CN205088638U - Arch dam table hole gate pier girder - Google Patents
Arch dam table hole gate pier girder Download PDFInfo
- Publication number
- CN205088638U CN205088638U CN201520900704.4U CN201520900704U CN205088638U CN 205088638 U CN205088638 U CN 205088638U CN 201520900704 U CN201520900704 U CN 201520900704U CN 205088638 U CN205088638 U CN 205088638U
- Authority
- CN
- China
- Prior art keywords
- gate pier
- crossbeam
- wide
- table hole
- arch dam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The utility model relates to an arch dam technical field especially relates to an arch dam table hole gate pier girder. The utility model discloses an arch dam table hole gate pier girder, including table hole, gate pier and girder, the girder set up in on the gate pier, the girder includes a plurality of girder sections, still includes wide -slot structure and the backfill grouting body, the wide -slot structure set up in on the gate pier, the pouring of the backfill grouting body is in in the wide -slot structure. The girder of this kind of structure has reduced the requirement to concrete placement ability, control by temperature change ability, has practiced thrift manpower and materials, has also reduced concrete cracking's possibility, has solved the bulky concrete of arch dam table hole girder and can not lead to the problem of pouring in succession in the storehouse.
Description
Technical field
The utility model relates to arch dam technical field, particularly relates to a kind of arch dam table hole gate pier crossbeam.
Background technology
Arch dam table hole is generally arranged in crown position, because table hole destroys the integrality of crown, is generally all provided with table hole crossbeam to ensure the rigidity that crown is enough, and transmits load to two sides arch abutment.The engineerings such as general gate dam, gravity dam are also provided with table hole, be different from the feature of the arch abutment power transmission of arch dam, gate dam, gravity dam are stressed alone by respective monolith, as long as its table hole crossbeam meets the operation of arc door, traffic requirement etc., crossbeam section is often relatively little, cast in situs ability, temperature control capacity can meet, and the cast in situs of table hole crossbeam does not have difficulties, or prefabricated rear in-site installation also can be adopted to be solved.
And large girder span table hole, arch dam table hole gate pier is arranged continuously, and section is large, engineering quantity is greatly to bear and to transmit load to arch abutment, if arch dam table hole crossbeam adopts cast-in-place, then require to carry out continuously during crossbeam concreting, to avoid occurring between New-old concrete that the length of time, gap was larger, to concrete-agitating, transport, put in storage, close a position and vibrate, temperature controls etc. require higher, equipment and the manpower of input are many, and in crossbeam structure length and width size, gap is excessive etc., and factor may cause concrete cracking, therefore, by the existing ability of building, temperature control capacity limit, be difficult to the disposable concreting without longitudinal joint of arch dam crossbeam, according to prefabricated rear in-site installation, because arch dam table hole crossbeam is often highly higher, reach several meters of even tens of rice, carry out scene lifting be often difficult to reach or cost higher.
Utility model content
Technical problem to be solved in the utility model is: provide a kind of easy moulding by casting and the arch dam table hole gate pier crossbeam of maintenance crossbeam integrality.
The utility model solves the arch dam table hole gate pier crossbeam that its technical problem adopts, comprise table hole, gate pier and crossbeam, described crossbeam is arranged on described gate pier, described crossbeam comprises multiple crossbeam section, also comprise wide crack structure and backfill grouting body, described wide crack structure is arranged on described gate pier, and described backfill grouting body is cast in described wide crack structure.
Be further, described wide crack structure comprises and flows to wide seam and horizontal wide seam, described upstream face and the downstream face flowing to wide seam and run through described crossbeam, the wide seam of described transverse direction is from the upstream face of described crossbeam along described gate pier Yokogawa to layout, and described crossbeam section is arranged between adjacent described wide crack structure.
Further, describedly flow to wide seam and flow to layout downstream along the gate pier center line of described gate pier.
Further, the wide crack structure of both sides, described table hole is arranged symmetrically with along table centerline hole in the horizontal plane.
Further, the wide seam of described transverse direction be positioned on middle described gate pier runs through described gate pier, is positioned at the wide seam of described transverse direction on the described gate pier at two ends and extends from the upstream face of described crossbeam and describedly flow to wide seam along connecing.
Further, the described seam flowing to wide seam and horizontal wide seam is wide is not less than 1 meter.
The beneficial effects of the utility model are: flow to wide seam and horizontal wide seam owing to being provided with on the gate pier of arch dam table hole, by table hole crossbeam along arch ring with the wide seam of gate pier for boundary is divided into some sections, can build each crossbeam section respectively, the later stage wide seam intersegmental to crossbeam backfills, ensure that each crossbeam section connects into entirety, meet its power transmission requirement, reduce concreting ability, the requirement of temperature control capacity, manpower and materials are saved, decrease the possibility of concrete cracking, solve the problem that arch dam table hole crossbeam concrete in mass can not lead to storehouse continuous placing.
Accompanying drawing explanation
Fig. 1 is the layout plan of the embodiment that the utility model relates to;
Fig. 2 is the close-up schematic view of Fig. 1;
Fig. 3 is that the B-B of Fig. 2 is to sectional view;
Component, position and numbering in figure: show hole 1, table centerline hole 11, gate pier 2, gate pier center line 21, crossbeam 3, crossbeam section 31, wide crack structure 4, flow to wide seam 41, laterally wide seam 42, upstream face 5, downstream face 6.
Detailed description of the invention
Below in conjunction with accompanying drawing, the utility model is described in further detail.It should be noted that at this, the explanation for these embodiments understands the utility model for helping, but does not form restriction of the present utility model.
As shown in Figure 1 to Figure 3, the utility model comprises table hole 1, gate pier 2 and crossbeam 3, and described crossbeam 3 is arranged on described gate pier 2, and described crossbeam 3 comprises multiple crossbeam section 31, also comprises wide crack structure 4 and backfill grouting body; Described wide crack structure 4 is arranged on described gate pier 2, preferably, described wide crack structure 4 comprise flow to downstream arrange flow to wide seam 41 and from the upstream face 5 of described crossbeam 3 along described gate pier 2 Yokogawa to the wide seam 42 of transverse direction arranged, described upstream face 5 and the downstream face 6 flowing to wide seam 41 and run through described crossbeam 3, described crossbeam section 31 is arranged between adjacent described wide crack structure 4; Described backfill grouting body is cast in described wide crack structure 4.The gate pier 2 of arch dam is higher than the part of close downstream face in the part near upstream face, forms hierarchic structure.Therefore, arrange above gate pier 2 flow to wide seam 41 and laterally wide seam 42 crossbeam section 31 and gate pier 2 can be departed from completely, each crossbeam section 31 of convenient cast.During enforcement, by crossbeam 3 along arch ring with the wide crack structure 4 above gate pier 2 for boundary is divided into some sections, first build each crossbeam section 31 respectively, the later stage backfills with backfill grouting body the wide crack structure 4 between crossbeam section 31, ensures that each crossbeam section 31 connects into entirety.After wide crack structure 4 is established for crossbeam 3, reduce the requirement to concreting ability, temperature control capacity, saved manpower and materials, decrease the possibility of concrete cracking.
Specifically, the stability of structure during in order to ensure to pour into a mould crossbeam section 31, describedly flows to wide seam 41 and flows to layout downstream along the gate pier center line 21 of described gate pier 2; The wide crack structure 4 of both sides, described table hole 1 is arranged symmetrically with along table centerline hole 11 in the horizontal plane.Wide seam 41 will be flowed to arrange along gate pier center line 21, can to make on every gate pier 2 suffered to come from the uniform distribution of adjacent two crossbeam section 31 gravitational loads, simultaneously, wide crack structure 4 is arranged symmetrically with along table centerline hole 11 in the horizontal plane, the two ends of each crossbeam section 31 can be made to lay respectively on adjacent two gate piers 2, the gravity of a crossbeam section 31 is distributed to adjacent two gate piers 2, make the load of bearing of each gate pier 2 reduce and be evenly distributed.
Specifically, in order to make crossbeam section 31 and gate pier 2 to be separated during cast crossbeam section 31, facilitate and follow-up backfill grouting is carried out to wide crack structure 4, the wide seam of described transverse direction 42 be positioned on middle described gate pier 2 runs through described gate pier 2, is positioned at the wide seam of described transverse direction 42 on the described gate pier 2 at two ends and extends from the upstream face 5 of described crossbeam 3 and describedly flow to wide seam 41 along connecing.
Specifically, conveniently carry out backfill grouting process to wide crack structure 4, the described seam flowing to wide seam 41 and horizontal wide seam 42 is wide is not less than 1 meter, with meet the later stage wide crack structure 4 is built time necessity operating space needs.To be done to each crossbeam section 31 build and bottom arch ring joint grouting after, carry out backfill and the grouting of wide crack structure 4, ensure crossbeam 3 connect into entirety.
Claims (6)
1. arch dam table hole gate pier crossbeam, comprise table hole (1), gate pier (2) and crossbeam (3), described crossbeam (3) is arranged on described gate pier (2), it is characterized in that:
Described crossbeam (3) comprises multiple crossbeam section (31), also comprises wide crack structure (4) and backfill grouting body,
Described wide crack structure (4) is arranged on described gate pier (2), and described backfill grouting body is cast in described wide crack structure (4).
2. arch dam table hole according to claim 1 gate pier crossbeam, it is characterized in that: described wide crack structure (4) comprises and flows to wide seam (41) and horizontal wide seam (42), described upstream face (5) and the downstream face (6) flowing to wide seam (41) and run through described crossbeam (3), the upstream face (5) of the wide seam of described transverse direction (42) from described crossbeam (3) is along described gate pier (2) Yokogawa to layout, and described crossbeam section (31) is arranged between adjacent described wide crack structure (4).
3. arch dam table hole according to claim 2 gate pier crossbeam, is characterized in that: the described wide seam (41) that flows to flows to layout downstream along the gate pier center line (21) of described gate pier (2).
4. arch dam table hole according to claim 3 gate pier crossbeam, is characterized in that: the wide crack structure (4) of described table hole (1) both sides is arranged symmetrically with along table centerline hole (11) in the horizontal plane.
5. arch dam table hole according to claim 4 gate pier crossbeam, it is characterized in that: the wide seam of described transverse direction (42) be positioned on middle described gate pier (2) runs through described gate pier (2), be positioned at the upstream face (5) of the wide seam of described transverse direction (42) on the described gate pier (2) at two ends from described crossbeam (3) and extend and describedly flow to wide seam (41) along connecing.
6. the arch dam table hole gate pier crossbeam according to claim arbitrary in claim 2 to 5, is characterized in that: the described seam flowing to wide seam (41) and horizontal wide seam (42) is wide is not less than 1 meter.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520900704.4U CN205088638U (en) | 2015-11-12 | 2015-11-12 | Arch dam table hole gate pier girder |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520900704.4U CN205088638U (en) | 2015-11-12 | 2015-11-12 | Arch dam table hole gate pier girder |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205088638U true CN205088638U (en) | 2016-03-16 |
Family
ID=55479340
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520900704.4U Active CN205088638U (en) | 2015-11-12 | 2015-11-12 | Arch dam table hole gate pier girder |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205088638U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113481944A (en) * | 2021-07-26 | 2021-10-08 | 中国三峡建工(集团)有限公司 | Dam surface hole connection girder supporting structure and construction method |
-
2015
- 2015-11-12 CN CN201520900704.4U patent/CN205088638U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113481944A (en) * | 2021-07-26 | 2021-10-08 | 中国三峡建工(集团)有限公司 | Dam surface hole connection girder supporting structure and construction method |
CN113481944B (en) * | 2021-07-26 | 2022-07-15 | 中国三峡建工(集团)有限公司 | Construction method of dam surface hole connection girder supporting structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106835998B (en) | Technique is pushed up on being filled under a kind of CFST Arch Bridge pipe inner concrete | |
CN205088638U (en) | Arch dam table hole gate pier girder | |
CN104328717A (en) | CRTS III type slab ballastless track self-compacting concrete casting tooling and method | |
CN106759478B (en) | A kind of prefabricated piping lane construction method | |
CN202291267U (en) | Strip-shaped product die casting mould pouring system | |
CN101966559B (en) | Bottom casting system of ingate of circular cross section | |
CN106087881A (en) | A kind of precast concrete box-structure and cast-in-place concrete convolution Sluice Pier structure and construction technology thereof | |
CN202989781U (en) | Width widened cast-in-place box beam moving support | |
CN116927818A (en) | Tunnel construction method with longitudinal slope and bracket | |
CN207846241U (en) | Whole assembly overlapping box culvert | |
CN205735443U (en) | A kind of template containing joint production for precast assembly | |
CN205529916U (en) | Inner formword with adjustable be used for construction of hollow mound of bridge variable cross section | |
CN105648991B (en) | The construction method of power station bulb-type tubular hydro set flow passage gradual change section | |
CN109162293A (en) | A kind of drainage pipeline foundation working process | |
CN109356126A (en) | Double of Precast Gallery structure and gallery construction method | |
CN102296969B (en) | Tunnel compartment wall lining construction method | |
CN104821534A (en) | Side channel cable trough combined body, preparation method and side channel cable trough combined structure | |
CN210129724U (en) | Steel reinforcement framework of prefabricated apron and prefabricated apron of cable pit corner | |
CN210459301U (en) | Positioning pouring device for steel shell concrete | |
CN111119945B (en) | Tunnel secondary lining concrete pumping extrusion type pouring construction method | |
CN105648911B (en) | Bridge construction Cast-in-situ Beam, bent cap, binder concrete adhesion type prestressed girder support | |
CN208235529U (en) | A kind of large hydropower station mass concrete quick conveyance system | |
CN113089498A (en) | Concrete ring-dividing and sectional cast-in-place method for main arch ring of large-span arch bridge | |
CN207314166U (en) | A kind of across electric railway Business Line swivel flute profile continuous beam mid-span closing device | |
CN215718811U (en) | Tunnel trolley material distribution system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |