U CN205189411 U CN 205189411U
Authority
CN
China
Prior art keywords
support frame
bracing frame
template
limiting plate
engaging lug
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201521041166.4U
Other languages
Chinese (zh)
Inventor
熊家奎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Anjiepeng Technology Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201521041166.4U priority Critical patent/CN205189411U/en
Application granted granted Critical
Publication of CN205189411U publication Critical patent/CN205189411U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model discloses a formwork support is striden to building height. The problem of among the prior art, the template off normal that causes because current construction technology is not enough, the elevation error is too big, and the shaping effect is poor, and the material that brings and manual work etc. Are wasted is solved. The utility model discloses a support frame sets up and is used for carrying out the engaging lug fixed with the support frame in support frame bottom to and set up in support frame top's limiting plate. Use the utility model discloses carry out the height and stride when being under construction, only need place the support frame in low striding to making the limiting plate arrange the construction detail design position in, then passing on the engaging lug is fixed in the low straddle in low the striding with the support frame through iron nail, bolt etc. So as to prevents that support frame positioning influence from placing the template positioning on it, then through having set up the limiting plate can be fine fix the template, further prevented the template positioning, influenced the shaping effect.

Description

Building high-low bay falsework
Technical field
The utility model relates to a kind of building high-low bay Template Location and absolute altitude controls support.
Background technology
Existingly hanging mould construction and be generally divided into that kitchen guarding hangs mould, balcony hangs mould, mould is hung in track, retaining wall hangs mould etc., usually adopting spacer to support bottom for controlling mixed earth absolute altitude; Iron wire is fixed on beam steel or by iron wire drawknot in far-end template, for control plane position in addition again.The shortcoming of this method is, can impact with concrete the mould that hangs caused subside because trample, off normal, be out of shape.Pick cutter repairing afterwards and can bring a large amount of artificial and material unaccounted-for (MUF)s.
Another kind method is: be welded on beam steel by hanging mould spacer bars, realize the control to absolute altitude and plane positioning.But the method needs professional welder to weld, and the labour cost that length consuming time produces is high, and solder technology is uneven, and Forming Quality can not ensure, and also can cause the waste of reinforcing bar.
Also have one directly will hang the colligation of mould iron wire on floor lid muscle or beam steel exactly, very easily cause and hang mould off normal, reinforcement cover does not meet national regulation requirement.
A kind of method is in addition: with Template nail hanging mould surrounding, for elevation control; Socket, for plane positioning by iron wire surrounding; This method can produce very easily off normal, template position equally and the shortcoming such as leak.
Utility model content
The purpose of this utility model there are provided a kind of fast, the building high-low bay falsework of economy, high-quality.Solve the deficiency of existing construction technology, and the template off normal caused, absolute altitude error is excessive, and molding effect is poor, the material brought and the artificial problem waiting waste.
To achieve these goals, the technical solution adopted in the utility model is as follows:
Building high-low bay falsework, comprises bracing frame, is arranged at the engaging lug for being fixed by bracing frame bottom bracing frame, and is arranged at the limiting plate at bracing frame top.
Wherein, bracing frame height is equal with design concrete thickness.
Further, described engaging lug is provided with connecting hole.
Again further, support frame as described above bottom even is distributed with plural engaging lug.
Further, support frame as described above is the prismatoid of hollow structure, cylinder, square body or round platform.
Preferred as one, described engaging lug, limiting plate and bracing frame are structure as a whole.
The utility model compared with prior art, has the following advantages and beneficial effect:
Use this use novel carry out high-low bay construction time, only bracing frame (bracing frame height is equal with concrete thickness) need be positioned over low across interior, and by limiting plate as planar design position, then bracing frame is fixed on low across in interior template by iron nail, bolt etc. through engaging lug, thus can prevents bracing frame off normal from affecting template off normal placed thereon; Then the limiting plate by arranging can be good at template to fix, and prevents template off normal further, thus affects molding effect.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
Wherein, mark corresponding component name in accompanying drawing to be called: 1-bracing frame, 2-engaging lug, 3-limiting plate, 4-connecting hole.
Detailed description of the invention
Below in conjunction with drawings and Examples, the utility model is described in further detail, and embodiment of the present utility model includes but not limited to the following example.
Embodiment
As shown in Figure 1, building high-low bay falsework, comprises bracing frame 1, is arranged at the engaging lug 2 for being fixed by bracing frame bottom bracing frame, and is arranged at the limiting plate 3 at bracing frame top.During use, only bracing frame need be positioned over low trans-regional, be placed in the plan-position of construction drawing design, then by engaging lug, bracing frame is fixed in low trans-regional interior template, then template to be positioned on bracing frame and to be fixed with limiting plate, this makes it possible to completing of quick high-quality and hang mould construction; Because bracing frame is fixed on substrate, so there will not be the situation of positioning when constructing; In addition, because template is fixed on limiting plate, so just make template can not shift phenomenon in work progress, thus ensure that molding effect.And owing to maintaining static simultaneously, so absolute altitude also can not change in construction works.
Conveniently be fixed on by bracing frame on low cross-module plate, described engaging lug is provided with connecting hole 4.By arranging connecting hole, when being fixed, easily iron nail, bolt etc. can being passed connecting hole, then fixing, thus bracing frame is fixed on low cross-module plate, easy to operate, and fixation.
In order to improve the stability of bracing frame further, support frame as described above bottom even is distributed with plural engaging lug.In actual use, an engaging lug can be set respectively in bracing frame both sides, and three, four engaging lugs are set in surrounding, this makes it possible to bracing frame is fixed on firmly on low straddle, thoroughly prevent bracing frame phenomenon such as run-off the straight, positioning in work progress.
Select as one, support frame as described above is the prismatoid of hollow structure, cylinder, square body or round platform.
Preferred as one, described engaging lug, limiting plate and bracing frame are structure as a whole, and can adopt single injection-molded.Intensity of the present utility model can be improved to a certain extent like this.
In order to the concrete compaction of bracing frame inside can be made, support frame as described above is that bar builds anyhow, and each face is Openworks shape, as shown in Figure 1, this makes it possible to allow concrete be wrapped by bracing frame, not only bracing frame outside has concrete to be fixed, and inside also has corresponding concrete to be fixed, thus strengthens the intensity of bracing frame widely.
According to above-described embodiment, just the utility model can be realized well.What deserves to be explained is; under prerequisite based on said structure design; for solving same technical problem; even if some making on the utility model are without substantial change or polishing; the essence of the technical scheme adopted is still the same with the utility model, therefore it also should in protection domain of the present utility model.

Claims (5)

1. build high-low bay falsework, it is characterized in that, comprise bracing frame (1), be arranged at the engaging lug (2) for being fixed by bracing frame bottom bracing frame, and be arranged at the limiting plate (3) at bracing frame top.
2. building high-low bay falsework according to claim 1, is characterized in that, described engaging lug is provided with connecting hole (4).
3. building high-low bay falsework according to claim 1 and 2, it is characterized in that, bottom support frame as described above, surrounding is evenly distributed with plural engaging lug.
4. building high-low bay falsework according to claim 1, is characterized in that, support frame as described above is prismatoid shape, cylindrical shape, square body shape or round table-like.
5. building high-low bay falsework according to claim 1 and 2, it is characterized in that, described engaging lug, limiting plate and bracing frame are structure as a whole.
CN201521041166.4U 2015-12-14 2015-12-14 Formwork support is striden to building height Active CN205189411U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201521041166.4U CN205189411U (en) 2015-12-14 2015-12-14 Formwork support is striden to building height

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201521041166.4U CN205189411U (en) 2015-12-14 2015-12-14 Formwork support is striden to building height

Publications (1)

Publication Number Publication Date
CN205189411U true CN205189411U (en) 2016-04-27

Family

ID=55782412

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201521041166.4U Active CN205189411U (en) 2015-12-14 2015-12-14 Formwork support is striden to building height

Country Status (1)

Country Link
CN (1) CN205189411U (en)

Similar Documents

Publication Publication Date Title
CN106065681B (en) It is a kind of based on BIM technology overall assembled building in superimposed sheet hoard strip construction method
CN106760495B (en) A kind of floor construction method
CN105649213B (en) A kind of construction method of intensive cloth muscle area large-scale steel structure built-in fitting
CN106142338A (en) A kind of prefabricated case beam framework of steel reinforcement loose tool binding construction method
CN107130628A (en) The construction method of embedding anchor bolts flange and embedding anchor bolts
CN205189411U (en) Formwork support is striden to building height
CN208514715U (en) A kind of scalable moulding bed of adhesion type for reinforcing bar binding
CN106638645A (en) Layering prefabricated structure and building method of basement bottom board water collection pit reinforcing mesh
CN207739086U (en) A kind of spliced interim subgrade case for building
CN207583391U (en) One kind two serves as a contrast plug steel end mould
CN206722225U (en) A kind of accurate spacing and strip thickness control device of concreting floor bar skeleton
CN206016235U (en) A kind of concrete slab reinforcing bar is anti-to trample scaffold
CN205969480U (en) Can dismantle reinforcement fetal membrane frame
CN203755682U (en) Secondary pouring form board constructing structure for small opening of concrete structure floor slab
CN108943373A (en) A kind of movable tooling for concrete prefabricated element production
CN107965145A (en) A kind of horizontal convex concrete construction joint hangs mould support device
CN203669189U (en) Novel concrete hollow block
CN207538506U (en) The independent supporting rack of efficient construction of precast floorslab
CN207436515U (en) The hoisting beam of efficient construction of precast floorslab
CN204040485U (en) Bars In Poured Concrete Slab thickness and reinforcement cover control support
CN207673006U (en) A kind of horizontal convex concrete construction joint hangs mould support device
CN205476517U (en) But reuse's floor lid muscle supports split heads
CN208431021U (en) Lateral wall formwork jumbo
CN206418512U (en) Basement bottom board catch pit bar-mat reinforcement is layered precast construction
CN205329686U (en) Modular supplementary formwork grudging post of single pile bored concrete pile circle template

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20200225

Address after: 610213 1st floor, 69 Zhengbei Middle Street, Huayang Street, Tianfu New District, Chengdu City, Sichuan Province

Patentee after: Sichuan anjiepeng Technology Co., Ltd

Address before: Yang Zhen Zigong city 643000 Sichuan Wanshou village seven Group No. 26 County of Fushun Province

Patentee before: Xiong Jiakui

TR01 Transfer of patent right