CN205145443U - Transformer upper portion construction safety belt hanging device - Google Patents
Transformer upper portion construction safety belt hanging device Download PDFInfo
- Publication number
- CN205145443U CN205145443U CN201520984972.9U CN201520984972U CN205145443U CN 205145443 U CN205145443 U CN 205145443U CN 201520984972 U CN201520984972 U CN 201520984972U CN 205145443 U CN205145443 U CN 205145443U
- Authority
- CN
- China
- Prior art keywords
- insertion pipe
- transformer
- column
- construction safety
- suspension arrangement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Emergency Lowering Means (AREA)
Abstract
The utility model provides a transformer upper portion construction safety belt hanging device for the transformer, including grafting device more than two or two, the grafting device includes bottom plate and stand including pipe and the base of fixed connection at the transformer top of pegging graft, base, and stand fixed connection is on the bottom plate, and the quantity of stand is equal with the quantity of the pipe of pegging graft, and bottom plate fixed connection is equipped with polylith gusset, the vertical setting of stand between the periphery of stand and bottom plate on the transformer, upper portion staff's safety belt does not have the problem that loses the protection when department hangs, hangs down string high usefulness and removes work location in the time of can effectively solving transformer installation and maintenance.
Description
Technical field
The utility model relates to substation transformer depressor construction equipment field, especially relates to a kind of suspension arrangement of safety belt.
Background technology
" power construction safety work order " specifies: " all height of fall datum level more than 2 meters, the operation that the height likely fallen carries out is called high-rise working "." high-rise working personnel must use of seat belts, and should use comprehensive anti-impact safety belt.Safety belt must be fastened on firmly component, and must not use by low extension height.In work progress, should check whether safety belt toggles at any time "." high-rise working personnel must not lose protection when transfer tasks position ".Annex upper height distance oil sump, the cobblestone layer plane height such as general substation transformer depressor top and high-power transformer radiator are all more than 2 meters.Transformer depressor top and top work all belong to the work high above the ground that " safety " specifies.The equipment characteristic of transformer depressor and the requirement of installation determine that transformer depressor is installed, maintenance time should not install safety shelter and scaffold carries out security protection.When this just causes transformer installation, maintenance is constructed, worker safety is with the problem hung nowhere or low extension is high, causes larger security threat, buried the potential safety hazard of falling from high altitude accident to transformer top staff.
Utility model content
The purpose of this utility model is to provide a kind of transformer top construction safety band suspension arrangement, effectively eliminates the safety hazards occurring falling from high altitude in staff's work, ensures the personal safety of staff.
The technical solution of the utility model is:
A kind of transformer top construction safety band suspension arrangement, for transformer, comprise two or more plug assembly, plug assembly comprises insertion pipe and is fixedly connected on the base of transformer top, and base comprises base plate and column, and column is fixedly connected on base plate, the quantity of column is equal with the quantity of insertion pipe, base plate is fixedly connected with on the transformer, and between the periphery and base plate of column, be provided with polylith gusset, upright post vertical is to setting; Insertion pipe is tubulose and insertion pipe lower ending opening, the opening shape of insertion pipe lower end and the cross sectional shape of column suitable; The top of insertion pipe and middle part are connected with multiple becket bridle for wire rope handling rope, rope is connected with between the becket bridle of adjacent insertion pipe, described rope is steel wire rope or chain, and insertion pipe lower end is inserted on column, adopts bolt to fix between the bottom of insertion pipe and column.
The top of insertion pipe and the both sides at middle part are respectively connected a pair becket bridle for wire rope handling rope.
Base plate is welded on the top of transformer.
Column cross sectional shape is circular, and the cross sectional shape of corresponding insertion pipe internal cavities is circular.
The opening inside diameter of insertion pipe lower end and the diameter of column suitable.
The top seal of insertion pipe.
For removably connecting between becket bridle and insertion pipe.
Described rope is steel chain.
The Basolateral of insertion pipe is provided with projection, is laterally provided with Inner bolt holes in projection, and bolt inserts Inner bolt holes and is fastened on column.
Advantage of the present utility model:
1. this device is steel pipe manufacturing, and lower pole is solid column, is firmly welded in transformer top when dispatching from the factory.Weld strength is enough large, meets through overtesting the requirement that multiple staff uses simultaneously completely.
2. lightweight, installation, convenient disassembly.The iron chains installed and device top, middle part all establish iron hoop that staff can be made to select hanging position flexibly as required.
3. stream oriented device arranges connection iron chains, and staff can be made when changing operating position, and safety belt hitch point moves with personnel and mobile, does not make to lose protection in work.
4. can increase iron chains length as required, so that extend safety belt flexibly, diverse location during convenient work uses.
The utility model sums up working experience; job requirement when constructing in conjunction with transformer installation and repairing; have developed the safety belt suspension device during construction of a kind of transformer top; when effectively can solve transformer installation and repairing top worker safety be with hang nowhere, low extensions height with and mobile operating position time lose de-protected problem; there is the safety hazards of falling from high altitude in effective elimination staff work, ensure the personal safety of staff.The utility model structure is simple, and low cost of manufacture, replicability is strong.
Accompanying drawing explanation
Fig. 1 is the structural representation of plug assembly of the present utility model;
Fig. 2 is the structural representation of the utility model using state.
Detailed description of the invention
As shown in Figure 1, 2, a kind of transformer top of the present utility model construction safety band suspension arrangement, for transformer 4, especially main transformer.It comprises two (or more) plug assembly, each plug assembly comprises 1 insertion pipe 1 and is fixedly connected on the base 2 at transformer 4 top, base 2 comprises base plate 3 and 1 column 5(the present embodiment vertically arranged adopts steel column), column 5 is fixedly connected on base plate 3, base plate 3 is welded on the top of transformer 4, between the periphery and base plate 3 of column 5, be provided with polylith gusset 6.The quantity one_to_one corresponding of insertion pipe 1 and column 5, can arrange multiple.
The top seal of insertion pipe 1, this is the invasion and attack in order to prevent sleet etc.Insertion pipe 1 is tubulose and insertion pipe 1 lower ending opening, the opening shape of insertion pipe 1 lower end and the cross sectional shape of column 5 suitable; Column 5 cross sectional shape is circular, and the cross sectional shape of corresponding insertion pipe 1 internal cavities is also circular.The opening inside diameter of insertion pipe 1 lower end and the diameter of column 5 suitable, slightly larger so that insert.Be connected with rope 8 between the becket bridle 7 of adjacent insertion pipe 1, rope is steel wire rope or steel chain.
Insertion pipe 1 lower end is inserted on column 5, adopts bolt to fix between the bottom of insertion pipe 1 and column 5.The Basolateral of insertion pipe 1 is provided with a projection 9, and be laterally provided with Inner bolt holes 10 in projection 9, bolt 11 inserts Inner bolt holes 10 and is fastened on column 5.
The top of insertion pipe 1 and middle part are connected with multiple becket bridle 7 for wire rope handling rope, and in the present embodiment, the top of insertion pipe 1 and the both sides at middle part are respectively connected a pair becket bridle 7 for wire rope handling rope.For removably connecting between becket bridle and insertion pipe, such as bolt fastener goes to be fastenedly connected, and the mode of welding also can be adopted to fix.
Manufacturing process:
As shown in Figure 1, the position that transformer top long axis direction is not affecting transformer safety and runs, is installed the permanent column 5 of two high 200mm when transformer manufacturing by manufacturer.The tubulose insertion pipe 1 made inserts on two root posts 5 when working, and locks with hand gear by installation, maintainer.According to construction needs can on two suspension arrangements installation activity iron chains, or with iron chains extend safety belt use length so that work time move and broaden the scope of work.
Using method: when transformer is installed, maintenance is constructed, insertion pipe 1 of the present utility model is plugged on the column 5 at transformer 4 top, locks with manual screw.According to need of work, iron chains is firmly connected on the iron hoop (becket bridle 7) on device top, then needs worker safety with being hanging on the iron hoop of iron chains or device according to operating position, just can start working.
Claims (9)
1. a transformer top construction safety band suspension arrangement, for transformer, it is characterized in that: comprise two or more plug assembly, plug assembly comprises insertion pipe and is fixedly connected on the base of transformer top, and base comprises base plate and column, and column is fixedly connected on base plate, the quantity of column is equal with the quantity of insertion pipe, base plate is fixedly connected with on the transformer, and between the periphery and base plate of column, be provided with polylith gusset, upright post vertical is to setting; Insertion pipe is tubulose and insertion pipe lower ending opening, the opening shape of insertion pipe lower end and the cross sectional shape of column suitable; The top of insertion pipe and middle part are connected with multiple becket bridle for wire rope handling rope, rope is connected with between the becket bridle of adjacent insertion pipe, described rope is steel wire rope or chain, and insertion pipe lower end is inserted on column, adopts bolt to fix between the bottom of insertion pipe and column.
2. transformer top according to claim 1 construction safety band suspension arrangement, is characterized in that: the top of insertion pipe and the both sides at middle part are respectively connected a pair becket bridle for wire rope handling rope.
3. transformer top according to claim 1 and 2 construction safety band suspension arrangement, is characterized in that: base plate is welded on the top of transformer.
4. transformer top according to claim 1 and 2 construction safety band suspension arrangement, is characterized in that: column cross sectional shape is for circular, and the cross sectional shape of corresponding insertion pipe internal cavities is circular.
5. transformer top according to claim 4 construction safety band suspension arrangement, is characterized in that: the opening inside diameter of insertion pipe lower end and the diameter of column suitable.
6. transformer top according to claim 1 and 2 construction safety band suspension arrangement, is characterized in that: the top seal of insertion pipe.
7. transformer top according to claim 1 and 2 construction safety band suspension arrangement, is characterized in that: for removably connecting between becket bridle and insertion pipe.
8. transformer top according to claim 1 and 2 construction safety band suspension arrangement, is characterized in that: described rope is steel chain.
9. transformer top according to claim 1 and 2 construction safety band suspension arrangement, is characterized in that: the Basolateral of insertion pipe is provided with projection, is laterally provided with Inner bolt holes in projection, and bolt inserts Inner bolt holes and is fastened on column.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520984972.9U CN205145443U (en) | 2015-12-02 | 2015-12-02 | Transformer upper portion construction safety belt hanging device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520984972.9U CN205145443U (en) | 2015-12-02 | 2015-12-02 | Transformer upper portion construction safety belt hanging device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205145443U true CN205145443U (en) | 2016-04-13 |
Family
ID=55681187
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520984972.9U Active CN205145443U (en) | 2015-12-02 | 2015-12-02 | Transformer upper portion construction safety belt hanging device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205145443U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105311771A (en) * | 2015-12-02 | 2016-02-10 | 三门峡电力设计有限责任公司 | Safety belt suspending device for upper construction of transformer |
CN106943689A (en) * | 2017-03-29 | 2017-07-14 | 国家电网公司 | A kind of transformer Special falling suspension arrangement |
TWI677361B (en) * | 2019-04-19 | 2019-11-21 | 中龍鋼鐵股份有限公司 | Fall Protection Bar |
-
2015
- 2015-12-02 CN CN201520984972.9U patent/CN205145443U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105311771A (en) * | 2015-12-02 | 2016-02-10 | 三门峡电力设计有限责任公司 | Safety belt suspending device for upper construction of transformer |
CN106943689A (en) * | 2017-03-29 | 2017-07-14 | 国家电网公司 | A kind of transformer Special falling suspension arrangement |
TWI677361B (en) * | 2019-04-19 | 2019-11-21 | 中龍鋼鐵股份有限公司 | Fall Protection Bar |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106348188B (en) | The manufacture method of planer-type building-construction lifting device | |
CN202080812U (en) | Dedicated sling system for large-scaled reinforcing cage | |
CN206580442U (en) | A kind of hanging apparatus suitable for Assembled Building gangboard prefabricated components | |
CN103470093B (en) | Concrete chimney dismantling method | |
CN205145443U (en) | Transformer upper portion construction safety belt hanging device | |
CN202643193U (en) | Movable hydraulic crane tripod | |
CN105311771A (en) | Safety belt suspending device for upper construction of transformer | |
CN205429566U (en) | Crossing structure | |
CN105464456A (en) | Method and lifting sling for assembling extra-high voltage transmission iron tower through helicopter | |
CN205114843U (en) | Prefabricated post hoist device with unhook function | |
CN106245986A (en) | The method for assembling of power network line steel tower and device | |
CN102182181B (en) | Device for lowering anchor cable | |
CN206971689U (en) | Support operating platform that is detachable and recycling | |
CN207829430U (en) | A kind of lifting type operating platform for hanging operation | |
CN108118885B (en) | vertical moving type protection platform and application thereof in steel structure column butt joint construction | |
CN103332624B (en) | A kind of pulley for high-altitude circuit or caliber and installation method thereof | |
CN204212065U (en) | Bridge crossing anticollision barrier punching block erection equipment | |
CN203112379U (en) | Quick-mounting tower cap climbing ladder of tower crane | |
CN105366559A (en) | Small hoisting machine fixed on channel steel framework | |
CN107217912B (en) | A kind of superelevation physical isolation construction method for neighbouring high-speed rail Business Line construction | |
CN105952369B (en) | A kind of maintenance ladder docked with transmission of electricity tower bar fixed ladder | |
CN203159027U (en) | A prefabricated iron tower foundation spreader | |
CN202785255U (en) | Turnover hoisting tool for reinforced concrete pipe joint | |
CN205132926U (en) | Special well word hoist of hydroelectric set tail water ell | |
CN211422500U (en) | A ladder that continues for steel pipe pole is climbed |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |