CN204940913U - A kind of adjustable jacking device of high and big die plate full hall scaffold top braces - Google Patents

A kind of adjustable jacking device of high and big die plate full hall scaffold top braces Download PDF

Info

Publication number
CN204940913U
CN204940913U CN201520449865.6U CN201520449865U CN204940913U CN 204940913 U CN204940913 U CN 204940913U CN 201520449865 U CN201520449865 U CN 201520449865U CN 204940913 U CN204940913 U CN 204940913U
Authority
CN
China
Prior art keywords
full hall
sleeve pipe
die plate
plate full
top braces
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520449865.6U
Other languages
Chinese (zh)
Inventor
刘先锋
张家浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongqi Jiaojian Group Corp Ltd
Original Assignee
Zhongqi Jiaojian Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongqi Jiaojian Group Corp Ltd filed Critical Zhongqi Jiaojian Group Corp Ltd
Priority to CN201520449865.6U priority Critical patent/CN204940913U/en
Application granted granted Critical
Publication of CN204940913U publication Critical patent/CN204940913U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model relates to construction equipment field, be specifically related to a kind of adjustable jacking device of high and big die plate full hall scaffold top braces, the upper end of sleeve pipe is connected with the jacking at its top by leading screw, and the lower end of sleeve pipe is socketed on scaffold upright rod, and cover tube side part is fixedly installed work-saving device; The upper end inwall of described sleeve pipe is provided with screw thread.Advantage of the present utility model: structure is simple, and cost is lower, easy to operate, adds the stability and operating efficiency of building and dismantle full hall bracing frame, alleviates the labour intensity of staff, thus reduce the maintenance cost in later stage, is applicable to commercial introduction and uses.

Description

A kind of adjustable jacking device of high and big die plate full hall scaffold top braces
Technical field
The utility model relates to construction equipment field, is specifically related to a kind of adjustable jacking device of high and big die plate full hall scaffold top braces.
Background technology
Full hall bracing frame is a kind of scaffold comparatively common in building operations.Its scaffold relative to other is more firm, is therefore mainly in use the effect playing load-bearing, reinforcing.
Full hall bracing frame mainly comprises vertical rod and horizon bar, and they are all be made up of steel pipe, and wherein horizon bar is divided into horizontal water horizon bar and vertical equity bar, and the top of vertical rod is often provided with jacking to carry out the corresponding concrete blinding of holding by corresponding steel pipe.
The working environment using full hall bracing frame is mostly relatively more severe, once connection bracket is got rusty or stained, then can give further support build and dismounting is made troubles, add the maintenance cost in later stage; Add the labour intensity of staff, this also reduces the stability and operating efficiency of building and dismantle full hall bracing frame to a certain extent.
Utility model content
For the deficiencies in the prior art, the utility model provides that a kind of structure is set up simply, the adjustable jacking device of the high and big die plate full hall scaffold top braces of safety labor-saving.
The utility model discloses a kind of adjustable jacking device of high and big die plate full hall scaffold top braces, and the upper end of sleeve pipe is connected with the jacking at its top by leading screw, and the lower end of sleeve pipe is socketed on scaffold upright rod, and cover tube side part is fixedly installed work-saving device; The upper end inwall of described sleeve pipe is provided with screw thread.
Preferred version is as follows:
Work-saving device is circle pier shape projection.During concrete operations, one end through hole of steel pipe is stuck in projection, promotes the opposite side of steel pipe, be equivalent to increase the arm of force, revoling tube, thus drive leading screw that the jacking at its top is risen.
Work-saving device is the collar, is placed with dismountable swing arm in the collar, and swing arm one end is provided with handle.During concrete operations, swing arm is placed in the collar, is equivalent to increase the arm of force, revoling tube, thus drive leading screw that the jacking at its top is risen.
Sleeve outer is 535-545mm, and internal diameter is 485-495mm;
It is 95-105mm that the upper end inwall of sleeve pipe is provided with the depth of thread.
Advantage of the present utility model: structure is simple, and cost is lower, easy to operate, adds the stability and operating efficiency of building and dismantle full hall bracing frame, alleviates the labour intensity of staff, thus reduce the maintenance cost in later stage, is applicable to commercial introduction and uses.
Accompanying drawing illustrates:
In order to be illustrated more clearly in the utility model embodiment or technical scheme of the prior art, be briefly described to the accompanying drawing used required in embodiment or description of the prior art below, apparently, accompanying drawing in the following describes is embodiments more of the present utility model, for those of ordinary skill in the art, under the prerequisite not paying creative work, other accompanying drawing can also be obtained according to these accompanying drawings.
Fig. 1 is the structure half sectional view of the utility model embodiment 1;
Fig. 2 is the structure half sectional view of the utility model embodiment 2;
In figure: 1, jacking, 2, leading screw, 3, sleeve pipe, 4, swing arm, 5, the collar, 6, scaffold upright rod, 7, protruding.
Detailed description of the invention:
Below in conjunction with accompanying drawing 1 and Fig. 2, detailed description of the invention of the present utility model is described in further detail, but the utility model is not limited to specific embodiment.
Embodiment 1:
An adjustable jacking device for high and big die plate full hall scaffold top braces, the upper end of sleeve pipe 3 is connected with the jacking 1 at its top by leading screw 2, and the lower end of sleeve pipe 3 is socketed on scaffold upright rod 6, and sleeve pipe 3 sidepiece is fixedly installed work-saving device; The upper end inwall of described sleeve pipe 3 is provided with screw thread.
Work-saving device is circle pier shape projection 7, during concrete operations, is stuck in by one end through hole of steel pipe on protruding 7, promotes the opposite side of steel pipe, be equivalent to increase the arm of force, revoling tube 3, thus drive leading screw 2 that the jacking 1 at its top is risen.
Sleeve pipe 3 external diameter is 535mm, and internal diameter is 495mm;
It is 95mm that the upper end inwall of sleeve pipe 3 is provided with the depth of thread.
Embodiment 2:
An adjustable jacking device for high and big die plate full hall scaffold top braces, the upper end of sleeve pipe 3 is connected with the jacking 1 at its top by leading screw 2, and the lower end of sleeve pipe 3 is socketed on scaffold upright rod 6, and sleeve pipe 3 sidepiece is fixedly installed work-saving device; The upper end inwall of described sleeve pipe 3 is provided with screw thread.
Work-saving device is the collar 5, is placed with dismountable swing arm 4 in the collar 5, and swing arm 4 one end is provided with handle.During concrete operations, swing arm 4 is placed in the collar 5, is equivalent to increase the arm of force, revoling tube 3, thus drive leading screw 2 that the jacking 1 at its top is risen.
Sleeve pipe 3 external diameter is 545mm, and internal diameter is 485mm;
It is 105mm that the upper end inwall of sleeve pipe 3 is provided with the depth of thread.
Above-described embodiment of the present utility model is only for the utility model example is clearly described, and is not the restriction to embodiment of the present utility model.For those of ordinary skill in the field, can also make other changes in different forms on the basis of the above description.Every belong to the technical solution of the utility model the apparent change of extending out or variation be still in the row of protection domain of the present utility model.

Claims (6)

1. an adjustable jacking device for high and big die plate full hall scaffold top braces, is characterized in that: the upper end of sleeve pipe is connected with the jacking at its top by leading screw, and the lower end of sleeve pipe is socketed on scaffold upright rod, and cover tube side part is fixedly installed work-saving device; The upper end inwall of described sleeve pipe is provided with screw thread.
2. the adjustable jacking device of a kind of high and big die plate full hall scaffold top braces according to claim 1, is characterized in that: described work-saving device is circle pier shape projection.
3. the adjustable jacking device of a kind of high and big die plate full hall scaffold top braces according to claim 1, is characterized in that: described work-saving device is the collar, is placed with dismountable swing arm in the collar.
4. the adjustable jacking device of a kind of high and big die plate full hall scaffold top braces according to claim 3, is characterized in that: described swing arm one end is provided with handle.
5. the adjustable jacking device of a kind of high and big die plate full hall scaffold top braces according to claim 1, it is characterized in that: described sleeve outer is 535-545mm, internal diameter is 485-495mm.
6. the adjustable jacking device of a kind of high and big die plate full hall scaffold top braces according to claim 1, is characterized in that: it is 95-105mm that the upper end inwall of described sleeve pipe is provided with the depth of thread.
CN201520449865.6U 2015-06-26 2015-06-26 A kind of adjustable jacking device of high and big die plate full hall scaffold top braces Expired - Fee Related CN204940913U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520449865.6U CN204940913U (en) 2015-06-26 2015-06-26 A kind of adjustable jacking device of high and big die plate full hall scaffold top braces

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520449865.6U CN204940913U (en) 2015-06-26 2015-06-26 A kind of adjustable jacking device of high and big die plate full hall scaffold top braces

Publications (1)

Publication Number Publication Date
CN204940913U true CN204940913U (en) 2016-01-06

Family

ID=55008354

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520449865.6U Expired - Fee Related CN204940913U (en) 2015-06-26 2015-06-26 A kind of adjustable jacking device of high and big die plate full hall scaffold top braces

Country Status (1)

Country Link
CN (1) CN204940913U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105863264A (en) * 2016-06-08 2016-08-17 苏州莲敬机械工程科技有限公司 Civil engineering fundamental mold side ejector

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105863264A (en) * 2016-06-08 2016-08-17 苏州莲敬机械工程科技有限公司 Civil engineering fundamental mold side ejector
CN105863264B (en) * 2016-06-08 2017-11-03 苏州莲敬机械工程科技有限公司 A kind of civil engineering basic mode side head part

Similar Documents

Publication Publication Date Title
CN203808484U (en) Integrated cantilevered and attached external scaffolding
CN202000651U (en) Adjustable wall-mounted supporting device for reinforcing upright columns
CN204001731U (en) A kind of shuttering supporting vertical rod base fixing device
CN204940913U (en) A kind of adjustable jacking device of high and big die plate full hall scaffold top braces
CN204717144U (en) A kind of concrete pump pipe setting tool cribbing
CN205077842U (en) Multi -use architecture support
CN205224017U (en) Device is prevented floating by bored concrete pile steel reinforcement cage
CN203475809U (en) Scaffold supporting structure convenient to mount and dismount
CN205152775U (en) Bridge height limiting device
CN203531350U (en) U-shaped pull ring for steel beam fixing of cantilever outer frame
CN203890893U (en) Supporting bracket for integral lifting of hollow slab girder
CN212613727U (en) Be applied to mould shell of close rib structure superstructure building
CN205421257U (en) Aquatic steel -pipe pile pile sinking auxiliary device
CN204386190U (en) Building site net frame leveling special carrier
CN204059947U (en) A kind of self-stabilization type outer wall formwork of basement support system
CN202519885U (en) Fixing device for GBF high-strength thin walled tube
CN205242988U (en) Cantilever type steel with inclined support at bottom
CN202544875U (en) Front canopy type temporary supporting suspension device for anchor pole supporting tunnel construction
CN205224557U (en) Lift scaffold pole setting connection structure
CN204418696U (en) Vertical reinforcement spreading lifting assistor
CN202248819U (en) Light wood structural construction scaffold
CN204152108U (en) A kind of light section steel structure glass canopy structure
CN204152174U (en) A kind of scaffold being convenient to dismounting and expansion
CN204626952U (en) A kind of furred ceiling of pre-buried working of plastics
CN104328900A (en) Gantry type scaffold

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160106

Termination date: 20160626

CF01 Termination of patent right due to non-payment of annual fee