CN205035779U - Construction branch tunnel suitable for pressure regulating of water delivery tunnel and maintenance traffic - Google Patents

Construction branch tunnel suitable for pressure regulating of water delivery tunnel and maintenance traffic Download PDF

Info

Publication number
CN205035779U
CN205035779U CN201520763827.8U CN201520763827U CN205035779U CN 205035779 U CN205035779 U CN 205035779U CN 201520763827 U CN201520763827 U CN 201520763827U CN 205035779 U CN205035779 U CN 205035779U
Authority
CN
China
Prior art keywords
tunnel
water
conveyance
working
inducer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520763827.8U
Other languages
Chinese (zh)
Inventor
张永进
赖勇
陈知渊
叶洁慧
虞鸿
王鑫
谢宇琦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Design Institute of Water Conservancy and Hydroelectric Power
Original Assignee
Zhejiang Design Institute of Water Conservancy and Hydroelectric Power
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Design Institute of Water Conservancy and Hydroelectric Power filed Critical Zhejiang Design Institute of Water Conservancy and Hydroelectric Power
Priority to CN201520763827.8U priority Critical patent/CN205035779U/en
Application granted granted Critical
Publication of CN205035779U publication Critical patent/CN205035779U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model provides a construction branch tunnel suitable for pressure regulating of water delivery tunnel and maintenance traffic, construction branch tunnel divide into inducer, barrel section and flat section down, the adverse slope structure high for the import, that hang down inside in proper order from ground to the water delivery tunnel. The elevation is higher than construction the highest free water level in the branch tunnel at the bottom of the inducer to guarantee that the water can not spill over when the simple formula pressure regulating well function of construction branch tunnel performance, the manger plate floodgate also can be established in the inducer entrance to a cave, with construction branch tunnel combination formation confined interval, and the function of construction branch tunnel performance air -cushion type surge -chamber. The barrel section is the hole section that the branch tunnel longitudinal gradient changes of being under construction, plays the transition effect to the inducer and the discrepancy in elevation of flat section down, the elevation flushes at the bottom of flat section end elevation and the water delivery tunnel down, plays the cushioning effect to advancing hole maintenance vehicle. Construction branch tunnel both can be used as the pressure regulating well of operation period, can be used as the traffic passageway of the big -and -middle -sized maintenance vehicle business turn over when examining and repairing of turning on the water again, both expanded construction branch tunnel the function, saved the construction investment, improved the degree of safety and the maintenance efficiency of the operation of water delivery tunnel again.

Description

A kind of working tunnel being applicable to water-conveyance tunnel pressure regulation and maintenance traffic
Technical field
The utility model relates to the working tunnel in a kind of water delivery engineering, is specifically related to a kind of working tunnel doubling as long distance water transfer tunnel surge shaft and maintenance access tunnel.
Background technology
In the hydraulic tunnel engineering adopting drill bursting construction, consider to slag tap, ventilate conveniently, reduction of erection time and investment, often arrange working tunnel in proper site, to play the effect of " hand-to-hand fight in tights of long hole ", connection earth's surface, working tunnel one end, one end connects water-conveyance tunnel, is the passage of Construction and Maintenance vehicle, equipment and constructor's turnover in the construction period, be also slag tap, ventilate, the passage of draining, after tunnel completion, often carrying out shutoff process with water-conveyance tunnel intersection.
Long distance pressure water conveyer tunnel problem of water hammer is the unfavorable factor affecting tunnel lining structural safety, for reducing water hammer to the destruction of lining cutting, general employing Structure of Surge Tank regulates hydraulic pressure, surge shaft is the passage of water hammer release, basic pattern is above tunnel, excavate formation in massif well formula or cavern's structure, the larger voltage regulation result of section is better, but corresponding engineering quantity and investment also larger.The vertical shaft type structure that existing long distance water transfer tunnel surge shaft is generally adjustment water hammer and designs, construction is complicated, and comprehensive utilization degree is lower.
The maintenance mode that water-conveyance tunnel is commonly used at present is the mode into people's maintenance, generally in working tunnel block section, bury steel pipe underground doubles as enter hole, steel pipe block section peripheral hardware silently, after tunnel emptying, open silently, personnel enter water-conveyance tunnel maintenance by pre-buried steel pipe, and maintenance vehicle and big-and-middle-sized equipment cannot enter water-conveyance tunnel by enter hole, and maintenance transportation work condition is poor.
Chinese patent CN201762695U discloses and is a kind ofly applicable to the structure that big-and-middle-sized plant equipment enters long tunnel for overhaul, diversion tunnel air vent is expanded and arranges that formation one size meets the service shaft well of big-and-middle-sized repair apparatus turnover, at the top surrounding concreting framed bent of vertical shaft, and on framed bent, cover prefabricated bridge to be opened/closed, this shaft structure has the function of ventilation, pressure regulation and maintenance traffic simultaneously, construction period also can be used as the passage of slagging tap, but the turnover of shaft structure maintenance vehicle arrangement needs special opening and closing device, and transportation condition is still poor.
Generally, existing Long tunnels is low to working tunnel producing level, has only played the traffic aisle function of construction period, and small part establishes steel bifurcated when completing shutoff, and the runtime is used as enter hole, and the traffic maintenance function played is limited.
Utility model content
The purpose of this utility model is to overcome the deficiencies in the prior art, a kind of working tunnel being applicable to water-conveyance tunnel pressure regulation and maintenance traffic is provided, by rationally arranging working tunnel structure, on the one hand, working tunnel can be used as the surge shaft of runtime, on the other hand, and the traffic aisle of big-and-middle-sized maintenance vehicle or equipment turnover when can be used as overhauling, both expand the function of working tunnel, saved construction investment, turn improve degree of safety and the overhaul efficiency of water-conveyance tunnel operation.
The technical scheme that the utility model adopts is: a kind of working tunnel being applicable to water-conveyance tunnel pressure regulation and maintenance traffic, working tunnel is divided into inducer, barrel section and lower flat section successively from ground to water-conveyance tunnel, the connection ground, top of inducer, the tail end of flat section is communicated with water-conveyance tunnel down, working tunnel entirety is the adverse slope structure that import is high, inside is low, mainly slag tap according to construction in footpath, hole and lining device size is determined, considers that maintenance vehicles while passing is convenient, adopts city-gate section.At the bottom of inducer, elevation is higher than table the highest in working tunnel, to ensure that water body can not overflow when working tunnel plays simple-type surge shaft function; Inducer landform is lower, when elevation at the bottom of inducer is lower than table the highest in working tunnel, also can establish retaining box at hole, by closing retaining box, retaining box and working tunnel are combined to form closed interval, and working tunnel also can play the function of air cushion type pressure balance chamber.When water-conveyance tunnel emptying backstop sluice is opened, working tunnel is as the access path of maintenance vehicle.Barrel section is the hole section of working tunnel change of longitudinal grade, the discrepancy in elevation of working tunnel inducer and lower flat section is played a transition role, because the discrepancy in elevation of working tunnel inducer and lower flat section is usually larger, engineering quantity is saved for reducing working tunnel length, abrupt slope should be adopted, but be considered as builder's road need meet local longitudinal gradient be not more than 9%, average gradient is not more than the requirement of 7.5%, therefore generally adopts the gradient of 5% ~ 9%; At the bottom of flat section, elevation flushes with elevation at the bottom of water-conveyance tunnel down, mainly plays cushioning effect to entering hole maintenance vehicle, is conducive to the speed of a motor vehicle being reduced before maintenance vehicle enters water-conveyance tunnel turning after barrel section descending.
Frame type management house can be established in inducer hole, carries out closed management to working tunnel, and meets working tunnel ventilation requirement, and when retaining box is established at hole, retaining box can be combined in frame type management house and arrange.
When barrel segment length is larger, suitably opens up in flat slope barrel section and dig, lay-by is set, optimize transportation condition.
Flat section can arrange plane turning down, and working tunnel and water-conveyance tunnel are with intersect with large-angle, favourable to river conjunction structural safety.
Working tunnel 1 can arrange two or more on water-conveyance tunnel 2 simultaneously, plays the effect of pressure regulation gang of wells.
The beneficial effects of the utility model are:
1) working tunnel horizontal section is large, and voltage regulation result is good.Working tunnel is ramp structure, average gradient with 9% calculates, table or pressure-bearing water surface area can reach more than 10 times of same open test pit footpath shaft area, working tunnel average gradient is more slow, table or pressure-bearing water surface area are larger with the ratio with open test pit footpath shaft area, and adjustment water hammer effect is better.
2) multistage that needs that working tunnel can be constructed in conjunction with segmentation is simultaneously arranged, and the effect of pressure regulation gang of wells is played in segmentation pressure regulation.Water-conveyance tunnel considers " hand-to-hand fight in tights of long hole ", often arranges more working tunnel, selects the working tunnel retaining proper site as surge shaft, can playing the effect of segmentation pressure regulation, can protect tunnel better than arranging single surge shaft to water-conveyance tunnel.
3) runtime maintenance is very convenient.Because working tunnel inherently passes in and out the passage of water-conveyance tunnel, maintenance vehicle directly can sail into when discharging water maintenance, and relative vertical shaft opens and closes and vertically passes in and out mode, both safe and reliable, energy-conservation again, improves runtime overhaul efficiency.
Accompanying drawing explanation
Fig. 1 is the utility model embodiment one plan view
Fig. 2 is the utility model embodiment one running status A-A sectional view
Fig. 3 is the utility model embodiment one inspecting state A-A sectional view
Fig. 4 is the utility model embodiment two plan view
Fig. 5 is the utility model embodiment two running status B-B sectional view
Fig. 6 is the utility model embodiment two inspecting state B-B sectional view
In figure: 1-working tunnel; 2-water-conveyance tunnel; 3-ground; 4-table; 5-overhauls vehicle; The 6-pressure-bearing water surface; 7-air cushion district; 8-water body; 11-inducer; 12-barrel section; Flat section under 13-; 14-frame type management house; 15-retaining box; 12a-slope barrel section; 12b-flat slope barrel section.
Detailed description of the invention
Below in conjunction with drawings and Examples, the utility model is described in further detail.
Embodiment one:
As shown in FIG. 1 to 3, a kind of working tunnel being applicable to water-conveyance tunnel pressure regulation and maintenance traffic of the utility model, working tunnel 1 is divided into inducer 11, barrel section 12 and lower flat section 13 successively from ground 3 to water-conveyance tunnel 2, the connection ground, top 3 of inducer 11, the tail end of flat section 13 is communicated with water-conveyance tunnel 2 down, and working tunnel 1 entirety is the adverse slope structure that import is high, inside is low.Inducer 11 end elevation is higher than table 4 the highest in working tunnel 1, and during to ensure that working tunnel 1 plays simple-type surge shaft function, water body 8 can not overflow.Barrel section 12 is hole sections of working tunnel 1 change of longitudinal grade, plays a transition role, generally adopt the gradient of 5% ~ 9% to the inducer 11 of working tunnel 1 with the discrepancy in elevation of lower flat section 13.Flat section 13 end elevation flushes with water-conveyance tunnel 2 end elevation down, mainly to entering hole maintenance vehicle 5 cushioning effects, being conducive to maintenance vehicle 5 and entering before water-conveyance tunnel 2 is turned after barrel section 12 descending and the speed of a motor vehicle reduced.
Working tunnel 1 can arrange two or more on water-conveyance tunnel 2 simultaneously, plays the effect of pressure regulation gang of wells.
Frame type management house 14 is established at inducer 11 hole, carries out closed management, and meet working tunnel ventilation requirement to working tunnel 1.
When barrel section 12 length is larger, flat slope barrel section 12b is suitably opened up to dig and puts lay-by, optimize transportation condition.
Barrel section 12 can overall be made up of slope barrel section 12a, also in the middle part of the barrel section 12a of slope, can arrange the flat slope barrel section 12b of multistage, in order to traffic safety in interval.
Flat section 13 arranges plane turning down, and working tunnel 1 and water-conveyance tunnel 2 are with intersect with large-angle, favourable to river conjunction structural safety.
Embodiment two:
As shown in Fig. 3 ~ Fig. 6, a kind of working tunnel being applicable to water-conveyance tunnel pressure regulation and maintenance traffic of the utility model, working tunnel 1 is divided into inducer 11, barrel section 12 and lower flat section 13 successively from ground 3 to water-conveyance tunnel 2, the connection ground, top 3 of inducer 11, the tail end of flat section 13 is communicated with water-conveyance tunnel 2 down, and working tunnel 1 entirety is the adverse slope structure that import is high, inside is low.Frame type management house 14 and retaining box 15 are established in inducer 11 hole, and retaining box 15 lock under the runtime cuts out, and in working tunnel 1, water body 8 forms the pressure-bearing water surface 6, and the pressure-bearing water surface 6 top is closed air cushion district 7.Barrel section 12 is hole sections of working tunnel 1 change of longitudinal grade, plays a transition role, generally adopt the gradient of 5% ~ 9% to the inducer 11 of working tunnel 1 with the discrepancy in elevation of lower flat section 13.Flat section 13 end elevation flushes with water-conveyance tunnel 2 end elevation down, mainly to entering hole maintenance vehicle 5 cushioning effects, being conducive to maintenance vehicle 5 and entering before water-conveyance tunnel 2 is turned after barrel section 12 descending and the speed of a motor vehicle reduced.
Working tunnel 1 can arrange two or more on water-conveyance tunnel 2 simultaneously, plays the effect of pressure regulation gang of wells.
Frame type management house 14 is established at inducer 11 hole, carries out closed management to working tunnel 1, and retaining box 15 combines and is arranged in frame type management house 14.
When retaining box 15 is closed, the pressure-bearing water surface 6 fluctuates, and working tunnel 1 plays air cushion type pressure balance chamber function; When water-conveyance tunnel 2 emptying backstop sluice 15 is opened, working tunnel 1 is as the access path of maintenance vehicle 5.
When barrel section 12 length is larger, flat slope barrel section 12b is suitably opened up to dig and puts lay-by, optimize transportation condition.
Barrel section 12 can overall be made up of slope barrel section 12a, also in the middle part of the barrel section 12a of slope, can arrange the flat slope barrel section 12b of multistage, in order to traffic safety in interval.
Flat section 13 arranges plane turning down, and working tunnel 1 and water-conveyance tunnel 2 are with intersect with large-angle, favourable to river conjunction structural safety.
The pressure regulation gang of wells be made up of plural working tunnel 1, both can all be made up of the working tunnel 1 in embodiment one or embodiment two, also can comprise the working tunnel 1 in embodiment one and embodiment two simultaneously.

Claims (7)

1. be applicable to a working tunnel for water-conveyance tunnel pressure regulation and maintenance traffic, it is characterized in that: described working tunnel is divided into inducer, barrel section and lower flat section successively from ground to water-conveyance tunnel; The connection ground, top of described inducer, the tail end of described lower flat section is communicated with water-conveyance tunnel; Described working tunnel entirety is the adverse slope structure that import is high, inside is low, adopts city-gate section; The end elevation of described lower flat section flushes with elevation at the bottom of water-conveyance tunnel.
2. the working tunnel being applicable to water-conveyance tunnel pressure regulation and maintenance traffic according to claim 1, is characterized in that: when the end elevation of described inducer is lower than table the highest in working tunnel, arranges retaining box at inlet segment hole; When retaining box is closed, working tunnel is as air cushion type pressure balance chamber; When water-conveyance tunnel emptying backstop sluice is opened, working tunnel is as the access path of maintenance vehicle.
3. the working tunnel being applicable to water-conveyance tunnel pressure regulation and maintenance traffic according to claim 1, it is characterized in that: described barrel section average gradient is not more than 7.5%, slope barrel section longitudinal gradient is not more than 9%.
4. the working tunnel being applicable to water-conveyance tunnel pressure regulation and maintenance traffic according to claim 1, is characterized in that: when described barrel segment length is larger, suitably opens up and dig, arrange lay-by in flat slope barrel section.
5. the working tunnel being applicable to water-conveyance tunnel pressure regulation and maintenance traffic according to claim 1, is characterized in that: described inducer hole is provided with frame type management house.
6. the working tunnel being applicable to water-conveyance tunnel pressure regulation and maintenance traffic according to claim 1, is characterized in that: described lower flat section arranges plane turning, and working tunnel and water-conveyance tunnel are with intersect with large-angle.
7. the working tunnel being applicable to water-conveyance tunnel pressure regulation and maintenance traffic according to any one of claim 1 to 6, is characterized in that: described working tunnel arranges two or more on water-conveyance tunnel simultaneously, forms pressure regulation gang of wells.
CN201520763827.8U 2015-09-29 2015-09-29 Construction branch tunnel suitable for pressure regulating of water delivery tunnel and maintenance traffic Active CN205035779U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520763827.8U CN205035779U (en) 2015-09-29 2015-09-29 Construction branch tunnel suitable for pressure regulating of water delivery tunnel and maintenance traffic

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520763827.8U CN205035779U (en) 2015-09-29 2015-09-29 Construction branch tunnel suitable for pressure regulating of water delivery tunnel and maintenance traffic

Publications (1)

Publication Number Publication Date
CN205035779U true CN205035779U (en) 2016-02-17

Family

ID=55294691

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520763827.8U Active CN205035779U (en) 2015-09-29 2015-09-29 Construction branch tunnel suitable for pressure regulating of water delivery tunnel and maintenance traffic

Country Status (1)

Country Link
CN (1) CN205035779U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106284240A (en) * 2016-08-29 2017-01-04 中国电建集团西北勘测设计研究院有限公司 A kind of power station is in construction time downstream interim water-supply structure and method
CN108644051A (en) * 2018-05-20 2018-10-12 张平 A kind of artesian water power generator
CN108798967A (en) * 2018-05-20 2018-11-13 张平 A kind of artesian water electricity-generating method
CN108951552A (en) * 2018-07-25 2018-12-07 中国电建集团北京勘测设计研究院有限公司 A kind of non-pressure tunnel access path with blow vent
CN110685256A (en) * 2019-10-29 2020-01-14 黄河勘测规划设计研究院有限公司 Structure using hydropower station pressure pipeline construction branch tunnel as maintenance channel and construction method

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106284240A (en) * 2016-08-29 2017-01-04 中国电建集团西北勘测设计研究院有限公司 A kind of power station is in construction time downstream interim water-supply structure and method
CN108644051A (en) * 2018-05-20 2018-10-12 张平 A kind of artesian water power generator
CN108798967A (en) * 2018-05-20 2018-11-13 张平 A kind of artesian water electricity-generating method
CN108951552A (en) * 2018-07-25 2018-12-07 中国电建集团北京勘测设计研究院有限公司 A kind of non-pressure tunnel access path with blow vent
CN108951552B (en) * 2018-07-25 2023-10-20 中国电建集团北京勘测设计研究院有限公司 Pressureless tunnel overhauling channel with air vents
CN110685256A (en) * 2019-10-29 2020-01-14 黄河勘测规划设计研究院有限公司 Structure using hydropower station pressure pipeline construction branch tunnel as maintenance channel and construction method
CN110685256B (en) * 2019-10-29 2021-06-04 黄河勘测规划设计研究院有限公司 Structure using hydropower station pressure pipeline construction branch tunnel as maintenance channel and construction method

Similar Documents

Publication Publication Date Title
CN205035779U (en) Construction branch tunnel suitable for pressure regulating of water delivery tunnel and maintenance traffic
CN104947780A (en) Inflow vertical shaft system connected into deep tunnel drainage system
CN109629525A (en) A kind of deep water intake system and its operating method
CN105781613A (en) Local dynamic dry-type waste water pump house for large-scale shield tunnel
CN202324058U (en) Double-layered pump and gate layout structure
CN110593949B (en) Mine sluicing wind shielding structure
CN206245390U (en) A kind of culvert pipe water channeling type pumping plant
CN209975621U (en) Open caisson formula water hammer protective equipment
CN117513260A (en) Drainage structure combining diversion tunnel, drainage tunnel and vertical shaft type flood drainage tunnel
CN106968227A (en) The maintenance arrangement of the permanent plug of induced joint diversion tunnel
CN207512707U (en) A kind of stiling basin for laying novel evacuation system
CN110593220A (en) Air supply ridge structure for drainage energy dissipation hole
CN204676504U (en) The emptying maintenance structure of a kind of long tailwater tunnel group without gravity flow ejectment condition
Schulze Hydraulic air compressors
CN207989064U (en) Tunnel construction with generating function
CN203768881U (en) Water seepage draining device for corridors of mountain and dam body
CN205894100U (en) Underground transfer passage
CN209194485U (en) A kind of diversion tunnel structure
CN104264642A (en) Drainage tunnel and drainage method for ditch water treatment
CN205314073U (en) Imitative nature fishway of tunnel style combines arranging of lifting means
CN212336278U (en) Large-scale underground type hydropower station factory building leakage drainage system combined with slope shaft
CN206928255U (en) The maintenance arrangement of the permanent plug of induced joint diversion tunnel
CN209603095U (en) Oblique stand alone type flood discharging tunnel water inlet tower structure
CN209493909U (en) A kind of aqueduct is across reservoir point water intaking structure
CN210315448U (en) Well tower separated water inlet

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant