CN205025459U - Test pipe column for liquid production profile of segmented fractured horizontal well - Google Patents

Test pipe column for liquid production profile of segmented fractured horizontal well Download PDF

Info

Publication number
CN205025459U
CN205025459U CN201520666553.0U CN201520666553U CN205025459U CN 205025459 U CN205025459 U CN 205025459U CN 201520666553 U CN201520666553 U CN 201520666553U CN 205025459 U CN205025459 U CN 205025459U
Authority
CN
China
Prior art keywords
pipe
packer
string
oil
horizontal well
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520666553.0U
Other languages
Chinese (zh)
Inventor
朱洪征
吕亿明
王百
罗有刚
牛彩云
崔文昊
常莉静
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Petrochina Co Ltd
Original Assignee
Petrochina Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Petrochina Co Ltd filed Critical Petrochina Co Ltd
Priority to CN201520666553.0U priority Critical patent/CN205025459U/en
Application granted granted Critical
Publication of CN205025459U publication Critical patent/CN205025459U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The utility model belongs to the technical field of oil extraction in oil fields, in particular to a staged fracturing horizontal well liquid production profile testing pipe column, a pipe column oil pipe string, a guide pipe plug, a tail pipe, an eye pipe, a flow water-containing tester, a packer, an oil pipe and a deep water swab, wherein the guide pipe plug and the tail pipe are connected at the bottom end of the oil pipe, the deep water swab is arranged at the top of the oil pipe string, the eye pipe and the flow water-containing tester are sequentially arranged at the middle part of the pipe string from bottom to top, the packer is sleeved outside the pipe string and is positioned at the upper part of the flow water-containing tester, the flow water-containing tester carried by the pipe column is adopted to be sent to a horizontal section for testing, a wellhead dragging packer is used for continuously swabbing, the downhole flow water-containing tester respectively measures the water content and flow of different combined sections, the purpose of testing staged liquid production profile and timely mastering the downhole liquid discharge condition is achieved, and the, the method solves the defects of the prior art, is convenient to construct and simple to operate, and can reduce the operation cost of site construction.

Description

A kind of staged fracturing horizontal well produced fluid cross section tubing string
Technical field
The utility model belongs to oil extraction in oil field technical field, is specifically related to a kind of staged fracturing horizontal well produced fluid cross section tubing string in oil extraction manufacturing process.
Background technology
Along with the prolongation of oil field development time, Horizontal Well number increases gradually, in horizontal wells process, needs often test segmentation production profile to grasp down-hole fluid situation in time, for water injection of horizontal well modification scenario and later stage water blockoff provide foundation.
Testing well section due to horizontal well is horizontal, cannot utilize instrument deadweight strength that instrument is delivered to testing well section.Current horizontal well produced fluid cross section technique substantially adopts tugger that combined test instrument is brought into down-hole horizontal section and tests, and crawl device method tester involves great expense, and cost is high.Therefore, horizontal well produced fluid cross section does not have better and widely to carry out, and particularly to adopt the production profile sectionalization test of horizontal well more difficult for machine.
Utility model content
The purpose of this utility model is to provide a kind of staged fracturing horizontal well produced fluid cross section tubing string, and test segmentation production profile grasps each section of down-hole fluid situation, in time for water injection of horizontal well modification scenario and later stage water blockoff provide foundation.
For this reason, the utility model provides a kind of staged fracturing horizontal well produced fluid cross section tubing string, comprise the oil pipe pipe string be connected together by multiple oil pipe string, also comprise guiding plug, tail pipe, eye pipe, the moisture tester of flow, packer, oil pipe and deep water swab, guiding plug and tail pipe are connected on the bottom of oil pipe pipe string, deep water swab is arranged on oil pipe pipe string top, in the middle part of oil pipe pipe string by lower and on be serially connected with eye pipe and the moisture tester of flow successively, oil pipe pipe string outer cover is equipped with packer, and described packer is positioned at the moisture tester top of flow.
Described oil pipe pipe string is also serially connected with downhole on-off actuator and Second Sight pipe, and described downhole on-off actuator is positioned at below packer, and described Second Sight pipe is positioned at the top of packer.
Described packer is cup packer.
The beneficial effects of the utility model: this staged fracturing horizontal well produced fluid cross section tubing string of the present utility model and method, adopt tubing string to carry the moisture tester of flow to deliver to horizontal segment and test, well head drags packer, the continuous pumping of ground deep water swab, the moisture tester of downhole flow measures the moisture of various combination interval and flow respectively, reach test segmentation production profile and grasp down-hole fluid situation in time, for water injection of horizontal well modification scenario and later stage water blockoff provide the object of foundation, solve the deficiencies in the prior art, and after implementing staged fracturing horizontal well produced fluid cross section tubing string and method, can complete efficiently horizontal well particularly low liquid measure machine adopt the multistage producing profile testing of level, ground is without the need to human metering, easy construction, operation is simple, Contraction in Site cost can be reduced.
Below with reference to accompanying drawing, the utility model is described in further details.
Accompanying drawing explanation
Fig. 1 is staged fracturing horizontal well produced fluid cross section tubing string schematic diagram.
Description of reference numerals: 1, lead plug; 2, tail pipe; 3, eye pipe; 4, the moisture tester of flow; 5, downhole on-off actuator; 6, packer; 7, Second Sight pipe; 8, oil pipe; 9, deep water swab.
Detailed description of the invention
Embodiment 1:
The present embodiment provides a kind of staged fracturing horizontal well produced fluid cross section tubing string, composition graphs 1, comprise the oil pipe pipe string be serially connected by multiple oil pipe 8, also comprise guiding plug 1, tail pipe 2, eye pipe 3, the moisture tester 4 of flow, packer 6, oil pipe 8 and deep water swab 9, guiding plug 1 and tail pipe 2 are connected on the bottom of oil pipe pipe string, deep water swab 9 is arranged on oil pipe pipe string top, in the middle part of oil pipe pipe string by lower and on be serially connected with a pipe 3 and the moisture tester 4 of flow successively, oil pipe pipe string outer cover is equipped with packer 6, described packer 6 is positioned at flow moisture tester 4 top, wherein packer 6 is cup packer.
This tubing string of the present embodiment is tested in accordance with the following steps:
Step one, running string: will enter in horizontal well under staged fracturing horizontal well produced fluid cross section tubing string, make the moisture tester 4 of guiding plug 1, tail pipe 2, eye pipe 3, flow, packer 6, be all positioned at the horizontal segment of horizontal well, now, packer 6 is positioned at test section bottom.Have three perforated intervals with reference in Fig. 1, figure, the perforated interval of rightmost is the perforated interval of bottom, and now, packer 6 is positioned at the right side of the test section of rightmost.
Step 2, production profile: promote tubing string, packer 6 is made to rise to above the perforated interval of bottom, namely packer 6 is made to be arranged in the middle of two, the right side perforated interval of Fig. 1, then deep water swab 9 is utilized to carry out swabbing operation, now, through the moisture tester 4 of inflow-rate of water turbine be all by the fluid of that perforated interval of the rightmost side.Promote tubing string gradually subsequently, packer 6 is made to pass through different perforated interval one by one, form the combination of different perforated interval, the moisture tester 4 of downhole flow continues metering various combination interval production fluid situation, such as promote a perforated interval on the basis of the above again, make packer 6 between the perforated interval of two, left side, then now moisture tester 4 metering of downhole flow is two, the right perforated intervals combination production fluid situations; When packer 6 is positioned at the left side of the perforated interval of the leftmost side time, then what the moisture tester 4 of downhole flow measured is three perforated interval combination production fluid situations.
Step 3, trips out test string: upper lifting pipe post, trips out test string.
Step 4, playback of data: take off the moisture tester 4 of flow, playback of data, contrast test plate draws Liquid output and the water content of various combination interval.Test plate is herein the curve map that the data recorded in each production fluid section in the well with known Liquid output carry out being combined to form.
Through contrast and analysis, the production fluid situation of each perforated interval in testing well section can be extrapolated.
Embodiment 2:
On the basis of embodiment 1, the present embodiment improves further, and as shown in Figure 1, oil pipe pipe string is also serially connected with downhole on-off actuator 5 and Second Sight pipe 7, described downhole on-off actuator 5 is positioned at below packer 6, and described Second Sight pipe 7 is positioned at the top of packer 6.
A method of testing for staged fracturing horizontal well produced fluid cross section tubing string, comprises the steps:
Step one, running string: will enter in horizontal well under staged fracturing horizontal well produced fluid cross section tubing string, make guiding plug 1, tail pipe 2, eye pipe 3, the moisture tester 4 of flow, derailing switch 5, packer 6, Second Sight pipe 7 is all positioned at the horizontal segment of horizontal well, now, derailing switch 5 is in open mode, packer 6 is entered under convenient, make, initial liquid outlet quantity flows away by derailing switch 5, packer 6 is finally made to be positioned at test section bottom, with reference to Fig. 1, three perforated intervals are had in figure, the perforated interval of rightmost is the perforated interval of bottom, now, packer 6 is positioned at the right side of the test section of rightmost.
Step 2, production profile: after derailing switch 5 cuts out, promote tubing string (in order to upwards promote packer 6 smoothly, be provided with Second Sight pipe 7, the fluid of the perforated interval above packer 6 is up flowed out by Second Sight pipe 7, the lifting of packer 6 can not be hindered) make packer 6 rise to above the perforated interval of bottom, namely packer 6 is made to be arranged in the middle of two, the right side perforated interval of Fig. 1, then deep water swab 9 is utilized to carry out swabbing operation, now, the fluid of the perforated interval of the rightmost side all enters tubing string by eye pipe 3, upwards extracted by deep water swab 9 after the moisture tester 4 of inflow-rate of water turbine again, all by the fluid of that perforated interval of the rightmost side through the moisture tester 4 of inflow-rate of water turbine.Promote tubing string gradually subsequently, packer 6 is made to pass through different perforated interval one by one, form the combination of different perforated interval, the moisture tester 4 of downhole flow continues metering various combination interval production fluid situation, such as promote a perforated interval on the basis of the above again, make packer 6 between the perforated interval of two, left side, then now moisture tester 4 metering of downhole flow is two, the right perforated intervals combination production fluid situations; When packer 6 is positioned at the left side of the perforated interval of the leftmost side time, then what the moisture tester 4 of downhole flow measured is three perforated interval combination production fluid situations.
Step 3, trips out test string: after derailing switch 5 reopens, and upper lifting pipe post, trips out test string.
Step 4, playback of data: take off the moisture tester 4 of flow, playback of data, contrast test plate draws Liquid output and the water content of various combination interval, then up analyzes stripping successively by the interval of bottom, draws Liquid output and the water content of each interval.Test plate is herein the curve map that the data recorded in each production fluid section in the well with known Liquid output carry out being combined to form.
Through contrast and analysis, the production fluid situation of each perforated interval in testing well section can be extrapolated.
Above-mentioned two embodiments are all be described with the situation of three perforated intervals, concrete perforation hop count should be as the criterion with actual quantity, method is identical with above-mentioned two embodiments, all constantly promote packer 6, measure various combination interval production fluid situation, then with the contrast of test plate, draw Liquid output and the water content of various combination interval, then calculate Liquid output and the water content of each interval by analysis.
More than exemplifying is only illustrate of the present utility model, does not form the restriction to protection domain of the present utility model, everyly all belongs within protection domain of the present utility model with the same or analogous design of the utility model.

Claims (3)

1. a staged fracturing horizontal well produced fluid cross section tubing string, comprise the oil pipe pipe string be serially connected by multiple oil pipe (8), it is characterized in that: also comprise guiding plug (1), tail pipe (2), eye pipe (3), the moisture tester of flow (4), packer (6), oil pipe (8) and deep water swab (9), guiding plug (1) and tail pipe (2) are connected on the bottom of oil pipe pipe string, deep water swab (9) is arranged on oil pipe pipe string top, in the middle part of oil pipe pipe string by lower and on be serially connected with eye pipe (3) and the moisture tester of flow (4) successively, oil pipe pipe string outer cover is equipped with packer (6), described packer (6) is positioned at the moisture tester of flow (4) top.
2. staged fracturing horizontal well produced fluid cross section tubing string as claimed in claim 1, it is characterized in that: described oil pipe pipe string is also serially connected with downhole on-off actuator (5) and Second Sight pipe (7), described downhole on-off actuator (5) is positioned at packer (6) below, and described Second Sight pipe (7) is positioned at the top of packer (6).
3. staged fracturing horizontal well produced fluid cross section tubing string as claimed in claim 1 or 2, is characterized in that: described packer (6) is cup packer.
CN201520666553.0U 2015-08-31 2015-08-31 Test pipe column for liquid production profile of segmented fractured horizontal well Active CN205025459U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520666553.0U CN205025459U (en) 2015-08-31 2015-08-31 Test pipe column for liquid production profile of segmented fractured horizontal well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520666553.0U CN205025459U (en) 2015-08-31 2015-08-31 Test pipe column for liquid production profile of segmented fractured horizontal well

Publications (1)

Publication Number Publication Date
CN205025459U true CN205025459U (en) 2016-02-10

Family

ID=55258002

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520666553.0U Active CN205025459U (en) 2015-08-31 2015-08-31 Test pipe column for liquid production profile of segmented fractured horizontal well

Country Status (1)

Country Link
CN (1) CN205025459U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106593422A (en) * 2016-12-01 2017-04-26 中国石油天然气股份有限公司 Storage type testing method in oil pipe of horizontal well and pipe column
CN107201893A (en) * 2017-07-28 2017-09-26 中国矿业大学 A kind of multiple seam gas well throughput contribution rate test grading device
CN110017133A (en) * 2019-05-23 2019-07-16 广州海洋地质调查局 A kind of test of horizontal well production profile and shutoff method and device
CN110185411A (en) * 2019-05-28 2019-08-30 西安思坦仪器股份有限公司 A kind of horizontal well closure test macro
CN111663929A (en) * 2020-05-25 2020-09-15 中国石油天然气股份有限公司 Multi-section fractured horizontal well production profile testing pipe column
CN113719270A (en) * 2021-10-07 2021-11-30 哈尔滨工业大学重庆研究院 Oil pipe dragging type horizontal well rapid sectional test system and implementation method

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106593422A (en) * 2016-12-01 2017-04-26 中国石油天然气股份有限公司 Storage type testing method in oil pipe of horizontal well and pipe column
CN107201893A (en) * 2017-07-28 2017-09-26 中国矿业大学 A kind of multiple seam gas well throughput contribution rate test grading device
CN107201893B (en) * 2017-07-28 2020-08-04 中国矿业大学 Multi-coal-bed gas well output contribution rate testing and grading device
CN110017133A (en) * 2019-05-23 2019-07-16 广州海洋地质调查局 A kind of test of horizontal well production profile and shutoff method and device
CN110017133B (en) * 2019-05-23 2024-05-10 广州海洋地质调查局 Method and device for testing output profile of horizontal well and plugging water
CN110185411A (en) * 2019-05-28 2019-08-30 西安思坦仪器股份有限公司 A kind of horizontal well closure test macro
CN111663929A (en) * 2020-05-25 2020-09-15 中国石油天然气股份有限公司 Multi-section fractured horizontal well production profile testing pipe column
CN113719270A (en) * 2021-10-07 2021-11-30 哈尔滨工业大学重庆研究院 Oil pipe dragging type horizontal well rapid sectional test system and implementation method

Similar Documents

Publication Publication Date Title
CN205025459U (en) Test pipe column for liquid production profile of segmented fractured horizontal well
CN105114061B (en) Multi-parameter combination test rapid water exploration pipe column and method for immobile pipe column of horizontal well
CN108104801A (en) Horizontal well tracer liquid production profile testing pipe column and method
CN104915512B (en) It is a kind of to predict oil field produced degree and the method for moisture content
CN105937393B (en) Horizontal well dragging type liquid production profile testing pipe column and testing method thereof
CN106522928B (en) Well testing method for unstable pressure drop of well logging head by stopping pump after acidizing and fracturing
CN103075143B (en) Method for testing fluid-producing section of horizontal pump well
CN107066769B (en) Efficient acidification design method suitable for ultra-deep layer crack type carbonate reservoir
CN103674593B (en) A kind of device and method for simulating the flood pot test of low permeability reservoir pressure break straight well
CN204299556U (en) A kind of separate layer acid treatment and down-hole dispensing integrated pipe column
CN106593422A (en) Storage type testing method in oil pipe of horizontal well and pipe column
US11136865B2 (en) Integrated construction method of fracturing and tertiary oil recovery for low-permeability reservoir
CN104389566B (en) A kind of method for judging that gas alters the ease time
CN103993877A (en) Radial well fracture testing device
CN104632195B (en) Gas lift flow aiding horizontal well water exploration pipe column and method
CN201963286U (en) Oil production pipe for reducing water content of central pipe of horizontal well
CN203626820U (en) Gas lift flow aiding horizontal well water exploration pipe column
CN109522619A (en) Low-permeability oilfield periodic oil extraction method
CN205025412U (en) Multi-parameter combination test rapid water exploration pipe column for fixed pipe column of horizontal well
CN205445599U (en) High-water-content horizontal well tracer injection water exploration double-sealing single-clamp process pipe column
CN203321507U (en) Water exploration pipe column for simultaneously monitoring subsection flow and water content of multi-section fractured horizontal well
CN205211283U (en) Experimental device for two gradient well drillings of efflux under simulation well
CN104389569A (en) Steam huff and puff mining method
CN104420836A (en) Horizontal well subsection setting type wellhead flow method water exploration pipe column and water exploration method thereof
CN204851223U (en) Tubular column combination of product is asked to oil well multilayer sectionalization test

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant